Construction device and construction method for side walls of narrow corridors

By introducing a rebar cage moving installation platform, a vibrating assembly, and a probe assembly into the construction device for the side walls of narrow corridors, automatic insertion and vibration of the vibrating rod are achieved, solving the problem of difficulty in ensuring the insertion depth of the vibrating rod in narrow spaces, and improving construction safety and concrete quality.

CN123109202APending Publication Date: 2026-11-17SHANDONG HUITONG CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611164972.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-03
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

During the construction of the side walls of narrow corridors, it is difficult to guarantee the insertion depth of the vibrator, resulting in incomplete concrete compaction and quality defects such as local under-vibration and missing vibration, which affect the integrity and load-bearing capacity of the structure.

Method used

A construction device was designed, including a rebar cage moving installation platform, a vibrating assembly, a positioning guide, and a probe assembly. The vibrating rod is raised, lowered, and moved by a controller to ensure that the vibrating rod is automatically inserted in a narrow space and avoids collision with the rebar.

Benefits of technology

It enables automatic vibration of the side walls of narrow corridors, reduces labor intensity, improves construction safety, ensures the compactness and quality of concrete, and avoids collision and interference between the vibrator and the reinforcing steel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109202A_ABST
    Figure CN123109202A_ABST
Patent Text Reader

Abstract

This invention provides a construction device and method for constructing a side wall of a narrow corridor. The construction device includes: a movable mounting platform, a vibration assembly, a positioning guide probe assembly, and a controller. The movable mounting platform is slidably mounted on a top guide rail and is equipped with a walking drive mechanism. The vibration assembly, mounted on the movable mounting platform, includes a vibrating rod that is vertically and flexibly mounted on the platform. The positioning guide is fixedly mounted at the bottom of the movable mounting platform and has a guide hole coaxial with the vibrating rod. The probe assembly is located on the side of the positioning guide facing the reinforcing cage and includes a probe for detecting the presence of reinforcing steel below. The controller is signal-connected to the probe assembly, the walking drive mechanism, and the vibration assembly. This application enables automatic vibration.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the field of corridor construction, and more specifically, to a construction device and method for the side wall of a narrow corridor. Background Technology

[0002] Open-cut double-layer tunnels typically have a narrow maintenance and evacuation corridor in the middle, with large-volume concrete sidewalls on both sides. Due to the limitations of the tunnel's structural layout, the interior space of the corridor is extremely small, and the sidewalls need to be poured to a great depth, which brings many difficulties to the construction of the concrete sidewalls.

[0003] Due to the narrow corridor space and the large depth of the side wall pouring, each layer of concrete from top to bottom needs to be vibrated to ensure compaction. When operating manually, it is difficult to guarantee the insertion depth of the vibrator and the vibration points are not fully covered. This easily leads to problems such as local missed vibration and under-vibration, resulting in quality defects such as non-compact concrete, voids, or honeycomb surface, which seriously affect the integrity and load-bearing capacity of the side wall structure. Summary of the Invention

[0004] This application provides a construction device and method for the side wall of a narrow corridor, which can achieve automatic vibration compaction.

[0005] Specifically, this application is implemented through the following technical solution: One aspect of this application provides a construction device for a narrow corridor side wall, the corridor side wall including a steel cage movable installation platform, placed above the steel cage and having a walking drive mechanism at the bottom; A vibratory assembly, mounted on the movable mounting platform, includes a vibratory rod that can be raised and lowered; A positioning guide is placed at the bottom of the movable mounting platform and has a guide hole for the vibrator to pass through; A probe assembly is positioned on the side of the positioning guide facing the rebar cage, and the probe assembly includes a probe for detecting whether there is rebar below; The controller is connected to the probe assembly, the walking drive mechanism, and the vibrating assembly respectively; the controller is configured to control the movement and stopping of the mobile mounting platform and the raising and lowering of the vibrating rod in response to the detection signal of the probe assembly.

[0006] Optionally, the construction device further includes a top guide rail, configured to be fixed along the length of the corridor sidewall and located above the reinforcing cage; The mobile mounting platform is slidably mounted on the top guide rail, and the walking drive mechanism is configured to drive the mobile mounting platform to move along the top guide rail. The guide hole is coaxially arranged with the vibrating rod, and the inner diameter of the guide hole is larger than the outer diameter of the vibrating rod, so that the vibrating rod can pass through. The probe is a retractable contact probe, and the detection end of the probe extends into the mesh gap of the steel mesh structure cage.

[0007] Optionally, the vibrating assembly further includes a flexible shaft, a vibrating motor, and a reel, wherein the vibrating motor is connected to the vibrating rod via the flexible shaft; The reel is rotatably mounted on the mobile mounting platform. The vibratory motor is fixed to the reel and rotates with it. The flexible shaft is wound around the outer circumference of the reel. When the reel is driven to rotate, it drives the flexible shaft to unwind or rewind, thereby driving the vibratory rod to descend or rise.

[0008] Optionally, the height of the guide hole along its axial direction of the positioning guide is 200mm to 400mm, and the inner diameter of the guide hole is larger than the outer diameter of the vibrator and the flexible shaft.

[0009] Optionally, the walking drive mechanism includes an active component and a driven component, and along the length direction of the top guide rail, the active component and the driven component are respectively disposed on opposite sides of the positioning guide; The top guide rail includes a first guide rail and a second guide rail arranged in parallel, and both the first guide rail and the second guide rail are provided with a rack structure. The active component includes an active gear shaft, a transmission component, and a drive motor. The drive motor is fixed on the movable mounting platform and is connected to the active gear shaft via the transmission component. The active gear shaft extends along the width direction of the top guide rail. The two ends of the active gear shaft are respectively provided with a first gear part and a second gear part. The first gear part meshes with a rack on the first guide rail, and the second gear part meshes with a rack on the second guide rail. The driven component includes a driven slider, which slides in cooperation with the first guide rail and the second guide rail respectively.

