Wharf riprap foundation combined dredging and grouting reinforcement system and construction method
By using a flexible sealing skirt and protective grid adsorption assembly, combined with a pipe delivery assembly and a filter assembly, the problems of clogging and high-frequency vibration damage in the sludge suction equipment were solved, enabling efficient dredging and grouting reinforcement of the old wharf, and improving construction efficiency and equipment lifespan.
Patent Information
- Application Number
- CN202611529586.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies for treating silt and cinders at old wharves often result in clogging of suction equipment and damage to the original foundation by high-frequency vibrating rods, making it difficult to achieve efficient dredging and grouting reinforcement.
The adsorption assembly, which uses a flexible sealing skirt and protective grid, combined with the pipe delivery assembly and the filter assembly, achieves low-frequency vibration to unlock the sludge and isolate the coal slag. The adsorption cylinder is raised and lowered by the pipe delivery motor, and a high-pressure water pump is set up to wash the boulders. The equipment integrates sludge suction, slag removal, backfilling and grouting into one unit.
This ensured the continuity and high efficiency of the sludge suction equipment, prevented equipment damage, improved construction efficiency, and guaranteed the reinforcement quality and equipment lifespan of the old wharf.
Smart Images

Figure CN123109241A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of old wharf renovation technology, and in particular to a wharf riprap foundation combined dredging and grouting reinforcement system and construction method. Background Technology
[0002] With the rapid development of the port industry, high-quality shoreline resources in coastal and inland river ports are becoming increasingly scarce, and the space for new construction is constantly shrinking. Older wharves generally suffer from insufficient berth capacity, aging facilities, and low operational efficiency, making them ill-suited to the trends of larger ships and more efficient port operations. Therefore, revitalizing existing shoreline and upgrading facilities through the renovation and expansion of old wharves has become an important way for the port industry to improve quality and efficiency and achieve high-quality development.
[0003] To carry out the renovation project of the old wharf, the existing technology usually uses sludge suction equipment, long-arm excavators, rubble backfilling equipment and grouting equipment for reinforcement work. Among them, sludge suction equipment is used to absorb silt, long-arm excavators are used to clean up coal slag, rubble backfilling equipment is usually a regular excavator or loader in conjunction with a long-arm excavator to fill the cleaned position with rubble, and grouting equipment is used to inject cement grout into the position of filling rubble to ensure the structural stability of the renovated wharf.
[0004] In some old wharves, coal slag and silt tend to accumulate in the waters near the riprap bed. It is necessary to clean up the silt and coal slag before proceeding with the riprap grouting. The preferred method is to use a sludge suction device to treat the silt. However, during the silt treatment process, coal slag can easily clog the suction end of the sludge suction device, which can easily lead to damage to the device.
[0005] Existing technology typically uses screens to block coal slag. However, the size of the coal slag varies, while the mesh size of the screen remains constant. During continuous use, some of the screen mesh holes will become clogged, which is not conducive to continuous mud suction. In other engineering operations, high-frequency vibratory rods are used to separate silt and cinder into layers before suctioning. However, continuous high-frequency vibration can affect the original foundation of the old wharf, so the use of high-frequency vibratory rods is not suitable for old wharf renovation projects.
[0006] Based on this, this application designs a combined dredging and grouting reinforcement system and construction method for wharf riprap foundation beds to solve the above problems. Summary of the Invention
[0007] To achieve the above objectives, this application provides the following technical solution: The combined dredging and grouting reinforcement system for the riprap foundation of the wharf includes: The base is equipped with mud suction equipment, long-arm excavator, riprap backfilling equipment and grouting equipment; The suction pipe and the extension pipe are slidably sleeved inside the suction pipe, and the other end of the suction pipe is connected to the absorption end of the suction equipment. An adsorption assembly is connected to the bottom end of an elongation tube. The adsorption assembly includes an adsorption cylinder, the top of which is connected to the bottom end of the elongation tube. A flexible sealing skirt is fixedly installed at the bottom of the adsorption cylinder, and a protective grid is fixedly installed at the bottom of the flexible sealing skirt. Side cylinders are fixedly installed on both sides of the adsorption cylinder. A rotating shaft is rotatably connected inside the side cylinder. Two sets of impellers are fixedly installed on the rotating shaft. A protrusion is fixedly installed on the rotating shaft and between the two sets of impellers. A positioning ring is sleeved on the rotating shaft and outside the protrusion. The end of the protrusion is always pressed against the inner wall of the positioning ring. A pull rod is fixedly installed at the bottom of the positioning ring. A transmission rod is rotatably connected to the bottom end of the pull rod. A vibrating rod is fixedly installed at the bottom end of the transmission rod. The filter assembly is located on one side of the discharge end of the sludge suction device.
[0008] Preferably, the rubble backfilling equipment includes: Two sets of support frames are fixedly mounted on the base, and a drive motor and transmission components are mounted on one set of support frames. The conveying mechanism includes a conveyor belt and a frame; The discharge hopper is arranged at an angle on one side of the conveying mechanism; The first support rod and the second support rod are connected. The top of the first support rod is rotatably connected to one side of the bottom of the discharge hopper. A buffer spring is also fixedly installed at the top of the second support rod, and the top of the buffer spring is fixedly connected to the other side of the bottom of the discharge hopper.
