Segmented construction method for cold storage wear-resistant flooring
By using a segmented construction method, the problems of cold storage flooring loss, waterproofing failure, and temperature stress cracking are solved, achieving a comprehensive improvement in the flooring's thermal insulation, waterproofing, and wear resistance, thus extending the service life of the cold storage facility.
Patent Information
- Application Number
- CN202611303453.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-26
- Publication Date
- 2026-11-17
AI Technical Summary
Cold storage flooring is prone to problems such as cold loss, waterproofing failure, temperature stress cracking, and insufficient surface wear resistance in low-temperature environments, which affect the performance and lifespan of the cold storage.
The construction method adopts a segmented approach, including foundation treatment, ventilation and antifreeze system, composite thermal insulation and waterproof structure, multiple mechanical finishing treatments and temperature compensation curing, forming an air barrier layer, thermal insulation layer, waterproof layer and wear-resistant surface layer, and setting up anti-deformation structure and expansion joints.
It significantly reduces cold loss, improves waterproof and airtight performance, lowers cold storage energy consumption, prevents floor cracking, enhances wear resistance, and extends the service life of cold storage.
Smart Images

Figure CN123109358A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of building construction technology, specifically to a segmented construction method for cold storage wear-resistant flooring. Background Technology
[0002] In the construction of large cold storage facilities, floor construction is a crucial step that determines the performance and lifespan of the cold storage. Because the interior of a cold storage facility is constantly exposed to low temperatures ranging from -18°C to -25°C, the floor must not only withstand the enormous pressure from the stacked goods and the repeated wear and tear from the frequent movement of forklifts and other handling equipment, but also face a series of technical challenges such as soil frost heave caused by low-temperature conduction, concrete temperature shrinkage and cracking, and continuous loss of cold energy along the floor structure. Currently, traditional cold storage floor construction methods typically involve only one layer of insulation board in terms of thermal insulation structure. Inadequate air-barrier measures lead to significant cold energy loss through weak points such as board joints and wall / column connections, resulting in high energy consumption during cold storage operation. Furthermore, the downward conduction of cold energy to the foundation soil can easily cause frost heave damage. Regarding waterproofing, conventional waterproofing layers often use spot or strip bonding methods, creating water-transfer channels between the membrane and the substrate. This makes it difficult to effectively prevent the upward infiltration of groundwater vapor from areas with high water tables, and also fails to prevent the downward diffusion of cold air from inside the storage area. The condensation of water vapor within the insulation layer leads to a sharp decline in insulation performance. Finally, regarding the floor's crack resistance... Large areas of concrete are prone to irregular cracks under temperature stress. The XPS boards in the insulation layer also expand and contract with temperature changes. If a reasonable stress relief structure is not set up, the cracks will be reflected from the insulation layer to the floor surface, seriously affecting the durability and aesthetics of the floor. In terms of surface wear resistance and maintenance, traditional manual finishing methods are difficult to form a high-density surface hardening layer with a low wear resistance coefficient. After a period of use, the floor surface is prone to dust and sand. At the same time, the hydration reaction of concrete is slow in low-temperature environments, and the curing cycle is long. If effective temperature compensation measures are not taken, insufficient early strength development will also aggravate the formation of drying shrinkage cracks.
[0003] The aforementioned problems may ultimately lead to quality defects in the cold storage floor, such as cracking, dust generation, insulation failure, and frost heave deformation, affecting the normal use of the cold storage, significantly increasing subsequent maintenance costs, and shortening the overall service life of the cold storage.
[0004] Therefore, there is an urgent need to develop a construction method for cold storage flooring that can systematically solve the above problems. Summary of the Invention
[0005] This invention was made to solve the above-mentioned technical problems. Its purpose is to provide a segmented construction method for cold storage wear-resistant flooring, which can solve the technical problems of cold storage flooring loss, waterproofing failure, temperature stress cracking and insufficient surface wear resistance, and achieve a comprehensive improvement in the thermal insulation performance, waterproofing performance, crack resistance and wear resistance of the flooring structure.