[0010] Optionally, the top guide rail further includes two stops, which are respectively disposed on the side of the first guide rail and the second guide rail that are close to each other. The stops are continuously disposed along the length direction of the top guide rail, and the stops are provided with elongated clearance slots extending along the length direction of the top guide rail. The drive gear shaft passes through the clearance slots.

[0011] Optionally, the probe assembly includes two contact probes, which are distributed on both sides of the guide hole along the length of the top guide rail; The positioning guide is provided with a telescopic hole, and the contact probe is slidably inserted into the telescopic hole. An elastic element is provided in the telescopic hole. One end of the elastic element is connected to the positioning guide, and the other end is connected to the contact probe, which is used to keep the detection end of the contact probe in an extended state. The detection end of the contact probe is provided with a pushing slope on both sides along the length of the top guide rail. The pushing slope is used to guide the probe to overcome the elastic force of the elastic element and retract into the telescopic hole when it comes into contact with the steel bar during the movement of the probe.

[0012] Another aspect of this application provides a construction method for a narrow corridor sidewall, using the construction device for a narrow corridor sidewall as described in any of the preceding claims. The probe assembly includes two contact probes, which are distributed along the length of the top guide rail on both sides of the guide hole. The construction method includes: The walking drive mechanism is controlled to drive the mobile mounting platform to move along the top guide rail a first preset distance to reach the target working position. The first preset distance is the distance between two adjacent vibration operation positions. After the mobile mounting platform reaches the target working position, the detection signals of the two contact probes are read: If neither of the two contact probes makes contact with the reinforcing bar, it is determined that the guide hole of the positioning guide is aligned with the grid hole of the reinforcing bar cage. The vibration assembly is then controlled to descend, allowing the vibrator to pass through the guide hole and vibrate the concrete layer. If at least one of the contact probes comes into contact with the reinforcing bar, it is determined that the guide hole is not aligned with the grid hole. The walking drive mechanism is then controlled to fine-tune the position of the mobile mounting platform until neither of the two contact probes comes into contact with the reinforcing bar. Then, the vibrator is controlled to descend and vibrate.

[0013] Optionally, during the movement of the mobile mounting platform along the top guide rail, the number of steel bars passed by the two contact probes along the direction of the top guide rail is counted according to the number of times the two contact probes are triggered by the steel bars pressing and shrinking. After the mobile mounting platform reaches the target working position: If the two contact probes trigger the same number of times, it is determined that the moving installation platform is moving normally, and the vibration assembly is controlled to descend for vibration. If the number of triggers of the two contact probes is different, it is determined that the movable mounting platform is offset, and one of the contact probes is triggered less than the other. When the number of triggers of the contact probe located behind along the moving direction of the top guide rail is less than that of the contact probe in front. The walking drive mechanism is controlled to continue moving along the original direction of movement a second preset distance, which is equal to the theoretical spacing between adjacent steel bars of the steel cage, so that the contact probe located behind is triggered again until the number of triggers of the two contact probes is the same. If, after moving the second preset distance, the number of triggers of the two contact probes is still different, or the contact probe located at the rear still cannot be triggered, then an alarm signal will be issued.

[0014] Optionally, the steel cage of the corridor side wall is provided with the following components from the outside to the inside of the corridor: a concrete layer, a temperature control cooling pipe network system, a crack-resistant reinforcing steel mesh and temperature reinforcement system, a heat insulation buffer fireproof transition layer, and an outer fireproof protective surface layer. The steel cage is equipped with three sets of temperature sensors along the height of the side wall, which are respectively arranged at the upper, middle and lower parts of the side wall. Each set of temperature sensors includes three temperature measuring points embedded in the interior, middle and surface of the side wall, which are used to monitor the temperature distribution during the pouring and curing of large-volume concrete.

[0015] This application provides a construction device and method for constructing a side wall in a narrow corridor. The technical advantages of this application include at least: 1. This application utilizes a top guide rail and a mobile installation platform to allow the vibratory compaction assembly to automatically travel along the length of the side wall to each compaction station. Combined with the vibratory rod, which can be raised and lowered on the mobile installation platform, automatic insertion and compaction of the vibratory rod can be achieved without personnel entering the narrow corridor cavity. This replaces the traditional method of manually holding the vibratory rod to enter the cavity, solving the technical problem of personnel being unable to enter or having difficulty operating it after entering during the construction of narrow corridor side walls, reducing labor intensity, and improving construction safety.

[0016] 2. Due to the limited mesh spacing in the reinforcing cage of the side wall steel mesh structure, the vibrator must pass through the mesh gaps when descending. Direct descent can easily result in collisions with the reinforcing bars, preventing the vibrator from reaching the vibration position or even damaging the equipment. This application incorporates a contact probe on the positioning guide. The probe's detection end extends into the mesh gap of the steel mesh structure to detect the presence of reinforcing bars below the probe in real time. Based on the probe's detection signal, the controller only allows the vibrator to descend when the positioning guide is directly facing the mesh hole, i.e., when the probe is not in contact with the reinforcing bars. This achieves automatic determination of the vibrator's descent path, ensuring that the vibrator can smoothly pass through the steel mesh structure's reinforcing cage to reach the concrete layer for vibration, avoiding collisions and interference between the vibrator and the reinforcing bars. Attached Figure Description

[0017] Figure 1 This is a schematic cross-sectional view of a corridor sidewall shown in an exemplary embodiment of this application; Figure 2This is a schematic diagram of a construction apparatus shown in an exemplary embodiment of this application; Figure 3 yes Figure 2 A magnified view of a portion of the image; Figure 4 This is an internal view of a mobile mounting platform illustrated in an exemplary embodiment of this application; Figure 5 This is a bottom schematic diagram of a positioning guide shown in an exemplary embodiment of this application; Figure 6 This is a schematic diagram of a probe assembly shown in an exemplary embodiment of this application; Figure 7 This is an exemplary embodiment of the present application illustrating the installation of a reinforcing cage and a cooling pipe network system.

