A water-stopping system and construction method for post-cast strips in basement exterior walls

By using sealing strips and restraint rods to form a "labyrinthine" interface in the post-cast strip of the basement exterior wall, the problem of water seepage at the junction of new and old concrete was solved, achieving a more efficient water-stopping effect and structural stability, and improving the building's waterproof performance and durability.

CN123109216APending Publication Date: 2026-11-17ZHEJIANG KECHENG CONSTR SUPERVISION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611277644.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-21
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The existing basement exterior wall post-cast strip is prone to forming tiny gaps at the junction of new and old concrete, which can lead to water infiltration, affect the water-stopping and seepage prevention effect, and reduce the structural durability.

Method used

The seal is embedded in the sealing groove, forming a "maze-like" interface with the interlocking area and the restraining rods, which enhances the sealing performance and structural rigidity. The combination of the bent part of the seal and the restraining rods increases the difficulty of the seepage path and the stability of the connection.

Benefits of technology

It effectively seals minute gaps, improves the overall water-stopping effect and structural stability of the post-cast strip of the basement exterior wall, enhances waterproofing capabilities, and improves the building's functionality and durability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109216A_ABST
    Figure CN123109216A_ABST
Patent Text Reader

Abstract

This application relates to the technical field of post-cast strips, and provides a water-stopping system and construction method for post-cast strips on basement exterior walls. The system includes a post-cast main body and multiple sealing strips. The basement exterior wall has a pre-reserved intermittent casting zone, within which the post-cast main body is cast. Two bonding interfaces are formed between the post-cast main body and the basement exterior wall, with sealing grooves for the embedding of sealing strips on both sides of each interface. This water-stopping system for basement exterior walls improves the sealing performance between the post-cast strip and the existing exterior wall.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This application relates to the technical field of post-cast strips, and in particular to a water-stopping system and construction method for post-cast strips on basement exterior walls. Background Technology

[0002] The post-cast strip of the basement exterior wall is a temporary intermittent casting strip pre-cast in the wall during the construction of the basement concrete exterior wall to offset the stress generated by concrete hardening shrinkage, temperature deformation and uneven structural settlement. It is a key structure to ensure the structural integrity of ultra-long and ultra-wide basement walls and avoid wall cracking, and is widely used in basement projects of various buildings.

[0003] Currently, the conventional construction method for post-cast strips on basement exterior walls is as follows: the main exterior wall is cast in one go, leaving an empty area for the post-cast strip. After the main wall concrete has completed shrinkage and settlement and reached the design age, the laitance and debris on the base surface of the post-cast strip are cleaned, auxiliary steel bars are tied, and conventional water-stopping components such as water-stop steel plates are used. Finally, the post-cast strip is sealed by integrally casting shrinkage-compensating concrete to complete the overall wall construction.

[0004] However, in practical applications, minute gaps easily form at the interface between new and old concrete, and conventional waterproofing components have limited sealing performance. Basements are constantly exposed to a damp and watery environment, and external moisture can easily seep through the gaps between the post-cast strip and the original wall, causing water seepage and dampness problems in the wall. This significantly reduces the overall waterproofing and seepage prevention effect of the exterior wall, affecting the basement's functionality and structural durability. Therefore, further optimization and improvement are needed. Summary of the Invention

[0005] To improve the sealing between the post-cast strip and the existing exterior wall, this application provides a water-stopping system and construction method for the post-cast strip of the basement exterior wall.

[0006] Firstly, the technical solution provided in this application for a post-cast strip water-stopping system for basement exterior walls is as follows: A water-stopping system for post-cast strips on basement exterior walls includes a post-cast main body and multiple sealing strips. The basement exterior wall has a pre-reserved intermittent casting area, and the post-cast main body is cast within the intermittent casting area. Two joint interfaces are formed between the post-cast main body and the basement exterior wall, and sealing grooves for embedding the sealing strips are provided on both sides of the joint interfaces.

[0007] By employing the aforementioned technical solution, seals are embedded within the sealing groove to seal the minute gaps between the basement exterior wall and the post-cast main structure, thereby improving the seepage path and increasing the difficulty of seepage. Seals are also embedded on both sides of the joint interface to further enhance overall sealing.

[0008] Optionally, the sealing groove is adapted to the shape of the sealing strip, and the sealing groove includes a first part set in the outer wall and a second part set in the post-cast main body.

