A construction method for a multi-layered composite structure of sloping roofs in ancient buildings
By adopting a multi-layered composite structure combining a water-stop support and a flexible waterproof sleeve in the construction of sloping roofs of ancient buildings, the problems of fatigue cracking of the waterproof layer and separation of the sealing material were solved, achieving a more stable sealing effect.
Patent Information
- Application Number
- CN202611553010.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-10-09
- Publication Date
- 2026-11-17
AI Technical Summary
The waterproofing layer around the anchoring points of the sloping roof of ancient buildings is prone to fatigue cracking, warping, or separation from the sealing material.
The construction method adopts a multi-layer composite structure. By setting water-stop support and flexible waterproof sleeve around the support neck, a closing form combining continuous support, flexible transition and mechanical compression is formed. Fixed nodes and sliding nodes are set in the temperature deformation unit to release the thermal expansion and contraction deformation of the load-bearing keel.
It improves the stress state and sealing stability of the main waterproof layer around the anchor point, and reduces the risk of fatigue cracking of the waterproof layer and detachment of the sealing material.
Smart Images

Figure CN123109345A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of ancient building construction technology, and in particular to a construction method for a multi-layered composite structure with a sloping roof in ancient buildings. Background Technology
[0002] Traditional sloping roofs are typically constructed using flat tiles, barrel tiles, glazed tiles, or other traditionally shaped roofing materials. Existing construction methods mainly include laying tiles with mortar, fixing them with steel nails, binding them with copper wire, and installing battens on the waterproof layer before hanging the tiles. For roofs with insulation features, the construction process typically involves, in sequence, a leveling layer, a vapor barrier or waterproof layer, an insulation layer, a protective layer, and the tile surface layer on the load-bearing base.
[0003] When using mortar to lay tiles, the tile surface layer and the mortar protective layer form a rigid bond. After the roof is subjected to temperature changes, changes in the moisture content of the wooden base layer, structural deflection, and wind suction, the mortar layer is prone to cracking, and the tiles are prone to loosening or relative displacement.
[0004] When using through-type nailing or post-installed anchors to fix the roof tile joists, the fasteners need to penetrate the waterproofing layer. The penetration points are typically sealed only with sealant, coating, or additional roofing membrane. Metal joists, concrete substrates, and wooden substrates have different temperature and humidity deformation characteristics compared to traditional roof tiles. After continuous joists are rigidly locked at multiple connection points, their expansion and contraction deformation accumulates near the anchor points, transmitting shear or tensile forces to the waterproofing layer. Under repeated wind suction, the anchor points penetrating the waterproofing layer also experience alternating pull-out forces. Therefore, the waterproofing layer around the anchor points is prone to fatigue cracking, warping, or detachment from the sealant.
[0005] Therefore, this application proposes a construction method for a multi-layered composite structure of sloping roofs in ancient buildings. Summary of the Invention
[0006] The purpose of this invention is to provide a construction method for a multi-layer composite structure of sloping roofs in ancient buildings, in order to solve the problems of fatigue cracking, warping, or separation from the sealing material in the waterproof layer around the anchoring points.
[0007] To achieve the above objectives, the present invention provides the following technical solution:
[0008] A construction method for a multi-layered composite structure of a sloping roof in traditional Chinese architecture includes the following steps:
[0009] S1. Measure and lay out the load-bearing base layer, determine the anchoring points, and divide the load-bearing keel into multiple temperature deformation units along the extension direction of the load-bearing keel to be installed.
[0010] S2. Install an anchoring assembly at the anchoring point. The anchoring assembly has an anchoring base fixed to the load-bearing base and a support neck connected to the anchoring base and extending outward from the roof.
[0011] S3. Lay an insulation layer around the support neck, forming a continuous pressure-bearing surface for the main waterproof layer to be laid on the outer side of the insulation layer on the roof, and install a water-stop support part on the outer periphery of the support neck, so that the support surface of the water-stop support part and the continuous pressure-bearing surface together form a continuous pressure-bearing laying surface for the main waterproof layer.
[0012] S4. Lay the main waterproof layer on the continuous pressure-bearing surface and the supporting surface, so that the main waterproof layer is laid flat around the support neck and turned up towards the outside of the roof along the outer periphery of the support neck; fit a flexible waterproof sleeve on the outside of the turned-up part of the main waterproof layer, and press the flexible waterproof sleeve and the turned-up part against the support neck by the clamping member installed around the flexible waterproof sleeve.
[0013] S5. The load-bearing keel is installed by a support installed at the outer end of the support neck. A fixed node and a sliding node are formed in each temperature deformation unit. The fixed node restricts the load-bearing keel from moving relative to the corresponding support along the length direction of the load-bearing keel. Both the fixed node and the sliding node restrict the load-bearing keel from moving laterally along the roof and outward from the roof. The sliding node allows the load-bearing keel to move along its length direction.
[0014] S6. Install the tile hanging component on the supporting keel, and install the ancient building tiles on the tile hanging component, so that the ancient building tiles are spaced apart from the main waterproof layer.
[0015] Furthermore, in step S2,
[0016] The anchoring base is plate-shaped and fixed to the load-bearing base layer;
[0017] The support neck has an inner end connected to the anchor base and an outer end extending outward toward the roof.
[0018] The anchoring assembly also has a heat-insulating connection portion disposed between the anchoring base and the support neck. The heat-insulating connection portion includes an upper connecting plate connected to the inner end of the support neck, a heat-insulating pad sandwiched between the upper connecting plate and the anchoring base, and a connector connecting the upper connecting plate, the heat-insulating pad, and the anchoring base. During installation, the anchoring base is first fixed to the load-bearing base, and then the support neck is installed to the anchoring base through the heat-insulating connection portion.
[0019] Furthermore, in step S3, the water-stopping support is composed of a first split support member and a second split support member arranged opposite to each other. Both the first split support member and the second split support member have a clamping part that fits against the outer periphery of the support neck and a support wing that extends outward from the clamping part.
[0020] When installing the water-stop support, the two clamping parts are connected to the support neck from opposite sides of the support neck, and the two support wings are joined together to form a support surface surrounding the support neck.
[0021] Furthermore, in step S3, when the compressive strength and flatness of the outer surface of the insulation layer meet the requirements for laying the main waterproof layer, the outer surface of the insulation layer forms the continuous pressure-bearing surface; otherwise, a pressure-bearing covering layer is laid on the outer surface of the insulation layer, and the outer surface of the pressure-bearing covering layer forms the continuous pressure-bearing surface.
[0022] When installing the water-stop support, the support surface should be flush with the continuous pressure-bearing surface.
[0023] Furthermore, in step S4, the flexible waterproof sleeve has a sleeve portion fitted around the outer periphery of the support neck and an overlapping portion extending outward from the sleeve portion. The sleeve portion covers the raised portion, and the overlapping portion covers and connects to the main waterproof layer around the raised portion.
[0024] The clamping member is in the shape of a hoop and is arranged around the sleeve portion. When the clamping member is installed, the sleeve portion and the flip-up portion are pressed against the support neck by tightening the clamping member.
[0025] Furthermore, prior to step S6, the following steps are also included:
[0026] A partitioned drainage isolation layer is laid on the outer side of the main waterproof layer of the roof so that water entering the partitioned drainage isolation layer is drained along the roof slope toward the eaves, and a water guide cover is installed on the outer periphery of the support neck;
[0027] The water guide cover has a sleeve surrounding the support neck, a cover body covering the clamping member, and a guide portion extending from the cover body toward the eaves. When installing the water guide cover, the water outlet end of the guide portion is positioned above the partitioned drainage isolation layer.