[0006] To achieve the above objectives, the present invention provides a segmented construction method for cold storage wear-resistant flooring, comprising the following steps: S1: Grind and roughen the base plate, moisten it with water, and then mark the position of the partition joint according to the compartment layout diagram. S2: Erect and level the formwork, and bury ventilation pipes in the base sand layer to form a ventilation and antifreeze system; S3: Construct the vapor barrier, insulation layer and waterproof layer in sequence to form a composite insulation and waterproof structure, and set an anti-deformation structure in the insulation layer; S4: Lay a double-layer steel mesh and tie it in place. Pour concrete using a pumping method, vibrate it to compact it, and then level it. S5: Perform multiple mechanical finishing processes on the concrete surface, cover with a film for moisture retention and curing, and combine with temperature compensation curing measures. S6: After the concrete has cured to the design strength, apply epoxy wear-resistant surface material by roller. S7: Cut the dividing seam according to the marked line, clean the seam opening and fill it with antifreeze sealant.
[0007] Preferably, step S3 includes the following steps: S31. Lay an air barrier layer on the surface of the concrete leveling layer, then lay an insulation layer. The joints of the boards are spliced with tongue and groove and coated with adhesive. The wall and column joints are wrapped with L-shaped insulation boards and filled with expansion rubber strips for sealing. S32. Construct and cure a leveling layer above the insulation layer, lay waterproof membrane, and fully adhere the membrane to the base layer. Add an additional layer on both sides of the expansion joint, reinforce the inside and outside corners with diagonal laying, and seal the interface between the waterproof layer and the ventilation pipe with a sealing sleeve to form a two-way waterproof and airtight structure. S33. Set elastic expansion joints at set intervals in the insulation layer, fill the joints with elastic sealing material, and attach fiberglass mesh to the splicing surface of the insulation board and fix it with adhesive to form a stress-relieving mesh.
[0008] Preferably, the air barrier layer is made of SBS modified bitumen membrane, the insulation layer is made of extruded polystyrene board, and the overlap length of the SBS modified bitumen membrane is 100~150mm.
[0009] Preferably, step S5 specifically includes: S51. Before the initial setting of concrete, a metal roller is used for initial compaction and finishing. Before the final setting, a low-speed grinder is used for rough grinding and a high-speed grinder for fine grinding, combined with multi-grit grinding discs for layered grinding to form a dense hardened layer on the surface. S52. After finishing, cover with breathable plastic film and press the edges firmly. Use intermittent watering for curing. Lay damp straw mats on both sides of the separation joint to release shrinkage stress. S53. Cover the concrete surface with insulation board and install temperature sensors to monitor the surface temperature in real time. When the temperature is lower than the set value, start the electric heat tracing system to maintain the curing environment within the set temperature range. S54. Before cutting the dividing joint, spray a curing agent on both sides of the joint to form a hardened film. Attach a guide strip along the marked line. When cutting, operate along the edge of the guide strip to control the joint depth.
[0010] Preferably, in step S51, the low-speed polisher rotates at a speed of 150-200 rpm, and the high-speed polisher rotates at a speed of 500-800 rpm.
[0011] Preferably, the thickness of the dense hardened layer is 0.5~1mm.
[0012] Preferably, the insulation board is an extruded polystyrene board.
[0013] Preferably, the concrete is C25 fine aggregate concrete, and the thickness of the concrete is 115mm~125mm.
[0014] Preferably, the temperature sensor is installed at a density of one sensor per 500㎡, and the maintenance environment temperature is 15~25℃.
[0015] Preferably, the cutting depth of the separation joint is 1 / 6 of the floor thickness, and the width is 3~6mm.