[0018] Among them: A1, reinforced steel mesh structure; A2, concrete layer; A3, temperature-controlled cooling pipe network system; A4, crack-resistant reinforced steel and temperature-resistant steel bar system; A5, heat-insulating buffer fireproof transition layer; A6, outer fireproof protective surface layer; 100, top guide rail; 110, first guide rail; 120, second guide rail; 130, stop; 200, mobile mounting platform; 210, walking drive mechanism; 211, active component; 2111, active gear shaft; 211 1a. First gear section; 2111b. Second gear section; 2112. Transmission assembly; 2113. Drive motor; 212. Driven assembly; 300. Vibration assembly; 310. Vibrating rod; 320. Flexible shaft; 330. Vibration motor; 340. Reel; 400. Positioning guide; 410. Guide hole; 420. Telescopic hole; 421. Elastic element; 500. Probe assembly; 510. Contactable probe; 600. Controller. Detailed Implementation

[0019] The technical solutions in the embodiments (or "implementations") of this application will be clearly and completely described herein with reference to the accompanying drawings. When the following description relates to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements.

[0020] If the embodiments of this application contain terms relating to directional indications or positional relationships (such as up, down, left, right, front, back, inside, outside, top, bottom, center, vertical, horizontal, longitudinal, transverse, length, width, counterclockwise, clockwise, axial, radial, circumferential, etc.), such terms are only used to explain the relative positional relationships and movement of the components in a specific posture (as shown in the attached figures); if the specific posture changes, the directional indications or positional relationships will also change accordingly. Furthermore, the terms "first" and "second" used in the embodiments of this application are only for descriptive convenience and should not be construed as indicating or implying relative importance.

[0021] refer to Figure 1 and Figure 2 This application provides a construction device for a side wall of a narrow corridor. The side wall includes a reinforcing cage and a concrete layer A2 poured on the reinforcing cage. Here, the concrete layer A2 is still concrete slurry when vibrated, and will be hardened after vibration. The construction device includes: a top guide rail 100, a movable mounting platform 200, a vibrating assembly 300, a positioning guide 400, a probe assembly 500, and a controller 600. A top guide rail 100 is fixedly installed along the length of the side wall and located above the reinforcing cage; a movable mounting platform 200 is slidably mounted on the top guide rail 100 and is equipped with a travel drive mechanism 210 for driving the movable mounting platform 200 to move along the top guide rail 100; a vibrating assembly 300 is mounted on the movable mounting platform 200 and includes a vibrating rod 310, which is vertically and vertically mounted on the movable mounting platform 200; a positioning guide 400 is fixedly installed at the bottom of the movable mounting platform 200, and a guide hole 410 is provided on the positioning guide 400, which is aligned with the vibrating rod 310. The shaft is set, and the inner diameter of the guide hole 410 is larger than the outer diameter of the vibrator 310, so that the vibrator 310 can pass through; the probe assembly 500 is set on the side of the positioning guide 400 facing the reinforcing cage. The probe assembly 500 includes a retractable contact probe. The detection end of the probe extends into the mesh gap of the reinforcing cage to detect whether there is reinforcing steel below the probe; the controller 600 is connected to the probe assembly 500, the walking drive mechanism 210 and the vibrator assembly 300 respectively; the controller 600 is configured to control the walking of the movable mounting platform 200 and the lifting of the vibrator 310 in response to the detection signal of the probe assembly 500.

[0022] Firstly, through the cooperation of the top guide rail 100 and the mobile installation platform 200, the vibratory compaction assembly 300 can automatically travel along the length of the side wall to each compaction station. Combined with the vibratory compactor 310, which can be raised and lowered on the mobile installation platform 200, the automatic insertion and compaction of the vibratory compactor 310 can be achieved without personnel entering the narrow corridor cavity. This replaces the traditional method of manually holding the vibratory compactor 310 into the cavity, solving the technical problem of personnel being unable to enter or having difficulty operating it after entering during the construction of narrow corridor side walls, reducing labor intensity, and improving construction safety.

[0023] Secondly, due to the limited mesh spacing of the side wall reinforcement cage, the vibrator 310 must pass through the mesh gaps when descending. Direct descent could easily result in collisions with the reinforcement bars, preventing the vibrator 310 from reaching the vibration position or even damaging the equipment. This application incorporates a contact probe on the positioning guide 400. The probe's detection end extends into the mesh gaps of the reinforcement cage to detect the presence of reinforcement bars below the probe in real time. Based on the probe's detection signal, the controller 600 only allows the vibrator 310 to descend when the positioning guide 400 is directly facing the mesh hole, i.e., when the probe is not in contact with the reinforcement bars. This achieves automatic determination of the vibrator 310's descent path, ensuring that the vibrator 310 can smoothly pass through the reinforcement cage to reach the concrete layer A2 for vibration, avoiding collisions and interference between the vibrator 310 and the reinforcement bars.