[0009] Preferably, it also includes a tube feeding assembly, wherein the tube feeding assembly includes: Two sets of support columns, with support seats fixedly installed at the top of the two sets of support columns; The tube feeding motor has a take-up roller coaxially fixed to its output end. The tube feeding motor is fixedly connected to the support base, and the take-up roller is rotatably connected to the support base. A cable is wound on the take-up roller. Two sets of drive plates are provided. One set of drive plates is fixedly connected to one side of the extension tube, and the other set of drive plates is fixedly connected to the outer wall of the adsorption cylinder. Both sets of drive plates are also fixedly connected to the cable.
[0010] Preferably, the filtering component includes: The filter tank is fixed on the base and located on one side of the discharge end of the sludge suction equipment. A filter cavity is provided inside the filter tank. The filter screen is movably connected to the top of the filter plate, and the filter plate is fixed inside the filter tank and divides the internal cavity of the filter tank into two parts. The drive box is fixedly installed on the side of the filter tank near the filter screen. Inside the drive box is a drive component for driving the filter screen to vibrate.
[0011] Preferably, the driving component includes: A partition is fixed inside the drive box. A filter motor is fixedly connected to one side of the partition. A transmission gear is coaxially fixed on the output shaft of the filter motor. A rotating drum is mounted on the partition plate. Arc-shaped protrusions are fixedly connected to both sides of the top of the drum. A driven gear is coaxially fixed at the bottom of the drum. A toothed belt is provided between the driven gear and the transmission gear for transmission. A sleeve is fixedly mounted on the drive box. A locking rod is slidably mounted inside the sleeve. A return spring is fixedly connected to the bottom of the inner wall of the sleeve, and one end of the return spring is fixedly connected to the locking rod. The vibrating guide rod is slidably connected to the filter tank. The end of the vibrating guide rod is movably connected to the filter screen, and the vibrating guide rod is also fixedly connected to the locking rod.
[0012] Preferably, a high-pressure water pump is installed on the base and on one side of the filter tank. The inlet end of the high-pressure water pump is connected to the filter tank, and a delivery pipe is connected to the outlet end of the high-pressure water pump. Two sets of spray pipes are connected to one end of the delivery pipe, and multiple high-pressure nozzles are installed on each of the two sets of spray pipes.
[0013] Preferably, the two sets of water spray pipes are symmetrically arranged on both sides above the rubble backfilling equipment, and multiple high-pressure nozzles are respectively arranged obliquely and symmetrically on both sides above the rubble backfilling equipment.
[0014] Preferably, the top of the vibrating rod is also fixedly provided with two sets of anti-detachment rods, and the top ends of the two sets of anti-detachment rods are fixedly connected to the inner side of the flexible sealing skirt.
[0015] Preferably, a limiting ring is also fixedly provided between the two sets of support columns, and the limiting ring is sleeved on the outside of the suction pipe.
[0016] The construction method of the combined dredging and grouting reinforcement system for wharf riprap foundation includes the following steps: Step 1: Move the base to the location to be modified, and control the adsorption component to be lowered to the bottom of the water through the pipe delivery assembly. The flexible sealing skirt contacts the silt to form a seal. After the sludge suction equipment is started, the fluid drives the impeller to rotate. Through the rotating shaft, protrusion, positioning ring, tie rod and transmission rod, the vibrating rod and protective grid vibrate, unlocking the silt into a fluid state and preventing coal slag from blocking it. The sludge suction equipment discharges the silt and water mixture into the filter tank. Step 2: After the mud enters the filtration tank, it is filtered by the filter screen. The filter motor drives the rotating drum to rotate through the transmission gear and toothed belt. The arc-shaped protrusion periodically pushes the locking rod, and the filter screen vibrates to prevent clogging through the vibrating guide rod. The filtered clear water enters the clear water chamber. Step 3: The high-pressure water pump draws out clean water and washes the stones conveyed on the conveying mechanism through the water spray pipe and high-pressure nozzle to remove surface dirt. Step 4: After rinsing, the rubble is backfilled into the cleaned area, and underwater anti-dispersion concrete is injected into the gaps between the rubble using grouting equipment to complete the reinforcement.
[0017] In summary, this application has the following beneficial effects: 1. This application utilizes a flexible sealing skirt and protective grid at the bottom of the suction cylinder. The fluid flow generated during the operation of the sludge suction equipment drives the impeller to rotate, which in turn drives the convex blocks to periodically push against the positioning ring via the rotating shaft. This causes the tie rod and transmission rod to drive the vibrating rod and protective grid to generate low-frequency vibration. This vibration can unlock the sludge from a static binnaire into a fluid medium, making it easier for the sludge suction equipment to absorb. At the same time, the vibration transmitted to the protective grid can prevent coal slag from clogging the mesh. This achieves sludge liquefaction and coal slag isolation without the use of high-frequency vibrating rods, avoiding vibration damage to the original foundation of the old wharf.