[0016] The segmented construction method for cold storage wear-resistant flooring of the present invention has the following advantages compared with existing construction methods: 1. By combining the vapor barrier and insulation layer in the construction, L-shaped insulation boards are wrapped and filled with expansion rubber strips at the wall and column joints, effectively blocking the transmission of cold energy along the weak parts of the structure. Compared with traditional insulation methods, this can significantly reduce cold energy loss and reduce the energy consumption of cold storage operation. 2. The waterproof membrane is fully adhered to the base layer to eliminate water seepage channels. Additional layers are added on both sides of the expansion joints, the inside and outside corners are laid diagonally, and the pipe openings are sealed with rubber sleeves to form a complete two-way waterproof and air-tight structure. This can simultaneously prevent groundwater vapor from seeping upwards and cold air from spreading downwards inside the cold storage, greatly improving the waterproof and air-tight effect and ensuring a stable temperature and humidity environment in the cold storage. 3. Elastic expansion joints are set at predetermined intervals in the insulation layer and filled with closed-cell foam rods. At the same time, fiberglass mesh is pasted on the splicing surface of the insulation board to form a stress-relieving mesh, which can effectively absorb and release the thermal expansion and contraction stress generated by the XPS board when the temperature changes, avoid the insulation layer from cracking and reflect the cracks to the floor surface, and significantly reduce the risk of floor cracking. Attached Figure Description
[0017] Figure 1 This is a flowchart illustrating a segmented construction method for a cold storage wear-resistant floor, as described in one embodiment of the present invention.
[0018] Figure 2 This is a flowchart of step S3 in one embodiment of the present invention.
[0019] Figure 3 This is a flowchart of step S5 in one embodiment of the present invention. Detailed Implementation
[0020] Exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, exemplary embodiments can be implemented in many forms and should not be construed as limited to the examples set forth herein; rather, these embodiments are provided so that this disclosure will be more comprehensive and complete, and will fully convey the concept of exemplary embodiments to those skilled in the art. The described features, structures, or characteristics may be combined in any suitable manner in one or more embodiments.
[0021] Furthermore, the accompanying drawings are merely illustrative of this disclosure and are not necessarily drawn to scale. The same reference numerals in the drawings denote the same or similar parts, and therefore repeated descriptions of them will be omitted. It should be noted that in this disclosure, the terms "comprising," "configured with," and "set in" are used to indicate an open-ended inclusion, meaning that additional elements / components / etc. may exist besides those listed; the terms "first," "second," etc., are used only as labels and are not intended to limit the number or order of objects; the terms "center," "upper," "lower," "left," "right," "vertical," "horizontal," "inner," and "outer," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation of the invention.
[0022] Unless otherwise explicitly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to fixed connections, detachable connections, or integral connections; they can refer to mechanical connections or electrical connections; they can refer to direct connections or indirect connections through an intermediate medium; and they can refer to the internal connection between two components. Those skilled in the art will understand the specific meaning of the above terms in this invention based on the specific circumstances.
[0023] Figure 1 This is an overall flowchart of a segmented construction method for a cold storage wear-resistant floor in one embodiment of the present invention, showing the sequence of steps S1 to S7. Figure 2 for Figure 1 The flowchart of step S3 shown illustrates the sub-steps of composite construction of the air barrier and insulation layer, construction of the two-way waterproof structure, and anti-deformation treatment of the insulation layer. Figure 3 for Figure 1 The flowchart of step S5 shows the sub-steps of multiple mechanical finishing, moisturizing and stress release, temperature compensation curing and pre-curing treatment of the expansion joint.
[0024] The specific embodiments of the present invention will now be described in detail with reference to the accompanying drawings.
[0025] Please refer to Figures 1 to 3 The present invention also provides a segmented construction method for wear-resistant flooring in cold storage, comprising the following steps: S1: Grind and roughen the base plate, moisten it with water, and then mark the position of the partition joint according to the compartment layout diagram. S2: Erect and level the formwork, and bury ventilation pipes in the base sand layer to form a ventilation and antifreeze system; S3: Construct the vapor barrier, insulation layer and waterproof layer in sequence to form a composite insulation and waterproof structure, and set an anti-deformation structure in the insulation layer; S4: Lay a double-layer steel mesh and tie it in place. Pour concrete using a pumping method, vibrate it to compact it, and then level it. S5: Perform multiple mechanical finishing processes on the concrete surface, cover with a film for moisture retention and curing, and combine with temperature compensation curing measures. S6: After the concrete has cured to the design strength, apply epoxy wear-resistant surface material by roller. S7: Cut the dividing seam according to the marked line, clean the seam opening and fill it with antifreeze sealant.