[0024] Combination Figure 3 In one embodiment, the vibratory assembly 300 further includes a flexible shaft 320, a vibratory motor 330, and a reel 340. The vibratory motor 330 is connected to the vibratory rod 310 via the flexible shaft 320. The reel 340 is rotatably mounted on the movable mounting platform 200. The vibratory motor 330 is fixed to the reel 340 and rotates with the reel 340. The flexible shaft 320 is wound around the outer circumference of the reel 340. When the reel 340 is driven to rotate, it drives the flexible shaft 320 to unwind or rewind, thereby causing the vibratory rod 310 to descend or ascend. The vibratory rod 310 is connected to the vibratory motor 330 via the flexible shaft 320. The flexible shaft 320 is wound around the outer circumference of the reel 340. When the reel 340 is driven to rotate, it drives the flexible shaft 320 to unwind or rewind, thereby causing the vibratory rod 310 to descend or ascend. The forward and reverse rotation of the reel 340 is controlled by a dedicated reel 340 drive motor 2113, such as a servo motor.

[0025] In this embodiment, the radius of the reel 340 is greater than the minimum bendable radius of the flexible shaft 320, i.e., not less than 500mm. This ensures that the flexible shaft 320 remains within a safe bending radius range during winding, preventing damage due to excessive bending, extending its service life, and guaranteeing the reliability of the vibration operation. The vibration motor 330 is fixed to the reel 340 and rotates with it, forming a single rotating unit. The vibration motor 330 directly drives the vibrating rod 310 via the flexible shaft 320. When the reel 340 rotates, it drives the vibration motor 330 and the flexible shaft 320 to rotate synchronously, completing the winding and unwinding of the flexible shaft 320.

[0026] In one embodiment, the guide hole 410 of the positioning guide 400 has an axial height of 200mm to 400mm, and the inner diameter of the guide hole 410 is larger than the outer diameter of the vibrating rod 310 and the flexible shaft 320. When the vibrating rod 310 and the flexible shaft 320 pass through the guide hole 410, the inner wall of the guide hole 410 forms a radial constraint on both. Since the guide hole 410 has a certain height, this radial constraint is continuously distributed vertically, forming a vertical guide channel. When the vibrating rod 310 descends, this channel forces the vibrating rod 310 and the flexible shaft 320 to maintain a vertical posture and move downwards, preventing the vibrating rod 310 from being misaligned and unable to align with the grid holes. At the same time, the flexible shaft 320 is guided by the hole wall when entering the guide hole 410, and its bending is restricted to a gradual transition within the guide hole 410, preventing the flexible shaft 320 from stacking at the entrance, allowing the flexible shaft 320 to pass smoothly through the guide hole 410.

[0027] refer to Figure 4 In one embodiment, the walking drive mechanism 210 includes an active component 211 and a driven component 212. Along the length of the top guide rail 100, the active component 211 and the driven component 212 are respectively disposed on opposite sides of the positioning guide member 400. The top guide rail 100 includes a first guide rail 110 and a second guide rail 120 arranged in parallel, both of which are provided with rack structures. The active component 211 includes an active gear shaft 2111, a transmission component 2112, and a drive mechanism. The drive motor 2113 is fixed on the movable mounting platform 200 and is connected to the drive gear shaft 2111 via the transmission assembly 2112. The drive gear shaft 2111 extends along the width direction of the top guide rail 100. A first gear portion 2111a and a second gear portion 2111b are respectively provided at both ends of the drive gear shaft 2111. The first gear portion 2111a meshes with a rack on the first guide rail 110, and the second gear portion 2111b meshes with a rack on the second guide rail 120. The driven assembly 212 includes a driven slider, which slides in contact with both the first guide rail 110 and the second guide rail 120.

[0028] The walking drive mechanism 210 adopts a double-sided gear and rack synchronous drive structure. The two ends of the drive gear shaft 2111 are respectively provided with a first gear section 2111a and a second gear section 2111b, which mesh with racks on the first guide rail 110 and the second guide rail 120, respectively. The driven component 212 slides with the guide rails via a driven slider. The drive motor 2113 drives the drive gear shaft 2111 to rotate via the transmission component 2112. The transmission component 2112 can be a bevel gear drive, with the gear sections at both ends of the drive gear shaft 2111 meshing and rolling synchronously on the racks on both sides, thereby driving the entire mobile mounting platform 200 to move along the guide rails. Because the gears on both sides are rigidly connected by the same drive gear shaft 2111, the walking displacement on both sides remains consistent, eliminating the problem of the mobile mounting platform 200 tilting or jamming due to asynchronous driving on both sides.

[0029] Gear and rack transmission is a meshing transmission, which is relatively precise and slip-free. The travel distance of the movable mounting platform 200 corresponds precisely to the rotation angle of the gear, and position control can be achieved when used with an encoder. At the same time, since the vibrating rod 310 is connected to the motor through the flexible shaft 320, the flexible shaft 320 has a certain degree of flexibility and can absorb some of the vibration generated during the vibration process. The vibration transmitted to the movable mounting platform 200 and the guide rail is small and will not significantly interfere with the normal meshing of the gear and rack, thus ensuring the stability and durability of the walking drive mechanism 210 during the vibration operation.

[0030] In one embodiment, the top guide rail 100 further includes two stops 130, which are respectively disposed on the side of the first guide rail 110 and the second guide rail 120 that are close to each other. The stops 130 are continuously disposed along the length direction of the top guide rail 100, and the stops 130 are provided with elongated clearance slots extending along the length direction of the top guide rail 100. The drive gear shaft 2111 passes through the clearance slots.

