A box girder guide beam assembly and its assembly method

The composite box girder with a three-section variable thickness transition design solves the problems of easy cracking of the UHPC shell and unstable connection in the steel-UHPC composite box girder during the jacking construction, realizes smooth force flow and improves structural stability, and ensures construction accuracy and safety.

CN123109076APending Publication Date: 2026-11-17CHINA METALLURGICAL ROAD & BRIDGE CONSTR CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611374161.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-07
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing jacking construction equipment and connection structures are difficult to adapt to the special structural characteristics of steel-UHPC composite box girders, resulting in UHPC shells being prone to cracking, crushing, and unstable connections, affecting construction accuracy and safety.

Method used

The connecting section of the composite box girder adopts a three-section variable thickness transition design, including an equal thickness section, a transition section, and a thickened section. Through the composite structure of the steel inner core and the UHPC shell, the force flow is ensured to be smoothly transmitted, the UHPC shell is prevented from being directly stressed, and the stiffness and strength of the connecting section are enhanced.

Benefits of technology

It effectively solved the problems of UHPC shell cracking and unstable connection, improved structural stability and construction quality, and ensured the accuracy and safety of jacking construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109076A_ABST
    Figure CN123109076A_ABST
Patent Text Reader

Abstract

This application discloses a box girder guide beam assembly and its assembly method. The assembly includes a UHPC composite box girder, a connecting section composite box girder, and a steel guide beam. The UHPC composite box girder has a first steel inner core and a first outer shell. The connecting section composite box girder includes a second steel inner core and a second outer shell. The second outer shell has a thickened section, a transition section, and a section of equal thickness arranged sequentially. The thickness of the section of equal thickness is equal to the thickness of the first outer shell, and the two are smoothly connected. The first steel inner core and the second steel inner core are welded and fixed. The thickness of the thickened section is greater than the thickness of the first outer shell. The upper surface of the second outer shell smoothly transitions to the upper surface of the first outer shell. The thickness of the transition section gradually transitions from the section of equal thickness to the thickened section. The steel guide beam is located on the side of the thickened section away from the section of equal thickness and is welded to the second steel inner core. This application, through the three-section variable thickness transition design of the connecting section composite box girder, effectively avoids the problems of easy cracking, crushing, and peeling damage of the outer shell when the UHPC composite box girder is directly connected to the steel guide beam, significantly improving structural stability and construction quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of bridge construction technology, and in particular to a box girder guide beam assembly and its assembly method. Background Technology

[0002] The incremental launching method has become one of the mainstream construction methods for the main girder erection of long-span bridges, especially those spanning railway lines and rivers, due to its advantages such as not requiring large lifting equipment, not occupying navigation and traffic space under the bridge, high construction safety, and good prefabrication. During the incremental launching process, to reduce the cantilever length of the main girder, lower the negative bending moment at the front end, improve the stress state of the girder, and provide guidance, a steel guide beam is usually installed at the front end of the main girder as a temporary auxiliary structure. The connection method between the steel guide beam and the main girder directly affects the force transmission efficiency during the incremental launching process and the structural safety of the end of the main girder.

[0003] Ultra-high performance concrete (UHPC) has garnered significant attention in bridge engineering in recent years due to its ultra-high strength, high toughness, high durability, and excellent impermeability. Steel-UHPC composite box girders, as a novel lightweight high-performance structure, utilize a steel inner core skeleton combined with a UHPC outer shell. This fully leverages the advantages of UHPC's high compressive strength and the steel core's high tensile strength and stiffness. Compared to traditional steel-concrete composite structures, it achieves significant weight reduction while substantially improving the structure's crack resistance, fatigue resistance, and durability. It effectively overcomes conventional bridge span limitations, making it suitable for large-span highways and cross-river / sea bridges, possessing significant technical and economic advantages.

[0004] However, existing jacking construction auxiliary equipment and connection structures are mostly designed for ordinary concrete box girders or conventional steel-concrete composite box girders, which are difficult to directly adapt to the special structural characteristics and construction requirements of steel-UHPC composite box girders, resulting in many technical defects.

[0005] First, while UHPC material boasts high strength, it is also relatively brittle, exhibiting significantly different local compressive stress characteristics compared to ordinary concrete. Existing rigid jacking blocks, sliding supports, and other auxiliary equipment, if applied directly to the UHPC shell, can easily cause surface crushing, peeling, and cracking, damaging the beam's appearance and structural integrity. If flexible blocks are used, there are issues with poor stiffness matching and susceptibility to deformation and displacement. Deformation of the blocks during jacking can lead to uneven stress distribution on the beam, resulting in localized stress concentrations and affecting the accuracy of the jacking construction and structural safety.

[0006] Secondly, when the steel guide beam is directly connected to the UHPC composite box girder, the UHPC composite box girder has a relatively thin outer shell. During the jacking process, under the concentrated force and bending moment transmitted by the steel guide beam, stress concentration is likely to occur at the interface between the UHPC outer shell and the steel inner core. This can easily lead to damage problems such as cracking, crushing, and peeling of the UHPC outer shell, which seriously restricts the structural stability and construction safety.

[0007] Secondly, the connection section between the steel guide beam and the composite box girder is a critical part for the transfer of jacking loads, and existing technologies lack specific local reinforcement structures for this section. During long-distance, high-tonnage jacking construction, problems such as deformation inconsistencies at the connection point are prone to occur, leading to beam slippage, misalignment, and alignment deviations, affecting the bridge's final alignment and construction accuracy. While existing technologies include design studies on steel-concrete transition sections, these primarily focus on conventional concrete box girder or pure steel box girder structures, neglecting the structural transition issues at the interface between the steel-UHPC composite box girder and the steel guide beam.

[0008] In summary, the current lack of an auxiliary equipment system for jacking construction that is suitable for the characteristics of steel-UHPC composite box girders, and the absence of an efficient and reliable connection method that matches the force transmission mechanism of its composite structure, leads to numerous problems such as beam damage, alignment deviation, connection failure, and low construction efficiency during the jacking construction of this new type of composite box girder, which seriously restricts the engineering promotion and application of steel-UHPC composite box girders. Summary of the Invention

[0009] To address one of the aforementioned technical problems, this application provides a box girder guide beam assembly and its assembly method.

[0010] The present invention adopts the following technical solution:

[0011] In a first aspect, embodiments of this application provide a box girder guide beam assembly, comprising:

[0012] UHPC composite box girder, having a first steel inner core and a first outer shell covering part of the first steel inner core;

[0013] A connecting section composite box girder includes a second steel inner core and a second outer shell covering part of the second steel inner core. The second outer shell has a thickened section, a transition section, and a section of equal thickness arranged sequentially. The thickness of the section of equal thickness is equal to the thickness of the first outer shell. The section of equal thickness and the first outer shell are smoothly connected. The first steel inner core and the second steel inner core are welded and fixed. The thickness of the thickened section is greater than the thickness of the first outer shell. The upper surface of the second outer shell and the upper surface of the first outer shell are smoothly transitioned. The thickness of the transition section gradually transitions from the section of equal thickness to the thickened section.

[0014] A steel guide beam is located on the side of the thickened section of the connecting section combined box girder away from the equal-thickness section, and the steel guide beam is welded to the second steel inner core.

