By using a tensioning mechanism consisting of curved plates, L-shaped connecting plates, and tensioning steel cables at the connection nodes of compressed fiber recycled concrete precast beams, the problems of easy corrosion and loosening of metal connecting bolts are solved, resulting in a more stable beam-to-beam connection and improved vibration resistance and service life.

CN123109288APending Publication Date: 2026-11-17FOSHAN UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611622030.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-20
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

In the prior art, metal connecting bolts are prone to oxidation and corrosion at the connection nodes of compressed fiber recycled concrete precast beams, which weakens the load-bearing capacity and is prone to loosening or breaking under vibration or external load, resulting in failure of the connection between beams.

Method used

The tensioning mechanism, consisting of an arc-shaped plate, an L-shaped connecting plate, an upper clamping plate, a tensioning cable, and a disc spring, provides adjustable clamping force through bolt connections and the coordination of the tensioning cable to buffer vibration and prevent bolts from loosening or breaking.

Benefits of technology

It improves the vibration resistance of the connection nodes, prevents bolts from loosening or breaking, ensures a stable connection between beams, and extends the service life of the nodes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123109288A_ABST
    Figure CN123109288A_ABST
Patent Text Reader

Abstract

This invention relates to the field of beam connection node construction technology, specifically to a connection node structure and construction method for a compressed fiber recycled concrete precast beam. The structure includes a recycled concrete precast beam and a steel beam. Several arc-shaped plates are installed on the outer side of the recycled concrete precast beam, and an L-shaped connecting plate is fixedly connected to the side of the arc-shaped plates away from the recycled concrete precast beam. Through the setting of a tensioning mechanism, this invention provides a slightly movable clamping force to the L-shaped limiting block when external vibrations cause the first and second connecting bolts to loosen or break. This allows the steel beam to move slightly and buffer after vibration, while preventing complete disconnection between the steel beam and the recycled concrete precast beam under the limiting action of the tensioning mechanism.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of beam connection node construction technology, specifically to a connection node structure and construction method for a compressed fiber recycled concrete precast beam. Background Technology

[0002] Compression-fiber recycled concrete (CFRAC) achieves a balance between green and low-carbon properties, cost savings, and excellent performance, while maintaining essentially the same mechanical and durability properties. This gives it broad market application prospects.

[0003] In existing technologies, beams are typically connected using steel sleeves or flange plates and secured with bolts to transfer bending moment, shear force, and axial force at the joint. However, during long-term service in natural environments, the metal connecting bolts of precast component joints are prone to oxidation and corrosion, leading to a weakening of their effective load-bearing cross-section and a continuous decrease in preload, inevitably resulting in initial loosening. When the joint is subjected to external vibrations such as earthquakes, strong winds, or traffic dynamic loads, the bolts and nuts may be directly dislodged or brittle fracture may occur due to excessive instantaneous shear force, causing the connection between beams to break. To address this, we propose a connection joint structure and construction method for compression-fiber recycled concrete precast beams. Summary of the Invention

[0004] The purpose of this invention is to provide a connection node structure and construction method for a compressed fiber recycled concrete precast beam, so as to solve the problems mentioned in the background art.

[0005] To achieve the above objectives, the present invention provides the following technical solution: A connection node structure for a compression-fiber recycled concrete precast beam includes a recycled concrete precast beam and a steel beam. Several arc-shaped plates are installed on the outer side of the recycled concrete precast beam. An L-shaped connecting plate is fixedly connected to the side of the arc-shaped plate away from the recycled concrete precast beam. An upper clamping plate is slidably connected to the outer side of the L-shaped connecting plate. The upper clamping plate is connected to the L-shaped connecting plate by several second connecting bolts. L-shaped limiting blocks are slidably connected inside the upper clamping plate and the L-shaped connecting plate. The lower end of the L-shaped limiting block is inclined. Inclined grooves are opened at both the upper and lower ends of the recycled concrete precast beam for the inclined lower end of the L-shaped limiting block to engage. Two side clamps are movably connected to the outer side of the L-shaped connecting plate. The two side clamps are connected by a first connecting bolt. A tensioning mechanism is provided on the side of the L-shaped connecting plate away from the recycled concrete precast beam. The tensioning mechanism is sleeved on the outer side of the L-shaped connecting plate and the upper clamp.