[0018] 2. This application sets up a pipe feeding assembly, which uses a pipe feeding motor to drive the winding roller to wind and unwind the cable, thereby driving the suction cylinder and the extension pipe to rise and fall synchronously. This allows the suction assembly to adapt to the working conditions of the dock corners at different water depths. The extension pipe and the suction pipe are slidably fitted together, and the seal is maintained throughout the lifting and lowering process of the suction cylinder, ensuring the continuity of the suction operation.
[0019] 3. This application sets up a filter assembly at the discharge end of the sludge suction equipment. After the sludge enters the filter tank, it is filtered by the filter screen. The drive assembly periodically pushes the locking rod through the arc-shaped protrusion on the rotating drum, which drives the vibrating guide rod to make the filter screen vibrate. This prevents impurities from clogging the mesh during the filtration process and ensures the filtration efficiency. The filtered clean water can be drawn out by a high-pressure water pump and used to wash the stones on the conveying mechanism through the water spray pipe and high-pressure nozzle. This removes the soil attached to the surface of the stones and improves the bonding strength between the subsequent grouting concrete and the stones, thus realizing the recycling of water resources.
[0020] 4. This application sets up a riprap backfilling device with an inclined hopper that is supported at the bottom by a first and second support rod in conjunction with a buffer spring. When the riprap slides down the hopper to the conveying mechanism, the buffer spring absorbs the impact load, reduces equipment wear, and extends service life.
[0021] 5. This application integrates sludge suction and dredging, coal slag grabbing, boulders backfilling and grouting reinforcement on the same base, with smooth material flow between each process. The filtered clean water is used for boulders washing, forming a combined dredging and reinforcement system, which improves the construction efficiency of the old wharf renovation project. Attached Figure Description
[0022] Figure 1 This is a schematic diagram of the overall structure of this application.
[0023] Figure 2 This is a structural diagram from another perspective of the entire application.
[0024] Figure 3 This is a schematic diagram of the tube feeding assembly in this application.
[0025] Figure 4 This is a schematic diagram of the adsorption component in this application.
[0026] Figure 5 This is a schematic diagram of the positioning ring in this application.
[0027] Figure 6 This is a schematic diagram of the structure of the filter pool in this application.
[0028] Figure 7 This is a schematic diagram of the structure of the driving component in this application.
[0029] Figure 8 This is a schematic diagram of the internal structure of the sleeve in this application.
[0030] Figure 9 This is a schematic diagram of the construction location for this application.
[0031] Explanation of reference numerals in the attached drawings: 1. Base; 2. Sludge suction equipment; 3. Long-arm excavator; 4. Rock backfilling equipment; 41. Support frame; 42. Conveying mechanism; 43. Support rod No. 1; 44. Discharge hopper; 45. Support rod No. 2; 46. Buffer spring; 5. Pipe delivery assembly; 51. Support column; 52. Support base; 53. Pipe delivery motor; 54. Rewind roller; 55. Cable; 56. Drive plate; 57. Limiting ring; 6. Adsorption assembly; 61. Adsorption cylinder; 62. Flexible sealing skirt; 63. Side cylinder; 64. Protective grid; 65. Vibrating rod; 66. Transfer rod; 67. Rotating shaft; 68. Impeller; 69. 610. Positioning ring; 611. Pull rod; 612. Protrusion; 613. Anti-detachment rod; 7. Filter assembly; 71. Filter tank; 72. Filter plate; 73. Filter screen; 74. Drive box; 75. Drive assembly; 751. Partition plate; 752. Filter motor; 753. Rotary drum; 754. Arc-shaped protrusion; 755. Sleeve; 756. Locking rod; 757. Vibration guide rod; 758. Transmission gear; 759. Driven gear; 7510. Toothed belt; 7511. Return spring; 8. High-pressure water pump; 9. Delivery pipe; 10. Spray pipe; 11. High-pressure nozzle; 12. Sludge suction pipe; 13. Extension pipe. Detailed Implementation
[0032] To make the objectives, technical solutions, and advantages of the embodiments of this application clearer, the technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this application, not all embodiments. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0033] Reference Figures 1-9 This application provides a combined dredging and grouting reinforcement system for wharf riprap foundations, including: The base 1 is equipped with a sludge suction device 2, a long-arm excavator 3, a riprap backfilling device 4, and a grouting device (not shown in the figure). The sludge suction device 2 is usually a sludge suction pump, which is used to absorb sludge. The long-arm excavator 3 is used to clean up coal slag. The riprap backfilling device 4 is used to replenish riprap to the cleaned position. The grouting device is used to inject concrete at the position of the filled riprap to ensure the strength of the modified wharf. The grouting device usually includes a slurry preparation system, a grouting pump, and an underwater grouting device. The concrete grouting method in this application is the same as the existing grouting method. The suction pipe 12 and the extension pipe 13 are slidably sleeved inside the suction pipe 12. The other end of the suction pipe 12 is connected to the absorption end of the suction device 2. During the lifting and lowering of the suction cylinder, the suction pipe 12 and the extension pipe 13 are always kept in sealed communication. The suction device 2, the suction pipe 12 and the extension pipe 13 are used to absorb the silt in the deep. The adsorption