[0015] Optionally, the second steel inner core includes a steel top plate, a steel bottom plate, and a steel web plate;

[0016] The steel web is located between the steel top plate and the steel bottom plate, and connects the steel top plate and the steel bottom plate respectively;

[0017] The second steel inner core has an extension wing on its top and bottom plates near the steel guide beam, which extends out of the steel web.

[0018] The extended wing and the portion of the steel top / bottom plate located inside the steel web are connected to and welded to the steel guide beam.

[0019] Optionally, the side frames on both sides of the steel guide beam each include a guide beam top plate and a guide beam bottom plate, and the guide beam top plate and guide beam bottom plate have a widened section at one end near the connecting section combined box girder;

[0020] The widened section is welded to the corresponding extended wing and the portion of the steel top / bottom plate located inside the steel web.

[0021] Optionally, the extended wing is only provided within the transition section and the thickened section, and the width of the extended wing within the thickened section is constant;

[0022] In the direction from the equal-thickness section to the thickened section, the extended wing in the transition section gradually widens at least locally, the thickness of the concrete web of the thickened section is greater than the thickness of the concrete web of the equal-thickness section, and the thickness of the concrete web of the transition section gradually increases at least locally.

[0023] Optionally, the steel top plate of the second steel core includes a first top plate, a second top plate, and a third top plate;

[0024] The height of the first top plate is higher than that of the third top plate;

[0025] The second top plate slopes and transitions from the first top plate to the third top plate;

[0026] The first top plate corresponds to the equal-thickness section and part of the transition section, the second top plate corresponds to the transition section, and the third top plate corresponds to the thickened section;

[0027] The second top plate and the gradually widening plate segments on the extended wing are staggered.

[0028] Optionally, the box girder guide beam assembly includes reinforcing steel bars;

[0029] Holes are provided on the extended wing of the steel top plate;

[0030] Some of the reinforcing bars are inserted through the holes and supported at the bottom on the extended wing of the steel base plate;

[0031] The inner diameter of the hole is larger than the outer diameter of the reinforcing steel bar.

[0032] Optionally, a steel inclined plate is provided between the steel top plate and the steel web plate of the second steel inner core;

[0033] Within the transition section and the thickened section, a cavity is formed between the steel inclined plate, the steel top plate, and the steel web;

[0034] The steel top plate is provided with holes that communicate with the cavity;

[0035] Some of the reinforcing bars are inserted into the holes, and their bottom ends abut against the inclined steel plate.

[0036] Optionally, the box girder guide beam assembly includes reinforcing supports;

[0037] An end plate is provided at one end of the second steel inner core near the steel guide beam, and the end plate is a closed plate.

[0038] The steel guide beam includes a web plate that connects the top plate and the bottom plate of the guide beam;

[0039] The guide beam web and the steel web are welded and fixed together.

[0040] The reinforcing support is located between the web of the guide beam and the end plate, and is welded to the web of the guide beam and the end plate respectively.

[0041] Optionally, the second steel inner core includes steel diaphragms, stiffening ribs, and steel transverse ribs;

[0042] The steel diaphragm is located inside the cavity of the second steel inner core and is connected to the steel top plate, steel bottom plate and steel web of the second steel inner core respectively. The steel diaphragm is provided with a manhole.

[0043] The stiffening rib is connected to the steel base plate, and the stiffening rib is perpendicular to the steel transverse diaphragm;

[0044] The steel transverse ribs are parallel to the steel transverse diaphragm and are welded to the steel top plate.

[0045] Secondly, embodiments of this application also provide an assembly method for a box girder guide beam assembly, including the following steps:

[0046] Step S1: Prefabricate steel guide beams, first steel inner core and second steel inner core in the factory; evenly distribute shear connectors on the outer surfaces of the first steel inner core and second steel inner core; pre-reserve holes in the second steel inner core.

[0047] Step S2: Transport the prefabricated components to the construction site, accurately align and install the steel guide beam, the first steel inner core and the second steel inner core to complete the initial connection and fixation, and then symmetrically assemble two sets of reinforcing supports at the connection between the steel guide beam and the second steel inner core on both sides of the steel web to complete the local reinforcement of the transition section and ensure the integrity of the force transmission structure.

[0048] Step S3: Insert reinforcing bars of the corresponding length into the holes of the second steel core, and tie and fix the reinforcing cage according to the specifications. Then, pour the UHPC material as a whole and vent and level it to complete the overall assembly construction.

[0049] By adopting the above technical solution, this application has the following beneficial effects:

[0050] This invention, through the composite structure design of the steel inner core and UHPC outer shell of the connecting section combined box girder, ensures that all jacking loads and sliding support loads during the entire jacking construction process are borne by the steel inner core, while the UHPC outer shell serves only as a protective structure and does not participate in the direct force bearing of the jacking. This avoids the cracking, crushing, and peeling damage caused by the rigid pad directly pressing the UHPC surface layer in the traditional jacking process from the source of the force transmission path, effectively ensuring the structural integrity and appearance quality of the UHPC outer shell.

[0051] The connecting section of the composite box girder in this application adopts a three-section UHPC shell structure consisting of equal-thickness section, variable-thickness section, and thickened section. This effectively solves the problem of UHPC shell cracking caused by sudden changes in structural stiffness and stress concentration when the steel guide beam is directly connected to the UHPC composite box girder. It achieves a smooth transition in structural stiffness and strength in the connecting section and greatly improves the structural stability and construction integrity of the connecting section.

[0052] The specific embodiments of the present invention will now be described in further detail with reference to the accompanying drawings. Attached Figure Description

[0053] The accompanying drawings, which form part of this application, are used to provide a further understanding of the invention. The illustrative embodiments and descriptions of the invention are used to explain the invention, but do not constitute an undue limitation of the invention. Obviously, the drawings described below are merely some embodiments, and those skilled in the art can obtain other drawings based on these drawings without creative effort. In the drawings:

[0054] Figure 1 This diagram shows a structural schematic of the box girder guide beam assembly provided in an embodiment of this disclosure;

[0055] Figure 2 This diagram shows a structural schematic of the UHPC composite box girder in the box girder guide beam assembly provided in an embodiment of this disclosure;

[0056] Figure 3 This diagram shows a structural schematic of the steel guide beam in the box girder guide beam assembly provided in this embodiment of the present disclosure;

[0057] Figure 4 This diagram illustrates the structure of the reinforcing support in the box girder guide beam assembly provided in this embodiment.

[0058] Figure 5This diagram shows a partial structural schematic of the box girder guide beam assembly provided in an embodiment of the present disclosure;

[0059] Figure 6 This diagram illustrates the structural cooperation of the steel guide beam, reinforcing support, and connecting section of the combined box girder in the box girder guide beam assembly provided in this embodiment of the present disclosure.

[0060] Figure 7 This diagram shows a structural schematic of the second steel inner core in the box girder guide beam assembly provided in an embodiment of this disclosure;

[0061] Figure 8 This diagram shows the internal structure of the second steel core in the box girder guide beam assembly provided in this embodiment of the present disclosure;

[0062] Figure 9 This diagram illustrates the structural arrangement of the second steel core and reinforcing bars in the box girder guide beam assembly provided in this embodiment of the present disclosure.

[0063] Figure 10 A partial structural diagram of the second steel inner core in the box girder guide beam assembly provided in this embodiment is shown.