[0006] The outer side of the recycled concrete precast beam has several snap-fit ​​grooves. The arc plate is fixedly connected to a snap-fit ​​block on the side near the recycled concrete precast beam. The snap-fit ​​block snaps into the snap-fit ​​groove. Several arc plates are connected to each other by several bolts.

[0007] Two first T-shaped blocks are fixedly connected to one end of the upper clamping plate. The first T-shaped blocks slide in the first T-shaped groove, which is opened in the arc plate. Guide grooves are opened in both the L-shaped connecting plate and the upper clamping plate. The L-shaped limiting block slides in the guide groove. U-shaped limiting rods are fixedly connected to the outer side of both the upper clamping plate and the L-shaped connecting plate.

[0008] Two second T-shaped sliders are fixedly connected to one end of the side clamping plate. The second T-shaped sliders slide in the second T-shaped groove, which is located on the outside of the L-shaped connecting plate.

[0009] The tensioning mechanism includes two tensioning steel cables. One end of each tensioning steel cable is fixedly connected to a connecting plate. The two connecting plates are connected to each other by mounting bolts. The end of the tensioning steel cable away from the connecting plate extends into the connecting frame and is fixedly connected to a cross-shaped sliding plate. The cross-shaped sliding plate slides within the connecting frame.

[0010] Several disc springs are sleeved on the outside of the tensioned steel cable. The uppermost disc spring contacts the connecting frame, and the lowermost disc spring contacts the upper part of the connecting plate.

[0011] Furthermore, to achieve the above objectives, the present invention also provides a construction method for a connection node structure, used for the connection node structure of the aforementioned compressed-fiber recycled concrete precast beam, comprising: S1. Install several arc-shaped plates on the outside of the recycled concrete precast beam with bolts. During the installation process, ensure that the snap-fit ​​blocks on the outside of the arc-shaped plates are aligned with the snap-fit ​​grooves on the outside of the recycled concrete precast beam. Hoist one end of the steel beam that needs to be installed with the recycled concrete precast beam to the upper end of the L-shaped connecting plate. S2. After passing several first connecting bolts through the holes opened in the steel beam, tighten the first connecting bolts. The two side clamps approach each other and finally contact the outside of the steel beam. Connect the upper clamp to the L-shaped connecting plate with several second connecting bolts. At the same time, clamp one end of the steel beam between the upper clamp and the L-shaped connecting plate. S3. Place two tension steel cables on the outside of the L-shaped connecting plate and the upper clamping plate. Connect the two connecting plates with two mounting bolts. As the mounting bolts are tightened, the two connecting plates will move closer together. After the two tension steel cables are tightly attached to the outside of the upper clamping plate and the L-shaped connecting plate, tighten the second connecting bolt to complete the connection of the steel beam recycled concrete precast beam.

[0012] Compared with the prior art, the beneficial effects of the present invention are: by setting up a tensioning mechanism, when the external environment causes the first connecting bolt and the second connecting bolt to loosen or break, the tensioning mechanism can provide a slightly movable clamping force to the L-shaped limiting block, so that the steel beam can move slightly to buffer after vibration. At the same time, under the limiting action of the tensioning mechanism, the steel beam and the recycled concrete precast beam will not completely separate. Attached Figure Description

[0013] Figure 1 This is a three-dimensional structural diagram of the installation state of several arc-shaped plates and precast recycled concrete beams of the present invention. Figure 2 This is a three-dimensional structural diagram of the connection state of several arc-shaped plates in this invention; Figure 3 This is a three-dimensional structural diagram of the steel beam in the installation state of the present invention; Figure 4 This is a schematic diagram of the three-dimensional structure of the recycled concrete precast beam of the present invention; Figure 5 This is a three-dimensional structural diagram of the steel beam and L-shaped connecting plate of the present invention in a separated state; Figure 6 This is a three-dimensional structural diagram illustrating the connection relationship between the upper clamping plate and the L-shaped connecting plate of the present invention; Figure 7 This is a three-dimensional structural diagram of the upper clamping plate and the L-shaped connecting plate of the present invention in a separated state; Figure 8 This is a three-dimensional structural diagram illustrating the connection between the tensioning steel cable and the cross-shaped sliding plate of the present invention.