[0009] By adopting the above technical solution, the first insert and the second insert combine to form a sealing groove for the seal strip to be inserted, which increases the difficulty for external water vapor to enter the joint interface and improves the overall water-stopping effect.

[0010] Optionally, the seal includes a first sealing portion and a second sealing portion, which are perpendicularly arranged between each other. The first sealing portion has a first bent portion, which is parallel to the second sealing portion. The second sealing portion has a second bent portion, which is parallel to the first sealing portion.

[0011] Optionally, the first sealing portion, the second sealing portion, the first bending portion, and the second bending portion together form an interlocking area, and the post-cast body has an interlocking portion that is embedded in the interlocking area.

[0012] By adopting the above technical solution, the interlocking area and interlocking part are used to form a "maze-like" joint gap between the seal and the post-cast body, which improves the water-stopping effect between the seal and the post-cast body. In addition, the seal utilizes the first bend and the second bend to enhance the connection stability between the seal and the post-cast body.

[0013] Optionally, a first constraint member is connected between two adjacent seals in the thickness direction of the outer wall, and a second constraint member is connected between two adjacent seals in the width direction of the intermittent pouring area. Both the first and second constraint members are embedded in the post-poured main body.

[0014] By adopting the above technical solution, multiple seals are connected in series to form a whole using the first and second constraint members, thereby improving the structural rigidity of the post-cast main body.

[0015] Optionally, the first constraint member includes a first rotating sleeve and two first connecting rods. The ends of the two first connecting rods that are close to each other are threaded into the first rotating sleeve, and the ends of the two first connecting rods that are far from each other are respectively connected to two adjacent seals in the thickness direction of the outer wall.

[0016] By adopting the above technical solution, when the first constraint rod is installed, the ends of the two first connecting rods that are far apart from each other are respectively connected to two adjacent seals in the thickness direction of the outer wall. Then, the first rotating sleeve is rotated to tighten the two adjacent seals in the thickness direction of the outer wall, so that the two adjacent seals in the thickness direction of the outer wall firmly hug the outer wall and improve the overall structural rigidity.

[0017] Optionally, the side wall of the seal is provided with a connecting hole, the inner diameter of which is adapted to the outer diameter of the first connecting rod, and the side wall of the seal is provided with an inlet and outlet groove that connects to the connecting hole; the outer peripheral wall of the end of the first connecting rod away from the first rotating sleeve is provided with two cutting surfaces, and the distance between the two cutting surfaces is adapted to the distance between the two opposite side walls of the inlet and outlet groove.

[0018] By adopting the above technical solution, when installing the first connecting rod and the seal, the two cutting surfaces of the first connecting rod are aligned with the two opposite side walls of the inlet / outlet slide groove and pushed in, so that the first connecting rod moves from the inlet / outlet slide groove into the connecting hole. Then, by rotating the first constraint rod as a whole, the first connecting rod can be locked in the connecting hole, improving the ease of operation for connecting the first connecting rod and the seal.

[0019] Optionally, the second constraint member includes a second rotating sleeve and two second connecting rods. The ends of the two second connecting rods that are close to each other are threaded into the second rotating sleeve, and the ends of the two second connecting rods that are far from each other abut against two adjacent seals in the width direction of the intermittent pouring area.

[0020] By adopting the above technical solution, when installing the second constraint rod, the ends of the two second connecting rods that are far apart from each other are respectively abutted against two adjacent seals in the width direction of the intermittent pouring area. Then, the second rotating sleeve is rotated to press against the two adjacent seals in the width direction of the intermittent pouring area, so that the two adjacent seals in the width direction of the intermittent pouring area are firmly pressed against the outer wall, thereby improving the overall structural rigidity and overall sealing performance.

[0021] Optionally, the end of the second connecting rod away from the second rotating sleeve is provided with an abutment block, and the end of the first connecting rod away from the first rotating sleeve is provided with a guide surface. The abutment block abuts against the guide surface to guide the first connecting rod to slide closer to the first rotating sleeve.

[0022] By adopting the above technical solution, the mutual contact between the abutment block and the guide surface restricts the free rotation of the first connecting rod, thereby reducing the possibility of the first connecting rod rotating freely and sliding out of the inlet / outlet groove, and improving the installation stability of the first constraint member. Secondly, when the second rotating sleeve drives the two second connecting rods away from each other, the abutment block pushes the first connecting rod through the guide surface, causing the first connecting rod to tighten the seal and improve the overall structural rigidity.