[0028] Furthermore, in step S1, the roof is divided laterally into multiple drainage zones extending from the upper part of the roof to the eaves. Before step S6, the following steps are also included:
[0029] Water-blocking partitions are provided on the drainage guide isolation layer along the boundary of the drainage zone to form drainage channels that are separated from each other and lead to the eaves respectively.
[0030] When installing the water guide cover, the water outlet end of the guide part should correspond to the drainage channel of the drainage section where the support neck is located.
[0031] Furthermore, in step S5, the support is a height-adjustable support, which has a lower connecting part connected to the support neck, a U-shaped upper support part supporting the load-bearing keel, and a rod-shaped height-adjusting part connecting the lower connecting part and the U-shaped upper support part.
[0032] After the load-bearing keel is installed, the height of the U-shaped upper support relative to the support neck is adjusted by the height adjustment part, so that the multiple load-bearing keels form a load-bearing reference surface that matches the designed ancient building roof curve, and the height adjustment part is locked.
[0033] Furthermore, in step S5, the fixed node is set in the middle of the corresponding temperature deformation unit, the sliding node is set on both sides of the fixed node, and the initial installation position and sliding allowance of the sliding node are determined according to the temperature deformation of the bearing keel.
[0034] In summary, the present invention has the following advantages compared with the prior art:
[0035] The construction method of the multi-layer composite structure of ancient building sloping roof disclosed in this invention involves setting a water-stopping support part around the support neck, which together with the continuous bearing surface forms the bearing surface of the main waterproof layer. This allows the main waterproof layer to remain flat around the anchor point and turn up towards the outside of the roof. A flexible waterproof sleeve and a clamping device are then used to mechanically press the turned-up part against the support neck, so that the waterproof structure around the anchor point forms a closing form that combines continuous support, flexible transition, and mechanical clamping. At the same time, by setting fixed nodes and sliding nodes in the temperature deformation unit, the temperature deformation of the bearing keel along the length direction is released, reducing the repeated pulling of the bearing keel on the support neck and the surrounding waterproof closing due to thermal expansion and contraction. This improves the stress state and sealing stability of the main waterproof layer around the anchor point, and reduces the risk of fatigue cracking, warping, or separation of the main waterproof layer from the sealing material. Attached Figure Description
[0036] Figure 1 This is a flowchart illustrating the construction steps of the multi-layered composite structure for sloping roofs of ancient buildings disclosed in this invention.
[0037] Figure 2 This is a sectional view of the overall layered structure of the multi-layered composite structure of the ancient building's sloping roof according to the present invention.
[0038] Figure 3 This is a schematic diagram of the anchoring components in the construction method of the multi-layer composite structure of the sloping roof of ancient buildings disclosed in this invention.
[0039] Figure 4 This is a schematic diagram of the height-adjustable support in the construction method of the multi-layer composite structure of the sloping roof of ancient buildings disclosed in this invention.
[0040] Figure label:
[0041] 1. Load-bearing base layer; 2. Base layer finishing layer; 3. Vapor barrier layer; 4. Thermal insulation layer; 5. Main waterproof layer; 6. Zoned drainage and isolation layer; 7. Ancient building tile surface layer;
[0042] 11. Anchor base; 12. Upper connecting plate; 13. Thermal insulation connection part; 14. Support neck; 15. Thermal insulation sleeve; 16. Thermal insulation washer; 17. Thermal insulation connecting bolt;
[0043] 21. Lower connecting seat; 22. Height adjusting screw; 23. Positioning pin; 24. U-shaped upper support; 25. Annular bearing shoulder. Detailed Implementation
[0044] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without creative effort are within the scope of protection of the present invention.
[0045] like Figure 1 and Figure 2 As shown in the figure, this embodiment discloses a construction method for a multi-layered composite structure of a sloping roof in ancient buildings, including the following steps:
[0046] Step S1: Measure and lay out the load-bearing base layer 1, determine the anchoring points, and divide the load-bearing keel into multiple temperature deformation units along the extension direction of the load-bearing keel to be installed.
[0047] Specifically, the ridge line, eaves line, roof slope, slope, structural joints and slope elevation of the load-bearing base 1 are measured, and the ridge control line, eaves control line, slope control line and structural joint control line are laid out on the load-bearing base 1 based on the measurement results.
[0048] The roof slope is divided into multiple drainage zones along the horizontal direction, with each zone extending continuously from the upper part of the roof to the eaves. Boundary lines are marked on both sides of each drainage zone, ensuring that each zone lies between two adjacent boundary lines. The boundary lines on the horizontal edges of the roof coincide with the corresponding water-blocking positions at the roof edges. In this embodiment, the width of the drainage zone is 1.2m.
[0049] The direction of the load-bearing keel to be installed along the roof slope is determined based on the roof slope and the location of the structural joints, and multiple temperature deformation units are divided along the extension direction. In this embodiment, the load-bearing keel is made of hot-dip galvanized steel square tubing, and the length of each temperature deformation unit is 6m. The location of the structural joints also serves as the boundary of the temperature deformation units.
[0050] The spacing of the anchoring components is determined based on the roof tile dead load, construction and maintenance load, snow load, and wind suction. In this embodiment, the basic spacing of the anchoring components along the slope is 1000mm, and the basic spacing along the roof transverse direction is 900mm. The arrangement density in the roof edge area and the roof corner area is determined by calculation. The anchoring points are marked on the load-bearing base layer 1 according to the determined arrangement spacing.
[0051] It should be noted that before measuring and setting out the load-bearing base layer 1, check for exposed reinforcement, honeycombing, holes, through cracks, and obvious deflection. For surface defects that do not affect structural safety, use cement-based finishing materials to repair holes and local depressions, and construct the base layer finishing layer 2 according to the designed slope to make the load-bearing base layer 1 a smooth slope suitable for the continuous laying of subsequent functional layers. For defects that affect structural safety, handle them according to the plan confirmed by the structural design unit. Measurement and setting out should be carried out after the base layer finishing is completed to avoid changing the slope elevation or covering the construction control lines and anchor points during the finishing construction.
[0052] Step S2: Install the anchoring assembly at the anchoring point. The anchoring assembly has an anchoring base 11 fixed to the load-bearing base 1 and a support neck 14 connected to the anchoring base 11 and extending outward from the roof.
[0053] Specifically, the surface of the load-bearing base layer 1 that has been repaired is cleaned, the ridge control line, eaves control line, slope control line, structural joint control line and anchoring point are checked, and the anchoring components are installed according to the checked anchoring point.
[0054] like Figure 3 As shown, the anchoring assembly includes an anchoring base 11, a support neck 14, and a thermal insulation connection portion 13. The anchoring base 11 is a metal plate structure. It has a first connecting hole for connecting to the load-bearing base layer 1 and a threaded connection portion that is partially thickened towards the outer side of the roof. The threaded connection portion has a second connecting hole for connecting to the thermal insulation connection portion 13. The first and second connecting holes are staggered. The second connecting hole is a blind threaded hole that does not penetrate the surface of the anchoring base 11 facing the load-bearing base layer 1. The support neck 14 has an inner end near the anchoring base 11 and an outer end away from the anchoring base 11, extending along the outer normal direction of the load-bearing base layer 1.
[0055] The anchor base 11 is placed at the anchoring point of the load-bearing base 1. An anchoring hole is formed on the load-bearing base 1 through the first connecting hole. After cleaning the anchoring hole, the anchoring bolt is installed, and the anchor base 11 is fixed to the load-bearing base 1 only by the anchoring bolt.