[0014] In the diagram: 1. Recycled concrete precast beam; 2. Steel beam; 3. Curved plate; 4. Upper clamping plate; 5. Clip-on block; 6. L-shaped limiting block; 7. L-shaped connecting plate; 8. Side clamping plate; 9. Connecting frame; 10. Second connecting bolt; 11. Inclined groove; 12. Mounting bolt; 13. Connecting plate; 14. Disc spring; 15. Cross-shaped sliding plate; 16. Tensioning steel cable; 17. First T-shaped groove; 18. Second T-shaped sliding groove; 19. Second T-shaped slider; 20. First connecting bolt; 21. First T-shaped block; 22. Guide groove; 23. U-shaped limiting rod; 24. Clip-on groove. Detailed Implementation

[0015] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.

[0016] Please see Figures 1-8 The present invention provides a technical solution: Example 1: A connection node structure for a compression-fiber recycled concrete precast beam includes a recycled concrete precast beam 1 and a steel beam 2. The recycled concrete precast beam 1 is constructed by incorporating an appropriate amount of fiber (such as basalt fiber) into the concrete during the casting stage and applying a certain pressure to it. Through the matrix densification, aggregate force chain effect, and fiber toughening effect generated by compression casting, the mechanical and durability properties of the concrete are significantly improved. Several arc-shaped plates 3 are installed on the outer side of the recycled concrete precast beam 1. During use, the steel beam can be installed at any position around the recycled concrete precast beam 1 as needed. Several snap-fit ​​grooves 24 are opened on the outer side of the recycled concrete precast beam 1. Snap-fit ​​blocks 5 are fixedly connected to the side of the arc-shaped plates 3 near the recycled concrete precast beam 1. The snap-fit ​​blocks 5 snap into the snap-fit ​​grooves 24. Several arc-shaped plates 3 are interconnected by several bolts. Several arc-shaped plates 3 are installed on the outer side of the recycled concrete precast beam 1 by bolts. During installation, it is ensured that the snap-fit ​​blocks 5 on the outer side of the arc-shaped plates 3 are aligned with the snap-fit ​​grooves 24 on the outer side of the recycled concrete precast beam 1.

[0017] An L-shaped connecting plate 7 is fixedly connected to the side of the arc-shaped plate 3 away from the recycled concrete precast beam 1. An upper clamping plate 4 is slidably connected to the outside of the L-shaped connecting plate 7. The upper clamping plate 4 is connected to the L-shaped connecting plate 7 by several second connecting bolts 10. The upper clamping plate 4 and the L-shaped connecting plate 7 can be connected together by several second connecting bolts 10. At the same time, one end of the steel beam 2 can be clamped between the upper clamping plate 4 and the L-shaped connecting plate 7. L-shaped limiting blocks 6 are slidably connected inside both the upper clamping plate 4 and the L-shaped connecting plate 7. The lower end of the limiting block 6 is inclined. The upper and lower ends of the recycled concrete precast beam 1 are provided with inclined grooves 11 for the lower inclined part of the L-shaped limiting block 6 to engage. The size of the lower inclined part of the L-shaped limiting block 6 is smaller than the size of the inclined groove 11. During the installation of the steel beam 2, it is necessary to ensure that the lower inclined part of the L-shaped limiting block 6 in the upper clamping plate 4 is engaged in the inclined groove 11 at the upper end of the steel beam 2, and that the L-shaped limiting block 6 in the L-shaped connecting plate 7 is engaged in the inclined groove 11 at the lower end of the steel beam 2.