assembly 6 is connected to the bottom end of the extension tube 13. The adsorption assembly 6 includes an adsorption cylinder 61, the top of which is connected to the bottom end of the extension tube 13. A flexible sealing skirt 62 is fixedly installed at the bottom of the adsorption cylinder 61, and a protective grid 64 is fixedly installed at the bottom of the flexible sealing skirt 62. Side cylinders 63 are fixedly installed on both sides of the adsorption cylinder 61. A rotating shaft 67 is rotatably connected inside the side cylinder 63. Two sets of impellers 68 are fixedly installed on the rotating shaft 67. A protrusion 611 is fixedly installed on the rotating shaft 67 between the two sets of impellers 68. A positioning ring 69 is sleeved on the rotating shaft 67 outside the protrusion 611. The end of the protrusion 611 is always pressed against the inner wall of the positioning ring 69. A pull rod 610 is fixedly installed at the bottom of the positioning ring 69. A transmission rod 66 is rotatably connected to the bottom end of the pull rod 610. A vibrating rod 65 is fixedly installed at the bottom end of the transmission rod 66. It should be noted that the flexible sealing skirt 62 is typically made of neoprene rubber. When absorbing silt from the bottom of the water, the bottom of the flexible sealing skirt 62 contacts the top of the silt, and then the silt is absorbed by the adsorption cylinder 61. The protective grid 64 has a pore size of 10~20mm to block large pieces of coal slag. The internal cavity of the adsorption cylinder 61 is connected to the internal cavity of the side cylinder 63. Part of the impeller 68 is located inside the internal cavity of the adsorption cylinder 61, and the blades of the impeller 68 can be driven to rotate by the fluid passing through the adsorption cylinder 61. The rotation of the impeller 68 drives the rotating shaft 67 to rotate, thereby changing the position of the protrusion 611. When the protrusion 611 is at the top, the positioning ring 69 moves to the top at the same time. When the protrusion 611 is at the bottom, the positioning ring 69 moves to the bottom at the same time. Then, when the impeller 68 continues to rotate, it can drive the positioning ring 69 to move continuously, which can synchronously drive the tie rod 610 to shake continuously, and then drive the bottom transmission rod 66 to shake. At this time, it synchronously drives the vibrating rod 65 and the protective grid 64 to vibrate. When the vibrating rod 65 vibrates, the sludge is liquefied through rapid vibration, and the coal slag settles in the sludge due to the density difference. At the same time, the low-frequency vibration of the vibrating rod 65 reduces the Bingham yield stress of the sludge, making it easier to absorb. At the same time, the vibration can be transmitted to the protective grid 64 to achieve dynamic isolation protection, and also prevent slightly larger coal slag from being stuck in the through holes of the protective grid 64 for a long time, thus ensuring that the sludge suction efficiency does not decrease. Filter assembly 7 is arranged on one side of the discharge end of the sludge suction device 2 and is used to filter the absorbed sludge. Reference Figure 9 , Figure 9 Point A represents the wharf, point B represents the mixture of coal slag and silt, and point C represents the foundation bed. After cleaning up the coal slag and silt, the cleaned areas are filled with rubble and then grouted with concrete to reinforce the wharf.
[0034] Furthermore, the rubble backfilling equipment 4 includes: Two sets of support frames 41 are fixedly mounted on the base 1. A drive motor and transmission components are mounted on one set of support frames 41. The conveying mechanism 42 includes a conveyor belt and a frame. The conveyor belt is driven to move on the frame by a drive motor and a transmission assembly, thereby realizing the conveying of the stones. The feeding hopper 44 is arranged at an angle on one side of the conveying mechanism 42; The first support rod 43 and the second support rod 45 are connected to the bottom side of the discharge hopper 44 by rotating the top of the first support rod 43. A buffer spring 46 is also fixedly installed at the top of the second support rod 45. The top of the buffer spring 46 is fixedly connected to the bottom side of the discharge hopper 44. It should be noted that the connection between the discharge hopper 44 and the first support rod 43 is located at a low position. The tilt angle of the discharge hopper 44 is usually 30~45°. After the stones are put into the discharge hopper 44, the stones slide down the discharge hopper 44 onto the conveying mechanism 42 for subsequent stone backfilling work.
[0035] Furthermore, it also includes a tube feeding assembly 5, wherein the tube feeding assembly 5 includes: Two sets of support columns 51, with support seats 52 fixedly installed at the top of the two sets of support columns 51; The tube feeding motor 53 has a take-up roller 54 coaxially fixed at its output end. The tube feeding motor 53 is fixedly connected to the support base 52, and the take-up roller 54 is rotatably connected to the support base 52. A cable 55 is wound on the take-up roller 54. Two sets of driving plates 56, one set of driving plates 56 is fixedly connected to one side of the extension tube 13, and the other set of driving plates 56 is fixedly connected to the outer wall of the adsorption cylinder 61. At the same time, both sets of driving plates 56 are fixedly connected to the cable 55. It should be noted that the cable 55 is fixed and passes through the upper drive plate 56. When the tube feeding motor 53 is working, its output shaft drives the take-up roller 54 to rotate, so that the cable 55 is wound or unwound on the take-up roller 54, which can control the height of the adsorption cylinder 61.