[0056] The thermal insulation connection 13 includes an upper connecting plate 12, a rigid thermal insulation pad, a thermal insulation connecting bolt 17, a thermal insulation sleeve 15, and a thermal insulation washer 16. The upper connecting plate 12 is continuously welded to the inner end of the support neck 14. The rigid thermal insulation pad is sandwiched between the upper connecting plate 12 and the anchoring base 11. The upper connecting plate 12 and the rigid thermal insulation pad are respectively provided with connecting holes corresponding to the second connecting hole. The thermal insulation sleeve 15 passes through the connecting holes of the upper connecting plate 12 and the rigid thermal insulation pad. The thermal insulation connecting bolt 17 passes through the thermal insulation washer 16 and the thermal insulation sleeve 15 from the outside of the roof and is then threaded into the second connecting hole. The thermal insulation connecting bolt 17 does not extend into the load-bearing base 1. The thermal insulation sleeve 15 separates the shank of the thermal insulation connecting bolt 17 from the upper connecting plate 12. The thermal insulation washer 16 is sandwiched between the head of the thermal insulation connecting bolt 17 and the upper connecting plate 12.
[0057] The rigid thermal insulation pad is made of glass fiber reinforced composite material or high-strength inorganic thermal insulation board capable of withstanding the compressive and shear stresses of the anchoring components. The thermal insulation sleeve 15 and thermal insulation gasket 16 are made of electrically insulating and low-thermal-conductivity weather-resistant materials. In this embodiment, the rigid thermal insulation pad is made of glass fiber reinforced epoxy resin laminate, the thermal insulation sleeve 15 and thermal insulation gasket 16 are made of glass fiber reinforced polyamide material, and the thermal insulation connecting bolt 17 is made of stainless steel bolt. The pressure and shear force on the support neck 14 are transmitted to the anchoring base 11 through the upper connecting plate 12, the thermal insulation connecting bolt 17, and the rigid thermal insulation pad; the rigid thermal insulation pad, thermal insulation sleeve 15, and thermal insulation gasket 16 together reduce the direct metal-to-metal contact between the upper connecting plate 12 and the anchoring base 11.
[0058] When installing the thermal insulation connection part 13, first place the rigid thermal insulation pad on the anchor base 11, then place the upper connecting plate 12, which is fixedly connected to the support neck 14, on the rigid thermal insulation pad, so that each connection hole corresponds to the second connection hole; then install the thermal insulation sleeve 15 and the thermal insulation washer 16, and screw the thermal insulation connection bolt 17 into the second connection hole, so that the upper connecting plate 12, the rigid thermal insulation pad and the anchor base 11 are clamped together.
[0059] The extension height of the support neck 14 is determined based on the actual total thickness of the vapor barrier 3, insulation layer 4, pressure-bearing cover layer, main waterproof layer 5, and zoned drainage isolation layer 6, as well as the required installation length of the water-stop support, clamping parts, water guide cover, and height adjustment support. After the construction of each functional layer is completed, the outer end of the support neck 14 still extends beyond the water guide cover for the lower connecting seat 21 of the height adjustment support to be fitted. This allows multiple support necks 14 on the same slope control line to be arranged sequentially.
[0060] The exposed metal surfaces of the anchor base 11, the support neck 14 and the upper connecting plate 12 are treated with anti-corrosion measures, and the heat-insulating connection part 13 is located between the inner ends of the anchor base 11 and the support neck 14 to reduce the thermal bridging effect between the support neck 14 and the load-bearing base 1.
[0061] It should be noted that when the anchor hole conflicts with the position of the steel bar or embedded pipeline inside the load-bearing base 1, the corresponding anchor point should be adjusted without changing the force system of the anchor component, and the support position of the load-bearing keel should be rechecked according to the adjusted anchor point. When the anchor bearing capacity of the post-installed anchor does not meet the design requirements, the method of adding anchors, adjusting the anchor base 11, or using embedded connectors should be adopted.
[0062] Step S3: Lay the insulation layer 4 around the support neck 14 to form a continuous pressure-bearing surface for the main waterproof layer 5 to be laid on the outer side of the insulation layer 4 on the roof. Install a water-stop support part on the outer periphery of the support neck 14 so that the support surface of the water-stop support part and the continuous pressure-bearing surface together form a continuous pressure-bearing laying surface for the main waterproof layer 5.
[0063] Specifically, the location of the vapor barrier 3 is determined based on the climate conditions of the building's location, the indoor design temperature and humidity, and the vapor permeability of each structural layer of the roof. In this embodiment, the vapor barrier 3 is laid on the outer side of the roof of the load-bearing base layer 1, and the vapor barrier 3 is laid continuously from the eaves to the upper part of the roof, with a sealed overlap between adjacent vapor barrier materials.
[0064] When the vapor barrier 3 is laid to the position of the support neck 14, an avoidance opening adapted to the cross section of the support neck 14 is formed on the vapor barrier 3, so that the support neck 14 can pass through the vapor barrier 3; the edge of the avoidance opening is continuously sealed along the outer periphery of the support neck 14, so that the vapor barrier 3 remains continuous around the support neck 14.
[0065] A thermal insulation bonding layer compatible with both the vapor barrier 3 and the insulation layer 4 is continuously applied to the outer side of the roof surface of the vapor barrier 3, and the insulation layer 4 is laid on the outer side of the thermal insulation bonding layer. The insulation layer 4 is made of water-repellent roofing rock wool board with compressive strength meeting the support requirements of the pressure-bearing cover layer, and its thickness is determined according to the design value of the roof's heat transfer coefficient. The insulation layer 4 is laid row by row from the eaves to the upper part of the roof. When laying the rock wool board, adjacent rows of rock wool boards are staggered, and the sides of adjacent rock wool boards are pressed together. The thermal insulation bonding layer forms a surface bond between the rock wool board and the vapor barrier 3.
[0066] When the insulation layer 4 is laid to the position of the support neck 14, mounting holes adapted to the support neck 14 are made in the insulation layer 4, allowing the support neck 14 to pass through the insulation layer 4; non-combustible insulation material is filled between the hole wall and the support neck 14, so that the insulation structure around the support neck 14 is continuously installed. The insulation layer 4 located at the ridge, eaves, structural joints and roof turning points is cut according to the contour of the corresponding part, so that the insulation layer 4 is continuously laid along the roof slope.
[0067] A continuous pressure-bearing surface for laying the main waterproof layer 5 is formed on the outer side of the roof of the insulation layer 4. When the insulation material itself has the surface compressive strength and flatness required for laying the waterproof layer, the outer surface of the roof of the insulation layer 4 is used as the continuous pressure-bearing surface; when the insulation material does not have the corresponding surface compressive strength or flatness, a pressure-bearing covering layer is laid on the outer side of the roof of the insulation layer 4. In this embodiment, water-repellent rock wool board is used as the insulation layer 4, and a pressure-bearing covering layer composed of non-combustible fiber-reinforced cement board is laid on the outer side of the roof of the insulation layer 4. The pressure-bearing covering layer is laid row by row from the eaves to the upper part of the roof, with adjacent rows of pressure-bearing covering boards staggered. The pressure-bearing covering boards are fixed to the insulation layer 4 by a surface-mounted adhesive material compatible with the insulation material, and the board joints are filled with a flexible sealant compatible with the main waterproof layer 5, so that a continuous and flat pressure-bearing surface is formed on the outer side of the roof of the pressure-bearing covering layer.