[0018] Two side clamps 8 are movably connected to the outer side of the L-shaped connecting plate 7. The two side clamps 8 are connected by the first connecting bolt 20. Several holes are opened in the steel beam 2 for the first connecting bolt 20 to pass through. After several first connecting bolts 20 are passed through the holes opened in the steel beam 2, the first connecting bolts 20 are tightened. At this time, the two side clamps 8 will approach each other and eventually contact the outer side of the steel beam 2. A tensioning mechanism is provided on the side of the L-shaped connecting plate 7 away from the recycled concrete precast beam 1. The tensioning mechanism is sleeved on the outer side of the L-shaped connecting plate 7 and the upper clamp 4.

[0019] Example 2: Based on Embodiment 1, in order to ensure that the steel beam 2 can still be connected to the precast recycled concrete beam 1 even after the first connecting bolt 20 or the second connecting bolt 10 is damaged under vibration, two first T-shaped blocks 21 are fixedly connected to one end of the upper clamping plate 4. The first T-shaped blocks 21 slide in the first T-shaped groove 17, which is opened in the arc plate 3. When the upper clamping plate 4 moves, the first T-shaped blocks 21 will move along the first T-shaped groove 17. Guide grooves 22 are opened in both the L-shaped connecting plate 7 and the upper clamping plate 4. The L-shaped limiting block 6 slides in the guide groove 22. T-shaped protrusions are provided on both sides of the L-shaped limiting block 6, and T-shaped recesses are provided in the guide groove 22. By sliding the T-shaped protrusions in the T-shaped recesses, the L-shaped limiting block 6 is limited in the guide groove 22.

[0020] U-shaped limiting rods 23 are fixedly connected to the outer sides of the upper clamping plate 4 and the L-shaped connecting plate 7. Two second T-shaped sliders 19 are fixedly connected to one end of the side clamping plate 8. The second T-shaped sliders 19 slide in the second T-shaped groove 18, which is located on the outer side of the L-shaped connecting plate 7. When the side clamping plate 8 moves, the second T-shaped sliders 19 move within the second T-shaped groove 18. The U-shaped limiting rods 23 prevent the L-shaped limiting block 6 from being blocked after moving a certain distance, thus preventing the tilted part of the L-shaped limiting block 6 from tilting outwards. The inclined groove 11 is completely disengaged. Two tensioning steel cables 16 are placed on the outside of the L-shaped connecting plate 7 and the upper clamping plate 4. Then, the two connecting plates 13 are connected by two mounting bolts 12. As the mounting bolts 12 are tightened, the two connecting plates 13 will move closer and closer. After the two tensioning steel cables 16 are tightly attached to the outside of the upper clamping plate 4 and the L-shaped connecting plate 7 respectively, the second connecting bolt 10 can be tightened. Grooves for limiting the tensioning steel cables 16 are provided on the outside of the L-shaped connecting plate 7 and the upper clamping plate 4.

[0021] The tensioning mechanism includes two tensioning cables 16. The materials and thickness of the tensioning cables 16 can be selected according to the usage conditions. One end of the tensioning cable 16 is fixedly connected to a connecting plate 13. The two connecting plates 13 are connected to each other by mounting bolts 12. The end of the tensioning cable 16 away from the connecting plate 13 extends into the connecting frame 9 and is fixedly connected to the cross-shaped sliding plate 15. The cross-shaped sliding plate 15 slides in the connecting frame 9. Several disc springs 14 are sleeved on the outside of the tensioning cable 16. The uppermost disc spring 14 contacts the connecting frame 9, and the lowermost disc spring 14 contacts the upper end of the connecting plate 13. The number and thickness of the disc springs 14 can be increased or decreased according to the usage conditions.