[0036] Furthermore, a limiting ring 57 is fixedly installed between the two sets of support columns 51. The limiting ring 57 is sleeved on the outside of the suction pipe 12 to support the suction pipe 12. A guide ring is fixedly connected to one side of the support base 52. The cable 55 can pass through the inside of the guide ring, so that the cable 55 can be limited when moving, ensuring that it can move stably.
[0037] Furthermore, the filter component 7 includes: The filter tank 71 is fixed on the base 1 and located on one side of the discharge end of the sludge suction device 2. A filter cavity is provided inside the filter tank 71. After the sludge suction device 2 absorbs the mixture of sludge and water, it can be discharged into the filter cavity inside the filter tank 71. The filter screen 73 is movably connected to the top of the filter plate 72. The filter plate 72 is fixed inside the filter tank 71 and divides the internal cavity of the filter tank 71 into two parts: one part is used to temporarily store sludge or impurities, and the other part is a water tank without large particles. The drive box 74 is fixedly installed on the filter tank 71 on the side near the filter screen 73. Inside the drive box 74 is a drive assembly 75 for driving the filter screen 73 to vibrate, which can filter the sludge mixture discharged from the sludge suction device 2, thereby facilitating the subsequent use of the filtered water.
[0038] Furthermore, the drive component 75 includes: A partition 751 is fixed inside the drive box 74. A filter motor 752 is fixedly connected to one side of the partition 751. A transmission gear 758 is coaxially fixed on the output shaft of the filter motor 752. A rotating drum 753 is rotatably mounted on a partition plate 751. Arc-shaped protrusions 754 are fixedly connected to both sides of the top of the rotating drum 753. A driven gear 759 is coaxially fixed to the bottom of the rotating drum 753. A toothed belt 7510 is provided between the driven gear 759 and the transmission gear 758 for transmission. When the filter motor 752 drives the transmission gear 758 to rotate, it can drive the driven gear 759 and the rotating drum 753 to rotate through the toothed belt 7510. A sleeve 755 is fixedly mounted on the drive box 74. A locking rod 756 is slidably mounted inside the sleeve 755. A return spring 7511 is fixedly connected to the bottom of the inner wall of the sleeve 755. One end of the return spring 7511 is fixedly connected to the locking rod 756 for resetting the locking rod 756. The vibrating guide rod 757 is slidably connected to the filter tank 71. The end of the vibrating guide rod 757 is movably connected to the filter screen 73. The vibrating guide rod 757 is also fixedly connected to the locking rod 756. It should be noted that the locking rod 756 is "mountain" shaped, with the middle part of the locking rod 756 being slidably connected to the sleeve 755. The other two ends of the locking rod 756 can abut against the arc-shaped protrusion 754. When the locking rod 756 abuts against the top of the arc-shaped protrusion 754, it can be pulled out of the sleeve 755 a certain distance, thereby driving the vibrating guide rod 757 to move axially, and then driving the filter screen 73 to move a certain distance, thereby achieving dynamic filtration. It should be further explained that the vibrating guide rod 757 is U-shaped and has a sliding seal connection with the filter tank 71. The above-mentioned movable connection can usually be connected by a spring so that it can move relative to the filter tank while maintaining the connection.
[0039] Furthermore, a high-pressure water pump 8 is installed on the base 1 and on one side of the filter tank 71. The inlet end of the high-pressure water pump 8 is connected to the filter tank 71, and the outlet end of the high-pressure water pump 8 is connected to a delivery pipe 9. Two sets of spray pipes 10 are connected to one end of the delivery pipe 9. Multiple high-pressure nozzles 11 are installed on both sets of spray pipes 10. The water sprayed by the high-pressure nozzles 11 washes the subsequently filled boulders, effectively removing the soil attached to the boulders, thereby ensuring a better bonding effect between the concrete and the boulders when the concrete is poured later. It should be noted that although the boulders will fall from the water to the bottom during filling, this only washes away the soil at the bottom of the boulders and the dust on the surface. Harder or stickier soil on the boulders is not easy to fall off, which will reduce the bonding strength between the concrete and the boulders.
[0040] Furthermore, two sets of water spray pipes 10 are symmetrically arranged on both sides above the rubble backfilling equipment 4, and multiple high-pressure nozzles 11 are respectively arranged obliquely and symmetrically on both sides above the rubble backfilling equipment 4. It should be noted that the inlet end of the high-pressure water pump 8 is connected to the part of the filter tank 71 that does not contain large particles, and is used to extract the water inside. The water sprayed by the high-pressure nozzle 11 can wash away the soil on the surface of the stones on the conveyor belt, thereby improving the bonding strength between the subsequently added stones and the concrete.