[0064] In the diagram: 1. UHPC composite box girder; 11. First steel inner core; 12. First outer shell; 2. Connecting section composite box girder; 21. Second steel inner core; 211. Steel top plate; 211a. Extension wing; 2111. First top plate; 2112. Second top plate; 2113. Third top plate; 212. Steel bottom plate; 213. Steel web plate; 214. Steel inclined plate; 215. End plate; 216. Steel diaphragm plate; 2 17. Stiffening rib; 218. Steel transverse rib; 22. Second shell; 221. Thickened section; 222. Transition section; 223. Equal thickness section; 3. Steel guide beam; 31. Guide beam top plate; 311. Widened section; 32. Guide beam bottom plate; 33. Guide beam web; 4. Reinforcing steel bars; 5. Reinforced support; 51. Vertically arranged steel plate; 52. Horizontally arranged steel plate; 6. Shear connector; a. Hole; b. Cavity.

[0065] It should be noted that these accompanying drawings and textual descriptions are not intended to limit the scope of the invention in any way, but rather to illustrate the concept of the invention to those skilled in the art by referring to specific embodiments. Detailed Implementation

[0066] To make the objectives, technical solutions, and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments will be clearly and completely described below with reference to the accompanying drawings. The following embodiments are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0067] In the description of this invention, it should be noted that the terms "upper", "lower", "inner", "outer", etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or component referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limitations on this invention.

[0068] In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation" and "connection" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.

[0069] like Figures 1 to 10 As shown, this application embodiment provides a box girder guide beam assembly, including: a UHPC composite box girder 1, a connecting section composite box girder 2, and a steel guide beam 3. The UHPC composite box girder 1 has a first steel inner core 11 and a first outer shell 12 covering a portion of the first steel inner core 11. The connecting section composite box girder 2 includes a second steel inner core 21 and a second outer shell 22 covering a portion of the second steel inner core 21. The second outer shell 22 has a thickened section 221, a transition section 222, and a constant thickness section 223 arranged sequentially. The thickness of the constant thickness section 223 is equal to the thickness of the first outer shell 12. The constant thickness section 223 and the first outer shell 12 are smoothly connected. The first steel inner core 11 and the second steel inner core 21 are welded and fixed. The thickness of the thickened section 221 is greater than the thickness of the first outer shell 12. The upper surface of the second outer shell 22 and the upper surface of the first outer shell 12 transition smoothly. The thickness of the transition section 222 gradually transitions from the constant thickness section 223 to the thickened section 221. The steel guide beam 3 is located on the side of the thickened section 221 of the connecting section combined box girder 2 away from the equal thickness section 223, and the steel guide beam 3 is welded to the second steel inner core 21.

[0070] The UHPC composite box girder 1 is a novel lightweight, high-performance bridge structure. It adopts a steel-UHPC composite structure, consisting of a first steel core 11 as the skeleton, and a first outer shell 12, formed by casting UHPC material, partially enclosing the first steel core 11. The first steel core 11 is a closed box-shaped steel skeleton structure, primarily bearing the structural load, characterized by high stiffness and strong load-bearing capacity. The first outer shell 12 is cast from ultra-high performance concrete (UHPC), utilizing the core advantages of UHPC material—ultra-high strength, high toughness, high impermeability, and high durability—to protect the internal steel skeleton and participate in structural stress coordination. The steel core and UHPC outer shell are reliably connected via shear connectors 6, ensuring coordinated deformation. Compared to traditional steel-concrete composite structures, this structure can achieve a weight reduction of over 30%, while significantly improving the structure's fatigue resistance, crack resistance, and corrosion resistance.

[0071] The connecting section composite box girder 2 is a key transitional component for achieving a reliable connection between the UHPC composite box girder 1 and the steel guide beam 3. It also adopts a steel-UHPC composite structure, including a second steel inner core 21 and a second outer shell 22 that partially covers the second steel inner core 21. The connecting section composite box girder 2 is characterized by its second outer shell 22 employing a three-section variable thickness transition design, specifically including:

[0072] Equal Thickness Section 223: The thickness of equal thickness section 223 is equal to the thickness of the first outer shell 12 of the UHPC composite box girder 1 (e.g., the thickness of the concrete top slab and the concrete web of both are matched, but whether the thicknesses of the concrete top slab and the concrete web are equal is not limited in this application). Equal thickness section 223 is smoothly connected to the first outer shell 12, ensuring that the outer shell thickness of the connecting section composite box girder 2 and the UHPC composite box girder 1 is consistent at the connection point, with a smooth surface transition without steps or abrupt changes, thus avoiding stress concentration caused by geometrical abrupt changes. Simultaneously, the first steel inner core 11 and the second steel inner core 21 are fixedly connected by welding to ensure the continuity of force transmission within the internal steel frame.

[0073] Thickened section 221: The thickened section 221 is located on the side of the connecting section composite box girder 2 near the steel guide beam 3, and its thickness is greater than that of the first outer shell 12. Specifically, the thickness of the web and top plate of the thickened section 221 is 1.5 to 3 times the corresponding dimensions of the equal-thickness section 223. The design purpose of the thickened section 221 is to enhance the structural strength of the steel guide beam 3 in the stress-bearing section. Since the steel guide beam 3 is a pure steel structure, its stiffness is relatively large, and the concentrated force and bending moment transmitted during the jacking process are relatively large. If the thickness of the UHPC outer shell is insufficient, stress concentration is likely to occur at the connection interface, which can lead to damage such as cracking, crushing, and peeling of the UHPC outer shell. By setting the thickened section 221, the thickness of the UHPC outer shell in the connecting section is effectively increased, improving the local load-bearing capacity and crack resistance of this area.

[0074] Transition section 222: Transition section 222 is located between thickened section 221 and equal-thickness section 223, with its thickness gradually transitioning from equal-thickness section 223 to thickened section 221. Specifically, the web thickness and top plate thickness of transition section 222 transition along the beam length from the dimensions of thickened section 221 to those of equal-thickness section 223. The design purpose of transition section 222 is to achieve a smooth transition in the thickness of the second outer shell 22 from thin to thick, avoiding sudden changes in stiffness and stress concentration caused by abrupt changes in thickness, ensuring a smooth transition in the stiffness and strength of the connecting section structure, thereby making the force flow transmission smoother.

[0075] In addition, the upper surface of the second outer shell 22 and the upper surface of the first outer shell 12 (the upper surface of the concrete top slab) are smoothly transitioned, ensuring the smoothness of the top surface of the assembly, which is beneficial to the passability and construction accuracy of the sliding device during the jacking construction.

[0076] Through the above structural design, the connection relationship between the UHPC composite box girder 1, the connecting section composite box girder 2, and the steel guide beam 3 is as follows: UHPC composite box girder 1 - connecting section composite box girder 2 (equal thickness section 223 - transition section 222 - thickened section 221) - steel guide beam 3. In this connection system, the connecting section composite box girder 2 plays a bridging role: on the one hand, its equal thickness section 223 has the same shell thickness as the UHPC composite box girder 1, achieving a smooth connection; on the other hand, its thickened section 221 provides sufficient thickness of UHPC shell and strength reserve for the connection of the steel guide beam 3; at the same time, the transition section 222 achieves a smooth transition in thickness and stiffness. This application effectively solves the technical problem of easy cracking, crushing, and peeling damage of the outer shell caused by the relatively weak structure and thin outer shell of the UHPC composite box girder when the steel guide beam 3 is directly connected to the UHPC composite box girder 1. The three-section variable thickness transition design of the connecting section composite box girder 2 effectively solves the technical problem of easy cracking, crushing, and peeling damage of the outer shell caused by the relatively weak structure and thin outer shell of the UHPC composite box girder 1. It realizes a smooth transition of stiffness and strength between the steel guide beam 3 and the UHPC composite box girder 1, and greatly improves the structural stability and construction quality.