[0068] When the pressure-bearing cover layer is laid to the location of the support neck 14, a support mounting opening adapted to the outer contour of the support tray is formed on the pressure-bearing cover layer. After the pressure-bearing cover layer is laid, a water-stop support part is installed on the outer periphery of each support neck 14. The water-stop support part includes a first semi-ring clamping seat and a second semi-ring clamping seat arranged opposite each other. The outer periphery of the first semi-ring clamping seat extends outward to form a first semi-ring support wing, and the outer periphery of the second semi-ring clamping seat extends outward to form a second semi-ring support wing. The first semi-ring clamping seat and the second semi-ring clamping seat are fixed by connecting lugs provided at the ends and clamping bolts passing through the opposite connecting lugs. After the first semi-ring clamping seat and the second semi-ring clamping seat are assembled, a clamping hole adapted to the outer contour of the support neck 14 is formed. After the first semi-ring support wing and the second semi-ring support wing are assembled, a support tray surrounding the support neck 14 is formed.
[0069] The first and second semi-ring clamps are respectively provided with support positioning holes that are laterally opposite to each other along the roof surface. The support neck 14 is provided with neck support holes that pass through its opposite sides. The first and second semi-ring clamps are fitted onto the outer periphery of the support neck 14 from its opposite sides, so that the two support positioning holes are coaxial with the neck support holes. After the positioning pin is passed through one support positioning hole, the neck support hole and the other support positioning hole in sequence, the protruding end of the positioning pin is fixed to prevent it from falling off, and then the clamping bolt is tightened. The clamping bolt is used to maintain the spliced state of the two semi-ring clamps, and the positioning pin is used to restrict the movement of the water-stop support part along the support neck 14 and to bear the force along the direction of the support neck 14.
[0070] The water-stop support is installed inside the support mounting opening, so that the lower surface of the support tray formed by the first and second semi-ring support wings presses against the insulation layer 4 around the support neck 14, and the upper surface of the support tray forms a continuous support surface for supporting the main waterproof layer 5. The opposite ends of the first and second semi-ring support wings respectively form staggered overlapping edges, and the two overlapping edges overlap each other to avoid the formation of unsupported gaps in the support tray at the splicing position. The installation elevation of the water-stop support is determined according to the elevation of the continuous pressure-bearing surface, so that the upper surface of the support tray is flush with the continuous pressure-bearing surface; the joint between the outer periphery of the support tray and the support mounting opening is filled with a flexible sealant compatible with the main waterproof layer 5.
[0071] It should be noted that when there is a gap between rock wool boards that exceeds the design allowable value, the gap should be filled with insulation strips of the same material, instead of directly filling it with ordinary mortar; when there is a height difference between the pressure-bearing cover boards, the corresponding pressure-bearing cover boards should be readjusted so that the flatness of the continuous pressure-bearing surface meets the laying requirements of the main waterproof layer 5.
[0072] When the vapor barrier 3 is damaged during the laying of the insulation layer 4, the damaged part is covered with a material compatible with the vapor barrier 3, and the covering material is continuously sealed with the original vapor barrier 3. When the water-stop support cannot stably hold the insulation layer 4, the clamping bolts are loosened and the position of the water-stop support is adjusted so that the support positioning hole and the neck support hole are aligned again. Then the positioning pin is installed and the clamping bolts are tightened.
[0073] Step S4: Lay the main waterproof layer 5 on the continuous pressure-bearing surface and the supporting surface, so that the main waterproof layer 5 is laid flat around the support neck 14 and turned up towards the outside of the roof along the outer periphery of the support neck 14; fit a flexible waterproof sleeve on the outside of the turned-up part of the main waterproof layer 5, and press the flexible waterproof sleeve and the turned-up part against the support neck 14 by the clamping member installed around the flexible waterproof sleeve.
[0074] Specifically, the continuous bearing surface and the continuous support surface of the waterstop support are cleaned, and a compatible primer is applied according to the construction requirements of the main waterproof layer 5 material. After the primer meets the laying conditions, the main waterproof layer 5 is laid on the continuous bearing surface and the continuous support surface. In this embodiment, the main waterproof layer 5 includes two layers of self-adhesive polymer-modified bitumen waterproof membrane. The first layer of waterproof membrane is laid from the eaves to the upper part of the roof, and the second layer of waterproof membrane is laid in a staggered manner with the first layer of waterproof membrane, so that the waterproof membrane located on the upper part of the roof covers the waterproof membrane located on the lower part of the roof in the direction of water flow.
[0075] When the main waterproof layer 5 is laid to the position of the support neck 14, a sleeve hole is formed on the waterproof membrane that is compatible with the cross section of the support neck 14, so that the flat part around the sleeve hole continuously covers the continuous support surface of the water-stop support part and the continuous pressure-bearing surface around it. Then, the periphery of the sleeve hole is turned up along the support neck 14 to the outside of the roof to form an upturned part that is close to the outer periphery of the support neck 14.
[0076] A flexible waterproof sleeve is fitted over the outer side of the upturned portion. The flexible waterproof sleeve includes a cylindrical sleeve portion fitted around the outer periphery of the support neck 14 and an annular overlapping portion extending outward from the lower edge of the cylindrical sleeve portion. The cylindrical sleeve portion and the annular overlapping portion are integrally molded from EPDM rubber. The cylindrical sleeve portion covers the upturned portion of the main waterproof layer 5. At least one elastic sealing rib is provided around the support neck 14 on the inner periphery of the cylindrical sleeve portion. The elastic sealing rib is interference-fitted with the outer surface of the support neck 14. The annular overlapping portion covers the main waterproof layer 5 around the root of the upturned portion and is continuously bonded to the main waterproof layer 5 through a butyl sealant layer. The support tray of the water-stopping support portion supports the area where the annular overlapping portion is located from below the main waterproof layer 5.
[0077] A clamping component is installed on the outside of the flexible waterproof sleeve. The clamping component includes a first semi-ring and a second semi-ring arranged opposite each other, connecting ears respectively located at the ends of the first and second semi-rings, and clamping bolts passing through the connecting ears. After the first and second semi-rings are assembled, they form an annular clamping surface that fits the outer circumference of the cylindrical sleeve. The first and second semi-rings are fitted onto the upper outer circumference of the cylindrical sleeve from opposite sides of the support neck 14, and the clamping bolts are tightened. This causes the annular clamping surface to continuously press the cylindrical sleeve and its inner upturned portion against the outer surface of the support neck 14 in a direction toward the outer circumference of the support neck 14, thereby forming a mechanically clamped waterproof seal.
[0078] The main waterproof layer 5 is laid continuously across the ridge control line at the ridge and extends to the installation area of the eaves drainage components. At the structural joints, the main waterproof layer 5 is bent away from the load-bearing base layer 1 to form a relaxed section that crosses the structural joint. A flexible additional waterproof strip is covered on the outside of the relaxed section. The two sides of the flexible additional waterproof strip are bonded to the main waterproof layer 5 on both sides of the structural joint to form a waterproof structure that can expand and contract with the structural joint.
[0079] It should be noted that when the main waterproof layer 5 has wrinkles, curling edges, or insufficient upward height at the support neck 14, the corresponding clamping parts and flexible waterproof sleeves should be removed, the upward part should be re-formed, and mechanical clamping should be performed; when the main waterproof layer 5 is damaged, a repair waterproof material compatible with the main waterproof layer 5 should be used to cover the damaged area, and the periphery of the repair waterproof material should be continuously bonded to the original main waterproof layer 5.