[0023] Secondly, the construction method for post-cast strips in basement exterior walls provided in this application adopts the following technical solution: A construction method for post-cast strips on basement exterior walls includes the following steps: S1, leaving and pre-treating the intermittent casting area; S2, erecting the sealing strip; S3, casting the main post-cast structure. Attached Figure Description

[0024] Figure 1 This is a cross-sectional view of the overall structure of Embodiment 1; Figure 2 This is a partial sectional view of Embodiment 1 illustrating the first and second constraint members; Figure 3 yes Figure 1 Enlarged view of point A in the middle; Figure 4 yes Figure 2 Enlarged view of point B in the middle; Figure 5 This is a partial cross-sectional view of the connecting hole in Embodiment 1; Figure 6 This is a partial cross-sectional view of the cutting surface in Example 1; Figure 7 This is a schematic diagram illustrating the structure of the abutment block in Example 1.

[0025] Explanation of reference numerals in the attached drawings: 1. Post-cast main body; 11. Interlocking part; 2. Sealing strip; 21. First sealing part; 22. Second sealing part; 23. First bending part; 24. Second bending part; 25. Interlocking area; 26. Connecting hole; 261. Inlet and outlet groove; 27. Anti-rotation groove; 3. Intermittent casting area; 31. Joint interface; 32. Sealing groove; 321. First insert; 322. Second insert; 323. First joint; 324. Second joint; 33. Foundation reinforcement; 4. First constraint member; 41. First rotating sleeve; 42. First connecting rod; 421. Cutting surface; 422. Guide surface; 5. Second constraint member; 51. Second rotating sleeve; 52. Second connecting rod; 53. Abutment block. Detailed Implementation

[0026] The following combination Figures 1-7 This application will be described in further detail. Example 1

[0027] This application discloses a water-stopping system for post-cast strips on basement exterior walls.

[0028] Reference Figure 1 , Figure 2 , Figure 3 A water-stopping system for post-cast strips on basement exterior walls includes a post-cast main body 1 and multiple sealing strips 2. The basement exterior wall has a pre-reserved intermittent casting zone 3, within which the post-cast main body 1 is cast. Multiple foundation reinforcement bars 33 are pre-reserved within the basement exterior wall, passing through the post-cast main body 1.

[0029] Two joint interfaces 31 are formed between the post-cast main body 1 and the basement exterior wall. Sealing grooves 32 are provided on both sides of each joint interface 31. The number of sealing strips 2 corresponds to the number of sealing grooves 32, and each sealing strip 2 is fixedly installed within its corresponding sealing groove 32. The sealing groove 32 is shaped to match the sealing strip 2. The sealing groove 32 includes a first embedding part 321 and a second embedding part 322. The first embedding part 321 is located on the exterior wall sidewall, and the second embedding part 322 is located on the sidewall of the post-cast main body 1.

[0030] It should be noted that during the pouring of the post-cast main body 1, baffles (not shown in the figure) need to be installed between two adjacent sealing strips 2 in the width direction of the intermittent pouring area 3. The baffles can be temporarily locked to the outer wall of the sealing strips 2 with screws. The two baffles and the two joint interfaces 31 together form an intermittent pouring area 3 with an open top. Compensating shrinkage concrete is poured into the intermittent pouring area 3. After the concrete solidifies, the post-cast main body 1 is obtained, and the second inlay 322 is formed. The first inlay 321 is formed by the second inlay 322 being separated by a partition plate during the pouring of the basement exterior wall. After the exterior wall concrete is poured and solidified, the first inlay 321 is formed.

[0031] Reference Figure 3 , Figure 4 In this embodiment, the seal 2 includes a first sealing part 21 and a second sealing part 22. The first sealing part 21 and the second sealing part 22 are arranged vertically between each other and are integrally formed to form a seal 2 with a "T" shaped cross-section. The first sealing parts 21 of two seals 2 that are adjacent in the thickness direction of the outer wall are arranged opposite each other.