[0077] In some possible implementations, such as Figures 7 to 9 As shown, the second steel inner core 21 includes a steel top plate 211, a steel bottom plate 212, and a steel web plate 213. The steel web plate 213 is located between the steel top plate 211 and the steel bottom plate 212, and connects the steel top plate 211 and the steel bottom plate 212 respectively. The steel top plate 211 and the steel bottom plate 212 at one end of the second steel inner core 21 near the steel guide beam 3 are both provided with an extension wing 211a. The extension wing 211a extends out of the steel web plate 213. The extension wing 211a and the part of the steel top plate 211 / steel bottom plate 212 located inside the steel web plate are connected to the steel guide beam 3 and welded to fix them.

[0078] The second steel inner core 21 consists of three main parts: a steel top plate 211, a steel bottom plate 212, and a steel web plate 213. The steel top plate 211 and the steel bottom plate 212 are arranged vertically opposite each other, while the steel web plate 213 is located between the steel top plate 211 and the steel bottom plate 212, and connects both plates. Specifically, the steel web plate 213 is located on both sides of the steel top plate 211 and the steel bottom plate 212, and is vertically welded to both sides, forming a closed box-shaped steel frame. This closed box-shaped steel frame structure has good bending and torsional stiffness and overall stability, and can effectively bear various loads during the jacking construction process.

[0079] The second steel inner core 21, near the end of the steel guide beam 3, has an extension wing 211a on both its top steel plate 211 and bottom steel plate 212. The extension wing 211a extends outward from the outer side of the steel web 213. The purpose of the extension wing 211a is to provide sufficient overlap and welding working surface for the connection between the steel guide beam 3 and the second steel inner core 21.

[0080] During the docking connection, the extension wing 211a and the portion of the steel top plate 211 / steel bottom plate 212 located inside the steel web are docked and welded to the steel guide beam 3. Specifically, the side of the second steel inner core 21 closest to the steel guide beam 3 adopts a precise size matching design, the steel web 213 is aligned and welded to the guide beam web 33, and the heights of the steel bottom plate 212 and steel top plate 211 are aligned with the heights of the guide beam bottom plate and guide beam top plate of the steel guide beam 3, respectively, and then welded.

[0081] The extension wing 211a of the steel base plate 212 can extend to half the width of the guide beam base plate 32 (such as the widened section at the end), and the extension wing 211a of the steel top plate 211 can extend to half the width of the guide beam top plate 31 (such as the widened section at the end). The other half is formed by the connection between a portion of the steel top plate 211 / steel base plate 212 located inside the steel web and the top or bottom plate of the steel guide beam 3. The purpose of this dimensional configuration is to increase the connection surface, accurately adapt to the guide beam structure, ensure the uniform and smooth transmission of the horizontal jacking force and vertical shear force, and avoid stress concentration and poor force transmission caused by abrupt changes in cross-section.

[0082] Through the above structural design, precise alignment and reliable connection are achieved between the second steel inner core 21 and the steel guide beam 3. All jacking loads are borne and transmitted by the steel inner core, and the UHPC shell does not directly participate in the jacking force. Moreover, the UHPC shell near the steel guide beam 3 has a large thickness, avoiding the problem of UHPC surface layer damage under pressure from the source of the force transmission path. At the same time, the combined welding method of the extension wing 211a with the steel top plate 211 and steel bottom plate 212 located on the inner side plate segment of the steel web 213 increases the welding contact area, improves the connection strength and reliability, effectively avoids problems such as segment slippage, misalignment, and linear deviation, and significantly improves the jacking construction accuracy.

[0083] In some possible implementations, such as Figure 1 As shown, the side frames on both sides of the steel guide beam 3 include a guide beam top plate 31 and a guide beam bottom plate 32. The guide beam top plate 31 and the guide beam bottom plate 32 have a widened section 311 at one end near the connecting section combined box girder 2. The widened section 311 is welded to the corresponding extension wing 211a and the part of the steel top plate 211 / steel bottom plate 212 located inside the steel web 213.

[0084] The side frames on both sides of the steel guide beam 3 each include a top plate 31 and a bottom plate 32. The steel guide beam 3 is a temporary auxiliary component of a pure steel structure. During the jacking construction, the steel guide beam 3 bears significant bending moments and shear forces; therefore, its structural stiffness and strength are crucial for the smooth progress of the jacking construction. In this application, the top plate 31 and the bottom plate 32 of the guide beam have a widened section 311 near the end of the connecting section combined box girder 2. This widened section 311 is a structure formed by extending and widening the top plate 31 and the bottom plate 32 laterally outwards. The purpose of the widened section 311 is to increase the contact area between the steel guide beam 3 and the second steel inner core 21, thereby improving the reliability and load-bearing capacity of the connection.

[0085] The widened section 311 is welded to the corresponding extension wing 211a and the portion of the steel top plate 211 / steel bottom plate 212 located inside the steel web 213. The widened section 311 of the guide beam top plate 31 is welded to the extension wing 211a of the steel top plate 211 of the second steel inner core 21 and the portion of the steel top plate 211 located inside the steel web 213. The widened section 311 of the guide beam bottom plate 32 is welded to the extension wing 211a of the steel bottom plate 212 of the second steel inner core 21 and the portion of the steel bottom plate 212 located inside the steel web 213. Through this lap welding method, the welding length between the steel guide beam 3 and the second steel inner core 21 is significantly increased. Compared with the traditional end butt welding, the welding area is larger, the connection strength is higher, and the force transmission is smoother.

[0086] In some possible implementations, such as Figure 5 As shown, the extension wing 211a is only provided in the transition section 222 and the thickened section 221, and the width of the extension wing 211a in the thickened section 221 is constant. In the direction from the equal thickness section 223 to the thickened section 221, the extension wing 211a in the transition section 222 gradually widens at least locally. The thickness of the concrete web of the thickened section 221 is greater than the thickness of the concrete web of the equal thickness section 223. The thickness of the concrete web of the transition section 222 gradually increases at least locally.

[0087] like Figure 9As shown, the extension wing 211a is only provided in the transition section 222 and the thickened section 221 of the connecting section composite box girder 2, and is not provided in the equal thickness section 223. The extension wing 211a is a structure used for welding connection with the widened section 311 of the steel guide beam 3. However, the steel guide beam 3 is only connected to the end of the thickened section 221 of the connecting section composite box girder 2, so the extension wing 211a does not need to extend to the equal thickness section 223. At the same time, this design also helps to achieve a smooth transition of the shell thickness between the connecting section composite box girder 2 and the UHPC composite box girder 1.

[0088] The width of the extension wing 211a within the thickened section 221 remains constant. Since the UHPC shell of the thickened section 221 has the greatest thickness and the highest structural strength, it is the main stress-bearing area for the load transfer of the steel guide beam 3. The constant width of the extension wing 211a helps to ensure the uniformity and stability of the connection structure in this area and avoids local stress concentration caused by changes in width.