[0031] The elongated clearance slot on the stop 130 provides clearance space for the drive gear shaft 2111 along the length of the guide rail, allowing the drive gear shaft 2111 to move freely with the movable mounting platform 200 without interfering with the stop 130. The length direction of the clearance slot is consistent with the direction of travel, without imposing additional constraints on the normal movement of the gear shaft. Furthermore, when the drive gear shaft 2111 passes through the clearance slot, the stop 130 limits the displacement of the gear shaft in the width direction of the guide rail, helping to maintain a stable meshing position between the gear shaft and the rack. It should be noted that both the active drive assembly and the driven assembly 212 are enclosed by a housing to prevent concrete splashing; only the positioning guide 400 and the probe assembly 500 are exposed.

[0032] Combination Figure 5 and Figure 6In one embodiment, the probe assembly 500 includes two contact probes, which are distributed on both sides of the guide hole 410 along the length of the top guide rail 100. The positioning guide 400 has a telescopic hole 420, in which the contact probes are slidably inserted. An elastic element 421 is provided in the telescopic hole 420. One end of the elastic element 421 is connected to the positioning guide 400, and the other end is connected to the contact probe, which is used to keep the detection end of the contact probe in an extended state. The detection end of the contact probe has a pushing slope on both sides along the length of the top guide rail 100. The pushing slope is used to guide the probe to overcome the elastic force of the elastic element 421 and retract into the telescopic hole 420 when it comes into contact with the reinforcing bar during the movement of the probe.

[0033] Two probes are positioned on either side of the guide hole 410. As the movable mounting platform 200 moves along the guide rail, the two probes pass over the same rebar sequentially. If neither probe is triggered, it indicates that there are no rebars obstructing either side of the guide hole 410, and the guide hole 410 is aligned with the grid gaps. If one probe is triggered, it indicates that there is a rebar below that side, and the guide hole 410 has shifted. Compared to a single probe, this avoids the situation where the edge of an adjacent rebar cannot be detected due to the probe being located in a gap, thus improving the reliability of the detection.

[0034] The elastic element 421 keeps the probe in the extended state, allowing the probe to extend into the gap of the steel mesh; when the probe touches the steel bar, it can overcome the elastic force of the elastic element 421 and retract into the telescopic hole 420.

[0035] Another aspect of this application provides a construction method for a narrow corridor sidewall. Using the construction device for the narrow corridor sidewall of any of the above claims, the probe assembly 500 includes two contact probes distributed along the length of the top guide rail 100 on both sides of the guide hole 410. The method includes: controlling the walking drive mechanism 210 to drive the movable mounting platform 200 to move along the top guide rail 100 a first preset distance to reach the target working position. The first preset distance is the distance between two adjacent vibration operation positions. After the movable mounting platform 200 reaches the target working position, the detection signals of the two contact probes are read. If neither contact probe contacts the reinforcing steel, it is determined that the guide hole 410 of the positioning guide 400 is aligned with the grid holes of the reinforcing steel cage. The vibration assembly 300 is then controlled to descend, allowing the vibrator 310 to pass through the guide hole 410 to vibrate the concrete layer A2. If at least one contact probe comes into contact with the reinforcing bar, it is determined that the guide hole 410 is not aligned with the grid hole. The walking drive mechanism 210 is controlled to fine-tune the position of the moving mounting platform 200 until neither of the two contact probes comes into contact with the reinforcing bar. Then, the vibrator 310 is controlled to descend and vibrate.

[0036] In the construction method provided in this application, the mobile installation platform 200 is first controlled to move along the guide rail a first preset distance to reach the target working position. This first preset distance is the interval between two adjacent vibration operation positions. This moves the vibrator 310 from the previous vibration point to the next vibration point, achieving continuous point-to-point vibration along the length of the side wall. After reaching the target working position, the detection signals of the two contact probes are read. When neither probe contacts the reinforcing steel, it indicates that there are gaps in the grid directly below the guide hole 410, and the descent path of the vibrator 310 is unobstructed. At this time, the vibrator 310 is controlled to descend for vibration, ensuring that the vibrator 310 does not collide with the reinforcing steel.

[0037] If at least one probe contacts the reinforcing bar, it indicates that the guide hole 410 is offset and the mesh gaps are not aligned with the guide hole 410. In this case, if the vibrator 310 is lowered directly, it may hit the reinforcing bar. Therefore, the method first controls the walking drive mechanism 210 to fine-tune the position of the moving mounting platform 200 until neither probe contacts the reinforcing bar before lowering it for vibration. This ensures that the position of the vibrator 310 is confirmed before each descent, avoiding collision with the reinforcing bar.

[0038] In one embodiment, during the movement of the mobile mounting platform 200 along the top guide rail 100, the number of reinforcing bars passed by the two contact probes along the direction of the top guide rail 100 is counted based on the number of times the two contact probes are triggered by the compression of the reinforcing bars. When the mobile mounting platform 200 reaches the target working position: if the number of triggers of the two contact probes is the same, it is determined that the mobile mounting platform 200 is moving normally, and the vibration assembly 300 is controlled to descend for vibration. If the number of triggers of the two contact probes is different, it is determined that the mobile mounting platform 200 is deviating, and one contact probe has fewer triggers than the other. When the number of triggers of the contact probe located at the rear along the moving direction of the top guide rail 100 is less than that of the contact probe in front, the walking drive mechanism 210 is controlled to continue moving along the original moving direction a second preset distance, the second preset distance being equal to the theoretical spacing between adjacent reinforcing bars in the reinforcing cage, so that the contact probe located at the rear is triggered again, until the number of triggers of the two contact probes is the same. If, after moving the second preset distance, the number of triggers for the two contact probes is still different, or if the contact probe located at the rear still cannot be triggered, the control will issue an alarm signal.