[0032] A first bend 23 is fixedly installed on the first sealing part 21, and the first bend 23 is arranged parallel to the second sealing part 22. A second bend 24 is fixedly installed on the second sealing part 22, and the second bend 24 is arranged parallel to the first sealing part 21. The first sealing part 21, the second sealing part 22, the first bend 23, and the second bend 24 together form an interlocking area 25, and the post-cast main body 1 has an interlocking part 11 embedded in the interlocking area 25. For ease of description, the contact surface between the sealing strip 2 and the outer wall is defined as the first joint 323, and the contact surface between the sealing strip 2 and the post-cast main body 1 is defined as the second joint 324. A water-stop pad (not shown in the figure) is installed at the first joint 323.

[0033] Reference Figure 2 , Figure 4 A first constraint member 4 is installed between two adjacent seals 2 in the thickness direction of the outer wall, and a second constraint member 5 is installed between two adjacent seals 2 in the width direction of the intermittent pouring area 3. Multiple first constraint members 4 and second constraint members 5 are arranged at intervals along the height direction. Both first constraint members 4 and second constraint members 5 are embedded in the post-poured main body 1.

[0034] Reference Figure 5 , Figure 6In this embodiment, the first constraint member 4 includes a first rotating sleeve 41 and two first connecting rods 42. The first rotating sleeve 41 is located between the two first connecting rods 42. The ends of the two first connecting rods 42 that are close to each other are threaded into the first rotating sleeve 41 (the threads of the first connecting rods 42 are not shown in the figure). The ends of the two first connecting rods 42 that are far apart from each other are respectively connected to two adjacent sealing strips 2 in the thickness direction of the outer wall. The threads of the first rotating sleeve 41 and the two first connecting rods 42 are arranged in opposite directions so that when the first rotating sleeve 41 rotates, the two first connecting rods 42 can move closer to each other or further apart.

[0035] The first bent portion 23 of the seal 2 has a connecting hole 26 on its side wall. The inner diameter of the connecting hole 26 is adapted to the outer diameter of the first connecting rod 42. The first bent portion 23 of the seal 2 has an inlet / outlet groove 261 on its side wall. The inlet / outlet groove 261 connects to the connecting hole 26 to allow the first connecting rod 42 to enter and exit. The outer peripheral wall of the end of the first connecting rod 42 away from the first rotating sleeve 41 has two cutting surfaces 421. The distance between the two cutting surfaces 421 is adapted to the distance between the two opposite side walls of the inlet / outlet groove 261.

[0036] Reference Figure 2 , Figure 4 In this embodiment, the second constraint member 5 includes a second rotating sleeve 51 and two second connecting rods 52. The second rotating sleeve 51 is located between the two second connecting rods 52. The ends of the two second connecting rods 52 that are close to each other are threaded into the second rotating sleeve 51 (the threads of the second connecting rods 52 are not shown in the figure). The ends of the two second connecting rods 52 that are far apart from each other are respectively used to abut against two adjacent sealing strips 2 in the width direction of the intermittent pouring area 3. The threads of the second rotating sleeve 51 and the two second connecting rods 52 are arranged in opposite directions so that when the second rotating sleeve 51 rotates, the two second connecting rods 52 can move closer to each other or further apart.

[0037] Reference Figure 4 , Figure 7 Each second link 52 has a fixed abutment block 53 at the end away from the second rotating sleeve 51. The second bend 24 of the seal 2 has an anti-rotation groove 27 for the abutment block 53 to be inserted. The first link 42 has a guide surface 422 at the end away from the first rotating sleeve 41. The abutment block 53 abuts against the guide surface 422. The abutment block 53 of the second link 52 abuts against the seal 2 through the guide surface 422 of the first link 42. When the second link 52 slides away from the second rotating sleeve 51, the abutment block 53 of the second link 52 pushes the first link 42 through the guide surface 422, so as to force the seal 2 to slide closer to the first rotating sleeve 41.

[0038] The implementation principle of Embodiment 1 of this application is as follows: the seal strip 2 is embedded in the sealing groove 32 to seal the tiny gap between the basement exterior wall and the post-cast main body 1. The shape of the seal strip 2 forms a first joint 323 and a second joint 324 with multiple bends, which greatly extends the seepage path, increases the difficulty for external water vapor to enter the joint interface 31, and improves the overall water-stopping effect.

[0039] By utilizing the interlocking area 25 and the interlocking part 11, a "maze-like" second joint 324 is formed between the seal 2 and the post-cast body 1, which improves the water-stopping effect between the seal 2 and the post-cast body 1. Furthermore, the seal 2 utilizes the first bending part 23 and the second bending part 24 to enhance the connection stability between the seal 2 and the post-cast body 1.