[0089] In the direction from the constant-thickness section 223 to the thickened section 221, the extension wing 211a within the transition section 222 gradually widens at least locally. Specifically, the width of the extension wing 211a in the transition section 222 gradually widens from zero width (or no width) on the side of the constant-thickness section 223 to a constant width on the side of the thickened section 221. This gradual widening design corresponds to the gradual increase in the thickness of the UHPC shell in the transition section 222, achieving a coordinated change in the structural width of the extension wing 211a and the thickness of the UHPC shell.

[0090] The thickness of the concrete web in the thickened section 221 is greater than that in the equal-thickness section 223. Specifically, the width of the web in the thickened UHPC shell section is 1.5 to 3 times the width of the web in the equal-thickness UHPC shell section. The thickness of the concrete web in the transition section 222 gradually increases, at least locally; that is, the thickness of the concrete web in the transition section 222 linearly transitions along the beam length from the dimension of the equal-thickness section 223 to the dimension of the thickened section 221. This linear transition design achieves a smooth change in the thickness of the concrete web from thin to thick, avoiding abrupt changes in stiffness and stress concentration caused by sudden thickness changes.

[0091] By coordinating the width of the extended wing 211a with the thickness of the concrete web of the UHPC shell, the composite box girder 2 in the connecting section achieves a synchronous and gradual transition between the steel structure and the UHPC structure within the transition section 222, ensuring a smooth transition in structural geometry and mechanical properties. This design effectively solves the problems of abrupt stiffness changes and stress concentration, making force flow transmission smoother and significantly improving the structural stability and crack resistance of the connecting section.

[0092] In some possible implementations, such as Figures 7 to 9As shown, the steel top plate 211 of the second steel inner core 21 includes a first top plate 2111, a second top plate 2112, and a third top plate 2113. The height of the first top plate 2111 is higher than that of the third top plate 2113. The second top plate 2112 is inclined and transitions from the first top plate 2111 to the third top plate 2113. The first top plate 2111 corresponds to the equal thickness section 223 and part of the transition section 222. The second top plate 2112 corresponds to the transition section 222. The third top plate 2113 corresponds to the thickened section 221. The gradually widening plate segments on the second top plate 2112 and the extension wing 211a are staggered.

[0093] The first top plate 2111 corresponds to the equal-thickness section 223, and its height is higher than that of the third top plate 2113. The first top plate 2111 has the same height as the steel core top plate of the UHPC composite box girder 1, ensuring a smooth connection of the steel core within the equal-thickness section 223. The third top plate 2113 corresponds to the thickened section 221, and its height is lower than that of the first top plate 2111. Since the thickness of the UHPC shell top plate in the thickened section 221 is greater than that in the equal-thickness section 223, in order to maintain the overall flatness of the top surface of the assembly, the steel top plate 211 is correspondingly reduced in height in the thickened section 221 to balance the height change caused by the increase in the thickness of the UHPC shell. The second top plate 2112 corresponds to the transition section 222, and it slopes from the first top plate 2111 to the third top plate 2113. The slope transition of the second top plate 2112 is coordinated with the gradual change in the thickness of the UHPC shell concrete top plate in the transition section 222 to jointly achieve a smooth transition of the top surface of the assembly.

[0094] The height of the first top plate 2111 is higher than that of the third top plate 2113, meaning that the height of the steel top plate 211 in the thickened section 221 is lower than that in the equal-thickness section 223. The purpose of this design is that the thickness of the UHPC shell concrete top plate in the thickened section 221 is greater than that in the equal-thickness section 223. If the height of the steel top plate 211 remains unchanged, the total height of the assembly at the thickened section 221 will increase, resulting in an uneven top surface. By reducing the height of the steel top plate 211 in the thickened section 221, the increased thickness of the UHPC shell concrete top plate at the thickened section 221 is offset by the reduced height of the steel top plate 211, ensuring a smooth transition between the upper surface of the second shell 22 and the upper surface of the first shell 12, resulting in a flush top surface of the assembly.

[0095] In this embodiment, the gradually widening plate segments on the second top plate 2112 and the extension wing 211a are staggered. Specifically, the starting / ending point of the inclination change in the height of the steel top plate 211 and the starting / ending point of the gradual widening of the width of the extension wing 211a are not at the same position along the beam length, but are offset from each other. The technical effect of this staggered arrangement is to avoid the superposition of geometrical abrupt changes and stress concentrations. If the change in the height of the top plate and the change in the width of the extension wing 211a occur simultaneously at the same cross-section, that cross-section will simultaneously bear double stress concentration caused by the changes in height and width, which is extremely detrimental to the structural stress. By staggering the two, the changes in height and width occur at different cross-sections, dispersing the stress concentration effect, making the structural stress more uniform and reasonable, and further improving the fatigue performance and durability of the connection section.

[0096] In some possible implementations, the box girder guide beam assembly includes reinforcing steel bars 4, and holes are provided on the extension wing 211a of the steel top plate 211. Part of the reinforcing steel bars 4 are inserted through the holes and supported at the bottom on the extension wing 211a of the steel bottom plate 212. The inner diameter of the holes is larger than the outer diameter of the reinforcing steel bars 4.

[0097] Reinforcing steel bar 4 is a steel reinforcement structure arranged inside the UHPC shell. Its main functions include: further improving the crack resistance of the UHPC shell, enhancing the overall structural integrity, and increasing the load-bearing capacity of the connection sections. Reinforcing steel bar 4, together with the steel cage, forms the steel reinforcement skeleton of the UHPC shell, effectively constraining the shrinkage deformation of the UHPC material and improving the structure's toughness and crack resistance.

[0098] Holes are provided on the extension wings 211a of the steel top plate 211. These holes are pre-drilled through holes in the steel top plate 211. The holes serve three purposes: first, they provide an installation channel for the reinforcing steel bar 4: the reinforcing steel bar 4 passes through the holes from above the steel top plate 211 and is inserted, enabling its positioning and installation; second, the holes serve as channels for the pouring of UHPC material, ensuring that the UHPC material can smoothly fill all parts between the upper and lower extension wings 211a of the second steel inner core 21, ensuring dense pouring; and third, during the UHPC pouring process, the holes serve as venting channels, effectively expelling internal air and avoiding construction defects such as voids and insufficient density.

[0099] Part of the reinforcing steel bar 4 is inserted through holes in the extension wing 211a of the steel top plate 211, and its bottom is supported on the extension wing 211a of the steel bottom plate 212. That is, the reinforcing steel bar 4 passes through the extension wing 211a of the steel top plate 211 in a vertical (or approximately vertical) direction, and its lower end abuts against the upper surface of the extension wing 211a of the steel bottom plate 212, providing bottom support through the extension wing 211a of the steel bottom plate 212.

[0100] The inner diameter of the hole can be larger than the outer diameter of the reinforcing steel bar 4, meaning the hole size is larger than the diameter of the steel bar. Preferably, the diameter of hole a (or construction hole) is 3 to 10 times the diameter of the reinforcing steel bar 4. This large-size hole design facilitates the insertion and positioning of the reinforcing steel bar 4, reduces construction difficulty, improves installation efficiency, provides sufficient flow channels for UHPC pouring, ensures pouring quality, and facilitates venting and leveling operations during the pouring process.

[0101] This application achieves the installation and positioning of the reinforcing steel bar 4 and the pouring and flow of UHPC through the pre-reserved holes on the extension wing 211a, realizing the multi-functional integration of a single hole. The large-size hole design effectively avoids construction defects such as pouring voids and insufficient density, significantly improving the forming quality and construction efficiency of the connection section.