[0039] The same number of triggers indicates that both probes have swept the same number of rebars during movement, the mobile mounting platform 200 is in a normal posture in the guide rail direction, and the two sides move synchronously. The different number of triggers indicates that one probe triggered one less time than the other, meaning that the probe on the side that triggered less time failed to sweep a certain rebar during movement. That is, there is a deviation in the relative position of the mobile mounting platform 200 and the rebar mesh hole on that side. The first preset distance and the multiple of the actual rebar spacing are not accurately matched, resulting in the two probes not being inserted into the same rebar mesh hole. At this time, lowering the vibrator may hit the rebar.

[0040] When the probe located behind the other probe triggers fewer times than the probe in front along the direction of movement, the controller 600 controls the walking drive mechanism 210 to continue moving a second preset distance along the original direction of movement, equal to the theoretical spacing of the reinforcing bars, so that the probe located behind triggers again, until the two probes trigger the same number of times. This fine-tuning operation utilizes the fixed spacing of the reinforcing bars. By advancing one reinforcing bar spacing, the probe on the lagging side encounters the next reinforcing bar and completes its triggering, thereby restoring the counting state of the two probes to be consistent, allowing both probes to be inserted into the same grid hole simultaneously.

[0041] Compared to manual inspection or machine shutdown for adjustment, this fine-tuning method automatically determines deviations through probe counting and compensates via programmed short-distance movements, eliminating the need for personnel to enter narrow cavities or to stop the machine. An alarm signal is only triggered to prompt manual inspection if the count discrepancy cannot be eliminated after moving a second preset distance, thus avoiding frequent alarms due to small deviations that could impact construction efficiency.

[0042] Combination Figure 1 and Figure 7 In one embodiment, the steel cage and concrete layer A2 of the corridor sidewall are arranged sequentially from the outside to the inside of the corridor, including a temperature-controlled cooling pipe network system A3, a crack-resistant reinforcing steel mesh and temperature reinforcement system, a heat-insulating buffer fireproof transition layer A5, and an outer fireproof protective surface layer A6. The steel cage is provided with three sets of temperature sensors along the height of the sidewall, which are respectively arranged in the upper, middle and lower parts of the sidewall. Each set of temperature sensors includes three temperature measuring points embedded in the interior, middle and surface of the sidewall, which are used to monitor the temperature distribution during the pouring and curing of large-volume concrete.

[0043] Among them, the main load-bearing crack-resistant concrete layer A2 adopts low heat of hydration and high fire-resistant modified concrete. Fly ash and mineral powder are added to the mix to replace part of the cement, which can reduce the amount of cement used, reduce the heat of hydration and temperature rise, and inhibit the generation of temperature cracks from the source. At the same time, steel fibers and polypropylene coarse fibers are added to improve the tensile strength and shrinkage resistance of the concrete matrix, improve the anti-cracking and anti-stripping performance of concrete under high temperature environment, and meet the fire protection requirements of the tunnel.

[0044] The temperature-controlled cooling pipe network system A3 consists of serpentine stainless steel cooling water pipes. These pipes are fixed inside the reinforcing steel frame using standardized positioning brackets, preventing displacement, floating, or bending during concrete pouring and vibration, ensuring a neat pipe network layout and smooth water circulation. Combined with three sets of temperature sensors installed along the sidewall height, the system can collect real-time temperature distribution data from different parts of the large-volume concrete. This allows construction personnel to adjust the cooling water flow rate promptly based on the temperature data, controlling the temperature difference between the inside and outside of the concrete within the specified range, generally not exceeding 25℃, effectively preventing temperature cracks caused by excessive internal and external temperature differences.

[0045] A double-layered system of crack-resistant reinforced steel mesh and temperature-resistant reinforcement is installed within the height of the sidewall. HRB400 ribbed steel bars are used for binding, and crack-resistant temperature-resistant reinforcement and horizontal tie bars are densely distributed in areas of large-volume concrete, above and below horizontal construction joints, and around expansion joints. This multi-layered reinforcement system, by restraining concrete shrinkage and temperature deformation, structurally prevents the initiation and propagation of cracks, thus improving the overall crack resistance of the sidewall.

[0046] The heat-insulating, buffer, and fireproof transition layer A5 is cast using aerogel composite fireproof mortar, with a thickness of 20mm to 40mm. Aerogel has extremely low thermal conductivity. During the concrete curing stage, this layer can play a role in heat preservation and moisture retention, reducing the temperature difference between the inside and outside of the wall. During the tunnel operation stage, it serves as a heat-insulating buffer layer, blocking the conduction of external high temperatures to the main concrete, while also buffering minor structural deformations to prevent cracking and peeling of the fireproof surface layer.

[0047] The outer fireproof protective layer A6 is made of rigid fireproof protective board, which is anchored to the inner structural layer through anti-corrosion metal anchors. This can improve the overall fire resistance limit of the side wall and resist the damage to the wall structure caused by the high temperature of tunnel fire.

[0048] In addition, fire-resistant expansion joints are provided at the section locations of the side walls. The joints are equipped with stainless steel frames and embedded waterstops. The joint cavities are filled with layers of fire-resistant fibers and fire-resistant sealant. When the structure deforms, the expansion joints can coordinate displacement and ensure water-stopping effect. At the same time, they can block the flow channels of flames and smoke along the structural joints, ensuring that the structural joints can still maintain fire resistance integrity in the event of a fire.

[0049] Secondly, a miniature high-definition camera and waterproof lighting supplement light can be installed on the side of the steel cage. The camera lens is angled towards the concrete feeding area and the vibration operation area. The video signal is pushed to the external display screen in real time through wired transmission. In addition to observing the concrete feeding and vibration slurry state in real time and judging the vibration quality, it can also help observe the initial shrinkage cracks on the concrete surface and the uniformity of material flow.