[0080] After step S4 is completed and before step S5 is started, a partitioned drainage isolation layer 6 is constructed on the main waterproof layer 5 and a water guide cover is installed.
[0081] Specifically, the zoned drainage isolation layer 6 adopts a weather-resistant polymer drainage module. The drainage module is made of high-density polyethylene sheet by hot pressing, including a sheet-like substrate and multiple ribs protruding from the sheet-like substrate toward the outside of the roof. The sheet-like substrate is laid on the outside of the main waterproof layer 5 on the roof, and the multiple ribs extend along the roof slope. A drainage space is formed between adjacent ribs along the roof slope. The height of the drainage space is determined according to the design drainage volume of the corresponding drainage zone. The ribs ensure that the drainage space maintains a water passage section when the zoned drainage isolation layer 6 is trampled during construction.
[0082] When laying the guide modules, lay them one by one from the eaves to the top of the roof, so that the guide modules located on the top of the roof overlap the guide modules located on the bottom of the roof in the direction of water flow; the side of the guide module facing the main waterproof layer 5 has a contact surface without sharp corners, and the guide modules are set to avoid the support neck 14.
[0083] Water-retaining partitions are continuously installed along the boundary lines of each zone formed by S1. The water-retaining partitions located on both sides of the roof's transverse edge are continuously connected to the corresponding roof edge water-retaining structures. The water-retaining partitions are either continuous strip-shaped ribs protruding outwards from a sheet-like substrate, or independent water-retaining strips bonded to the sheet-like substrate. The water-retaining partitions are higher than ordinary protruding ribs within the drainage space. Each drainage zone is defined by the water-retaining partitions on its transverse sides, forming a drainage channel extending along the roof slope. The water-retaining partitions on adjacent drainage modules are connected by flexible connecting strips or by overlapping ends, allowing each drainage channel to continuously extend from the upper part of the roof to the eaves.
[0084] The eaves water collection component includes a metal water collection trough extending along the eaves, multiple metal partitions installed within the trough, and multiple short drainage pipes installed on the outer wall of the trough. The bottom and side edges of each metal partition are continuously welded to the water collection trough and sealed. The partitions divide the trough into water collection chambers corresponding to each drainage channel. The upper part of each water collection chamber connects to the corresponding drainage channel, and the lower part of each water collection chamber connects to a short drainage pipe, the outer end of which forms a drainage outlet. The eaves water collection component is installed below the drainage channels, isolating adjacent drainage channels from each other before reaching the corresponding water collection chamber. A removable filter screen and a transparent observation joint are installed at each drainage outlet.
[0085] The water guide cover is formed by bending a corrosion-resistant metal sheet and includes a first cover body and a second cover body arranged opposite each other. When the first and second cover bodies are joined together, they form an upper sleeve around the support neck 14, a cover cavity covering the clamping member, and a guide channel extending obliquely from the cover cavity towards the eaves. The opposite edges of the first and second cover bodies are provided with overlapping folded edges, which are detachably connected by screws or clips. The lower end of the guide channel forms an open drainage end. The first and second cover bodies are joined around the support neck 14 such that the upper sleeve is located outside the clamping member on the roof, the cover cavity covers the clamping member, and the drainage end is located above the drainage channel corresponding to the support neck 14.
[0086] It should be noted that when a backflow occurs between adjacent upper and lower guide modules, the corresponding guide module should be disassembled and reconnected in the manner of the upper module covering the lower module; when there is crossflow between adjacent drainage channels, check the continuation position of the water-blocking partition and ensure that the corresponding water-blocking partition is continuously installed by adding connecting water-blocking strips or re-splicing the water-blocking partition.
[0087] Step S5: Install the load-bearing keel by means of the support installed at the outer end of the support neck 14, and form a fixed node and a sliding node in each temperature deformation unit. The fixed node restricts the load-bearing keel from moving relative to the corresponding support along the length direction of the load-bearing keel. Both the fixed node and the sliding node restrict the load-bearing keel from moving laterally along the roof and outwards from the roof. The sliding node allows the load-bearing keel to move along its length direction.
[0088] Specifically, the support is positioned between the support neck 14 and the load-bearing keel and is used to support the load-bearing keel. The support includes a lower connecting part connected to the outer end of the support neck 14 and an upper supporting part that supports and constrains the load-bearing keel. The upper supporting part includes a base plate and two side plates respectively connected to the lateral sides of the base plate. A limiting space for accommodating the load-bearing keel is formed between the base plate and the two side plates. For parts of the load-bearing base 1 where the designed ancient building roof curve has already been formed and no height compensation is required, a fixed-height support can be used. The lower connecting part of the fixed-height support is sleeve-shaped and adapted to the outer end of the support neck 14 and is fixed to the support neck 14 by a positioning pin 23. Its upper supporting part is U-shaped and welded to or integrally formed with the lower connecting part. For parts where the ancient building roof curve needs to be re-formed or adjusted on the outside of the load-bearing base 1, a height-adjustable support is used that can adjust and lock the height of the upper supporting part relative to the support neck 14. This embodiment uses a height-adjustable support.
[0089] like Figure 4 As shown, the height adjustment support includes a lower connecting seat 21, a height adjustment screw 22, a U-shaped upper support 24, and a locking nut.
[0090] The lower connecting seat 21 is sleeve-shaped, and its lower part forms a connecting cavity that matches the outer end of the support neck 14. The side wall of the connecting cavity is provided with a support positioning hole, and the outer end of the support neck 14 is provided with a neck support hole corresponding to the support positioning hole. The upper part of the lower connecting seat 21 forms a threaded hole extending along the extension direction of the support neck 14. The height adjustment screw 22 is cylindrical, with an external thread on its lower outer circumference that matches the threaded hole. Its middle part is provided with a wrench for clamping, and its upper end forms a rotating connector with a diameter smaller than the threaded rod section. An annular bearing shoulder 25 is formed between the rotating connector and the threaded rod section. The U-shaped upper support 24 includes a base plate and two side plates connected to the transverse sides of the base plate. The base plate is provided with a rotating connecting hole, and a limiting space for accommodating the bearing keel is formed between the two side plates. The locking nut has an internal thread that matches the external thread of the height adjustment screw 22.
[0091] The connecting cavity of the lower connecting seat 21 is sleeved on the outer end of the support neck 14. The positioning pin 23 passes through the positioning hole of the support and the support hole of the neck to fix the lower connecting seat 21 to the support neck 14. The lower part of the height adjustment screw 22 is threaded into the threaded hole of the lower connecting seat 21. The rotating connector at the upper end of the height adjustment screw 22 passes through the rotating connector hole on the bottom plate of the U-shaped upper support 24. The end of the rotating connector that protrudes from the rotating connector hole is pressed to form a limiting head with a diameter larger than the rotating connector hole. The bottom plate is supported on the annular bearing shoulder 25, so that the U-shaped upper support 24 and the height adjustment screw 22 form a connection that can rotate relative to each other and cannot be separated axially. The locking nut is threaded onto the height adjustment screw 22 and is located above the lower connecting seat 21.
[0092] When the height adjustment screw 22 is rotated, it moves relative to the lower connecting seat 21 along the extension direction of the support neck 14. The U-shaped upper support 24 rises and falls with the height adjustment screw 22 and maintains the predetermined extension direction of the load-bearing keel. When the locking nut abuts against the lower connecting seat 21, it restricts the height adjustment screw 22 from continuing to rotate. The bottom plate of the U-shaped upper support 24 supports the load-bearing keel, and the two side plates are located on both sides of the load-bearing keel to restrict the lateral movement of the load-bearing keel.