[0102] In some possible implementations, a steel inclined plate 214 is provided between the steel top plate 211 and the steel web plate 213 of the second steel inner core 21. Within the transition section 222 and the thickened section 221, a cavity b is formed between the steel inclined plate 214, the steel top plate 211, and the steel web plate 213. The cavity b is located outside the cavity of the second steel inner core and has an opening facing the equal thickness section. A hole a is provided on the steel top plate 211 to communicate with the cavity b. Part of the reinforcing steel bar 4 passes through the hole a and its bottom end abuts against the steel inclined plate 214.

[0103] like Figures 7 to 10 As shown, a steel inclined plate 214 is provided between the steel top plate 211 and the steel web plate 213 of the second steel inner core 21. The steel inclined plate 214 is a reinforcing transition plate inclinedly set in the corner connection area between the steel top plate 211 and the steel web plate 213. One end of it is connected to the steel top plate 211, and the other end is connected to the steel web plate 213, forming a triangular support structure. The steel inclined plate 214 is used to enhance the stiffness and strength of the connection node between the steel top plate 211 and the steel web plate 213, improve the stress distribution in the corner area, reduce stress concentration, and improve the overall torsional stiffness and buckling resistance of the steel inner core.

[0104] like Figure 9 and Figure 10As shown, the extension wing 211a can be understood as an extension plate segment extending from the edge of the steel top plate or steel bottom plate to the steel web plate. Within the equal thickness section, the steel inclined plate 214 connects the edges of the steel top plate 211 and the steel web plate 213 on both sides respectively. The steel top plate 211 and the steel web plate 213 do not extend beyond the steel inclined plate 214. Within the transition section 222 and the thickened section 221, steel inclined plates 214 connect the steel top plate 211 and the steel web plate 213 near the edge but not at the edge, respectively. Both the steel top plate 211 and the steel web plate 213 extend beyond the steel inclined plates 214. The section of the steel top plate 211 located between the steel inclined plates 214 and the steel web plate 213 forms the top surface of cavity b. The section of the steel top plate extending beyond the steel web plate 213 forms the extension wing 211a. The section of the steel web plate 213 extending beyond the steel inclined plates 214 forms the side surface of cavity b. The steel inclined plates 214 form the inclined bottom surface of cavity b. Together, these three elements enclose a closed or semi-closed cavity b structure. This cavity can accommodate UHPC material during UHPC casting, allowing UHPC to fill the interior of cavity b, forming a steel-UHPC composite structure.

[0105] A hole a is provided on the steel top plate 211 to connect to the cavity, which serves as an installation channel for the reinforcing steel bar 4, allowing the reinforcing steel bar 4 to pass through the steel top plate 211 and enter the cavity. The hole also serves as a pouring channel for UHPC material to enter the cavity, ensuring that the cavity is fully filled with UHPC. The hole also serves as an exhaust channel during the pouring process.

[0106] Part of the reinforcing steel bar 4 is inserted into the hole, and its bottom end abuts against the steel inclined plate 214. That is, the reinforcing steel bar 4 passes through the hole from above the steel top plate 211 into the cavity, and its lower end abuts against the upper surface of the steel inclined plate 214, which provides bottom support. The steel inclined plate 214 serves as the bottom support structure for the reinforcing steel bar 4.

[0107] This application, by setting a steel inclined plate 214 between the steel top plate 211 and the steel web plate 213, not only enhances the stiffness and strength of the steel core node area and improves the stress performance of the corner area, but also utilizes the cavity formed between the steel inclined plate 214, the steel top plate 211, and the steel web plate 213 to provide installation space and bottom support for the reinforcing steel bar 4. This integrated structural design achieves the dual functions of structural strengthening and steel bar installation, improving structural efficiency and construction convenience.

[0108] In some possible implementations, the box girder guide beam assembly includes a reinforcing support 5, and a second steel inner core 21 with an end plate 215 near one end of the steel guide beam 3. The end plate 215 is a closed plate. The steel guide beam 3 includes a guide beam web 33 connecting the guide beam top plate 31 and the guide beam bottom plate 32. The guide beam web 33 and the steel web 213 are welded and fixed. The reinforcing support 5 is located between the guide beam web 33 and the end plate 215, and is welded to the guide beam web 33 and the end plate 215 respectively.

[0109] Reinforcing supports 5 are installed between the steel guide beam 3 and the connecting section composite box girder 2. Specifically, two sets of reinforcing supports 5 are symmetrically arranged at the connection points of the left and right webs of the steel guide beam 3 and the connecting section composite box girder 2. The purpose of installing reinforcing supports 5 is to locally reinforce the connection transition section between the steel guide beam 3 and the connecting section composite box girder 2, ensure the integrity of the force transmission structure, achieve a smooth transition of stiffness, and suppress the shaking, warping, and deformation of the beam during the jacking process.

[0110] An end plate 215 is provided at one end of the second steel inner core 21 near the steel guide beam 3. The end plate 215 is a closed plate. The end plate 215 is located at the end of the second steel inner core 21, specifically at the interface where the connecting section of the combined box girder 2 connects to the steel guide beam 3. The end plate 215 is a closed plate structure without any manholes and is a solid plate structure. The end plate 215 serves as a sealing plate and reinforcing structure at the end of the second steel inner core 21, improving the rigidity and overall integrity of the end. As a force-transmitting component connected to the steel guide beam 3, the end plate 215 evenly transfers the load transmitted by the steel guide beam 3 to the second steel inner core 21. The end plate 215 also serves as the welding base for the reinforcing support 5, providing a reliable welding connection surface for the reinforcing support 5.

[0111] The steel guide beam 3 includes a guide beam web 33 connecting the top plate 31 and the bottom plate 32. The guide beam web 33 is the main vertical load-bearing component of the side frames on both sides of the steel guide beam 3, bearing the main shear force and bending moment. The guide beam web 33 and the steel web 213 are welded together. That is, the guide beam web 33 of the steel guide beam 3 is fixedly connected to the steel web 213 of the second steel inner core 21 by welding. Specifically, butt welding is used; the steel web 213 is welded to the guide beam web 33 after complete alignment, ensuring that the horizontal pushing force and vertical shear force are directly and uniformly transmitted through the web.

[0112] The reinforcing support 5 is located between the web 33 of the guide beam and the end plate 215, and is welded to the web 33 and the end plate 215 respectively. That is, the reinforcing support 5 spans between the web 33 of the steel guide beam 3 and the end plate 215 of the second steel inner core 21, with one end welded to the inner side of the web 33 and the other end welded to the outer side of the end plate 215, forming a supporting and reinforcing member connecting the two.

[0113] Each reinforcing support 5 comprises two vertically arranged steel plates 51 and multiple horizontally arranged steel plates 52. The height of the horizontally arranged steel plates 52 is exactly the same as the height of the stiffening ribs 217 of the steel guide beam 3. The two vertical steel plates are connected at an angle to each other and are arranged longitudinally between the web plate 33 and the end plate 215 of the guide beam, with one end welded to the web plate 33 and the other end welded to the end plate 215, forming a vertical support. The multiple horizontal steel plates are welded between the two vertical steel plates, forming a transverse connection. The height of the horizontal steel plates is the same as the height of the stiffening ribs 217 of the steel guide beam 3 and they are welded together, ensuring the vertical alignment of the reinforcing support 5 and the stiffening ribs 217 of the steel guide beam 3, and achieving a continuous transition of stiffness.