[0050] In another embodiment, a flexible guide tube capable of passing through the mesh holes of the reinforcing cage can be installed along the height direction of the reinforcing cage. The top of the guide tube connects to the discharge port of the concrete pump truck, and the tube body extends along the height direction of the side wall to a position near the bottom of the wall. The guide tube is made of wear-resistant flexible material. Concrete enters the guide tube through the pump pipe and falls smoothly to the pouring surface along the vertical channel inside the tube, significantly reducing the free fall height of the concrete, completely avoiding the separation of aggregate and mortar, and effectively preventing concrete segregation.

[0051] The construction process includes: accurately marking the positions of the narrow tunnel corridor sidewalls, marking the installation positions of reinforcing bars, cooling water pipes, guide tubes, top guide rails (100mm), and formwork; cleaning the work surface and erecting the formwork support. Then, the main reinforcing bars, distribution bars, and double-layer crack-resistant reinforcing mesh of the sidewall structure are tied. Crack-resistant temperature bars and tie bars are added around large-volume concrete areas, construction joints, and expansion joints to ensure that the spacing of the reinforcing bars and the thickness of the protective layer meet the design requirements. Cooling water pipe positioning brackets are installed on the reinforcing bar skeleton, and the cooling water pipes are laid out and fixed in a serpentine pattern. Temperature sensors are pre-embedded, and all sensor wires are uniformly led to an external control panel. Water pressure testing of the pipelines is completed, and no leakage is checked. The above construction devices are then fixed to the top formwork of the sidewall. Flexible guide tubes are installed and fixed along the height of the sidewall. All equipment lines are connected and debugged to ensure normal equipment operation. Afterwards, the sidewall side formwork and end formwork are sealed, the formwork gaps are sealed, and the rigidity and sealing of the formwork are checked. The formwork is then accepted.

[0052] Then, the low-heat-of-hydration, high-refractory-resistant modified large-volume concrete is poured using a layered and segmented skip-pour method, with the thickness of each layer controlled to be no more than 500mm. The concrete is then pumped into a vertical guide tube and falls smoothly down to the bottom of the cavity. The vibrating unit is then moved and raised to achieve vibration. The vibration status is observed using a camera, and the standard for qualified vibration is that the concrete surface is covered with slurry and no air bubbles rise to the surface.

[0053] During the initial setting stage of the concrete, the cooling water circulation system is activated, and the internal temperature of the concrete is monitored in real time using pre-embedded temperature sensors to control the temperature difference between the inside and outside of the concrete to be no greater than 25℃. Thermal insulation and moisture retention curing are carried out according to specifications to reduce temperature stress and shrinkage deformation. After the concrete has cured to its design strength, the side wall formwork is removed. The heat-insulating, buffering, and fireproof transition layer A5 and the outer fireproof protective layer A6 are then constructed in layers. Fire-resistant embedded waterstops are installed at the horizontal construction joints and expansion joints of the side walls, and fire-resistant fibers and fireproof sealant are filled in layers to complete the fireproofing, water-stopping, and crack-resistant sealing of the structural joints. After inspection and acceptance, the overall construction is completed.

[0054] It should be noted that the technical solutions or features described in the above embodiments can be combined or supplemented with each other without conflict. The scope of protection of this application is not limited to the precise structures described in the above embodiments and shown in the accompanying drawings; all modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of this application should be included within the scope of protection of this application.

Claims

1. A construction device for a side wall of a narrow corridor, characterized in that, The corridor side wall includes a steel cage movable installation platform (200), which is placed above the steel cage and has a walking drive mechanism (210) at the bottom. A vibratory assembly (300) is mounted on the movable mounting platform (200) and includes a vibratory rod (310) that can be raised and lowered. A positioning guide (400) is placed at the bottom of the movable mounting platform (200) and has a guide hole (410) for the vibrator (310) to pass through. A probe assembly (500) is positioned on the side of the positioning guide (400) facing the rebar cage, the probe assembly (500) including a probe for detecting whether there is rebar below; The controller (600) is connected to the probe assembly (500), the walking drive mechanism (210) and the vibrating assembly (300) respectively; the controller (600) is configured to control the movement and stopping of the mobile mounting platform (200) and the raising and lowering of the vibrating rod (310) in response to the detection signal of the probe assembly (500).

2. The construction device for the side wall of a narrow corridor as described in claim 1, characterized in that, The construction device also includes a top guide rail (100), which is configured to be fixed along the length of the corridor sidewall and located above the steel cage; The mobile mounting platform (200) is slidably disposed on the top guide rail (100), and the walking drive mechanism (210) is configured to drive the mobile mounting platform (200) to move along the top guide rail (100); The guide hole (410) is coaxially arranged with the vibrating rod (310), and the inner diameter of the guide hole (410) is larger than the outer diameter of the vibrating rod (310) for the vibrating rod (310) to pass through. The probe is a retractable contact probe, and the detection end of the probe extends into the mesh gap of the steel mesh structure cage.

3. The construction device for the side wall of a narrow corridor as described in claim 2, characterized in that, The vibratory assembly (300) also includes a flexible shaft (320), a vibratory motor (330), and a reel (340), wherein the vibratory motor (330) is connected to the vibratory rod (310) via the flexible shaft (320); The reel (340) is rotatably mounted on the mobile mounting platform (200). The vibratory motor (330) is fixed on the reel (340) and rotates with the reel (340). The flexible shaft (320) is wound around the outer periphery of the reel (340). When the reel (340) is driven to rotate, it drives the flexible shaft (320) to unwind or rewind, thereby driving the vibratory rod (310) to descend or rise.