[0022] Furthermore, to achieve the above objectives, the present invention also provides a construction method for a connection node structure, used for the connection node structure of the aforementioned compressed-fiber recycled concrete precast beam, comprising: S1. Install several arc-shaped plates 3 on the outside of the recycled concrete precast beam 1 with bolts. During the installation process, ensure that the snap-fit ​​block 5 on the outside of the arc-shaped plate 3 is connected with the snap-fit ​​groove 24 opened on the outside of the recycled concrete precast beam 1. Hoist one end of the steel beam 2 that needs to be installed with the recycled concrete precast beam 1 to the upper end of the L-shaped connecting plate 7. S2. After passing several first connecting bolts 20 through the holes opened in the steel beam 2, tighten the first connecting bolts 20. The two side clamps 8 approach each other and finally contact the outside of the steel beam 2. The upper clamp 4 and the L-shaped connecting plate 7 are connected together by several second connecting bolts 10. At the same time, one end of the steel beam 2 is clamped between the upper clamp 4 and the L-shaped connecting plate 7. S3. Place two tensioned steel cables 16 on the outside of the L-shaped connecting plate 7 and the upper clamping plate 4. Connect the two connecting plates 13 with two mounting bolts 12. As the mounting bolts 12 are tightened, the two connecting plates 13 will move closer together. After the two tensioned steel cables 16 are tightly attached to the outside of the upper clamping plate 4 and the L-shaped connecting plate 7 respectively, tighten the second connecting bolt 10 to complete the connection of the steel beam 2 and the recycled concrete precast beam 1.

[0023] Working principle: During use, several arc-shaped plates 3 are installed on the outside of the recycled concrete precast beam 1 with bolts. During the installation process, ensure that the snap-fit ​​blocks 5 on the outside of the arc-shaped plates 3 are aligned with the snap-fit ​​grooves 24 on the outside of the recycled concrete precast beam 1. Hoist one end of the steel beam 2 that needs to be installed with the recycled concrete precast beam 1 to the upper end of the L-shaped connecting plate 7. After several first connecting bolts 20 are passed through the holes opened in the steel beam 2, tighten the first connecting bolts 20. At this time, the two side clamping plates 8 will approach each other and eventually contact the outside of the steel beam 2. The upper clamping plate 4 and the L-shaped connecting plate 7 can be connected together by several second connecting bolts 10. At the same time, one end of the steel beam 2 can be clamped between the upper clamping plate 4 and the L-shaped connecting plate 7. Two tension steel cables 16 are placed on the outside of the L-shaped connecting plate 7 and the upper clamping plate 4. Then, the two connecting plates 13 are connected by two mounting bolts 12. As the mounting bolts 12 are tightened, the two connecting plates 13 will move closer and closer. After the two tension steel cables 16 are tightly attached to the outside of the upper clamping plate 4 and the L-shaped connecting plate 7 respectively, the second connecting bolt 10 is tightened to complete the connection of the steel beam 2 and the recycled concrete precast beam 1. When the first connecting bolt 20 or the second connecting bolt 10 becomes loose or breaks due to strong external vibration, the steel beam 2 will move slightly under the impact of the vibration. During the movement of the steel beam 2, since the inclined part of the lower end of the L-shaped limiting block 6 is engaged in the inclined groove 11 on the outside of the steel beam 2, the L-shaped limiting block 6 will be pushed upward when the steel beam 2 moves outward. The synchronous movement of the two L-shaped limiting blocks 6 will push the tensioning steel cable 16 in contact with them. When the tensioning steel cable 16 moves, it will cause the cross-shaped sliding plate 15 to move within the connecting frame 9. At this time, several disc springs 14 are compressed. The setting of several disc springs 14 allows the steel beam 2 to swing slightly when vibration occurs, achieving a buffering effect. At the same time, the setting of the U-shaped limiting rod 23 can block the L-shaped limiting block 6 after it moves a certain distance, preventing the inclined part of the L-shaped limiting block 6 from completely disengaging from the inclined groove 11.