[0114] This application achieves a smooth transition in stiffness between the steel guide beam 3 and the connecting composite box girder 2 by setting symmetrical reinforcing supports 5, thus preventing abrupt changes in stress during the jacking process. The combined welding of the reinforcing supports 5 with the end plates 215 and the guide beam web 33 forms a reliable local reinforcement system, effectively suppressing beam vibration, warping, and deformation during the jacking process and improving the overall stability of the transition section 222. The consistent matching of the height of the horizontal steel plate with the height of the guide beam stiffening ribs 217 ensures the coordinated work of the reinforcing supports 5 and the guide beam stiffening ribs 217, achieving a continuous transition in stiffness. The symmetrical arrangement of two sets of reinforcing supports 5 ensures balanced stress at the connection between the left and right webs, avoiding eccentric loading and torsion problems caused by uneven stress on one side.

[0115] In some possible implementations, the second steel inner core 21 includes a steel diaphragm 216, stiffening ribs 217 and steel ribs 218. The steel diaphragm 216 is located within the cavity of the second steel inner core 21 and is connected to the steel top plate 211, steel bottom plate 212 and steel web plate 213 of the second steel inner core 21. The steel diaphragm 216 is provided with a manhole. The stiffening ribs 217 are connected to the steel bottom plate 212 and are perpendicular to the steel diaphragm 216. The steel ribs 218 are parallel to the steel diaphragm 216 and are welded to the steel top plate 211.

[0116] The steel diaphragm 216 is located within the cavity of the second steel inner core 21 and connects to the steel top plate 211, steel bottom plate 212, and steel web plate 213 of the second steel inner core 21. The steel diaphragm 216 is a transverse partition installed inside the steel inner core box, with its outer edge welded and fixed to the inner walls of the steel top plate 211, steel bottom plate 212, and the two side steel web plates 213, dividing the interior of the steel inner core into several independent compartments along the beam length. Manholes are provided on the steel diaphragm 216. These manholes are passageways located in the middle of the steel diaphragm 216, and their dimensions should meet the passage requirements of construction and maintenance personnel. The manholes allow construction personnel to move between the compartments inside the steel inner core, facilitating reinforcement placement, welding operations, and equipment maintenance. The steel diaphragm 216 with manholes has symmetrically arranged stiffening ribs 217 on both sides, ensuring structural rigidity while meeting passage requirements.

[0117] Preferably, steel diaphragms without manholes (i.e., end plates 215 mentioned above) and steel diaphragms with manholes are arranged at intervals along the length of the beam inside the steel core. The steel diaphragms without manholes are solid plate structures with stiffening ribs 217 arranged on one side, concentrated at key stress-bearing sections such as the jacking critical section and the support section, to ensure uniform diffusion and overall transmission of the jacking load; the steel diaphragms 216 with manholes are arranged in non-critical stress-bearing sections, taking into account passage requirements while meeting structural stiffness requirements.

[0118] Stiffening ribs 217 are connected to the steel base plate 212 and are perpendicular to the steel transverse diaphragm 216. Specifically, multiple stiffening ribs 217 are longitudinally welded to the bottom of the steel base plate 212. The stiffening ribs 217 are arranged along the entire length of the beam and intersect the steel transverse diaphragm 216 perpendicularly. The installation of stiffening ribs 217 on the steel base plate 212 significantly improves the out-of-plane stiffness and buckling resistance of the steel base plate 212, avoiding local deformation of the base plate during the jacking and sliding process.

[0119] In this application, the steel transverse ribs 218 are parallel to the steel transverse diaphragms 216 and welded to the steel top plate 211. The steel transverse ribs 218 are arranged inside the steel core, spaced apart along the length of the beam, and are used to connect the steel top plate 211. The steel transverse ribs 218 and the steel transverse diaphragms 216 are arranged in parallel. The difference between the two is that the steel transverse ribs 218 do not have manholes and are solid plate structures. The setting of the steel transverse ribs 218 can significantly improve the overall torsional stiffness and spatial integrity of the steel core.

[0120] A steel transverse diaphragm (end plate 215) without manholes with single-sided stiffening ribs 217 is arranged in the key stress section of the jacking operation to ensure uniform and concentrated load transfer. In the conventional section, a steel transverse diaphragm 216 with manholes and double-sided stiffening ribs 217 is arranged to meet the overall rigidity requirements while also accommodating the needs of construction and maintenance passage within the box girder. The densely arranged steel transverse ribs 218 connect the steel top plate 211, steel bottom plate 212, and steel web plate 213, and the stiffening ribs 217 of the steel bottom plate 212 enhance the rigidity of the bottom plate, comprehensively improving the overall bending, torsional, and buckling resistance of the steel core. The structural layout is scientific and reasonable, suitable for long-distance, high-tonnage jacking construction conditions.

[0121] This application also provides an assembly method for the box girder guide beam assembly, including the following steps:

[0122] Step S1: Factory prefabricate steel guide beam 3, first steel inner core and second steel inner core; evenly distribute shear connectors 6 on the outer surface of the first steel inner core and second steel inner core; pre-reserve holes in the second steel inner core.

[0123] The steel guide beam 3, the first steel inner core, and the second steel inner core are prefabricated in the factory. Specifically, the steel inner core skeleton (including the first and second steel inner cores) is integrally welded, and shear connectors 6 are evenly distributed on the outer surface of the steel inner core. Holes are pre-drilled in the second steel inner core, and the prefabricated components are then precision-machined. The advantages of factory prefabrication are: high processing precision, controllable quality, and no limitation by on-site construction conditions, which can effectively ensure the welding quality and dimensional accuracy of the steel inner core skeleton. The shear connectors 6 are arranged in the factory, which ensures their accurate positioning and reliable welding quality. The pre-drilled holes in the factory avoid potential damage and accuracy deviations to the structure caused by on-site drilling.

[0124] Step S2: Transport the prefabricated components to the construction site, accurately align and install the steel guide beam 3, the first steel inner core and the second steel inner core, and complete the initial connection and fixation. Then, symmetrically assemble two sets of reinforcing supports 5 at the connection between the steel guide beam 3 and the second steel inner core on both sides of the steel web 213 to complete the local reinforcement of the transition section 222 and ensure the integrity of the force transmission structure.

[0125] The prefabricated components are transported to the construction site, and the steel guide beam 3, the first steel inner core, and the second steel inner core are precisely aligned and installed, then welded together to complete the initial connection and fixation. Specifically, the first and second steel inner cores are welded and fixed, and the steel guide beam 3 is welded to the second steel inner core to achieve the overall connection of the internal steel frame. Subsequently, two sets of reinforcing supports 5 are symmetrically installed at the connection points of the steel webs 213 on both sides of the steel guide beam 3 and the second steel inner core to complete the local reinforcement of the transition section 222 and ensure the integrity of the force transmission structure. The installation of the reinforcing supports 5 is carried out after the initial connection of the steel frame. The reinforcing supports 5 provide additional reinforcement to the connection transition section, further improving the connection stiffness and stability.

[0126] Step S3: Insert reinforcing steel bars 4 of the corresponding length into the holes of the second steel core, and tie and fix the steel cage according to the specifications. Then, pour the UHPC material as a whole and vent and level it to complete the overall assembly construction.