[0093] When installing the height-adjustable support, first place the connecting cavity of the lower connecting seat 21 on the outer end of the support neck 14, align the support positioning hole with the neck support hole, and insert the positioning pin 23; then screw the locking nut into the height-adjusting screw 22, and screw the height-adjusting screw 22 into the threaded hole of the lower connecting seat 21, and then rotate each U-shaped upper support 24 so that the limiting space of the multiple U-shaped upper supports 24 is arranged along the roof slope.
[0094] The supporting keel is a rectangular tube extending along the roof slope and is made of hot-dip galvanized steel square tube. Its cross-sectional dimensions and wall thickness are determined according to the support spacing and design load of the supporting keel. The bottom wall of the supporting keel is used to support the bottom plate of the U-shaped upper support 24, and the two side walls of the supporting keel are opposite to the two side plates of the U-shaped upper support 24 respectively.
[0095] The fixed nodes include first circular fixing holes respectively set on the two side walls of the bearing keel, second circular fixing holes respectively set on the two side plates of the U-shaped upper support 24, fixing support sleeves that pass through the two first circular fixing holes laterally, fixing through bolts that pass through the two second circular fixing holes and the fixing support sleeves, fixing washers set at both ends of the fixing through bolts, and fixing nuts connected to the fixing through bolts.
[0096] Two first circular fixing holes are coaxially arranged laterally along the roof surface. The outer diameter of the fixing support sleeve is adapted to the first circular fixing holes. The axial length of the fixing support sleeve is greater than the lateral outer width of the supporting keel and not greater than the inner distance between the two side plates of the U-shaped upper support 24 when not under clamping force, so that its two ends extend out of the two side walls of the supporting keel respectively. Two second circular fixing holes correspond to the inner holes of the fixing support sleeve. The fixing bolt passes through one second circular fixing hole, the fixing support sleeve and the other second circular fixing hole in sequence from one side of the U-shaped upper support 24. The fixing washer and the fixing nut are both located on the outside of the U-shaped upper support 24. After tightening the fixing nut, the two side plates of the U-shaped upper support 24 clamp the two ends of the fixing support sleeve without squeezing the side walls of the supporting keel. The fixing support sleeve cooperates with the first circular fixing holes to limit the displacement of the supporting keel along its length and away from the U-shaped upper support 24.
[0097] Before installing the fixed nodes, pass the fixed support sleeve through the first circular fixing hole on the two side walls of the bearing keel in the middle of each temperature deformation unit, so that the two ends of the fixed support sleeve extend out of the two side walls of the bearing keel respectively.
[0098] The sliding node includes oblong sliding holes respectively set on the two side walls of the bearing keel, circular limiting holes respectively set on the two side plates of the U-shaped upper support 24, sliding sleeves that pass through the two oblong sliding holes laterally, limiting through bolts that pass through the two circular limiting holes and the sliding sleeves, limiting gaskets set at both ends of the limiting through bolts, and limiting nuts connected to the limiting through bolts.
[0099] Two elongated sliding holes are arranged laterally opposite each other along the roof surface, each extending along the length of the supporting keel. The outer diameter of the sliding sleeve is smaller than the width of the elongated sliding hole, and the axial length of the sliding sleeve is greater than the lateral outer width of the supporting keel but not greater than the inner distance between the two side plates of the U-shaped upper support 24 when not under clamping force, so that its two ends extend out of the two side walls of the supporting keel respectively. The limiting bolt passes through one circular limiting hole, the sliding sleeve, and the other circular limiting hole in sequence. After tightening the limiting nut, the two side plates of the U-shaped upper support 24 clamp the two ends of the sliding sleeve without clamping the two side walls of the supporting keel, so that the sliding sleeve is held on the U-shaped upper support 24, and the supporting keel can move relative to the sliding sleeve along the elongated sliding hole. The sliding sleeve and the limiting bolt restrict the supporting keel from moving away from the U-shaped upper support 24.
[0100] Before installing the sliding nodes, pass the sliding sleeves sequentially through the elongated sliding holes on the two side walls of the supporting keel at the remaining connection positions on both sides of the fixed node. Determine the initial position of the sliding sleeve in the elongated sliding hole based on the linear expansion coefficient of the supporting keel, the distance from the fixed node to the corresponding sliding node, the design temperature difference, and the installation temperature, and ensure that both ends of the temperature deformation unit retain an effective sliding margin sufficient to meet the calculated displacement.
[0101] After the fixed support sleeve and sliding sleeve are pre-installed, the load-bearing keel is placed into multiple U-shaped upper brackets 24 arranged along the roof slope. At the fixed joints, the inner hole of the fixed support sleeve is aligned with the two second circular fixing holes, and the fixing bolts are inserted from one side of the U-shaped upper bracket 24, with fixing washers and fixing nuts installed on the other side. At the sliding joints, the inner hole of the sliding sleeve is aligned with the two circular limiting holes, and the limiting bolts are inserted from one side of the U-shaped upper bracket 24, with limiting washers and limiting nuts installed on the other side. The tightening of both the fixed and limiting bolts is completed on the outside of the load-bearing keel.
[0102] After the fixed and sliding nodes are installed, rotate each height adjustment screw 22 according to the ridge control line, eaves control line and the designed ancient building roof curve. First, adjust the height adjustment support at the ridge and eaves positions, and then adjust the height adjustment support at the turning point and middle position of the roof curve, so that multiple load-bearing keels can jointly form a load-bearing reference surface that matches the designed ancient building roof curve. After the load-bearing reference surface is formed, tighten each locking nut to abut against the corresponding lower connecting seat 21, and maintain the sliding state of each sliding node along the length direction of the load-bearing keel.
[0103] It should be noted that when the bearing reference plane formed by the bearing keel is inconsistent with the design curve of the ancient building roof, loosen the locking nut and rotate the height adjustment screw 22 to readjust the height of the corresponding bearing keel. Do not adjust by stacking pads on the main waterproof layer 5 or the partition guide isolation layer 6. When the sliding node cannot slide, check the axial length of the sliding sleeve and the fitting clearance between the sliding sleeve and the elongated sliding hole. Replace the sliding sleeve with one whose axial length is greater than the transverse outer width of the bearing keel and not greater than the inner distance between the two side plates of the U-shaped upper support 24 when it is not clamped. Alternatively, clean the elongated sliding hole so that the two side plates of the U-shaped upper support 24 do not clamp the bearing keel and the sliding sleeve can move along the elongated sliding hole.
[0104] Step S6: Install the tile hanging component on the supporting keel, and install the ancient building tiles on the tile hanging component, so that the ancient building tiles are spaced apart from the main waterproof layer 5.
[0105] Specifically, the ancient building tiles installed on the tile hanging components together form the ancient building tile surface layer 7; the tile hanging components include horizontal tile strips, flat tile support components, barrel tile limiting components, wind-resistant connecting components, and adjusting connecting components.
[0106] The horizontal batten is a long strip that extends horizontally along the roof surface. The side of the horizontal batten facing the supporting keel has a keel connection hole, and the side of the horizontal batten facing the outer side of the roof surface has a T-shaped installation groove that extends horizontally along the roof surface and has a groove width smaller than the groove cavity width.
[0107] The roof tile support includes a first mounting plate, a support plate extending outward from the first mounting plate to the outside of the roof, and a stop plate bending outward from the lower edge of the support plate.
[0108] The barrel tile limiting component includes a second mounting plate and two limiting arms extending from the second mounting plate outwards from the roof surface, with the two limiting arms spaced apart.