[0041] Furthermore, two sets of anti-detachment rods 612 are fixedly installed on the top of the vibrating rod 65. The top ends of the two sets of anti-detachment rods 612 are fixedly connected to the inside of the flexible sealing skirt 62, which can improve the stability of the connection of the vibrating rod 65 and make it easier to insert into the silt.
[0042] Furthermore, multiple casters are provided at the bottom of the base 1, which facilitates the movement or turning of the base 1 on the dock.
[0043] The construction method of the combined dredging and grouting reinforcement system for wharf riprap foundation includes the following steps: Step 1: Move the base 1 to the location to be modified, and control the adsorption component 6 to be lowered to the bottom of the water through the pipe delivery component 5. The flexible sealing skirt 62 comes into contact with the silt to form a seal. After the sludge suction device 2 is started, the fluid drives the impeller 68 to rotate. Through the rotating shaft 67, protrusion 611, positioning ring 69, pull rod 610 and transmission rod 66, the vibrating rod 65 and protective grid 64 vibrate, unlocking the silt into a fluid state and preventing coal slag from blocking it. The sludge suction device 2 discharges the silt and water mixture to the filter tank 71. Step 2: After the mud enters the filter tank 71, it is filtered by the filter screen 73. The filter motor 752 drives the rotating drum 753 to rotate through the transmission gear 758 and the toothed belt 7510. The arc-shaped protrusion 754 periodically pushes the locking rod 756, and the filter screen 73 vibrates to prevent clogging through the vibration guide rod 757. The filtered clean water enters the clean water chamber. Step 3: The high-pressure water pump 8 draws out clean water and washes the stones conveyed on the conveying mechanism 42 through the water spray pipe 10 and the high-pressure nozzle 11 to remove the surface dirt. Step 4: After rinsing, the rubble is backfilled into the cleaned area, and underwater anti-dispersion concrete is injected into the gaps between the rubble using grouting equipment to complete the reinforcement.
[0044] It needs to be further explained that: In step one, the base 1 is equipped with casters at its bottom. During construction, the base 1 is moved to the corner of the old dock that needs to be renovated. The pipe feeding motor 53 is started, and the output shaft of the pipe feeding motor 53 drives the take-up roller 54 to rotate. The cable 55 on the take-up roller 54 is guided by the guide ring and then two sets of drive plates 56 are lowered. One set of drive plates 56 is fixed to one side of the extension pipe 13, and the other set of drive plates 56 is fixed to the outer wall of the suction cylinder 61. Under the action of gravity, the extension pipe 13 slides down from the sludge suction pipe 12, controlling the suction cylinder 61. The suction cylinder 61 moves downwards to the bottom of the water to reach the mixture of coal slag and silt. After reaching the working position, the flexible sealing skirt 62, made of neoprene rubber, deforms and conforms to the silt surface after its bottom contacts the top of the silt, forming a local sealing cavity. The suction device 2 is then activated. The suction device 2 generates negative pressure inside the suction cylinder 61 through the suction pipe 12 and the extension pipe 13, drawing in the silt and water. As the fluid passes through the inside of the suction cylinder 61, the water flow drives the impeller 68 inside the side cylinder 63 to rotate. The impeller 68 is fixed on the rotating shaft 67. The two sides of the rotating shaft 67... The end is rotatably connected inside the side cylinder 63. When the rotating shaft 67 rotates, the protrusion 611 fixed on the rotating shaft 67 rotates accordingly. The end of the protrusion 611 is always pressed against the inner wall of the positioning ring 69. Since the protrusion 611 is an eccentric cam structure, when the protrusion 611 rotates to different positions, it pushes the positioning ring 69 to move. The positioning ring 69 drives the transmission rod 66 through the pull rod 610. The vibrating rod 65 at the bottom of the transmission rod 66 then generates axial vibration. At the same time, the transmission rod 66 transmits the vibration to the protective grid 64. The vibrating rod 65 is inserted into... In the sludge, low-frequency vibration reduces the Bingham yield stress, transforming the sludge from a static plastic mass into a flowable liquid, facilitating suction by the sludge suction device 2. Synchronous vibration of the protective grid 64 dislodges coal slag trapped in the mesh, preventing blockage. The protective grid 64 has a mesh size of 10 to 20 mm, allowing sludge to pass through while preventing large pieces of coal slag from entering the adsorption cylinder 61. The anti-detachment rod 612 connects at both ends to the top of the vibrating rod 65 and the inner side of the flexible sealing skirt 62, respectively, improving the connection stability of the vibrating rod 65 during vibration. The sludge suction device 2 discharges the suctioned sludge and water mixture into the filter tank 71.