[0040] By using the first constraint member 4 and the second constraint member 5, multiple seals 2 are connected in series to form a whole, thereby improving the structural rigidity of the post-cast main body 1. The mutual abutment of the abutment block 53 and the guide surface 422 restricts the free rotation of the first connecting rod 42, thus reducing the possibility of the first connecting rod 42 rotating freely and sliding out of the inlet / outlet groove 261, and improving the installation stability of the first constraint member 4. Secondly, when the second rotating sleeve 51 drives the two second connecting rods 52 away from each other, the abutment block 53 pushes the first connecting rod 42 through the guide surface 422, causing the first connecting rod 42 to tighten the seal 2, thereby improving the overall structural rigidity. Example 2

[0041] This application also discloses a construction method for post-cast strips on basement exterior walls.

[0042] A construction method for post-cast strips on basement exterior walls, specifically including the following steps: S1. Reservation and Pre-treatment of Intermittent Pouring Zone 3: This step is for the formation of the post-pouring strip foundation, mainly completing the reservation and sealing protection construction of the intermittent pouring zone 3 during the main concrete pouring stage of the exterior wall. During construction, the location of the intermittent pouring zone 3 is strictly located according to the design drawings. The width of the conventional external wall post-pouring strip is set at 800-1000mm, running through the exterior wall from top to bottom. First, the original wall reinforcement of the intermittent pouring zone 3 is sorted and regulated to ensure that the reinforcement spacing and protective layer thickness meet the design requirements, and there are no bending, displacement, or corrosion issues.

[0043] Subsequently, double-layer steel wire mesh was installed to seal the concrete interfaces on both sides of the intermittent pouring area 3. The steel wire mesh was securely tied to the reinforcing steel frame, and the intersections of the horizontal and vertical reinforcing bars were fully secured to prevent grout leakage and sand runoff during concrete pouring. After the sealing was completed, the main structure concrete of the exterior wall was poured. During the pouring process, the boundary of the post-pouring strip was strictly controlled, and concrete overflow and accumulation into the intermittent pouring area 3 were strictly prohibited. At the same time, vibration was carried out to ensure the density of the concrete on both sides of the wall. After the main concrete was poured, the intermittent pouring area 3 was promptly sealed and protected with a protective film to prevent debris, construction waste, and rainwater from entering the trench, thus completing the construction of the intermittent pouring area 3.

[0044] S2. Construction of Seal 2: Seal 2, the first constraint member 4, and the second constraint member 5 are constructed within the intermittent pouring area 3. After construction, baffles are installed between two adjacent seals 2 in the width direction of the intermittent pouring area 3. The two baffles and the two connecting interfaces 31 together form an open-top intermittent pouring area 3. The baffles are tightly joined and firmly reinforced to prevent formwork bulging and grout leakage during pouring. The verticality and flatness of the formwork meet the wall construction standards.

[0045] S3. Pouring of post-cast main body 1: After the baffle is accepted, micro-expansion impermeable concrete that meets the design requirements is used for pouring. The concrete strength grade is one grade higher than that of the original wall concrete on both sides. The concrete slump and mix ratio are strictly controlled to prevent unqualified materials from entering the site.

[0046] The post-cast main structure 1 is poured using a layered, continuous pouring method, with each layer thickness controlled within 300mm. Simultaneously, an immersion vibrator is used for thorough compaction, with particular emphasis on the interface between new and old concrete. This ensures the concrete is dense and free of honeycomb, pitting, and voids, and is poured in one continuous pour, with no interruptions or secondary joints permitted. After pouring, the surface is promptly finished and pressed. Once initial setting is achieved, the baffle is removed, and waterproofing reinforcement work is immediately carried out on the outside of the post-cast strip of the exterior wall. This work connects to the overall waterproofing system of the exterior wall, sealing construction gaps and enhancing seepage prevention.

[0047] Finally, the standardized curing stage begins. After the post-cast main body 1 concrete is formed, it should be promptly covered with moisturizing material and continuously moisturized for no less than 14 days. Temperature and humidity must be strictly controlled during the curing period to prevent the concrete from losing water too quickly and causing shrinkage cracks. During the curing period, external impacts and vibrations to the wall are prohibited. Subsequent processes such as backfilling and decoration of the exterior wall can only be carried out after the concrete strength reaches 100% of the design strength, and then the entire cast-in-place strip is constructed.