[0109] The wind-resistant connector is in the form of an elastic sheet, including a fixed end, an elastic arm extending from the fixed end toward the tile, and a retaining end formed at the end of the elastic arm.
[0110] The adjusting connector includes a T-bolt, an adjusting shim, and an adjusting nut. The head of the T-bolt is accommodated within the cavity of the T-shaped mounting groove and is prevented from exiting by the groove opening. The shank of the T-bolt passes through the first or second mounting plate and is connected to the adjusting shim and adjusting nut in sequence. When the adjusting nut is loosened, the T-bolt can move the first or second mounting plate along the T-shaped mounting groove; when the adjusting nut is tightened, the first or second mounting plate is fixed to the transverse batten strip.
[0111] Rivet nuts are installed on the top wall of the supporting keel at positions corresponding to the keel connection holes. Horizontal battens are fixed to the supporting keel by connecting bolts that pass through the keel connection holes and are threaded to the rivet nuts. The rivet nuts are riveted to the top wall of the supporting keel from the outside. The installation and removal of the connecting bolts are both completed from the outside of the supporting keel. The first and second mounting plates are respectively installed in the T-shaped mounting grooves through adjusting connectors.
[0112] The lower edge of the flat tile is supported by the support plate and restricted from sliding down the slope by the stop plate; the two limiting arms abut against the inner wall or the two sides of the barrel tile to restrict the lateral movement of the barrel tile; the fixed end of the wind-resistant connector is connected to the horizontal batten strip, and the clamping end is used to clamp the inner edge of the flat tile or barrel tile to restrict the movement of the corresponding tile away from the roof.
[0113] Before installing the tile hanging components, sample measurements are taken from the same batch of flat tiles and barrel tiles. The spacing of the horizontal tile hanging strips along the slope is determined based on the actual length, width, curvature, and effective overlap length of the flat tiles and barrel tiles.
[0114] When installing the tile hanging components, install the horizontal tile strips sequentially on the supporting keel from the eaves to the ridge, and reserve the ridge node construction area on both sides of the ridge control line for the installation of ridge ventilation components and ridge support components; then, according to the horizontal arrangement of the flat tiles and barrel tiles, install the flat tile support and barrel tile limiting components in the T-shaped installation grooves of each horizontal tile strip outside the ridge node construction area, and adjust the position of the flat tile support and barrel tile limiting components by adjusting the connecting parts.
[0115] When laying the roof tiles for traditional sloping buildings, lay the tiles row by row from the eaves towards the ridge joint construction area, ensuring that the lower part of the previous row of tiles covers the upper part of the next row, and that the lower edge of each tile is supported by its corresponding tile support. Install barrel tiles above the joints of adjacent tiles, overlapping them sequentially along the slope, and positioning the barrel tiles between the two limiting arms of their corresponding limiting components. Stop laying tiles upon reaching the ridge joint construction area, leaving the connection points of the load-bearing joists on both sides of the ridge exposed.
[0116] According to the roof wind pressure zoning, wind-resistant connectors are installed in at least part of the overlapping area of flat tiles and barrel tiles, so that the fixed end connects to the horizontal batten and the clamping end clamps the inner edge of the corresponding tile.
[0117] When installing the bottom row of flat tiles and barrel tiles at the eaves, the lower end of the flat tiles and barrel tiles should extend beyond the location of the drainage outlet of the eaves water collection component. This allows the water flowing along the outer surface of the ancient building tiles to pass over the eaves water collection component and drain to the outside of the roof, while allowing the water under the tiles in the drainage channel to be discharged independently through the corresponding drainage outlet.
[0118] After installation, the ancient building tiles and hanging tile components are spaced apart from the insulation layer 4 and the main waterproof layer 5. The load borne by the ancient building tiles is transferred to the load-bearing base layer 1 through the hanging tile components, the load-bearing keel, the height adjustment support, the support neck 14 and the anchor base 11 in sequence.
[0119] It should be noted that when the dimensional deviation of ancient building tiles causes adjacent tiles to not maintain the designed overlapping relationship, loosen the adjusting nut and adjust the position of the tile support or barrel tile limiter along the T-shaped mounting groove, and then tighten the adjusting nut again. For tiles with cracks, missing corners, or deformation that affect the overlapping or connection, use tiles of the same shape to replace them, and do not use thickened mortar to compensate for the dimensional deviation of the tiles.
[0120] After the ancient building tiles on the slope are laid, the construction of the ridge ventilation nodes and ridge tiles will continue in the ridge node construction area reserved in step S6, and the independent connection relationship of the zoned drainage channels will be verified.
[0121] Specifically, the ridge node includes ridge ventilation components and ridge support components; the ridge ventilation components include two ventilation bases respectively set on both sides of the ridge, a top rainproof plate connecting the two ventilation bases, and insect-proof nets respectively set on the two ventilation bases; the ridge support components include ridge spanning brackets, ridge tile strips, and ridge tile clips.
[0122] The ventilation base is a long strip extending along the ridge, with its lower part forming an air inlet that connects to the space under the tiles, and its part facing the side of the ridge forming a ventilation outlet; the top rain cover is inverted V-shaped or arc-shaped, with its two sides extending downward to form rain-proof edges covering the corresponding ventilation outlets; each ventilation base has an upward-bent water-blocking fold inside the ventilation outlet, and the rain-proof edges and water-blocking folds are staggered; the insect-proof net is mesh-like and covers the corresponding air inlet or ventilation outlet.
[0123] The ridge support is a frame that spans the ridge, the ridge tile strips are long strips that extend along the ridge, and the ridge tile clips have an installation end that connects to the ridge tile strips and a clipping end for holding the ridge tiles.
[0124] Two ventilation bases are connected to the rivet nuts on the top wall of the load-bearing keel on both sides of the ridge by connecting bolts. The top rain cover is connected to the two ventilation bases by screws, so that the ventilation bases, the water-blocking folds and the top rain cover together form a curved air circulation path from the space under the tiles to the outside of the roof. The rain cover covers the ventilation outlet, and the water-blocking folds block the water flowing inward along the ventilation base.
[0125] Both ends of the ridge support are connected to the rivet nuts on the top wall of the load-bearing keel on both sides of the ridge by connecting bolts. The ridge tile strips are fixed to the ridge support by bolts. The ridge tile clips are connected to the ridge tile strips and hold the ridge tiles, so that the ridge tiles are located outside the ridge ventilation components and cover the top rain shelter.
[0126] When installing the ridge node, first, within the ridge node construction area reserved in step S6, place two ventilation bases on the outside of the main waterproof layer 5 of the roof at the ridge, and connect the two ventilation bases to the exposed load-bearing keels on both sides of the ridge using connecting bolts; after installing the insect-proof net, install the top rain cover above the two ventilation bases. Then, connect the ridge spanning bracket between the load-bearing keels on both sides of the ridge, and install the ridge tile strips on the ridge spanning bracket; according to the outer contour of the ventilation base and the ridge spanning bracket, add the flat tiles and barrel tiles within the ridge node construction area, and finally install the ridge tiles sequentially from one end of the ridge to the other using the ridge tile clips.
[0127] After the ridge node is installed, water is sequentially supplied to each drainage channel according to the drainage zone, so that the test water flows into the eaves water collection component along the corresponding drainage channel and is discharged from the corresponding drainage outlet, in order to confirm the independent connection between each drainage channel and the corresponding drainage outlet.