4. The construction device for the side wall of a narrow corridor as described in claim 3, characterized in that, The guide hole (410) of the positioning guide (400) has a height of 200mm to 400mm along its axial direction, and the inner diameter of the guide hole (410) is larger than the outer diameter of the vibrating rod (310) and the flexible shaft (320).

5. The construction device for the side wall of a narrow corridor as described in claim 2, characterized in that, The walking drive mechanism (210) includes an active component (211) and a driven component (212). Along the length direction of the top guide rail (100), the active component (211) and the driven component (212) are respectively disposed on opposite sides of the positioning guide (400). The top guide rail (100) includes a first guide rail (110) and a second guide rail (120) arranged in parallel, and both the first guide rail (110) and the second guide rail (120) are provided with rack structures; The active component (211) includes an active gear shaft (2111), a transmission component (2112), and a drive motor (2113). The drive motor (2113) is fixed on the movable mounting platform (200) and is connected to the active gear shaft (2111) via the transmission component (2112). The active gear shaft (2111) extends along the width direction of the top guide rail (100). The two ends of the active gear shaft (2111) are respectively provided with a first gear part (2111a) and a second gear part (2111b). The first gear part (2111a) meshes with the rack on the first guide rail (110), and the second gear part (2111b) meshes with the rack on the second guide rail (120). The driven component (212) includes a driven slider, which slides in cooperation with the first guide rail (110) and the second guide rail (120) respectively.

6. The construction device for the side wall of a narrow corridor as described in claim 5, characterized in that, The top guide rail (100) also includes two stops (130), which are respectively disposed on the side of the first guide rail (110) and the second guide rail (120) that are close to each other. The stops (130) are continuously disposed along the length direction of the top guide rail (100), and the stops (130) are provided with elongated clearance slots extending along the length direction of the top guide rail (100). The drive gear shaft (2111) passes through the clearance slots.

7. The construction device for the side wall of a narrow corridor as described in claim 2, characterized in that, The probe assembly (500) includes two contact probes, which are distributed on both sides of the guide hole (410) along the length of the top guide rail (100). The positioning guide (400) has a telescopic hole (420), and the contact probe is slidably inserted into the telescopic hole (420). An elastic element (421) is provided in the telescopic hole (420). One end of the elastic element (421) is connected to the positioning guide (400), and the other end is connected to the contact probe, which is used to keep the detection end of the contact probe in an extended state. The detection end of the contact probe is provided with a pushing slope on both sides along the length direction of the top guide rail (100). The pushing slope is used to guide the probe to overcome the elastic force of the elastic element (421) and retract into the telescopic hole (420) when it comes into contact with the steel bar during the movement of the probe.

8. A construction method for a side wall of a narrow corridor, characterized in that, Using the construction apparatus for the narrow corridor sidewall according to any one of claims 2 to 6, the probe assembly (500) includes two contact probes distributed on both sides of the guide hole (410) along the length direction of the top guide rail (100), and the construction method includes: The walking drive mechanism (210) is controlled to drive the mobile mounting platform (200) to move along the top guide rail (100) a first preset distance to reach the target working position. The first preset distance is the distance between two adjacent vibration operation positions. After the mobile mounting platform (200) reaches the target working position, the detection signals of the two contact probes are read: If neither of the two contact probes makes contact with the reinforcing bar, it is determined that the guide hole (410) of the positioning guide (400) is aligned with the grid hole of the reinforcing bar cage. The vibrating assembly (300) is then controlled to descend, allowing the vibrating rod (310) to pass through the guide hole (410) for vibration. If at least one of the contact probes comes into contact with the reinforcing bar, it is determined that the guide hole (410) is not aligned with the grid hole. The walking drive mechanism (210) is controlled to fine-tune the position of the mobile mounting platform (200) until neither of the two contact probes comes into contact with the reinforcing bar. Then, the vibrator (310) is controlled to descend and vibrate.

9. The construction method for the side wall of a narrow corridor as described in claim 8, characterized in that, As the mobile mounting platform (200) moves along the top guide rail (100), the number of steel bars that the two contact probes pass through along the direction of the top guide rail (100) is counted according to the number of times the two contact probes are triggered by the steel bars pressing and shrinking. After the mobile mounting platform (200) reaches the target working position: If the two contact probes trigger the same number of times, it is determined that the moving mounting platform (200) is moving normally, and the vibrating assembly (300) is controlled to descend for vibration. If the number of triggers of the two contact probes is different, it is determined that the movable mounting platform (200) is offset, and one of the contact probes has fewer triggers than the other. When the number of triggers of the contact probe located behind along the moving direction of the top guide rail (100) is less than that of the contact probe in front. Control the walking drive mechanism (210) to continue moving a second preset distance along the original moving direction. The second preset distance is equal to the theoretical spacing between adjacent steel bars of the steel cage, so that the contact probe located behind is triggered again until the number of triggers of the two contact probes is the same. If, after moving the second preset distance, the number of triggers of the two contact probes is still different, or the contact probe located at the rear still cannot be triggered, then an alarm signal will be issued.

10. The construction method for the side wall of a narrow corridor as described in claim 8, characterized in that, The steel cage of the corridor side wall is arranged from the outside to the inside of the corridor as follows: a concrete layer (A2), a temperature control cooling pipe network system (A3), a crack-resistant reinforcing steel mesh and temperature reinforcement system, a heat insulation buffer fireproof transition layer (A5), and an outer fireproof protective surface layer (A6). The steel cage is equipped with three sets of temperature sensors along the height of the side wall, which are respectively arranged at the upper, middle and lower parts of the side wall. Each set of temperature sensors includes three temperature measuring points embedded in the interior, middle and surface of the side wall, which are used to monitor the temperature distribution during the pouring and curing of large-volume concrete.