[0024] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A connection node structure for a compression-fiber recycled concrete precast beam, comprising a recycled concrete precast beam and a steel beam, characterized in that: Several arc-shaped plates are installed on the outer side of the recycled concrete precast beam. An L-shaped connecting plate is fixedly connected to the side of the arc-shaped plate away from the recycled concrete precast beam. An upper clamping plate is slidably connected to the outer side of the L-shaped connecting plate. The upper clamping plate is connected to the L-shaped connecting plate by several second connecting bolts. An L-shaped limiting block is slidably connected inside the upper clamping plate and the L-shaped connecting plate. The lower end of the L-shaped limiting block is inclined. Inclined grooves are opened at both the upper and lower ends of the recycled concrete precast beam for the lower inclined part of the L-shaped limiting block to be engaged. Two side clamps are movably connected to the outer side of the L-shaped connecting plate. The two side clamps are connected by a first connecting bolt. A tensioning mechanism is provided on the side of the L-shaped connecting plate away from the recycled concrete precast beam. The tensioning mechanism is sleeved on the outer side of the L-shaped connecting plate and the upper clamp.

2. The connection node structure of a compression-fiber recycled concrete precast beam according to claim 1, characterized in that: The outer side of the recycled concrete precast beam has several snap-fit ​​grooves. The arc plate is fixedly connected to a snap-fit ​​block on the side near the recycled concrete precast beam. The snap-fit ​​block snaps into the snap-fit ​​groove. Several arc plates are connected to each other by several bolts.

3. The connection node structure of a compression-fiber recycled concrete precast beam according to claim 1, characterized in that: Two first T-shaped blocks are fixedly connected to one end of the upper clamping plate. The first T-shaped blocks slide in the first T-shaped groove, which is opened in the arc plate. Guide grooves are opened in both the L-shaped connecting plate and the upper clamping plate. The L-shaped limiting block slides in the guide groove. U-shaped limiting rods are fixedly connected to the outer side of both the upper clamping plate and the L-shaped connecting plate.

4. The connection node structure of a compression-fiber recycled concrete precast beam according to claim 3, characterized in that: Two second T-shaped sliders are fixedly connected to one end of the side clamping plate. The second T-shaped sliders slide in the second T-shaped groove, which is located on the outside of the L-shaped connecting plate.

5. The connection node structure of a compression-fiber recycled concrete precast beam according to claim 1, characterized in that: The tensioning mechanism includes two tensioning steel cables. One end of each tensioning steel cable is fixedly connected to a connecting plate. The two connecting plates are connected to each other by mounting bolts. The end of the tensioning steel cable away from the connecting plate extends into the connecting frame and is fixedly connected to a cross-shaped sliding plate. The cross-shaped sliding plate slides within the connecting frame.

6. The connection node structure of a compression-fiber recycled concrete precast beam according to claim 5, characterized in that: Several disc springs are sleeved on the outside of the tensioned steel cable. The uppermost disc spring contacts the connecting frame, and the lowermost disc spring contacts the upper part of the connecting plate.

7. A construction method for a connection node, used for the connection node construction of the compressed-fiber recycled concrete precast beam according to any one of claims 1-6, characterized in that, include: S1. Install several arc-shaped plates on the outside of the recycled concrete precast beam with bolts. During the installation process, ensure that the snap-fit ​​blocks on the outside of the arc-shaped plates are aligned with the snap-fit ​​grooves on the outside of the recycled concrete precast beam. Hoist one end of the steel beam that needs to be installed with the recycled concrete precast beam to the upper end of the L-shaped connecting plate. S2. After passing several first connecting bolts through the holes opened in the steel beam, tighten the first connecting bolts. The two side clamps approach each other and finally contact the outside of the steel beam. Connect the upper clamp to the L-shaped connecting plate with several second connecting bolts. At the same time, clamp one end of the steel beam between the upper clamp and the L-shaped connecting plate. S3. Place two tension steel cables on the outside of the L-shaped connecting plate and the upper clamping plate. Connect the two connecting plates with two mounting bolts. As the mounting bolts are tightened, the two connecting plates will move closer together. After the two tension steel cables are tightly attached to the outside of the upper clamping plate and the L-shaped connecting plate, tighten the second connecting bolt to complete the connection of the steel beam recycled concrete precast beam.