[0127] Insert reinforcing bars 4 of the corresponding length into the holes of the second steel inner core, and tie and fix the reinforcing cage according to the specifications. The reinforcing bars 4 are inserted into the steel inner core through the pre-set holes a of the steel top plate 211, and the bottom is supported on the steel bottom plate 212 or the steel inclined plate 214 to achieve precise positioning.

[0128] Following this, the UHPC material was poured and vented for leveling. The UHPC material was poured through pre-set construction channels in the steel top plate 211. Under its own weight and pressure, the material filled all parts of the steel core, including the cavities between the steel inclined plate 214 and the steel top plate 211, and the steel web plate 213. Venting was carried out through the channels during pouring to ensure the UHPC material was dense and free of voids. After standard curing, the integrated connecting section composite box girder 2 was formed, completing the overall assembly construction.

[0129] In this application, the construction mode of factory prefabrication, on-site assembly, and integral casting is simple in process, avoids welding heat damage, and eliminates the need for long curing periods, highly adapting to the development trend of rapid construction of prefabricated bridges. The reinforcement bars are positioned and installed, and the UHPC is cast, through the 211 holes a in the steel top plate, effectively avoiding construction defects such as voids and insufficient density, significantly improving forming quality and construction efficiency. The steel core bears the entire jacking load, while the UHPC shell serves only as a protective structure, completely avoiding the problem of UHPC surface layer damage under pressure in traditional processes. The construction process of this application is scientifically sound, forming the steel frame integrally before casting the UHPC, ensuring the connection quality of the steel structure and the casting quality of the UHPC, resulting in good structural integrity and high reliability.

[0130] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention in any way. Although the present invention has been disclosed above with reference to preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art can make some modifications or alterations to the above-described technical content to create equivalent embodiments without departing from the scope of the present invention. Any simple modifications, equivalent changes, and alterations made to the above embodiments based on the technical essence of the present invention without departing from the scope of the present invention shall still fall within the scope of the present invention.

Claims

1. A box girder guide beam assembly, characterized in that, include: UHPC composite box girder, having a first steel inner core and a first outer shell covering part of the first steel inner core; A connecting section composite box girder includes a second steel inner core and a second outer shell covering part of the second steel inner core. The second outer shell has a thickened section, a transition section, and a section of equal thickness arranged sequentially. The thickness of the section of equal thickness is equal to the thickness of the first outer shell. The section of equal thickness and the first outer shell are smoothly connected. The first steel inner core and the second steel inner core are welded and fixed. The thickness of the thickened section is greater than the thickness of the first outer shell. The upper surface of the second outer shell and the upper surface of the first outer shell are smoothly transitioned. The thickness of the transition section gradually transitions from the section of equal thickness to the thickened section. A steel guide beam is located on the side of the thickened section of the connecting section combined box girder away from the equal-thickness section, and the steel guide beam is welded to the second steel inner core.

2. The box girder guide beam assembly according to claim 1, characterized in that, The second steel inner core includes a steel top plate, a steel bottom plate, and a steel web plate; The steel web is located between the steel top plate and the steel bottom plate, and connects the steel top plate and the steel bottom plate respectively; The second steel inner core has an extension wing on its top and bottom plates near the steel guide beam, which extends out of the steel web. The extended wing and the portion of the steel top / bottom plate located inside the steel web are connected to and welded to the steel guide beam.

3. The box girder guide beam assembly according to claim 2, characterized in that, The side frames on both sides of the steel guide beam each include a guide beam top plate and a guide beam bottom plate, and the guide beam top plate and guide beam bottom plate have a widened section at the end near the connecting section combined box girder; The widened section is welded to the corresponding extended wing and the portion of the steel top / bottom plate located inside the steel web.

4. The box girder guide beam assembly according to claim 3, characterized in that, The extended wing is only provided within the transition section and the thickened section, and the width of the extended wing within the thickened section is constant; In the direction from the equal-thickness section to the thickened section, the extended wing in the transition section gradually widens at least locally, the thickness of the concrete web of the thickened section is greater than the thickness of the concrete web of the equal-thickness section, and the thickness of the concrete web of the transition section gradually increases at least locally.

5. The box girder guide beam assembly according to claim 4, characterized in that, The steel top plate of the second steel inner core includes a first top plate, a second top plate, and a third top plate; The height of the first top plate is higher than that of the third top plate; The second top plate slopes and transitions from the first top plate to the third top plate; The first top plate corresponds to the equal-thickness section and part of the transition section, the second top plate corresponds to the transition section, and the third top plate corresponds to the thickened section; The second top plate and the gradually widening plate segments on the extended wing are staggered.

6. The box girder guide beam assembly according to claim 5, characterized in that, Including reinforcing steel bars; Holes are provided on the extended wing of the steel top plate; Some of the reinforcing bars are inserted through the holes and supported at the bottom on the extended wing of the steel base plate; The inner diameter of the hole is larger than the outer diameter of the reinforcing steel bar.

7. The box girder guide beam assembly according to claim 6, characterized in that, A steel inclined plate is provided between the steel top plate and the steel web plate of the second steel inner core; Within the transition section and the thickened section, a cavity is formed between the steel inclined plate, the steel top plate, and the steel web plate. The cavity is located outside the cavity of the second steel inner core and has an opening facing the equal-thickness section. The steel top plate is provided with holes that communicate with the cavity; Some of the reinforcing bars are inserted into the holes, and their bottom ends abut against the inclined steel plate.

8. The box girder guide beam assembly according to claim 1, characterized in that, This includes strengthening support; An end plate is provided at one end of the second steel inner core near the steel guide beam, and the end plate is a closed plate. The steel guide beam includes a web plate that connects the top plate and the bottom plate of the guide beam; The guide beam web and the steel web are welded and fixed together. The reinforcing support is located between the web of the guide beam and the end plate, and is welded to the web of the guide beam and the end plate respectively.

9. The box girder guide beam assembly according to claim 2, characterized in that, The second steel inner core includes steel transverse diaphragms, stiffening ribs, and steel transverse ribs; The steel diaphragm is located inside the cavity of the second steel inner core and is connected to the steel top plate, steel bottom plate and steel web of the second steel inner core respectively. The steel diaphragm is provided with a manhole. The stiffening rib is connected to the steel base plate, and the stiffening rib is perpendicular to the steel transverse diaphragm; The steel transverse ribs are parallel to the steel transverse diaphragm and are welded to the steel top plate.

10. The assembly method of the box girder guide beam assembly as described in any one of claims 1-9, characterized in that, Includes the following steps: Step S1: Prefabricate steel guide beams, first steel inner core and second steel inner core in the factory; evenly distribute shear connectors on the outer surfaces of the first steel inner core and second steel inner core; pre-reserve holes in the second steel inner core. Step S2: Transport the prefabricated components to the construction site, accurately align and install the steel guide beam, the first steel inner core and the second steel inner core to complete the initial connection and fixation, and then symmetrically assemble two sets of reinforcing supports at the connection between the steel guide beam and the second steel inner core on both sides of the steel web to complete the local reinforcement of the transition section and ensure the integrity of the force transmission structure. Step S3: Insert reinforcing bars of the corresponding length into the holes of the second steel core, and tie and fix the reinforcing cage according to the specifications. Then, pour the UHPC material as a whole and vent and level it to complete the overall assembly construction.