[0048] The above are preferred embodiments of this application, and are not intended to limit the scope of protection of this application. Therefore, all equivalent changes made to the structure, shape and principle of this application should be covered within the scope of protection of this application.

Claims

1. A water-stopping system for post-cast strips on basement exterior walls, characterized in that: It includes a post-cast main body (1) and multiple seals (2). The basement exterior wall has a reserved intermittent casting area (3). The post-cast main body (1) is cast in the intermittent casting area (3). Two joint interfaces (31) are formed between the post-cast main body (1) and the basement exterior wall. Sealing grooves (32) for the seals (2) to be embedded are opened on both sides of the joint interface (31).

2. The basement exterior wall post-cast strip water-stopping system according to claim 1, characterized in that: The sealing groove (32) is adapted to the shape of the sealing strip (2). The sealing groove (32) includes a first inlay (321) provided on the outer wall and a second inlay (322) provided on the post-cast body (1).

3. The basement exterior wall post-cast strip water-stopping system according to claim 1, characterized in that: The seal (2) includes a first sealing part (21) and a second sealing part (22), which are arranged perpendicularly to each other. The first sealing part (21) has a first bend (23), which is arranged parallel to the second sealing part (22). The second sealing part (22) has a second bend (24), which is arranged parallel to the first sealing part (21).

4. The basement exterior wall post-cast strip water-stopping system according to claim 3, characterized in that: The first sealing part (21), the second sealing part (22), the first bending part (23) and the second bending part (24) surround and form an interlocking area (25), and the post-cast body (1) has an interlocking part (11) that is embedded in the interlocking area (25).

5. A water-stopping system for post-cast strips on basement exterior walls according to claim 1, characterized in that: The two adjacent seals (2) in the thickness direction of the outer wall are connected by a first constraint member (4), and the two adjacent seals (2) in the width direction of the intermittent pouring area (3) are connected by a second constraint member (5). The first constraint member (4) and the second constraint member (5) are both embedded in the post-pouring body (1).

6. A water-stopping system for post-cast strips on basement exterior walls according to claim 5, characterized in that: The first constraint member (4) includes a first rotating sleeve (41) and two first connecting rods (42). The ends of the two first connecting rods (42) that are close to each other are threaded into the first rotating sleeve (41), and the ends of the two first connecting rods (42) that are far apart from each other are respectively connected to two adjacent seals (2) in the thickness direction of the outer wall.

7. A water-stopping system for post-cast strips on basement exterior walls according to claim 6, characterized in that: The side wall of the seal (2) is provided with a connecting hole (26), the inner diameter of the connecting hole (26) is adapted to the outer diameter of the first connecting rod (42), and the side wall of the seal (2) is provided with an inlet and outlet groove (261) that connects to the connecting hole (26); the outer peripheral wall of the end of the first connecting rod (42) away from the first rotating sleeve (41) is provided with two cutting surfaces (421), and the distance between the two cutting surfaces (421) is adapted to the distance between the two opposite side walls of the inlet and outlet groove (261).

8. A water-stopping system for post-cast strips on basement exterior walls according to claim 6, characterized in that: The second constraint member (5) includes a second rotating sleeve (51) and two second connecting rods (52). The ends of the two second connecting rods (52) that are close to each other are threaded into the second rotating sleeve (51), and the ends of the two second connecting rods (52) that are far apart from each other abut against two adjacent seals (2) in the width direction of the intermittent pouring area (3).

9. A water-stopping system for post-cast strips on basement exterior walls according to claim 8, characterized in that: The second link (52) has an abutment block (53) at one end away from the second rotating sleeve (51), and the first link (42) has a guide surface (422) at one end away from the first rotating sleeve (41). The abutment block (53) abuts against the guide surface (422) to guide the first link (42) to slide closer to the first rotating sleeve (41).

10. A construction method for a post-cast strip on the exterior wall of a basement, based on a water-stopping system for a post-cast strip on the exterior wall of a basement as described in any one of claims 1-9, comprising the following steps: S1, placement and pretreatment of the intermittent pouring area (3); S2, construction of the sealing strip (2); S3, pouring of the post-cast main body (1).