[0128] The construction of the multi-layered composite structure of the ancient building's sloping roof is now complete. The load of the ancient building's tiles is transferred to the load-bearing base layer 1 through the tile hanging components, load-bearing keel, and anchoring components; water entering the space under the tiles is confined to the corresponding drainage channels by the water-blocking partition and discharged towards the eaves; the temperature deformation of the load-bearing keel along its length is released through the sliding joints.
[0129] It should be noted that when a drainage channel cannot discharge water from its corresponding outlet during zoned water supply, the overlapping positions of the guide modules and the outlet within that drainage channel should be cleared. The overall water spraying, anchor component connection inspection, fixed node tightening inspection, sliding node sliding allowance inspection, and tile connection inspection after roof construction are completed should be carried out according to the roof engineering acceptance requirements and are not considered independent construction steps for forming the aforementioned multi-layered composite structure.
[0130] The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. The singular forms “a,” “the,” and “the” used in this invention and the appended claims are also intended to include the plural forms unless the context clearly indicates otherwise. It should also be understood that the term “and / or” as used herein refers to and includes any or all possible combinations of one or more of the associated listed items.
[0131] It should be understood that although the terms first, second, third, etc., may be used in this invention to describe various information, this information should not be limited to these terms. These terms are only used to distinguish information of the same type from one another. For example, first information may also be referred to as second information without departing from the scope of this invention, and similarly, second information may also be referred to as first information. Depending on the context, the word "if" as used herein may be interpreted as "when," "when," or "in response to a determination."
[0132] Although embodiments of the invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made to these embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.
Claims
1. A construction method for a multi-layered composite structure of a sloping roof in ancient architecture, characterized in that, Includes the following steps: S1. Measure and lay out the load-bearing base layer, determine the anchoring points, and divide the load-bearing keel into multiple temperature deformation units along the extension direction of the load-bearing keel to be installed. S2. Install an anchoring assembly at the anchoring point. The anchoring assembly has an anchoring base fixed to the load-bearing base and a support neck connected to the anchoring base and extending outward from the roof. S3. Lay an insulation layer around the support neck, forming a continuous pressure-bearing surface for the main waterproof layer to be laid on the outer side of the insulation layer on the roof, and install a water-stop support part on the outer periphery of the support neck, so that the support surface of the water-stop support part and the continuous pressure-bearing surface together form a continuous pressure-bearing laying surface for the main waterproof layer. S4. Lay the main waterproof layer on the continuous pressure-bearing surface and the supporting surface, so that the main waterproof layer is laid flat around the support neck and turned up towards the outside of the roof along the outer periphery of the support neck; fit a flexible waterproof sleeve on the outside of the turned-up part of the main waterproof layer, and press the flexible waterproof sleeve and the turned-up part against the support neck by the clamping member installed around the flexible waterproof sleeve. S5. The load-bearing keel is installed by a support installed at the outer end of the support neck. A fixed node and a sliding node are formed in each temperature deformation unit. The fixed node restricts the load-bearing keel from moving relative to the corresponding support along the length direction of the load-bearing keel. Both the fixed node and the sliding node restrict the load-bearing keel from moving laterally along the roof and outward from the roof. The sliding node allows the load-bearing keel to move along its length direction. S6. Install the tile hanging component on the supporting keel, and install the ancient building tiles on the tile hanging component, so that the ancient building tiles are spaced apart from the main waterproof layer.
2. The construction method for the multi-layer composite structure of the sloping roof of ancient buildings according to claim 1, characterized in that, In step S2, The anchoring base is plate-shaped and fixed to the load-bearing base layer; The support neck has an inner end connected to the anchor base and an outer end extending outward toward the roof. The anchoring assembly also has a heat-insulating connection portion disposed between the anchoring base and the support neck. The heat-insulating connection portion includes an upper connecting plate connected to the inner end of the support neck, a heat-insulating pad sandwiched between the upper connecting plate and the anchoring base, and a connector connecting the upper connecting plate, the heat-insulating pad, and the anchoring base. During installation, the anchoring base is first fixed to the load-bearing base, and then the support neck is installed to the anchoring base through the heat-insulating connection portion.
3. The construction method for the multi-layered composite structure of the sloping roof of ancient buildings according to claim 1, characterized in that, In step S3, the water-stopping support is composed of a first split support and a second split support arranged opposite to each other. Both the first split support and the second split support have a clamping part that fits against the outer periphery of the support neck and a support wing that extends outward from the clamping part. When installing the water-stop support, the two clamping parts are connected to the support neck from opposite sides of the support neck, and the two support wings are joined together to form a support surface surrounding the support neck.
4. The construction method for the multi-layer composite structure of the sloping roof of ancient buildings according to claim 3, characterized in that, In step S3, when the compressive strength and flatness of the outer surface of the insulation layer meet the requirements for laying the main waterproof layer, the outer surface of the insulation layer forms the continuous pressure-bearing surface; otherwise, a pressure-bearing covering layer is laid on the outer surface of the insulation layer, and the outer surface of the pressure-bearing covering layer forms the continuous pressure-bearing surface. When installing the water-stop support, the support surface should be flush with the continuous pressure-bearing surface.
5. The construction method for the multi-layered composite structure of the sloping roof of ancient buildings according to claim 1, characterized in that, In step S4, the flexible waterproof sleeve has a sleeve portion fitted around the outer periphery of the support neck and an overlapping portion extending outward from the sleeve portion. The sleeve portion covers the raised portion, and the overlapping portion covers and connects to the main waterproof layer around the raised portion. The clamping member is in the shape of a hoop and is arranged around the sleeve portion. When the clamping member is installed, the sleeve portion and the flip-up portion are pressed against the support neck by tightening the clamping member.
6. The construction method for the multi-layered composite structure of the sloping roof of ancient buildings according to claim 1, characterized in that, Before step S6, the following steps are also included: A partitioned drainage isolation layer is laid on the outer side of the main waterproof layer of the roof so that water entering the partitioned drainage isolation layer is drained along the roof slope toward the eaves, and a water guide cover is installed on the outer periphery of the support neck; The water guide cover has a sleeve surrounding the support neck, a cover body covering the clamping member, and a guide portion extending from the cover body toward the eaves. When installing the water guide cover, the water outlet end of the guide portion is positioned above the partitioned drainage isolation layer.
7. The construction method for the multi-layered composite structure of the sloping roof of ancient buildings according to claim 6, characterized in that, In step S1, the roof is divided into multiple drainage zones extending from the upper part of the roof to the eaves in a horizontal direction. Before step S6, the following steps are also included: Water-blocking partitions are provided on the drainage guide isolation layer along the boundary of the drainage zone to form drainage channels that are separated from each other and lead to the eaves respectively. When installing the water guide cover, the water outlet end of the guide part should correspond to the drainage channel of the drainage section where the support neck is located.
8. The construction method for the multi-layer composite structure of the sloping roof of ancient buildings according to claim 1, characterized in that, In step S5, the support is a height-adjustable support, which has a lower connecting part connected to the support neck, a U-shaped upper support part supporting the load-bearing keel, and a rod-shaped height-adjusting part connecting the lower connecting part and the U-shaped upper support part. After the load-bearing keel is installed, the height of the U-shaped upper support relative to the support neck is adjusted by the height adjustment part, so that the multiple load-bearing keels form a load-bearing reference surface that matches the designed ancient building roof curve, and the height adjustment part is locked.
9. The construction method for the multi-layered composite structure of the sloping roof of ancient buildings according to claim 1, characterized in that, In step S5, the fixed node is set in the middle of the corresponding temperature deformation unit, the sliding node is set on both sides of the fixed node, and the initial installation position and sliding allowance of the sliding node are determined according to the temperature deformation of the bearing keel.