[0045] In step two, the mixture discharged from the sludge suction device 2 enters the filter cavity of the filter tank 71. The sludge first falls onto the filter screen 73, while water and small particles pass through the filter screen 73 and filter plate 72 into the clear water cavity below the filter plate 72. The filter motor 752 is started, and the output shaft of the filter motor 752 drives the transmission gear 758 to rotate. The transmission gear 758 drives the driven gear 759 to rotate through the toothed belt 7510. The driven gear 759 drives the rotating drum 753 to rotate on the partition plate 751. The arc-shaped protrusion 754 at the top of the rotating drum 753 rotates with the rotating drum 753. When the arc-shaped protrusion 754 rotates to the position of the locking rod 75... When the end of 6 contacts, the locking rod 756 is pushed out a certain distance from the sleeve 755. The locking rod 756 moves upward against the elastic force of the return spring 7511. The locking rod 756 drives the vibrating guide rod 757 to move axially. During the continuous rotation of the rotating drum 753, the vibrating guide rod 757 continuously pushes and pulls the filter screen 73 on the filter plate 72 to generate vibration, causing the impurities attached to the filter screen 73 to fall off and keep the filtration unobstructed. When the arc-shaped protrusion 754 rotates away from the end of the locking rod 756, the return spring 7511 pulls the locking rod 756 back to its original position, completing one vibration cycle. This process is continuous, realizing dynamic filtration.
[0046] In step three, the inlet pipe of the high-pressure water pump 8 is connected to one side of the clear water chamber of the filter tank 71 to extract the filtered clear water. The clear water is distributed to two sets of spray pipes 10 through the conveying pipe 9. The spray pipes 10 are symmetrically arranged on both sides above the conveying mechanism 42. Multiple high-pressure nozzles 11 are tilted towards the stones on the conveyor belt. The stones are put into the discharge hopper 44. The discharge hopper 44 is tilted and its bottom is supported by the first support rod 43 and the second support rod 45. The buffer spring 46 at the top of the second support rod 45 absorbs the impact load of the falling stones. The stones slide down the discharge hopper 44 onto the conveyor belt of the conveying mechanism 42. The conveyor belt transports the stones under the drive of the drive motor and transmission components. When the stones pass under the high-pressure nozzles 11, the high-pressure water jet washes the surface of the stones to remove the attached mud and fine particles. The clean surface of the washed stones is beneficial to the bonding of concrete and stones during subsequent grouting.
[0047] In step four, the washed boulders are transported to the cleaned foundation bed location via conveyor 42 to complete the backfilling. Then, underwater anti-dispersion concrete is injected into the gaps between the boulders using grouting equipment. The grouting equipment includes a grouting system, a grouting pump, and an underwater conduit. The concrete is injected through the conduit method, with the conduit opening always embedded in the poured concrete to prevent water from mixing in and affecting the concrete quality. After grouting is completed, the concrete hardens and forms a reinforcement layer together with the boulders, completing the renovation and reinforcement of the old wharf.
[0048] This specific embodiment is merely an explanation of this application and is not intended to limit it. After reading this specification, those skilled in the art can make modifications to this embodiment without contributing any inventive step, but such modifications are protected by patent law as long as they are within the scope of the claims of this invention.
Claims
1. A combined dredging and grouting reinforcement system for wharf riprap foundations, characterized in that, include: The base (1) is equipped with a mud suction device (2), a long-arm excavator (3), a riprap backfilling device (4) and a grouting device; The suction pipe (12) and the extension pipe (13) are slidably sleeved inside the suction pipe (12), and the other end of the suction pipe (12) is connected to the absorption end of the suction device (2). An adsorption assembly (6) is connected to the bottom end of an extension tube (13). The adsorption assembly (6) includes an adsorption cylinder (61), the top of which is connected to the bottom end of the extension tube (13). A flexible sealing skirt (62) is fixedly installed at the bottom of the adsorption cylinder (61), and a protective grid (64) is fixedly installed at the bottom of the flexible sealing skirt (62). Side cylinders (63) are fixedly installed on both sides of the adsorption cylinder (61), and a rotating shaft (67) is rotatably connected inside the side cylinder (63). Two sets of impellers (68) are fixedly installed. A protrusion (611) is fixedly installed on the rotating shaft (67) between the two sets of impellers (68). A positioning ring (69) is sleeved on the rotating shaft (67) and outside the protrusion (611). The end of the protrusion (611) is always pressed against the inner wall of the positioning ring (69). A pull rod (610) is fixedly installed at the bottom of the positioning ring (69). A transmission rod (66) is rotatably connected to the bottom end of the pull rod (610). A vibrating rod (65) is fixedly installed at the bottom end of the transmission rod (66). The filter assembly (7) is arranged on one side of the discharge end of the sludge suction device (2).
2. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 1, characterized in that, The rubble backfilling equipment (4) includes: Two sets of support frames (41) are fixedly mounted on the base (1). A drive motor and transmission assembly are mounted on one set of support frames (41). The conveying mechanism (42) includes a conveyor belt and a frame; The feeding hopper (44) is arranged at an angle on one side of the conveying mechanism (42); The first support rod (43) and the second support rod (45) are connected to the bottom side of the discharge hopper (44) by a rotating top end. A buffer spring (46) is also fixedly installed at the top end of the second support rod (45). The top end of the buffer spring (46) is fixedly connected to the bottom side of the discharge hopper (44).
3. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 1, characterized in that, It also includes a tube feeding assembly (5), wherein the tube feeding assembly (5) includes: Two sets of support columns (51) are provided with support seats (52) fixedly installed at the top of the two sets of support columns (51); A tube feeding motor (53) is provided. A take-up roller (54) is coaxially fixed to the output end of the tube feeding motor (53). The tube feeding motor (53) is fixedly connected to the support base (52). The take-up roller (54) is rotatably connected to the support base (52). A cable (55) is wound on the take-up roller (54). Two sets of drive plates (56), one set of drive plates (56) is fixedly connected to one side of the extension tube (13), and the other set of drive plates (56) is fixedly connected to the outer wall of the adsorption cylinder (61). At the same time, both sets of drive plates (56) are fixedly connected to the cable (55).
4. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 1, characterized in that, The filter assembly (7) includes: The filter tank (71) is fixed on the base (1) and located on one side of the discharge end of the sludge suction device (2). A filter cavity is provided inside the filter tank (71). The filter screen (73) and the filter plate (72) are connected to the top of the filter plate (72). The filter plate (72) is fixed inside the filter tank (71) and divides the internal cavity of the filter tank (71) into two parts. The drive box (74) is fixedly installed on the side of the filter tank (71) near the filter screen (73). Inside the drive box (74) is a drive assembly (75) for driving the filter screen (73) to vibrate.
5. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 4, characterized in that, The drive component (75) includes: A partition (751) is fixed inside the drive box (74). A filter motor (752) is fixedly connected to one side of the partition (751). A transmission gear (758) is coaxially fixed on the output shaft of the filter motor (752). A rotating drum (753) is rotatably mounted on a partition (751). Arc-shaped protrusions (754) are fixedly connected to both sides of the top of the rotating drum (753). A driven gear (759) is coaxially fixed at the bottom of the rotating drum (753). A toothed belt (7510) is provided between the driven gear (759) and the transmission gear (758). A sleeve (755) is fixedly mounted on the drive box (74). A locking rod (756) is slidably mounted inside the sleeve (755). A return spring (7511) is fixedly connected to the bottom of the inner wall of the sleeve (755). One end of the return spring (7511) is fixedly connected to the locking rod (756). The vibrating guide rod (757) is slidably connected to the filter tank (71). The end of the vibrating guide rod (757) is movably connected to the filter screen (73). The vibrating guide rod (757) is also fixedly connected to the locking rod (756).
6. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 4, characterized in that, A high-pressure water pump (8) is provided on the base (1) and on one side of the filter tank (71). The inlet end of the high-pressure water pump (8) is connected to the filter tank (71), and a delivery pipe (9) is connected to the outlet end of the high-pressure water pump (8). Two sets of spray pipes (10) are connected to one end of the delivery pipe (9), and multiple high-pressure nozzles (11) are provided on both sets of spray pipes (10).
7. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 6, characterized in that, Two sets of water spray pipes (10) are symmetrically arranged on both sides above the rubble backfilling equipment (4), and multiple high-pressure nozzles (11) are respectively arranged symmetrically on both sides above the rubble backfilling equipment (4).
8. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 1, characterized in that, The top of the vibrating rod (65) is also fixedly provided with two sets of anti-detachment rods (612), and the top ends of the two sets of anti-detachment rods (612) are fixedly connected to the inner side of the flexible sealing skirt (62).
9. The combined dredging and grouting reinforcement system for wharf riprap foundations according to claim 3, characterized in that, A limiting ring (57) is also fixedly installed between the two sets of support columns (51), and the limiting ring (57) is sleeved on the outside of the suction pipe (12).
10. The construction method of the combined dredging and grouting reinforcement system for wharf riprap foundations according to any one of claims 1-9, characterized in that, Includes the following steps: Step 1: Move the base (1) to the location to be modified, and control the adsorption component (6) to be lowered to the bottom of the water through the pipe delivery component (5). The flexible sealing skirt (62) comes into contact with the silt to form a seal. After the sludge suction device (2) is started, the fluid drives the impeller (68) to rotate. Through the rotating shaft (67), protrusion (611), positioning ring (69), pull rod (610) and transmission rod (66), the vibrating rod (65) and protective grid (64) vibrate, unlocking the silt into a fluid state and preventing coal slag from blocking it. The sludge suction device (2) discharges the silt and water mixture to the filter tank (71). Step 2: After the mud enters the filter tank (71), it is filtered by the filter screen (73). The filter motor (752) drives the rotating drum (753) to rotate through the transmission gear (758) and toothed belt (7510). The arc-shaped protrusion (754) periodically pushes the locking rod (756), and the filter screen (73) vibrates to prevent clogging through the vibration guide rod (757). The filtered clean water enters the clean water chamber. Step 3: The high-pressure water pump (8) draws out clean water and washes the stones conveyed on the conveying mechanism (42) through the water spray pipe (10) and high-pressure nozzle (11) to remove surface dirt. Step 4: After rinsing, the rubble is backfilled into the cleaned area, and underwater anti-dispersion concrete is injected into the gaps between the rubble using grouting equipment to complete the reinforcement.