[0026] First, the foundation slab needs to be treated and marked with positioning lines. Before construction begins, the foundation slab must be thoroughly treated. A professional floor grinder is used to grind the foundation slab, removing any residual laitance. Laitance is a layer of low-strength cement paste that forms on the surface after concrete pouring. If this laitance is not removed, the subsequent flooring will not bond firmly to the foundation slab. Grinding also roughens the concrete surface, significantly increasing its roughness. This rough surface facilitates mechanical bonding between the subsequently poured concrete and the existing foundation slab, thereby enhancing their bond strength. After grinding and roughening, the base layer needs to be moistened with water. Watering prevents the base layer from excessively absorbing moisture from the concrete, but it's crucial to ensure there is no standing water on the surface afterward, as standing water will dilute the cement paste on the concrete surface, affecting the concrete's strength.
[0027] In addition, after completing the base treatment, it is necessary to mark the positions on-site according to the design drawings. The marking is based on the compartment layout diagram of the detailed design, which divides the entire floor into several construction areas, each measuring 4000mm × 5000mm. This compartmentalization is used to control shrinkage cracks in the concrete. By dividing a large floor area into several smaller sections, shrinkage stress can be concentrated at the expansion joints, thus preventing random cracking of the floor. During the marking process, it is also necessary to mark the locations of the expansion joints on the walls and columns, ensuring that the positions of the expansion joints are completely consistent with the joint locations left during subsequent self-leveling construction. This avoids aesthetic problems and stress concentration issues caused by inconsistent joint locations between different construction processes.
[0028] In addition, after completing the base treatment, the formwork is erected and the ventilation pipes are arranged. The formwork is a temporary structure used to restrain the flow of concrete during pouring. In this embodiment, angle steel is used as the formwork, with a cross-sectional dimension of 8cm × 5cm. Before placing the angle steel, a 20mm thick layer of cement mortar is first laid at the bottom of the angle steel for leveling. Leveling ensures that the top surface of the angle steel is at a consistent elevation. After leveling, the angle steel is accurately placed on the cement mortar according to the leveled elevation line, and then fixed to the base plate below with 12mm diameter steel bars. The spacing of the steel bars should not exceed 2m to ensure that the angle steel will not shift during concrete pouring. Simultaneously with the formwork erection, ventilation pipes need to be arranged in the sand layer of the base. The ventilation pipes are 250mm in diameter, made of concrete, and arranged at 800mm intervals. The length of the ventilation pipes needs to be controlled within 30m, and they need to be placed in the middle of the sand layer. After the ventilation pipes are arranged, they are wrapped tightly with coarse sand. The function of ventilation ducts is to form a ventilation and antifreeze system. During cold storage operation, the low temperature inside the storage will be conducted downwards through the floor, causing the soil beneath to freeze. Once the soil freezes, it generates frost heave, which can lift the floor, causing it to crack or even break. By installing ventilation ducts in the sand layer, outside air can circulate within the ducts, using heat exchange to carry away the cold air and thus prevent the soil from freezing.
[0029] Further, the construction of the insulation layer and waterproof layer is carried out. The construction of the insulation layer and waterproof layer includes three main parts: the composite construction of the air barrier layer and the insulation layer, the construction of the two-way waterproof structure, and the anti-deformation treatment of the insulation layer.
[0030] In the composite construction stage of the vapor barrier and insulation layer, a layer of cold primer is first applied to the surface of the concrete leveling layer. This cold primer is an asphalt-based material that penetrates into the micropores of the leveling layer, enhancing the adhesion between the subsequent roofing membrane and the substrate. After the cold primer is applied, a 4mm thick SBS modified asphalt vapor barrier is laid using a cold-bonding method. During membrane laying, the overlap length between adjacent membrane rolls is controlled between 10 and 15mm. This overlap ensures there are no gaps between the membrane rolls, forming a complete vapor barrier. After laying, a special roller is used to compact the membrane, expelling air underneath and ensuring a firm bond between the membrane and the substrate, preventing hollow areas. After the vapor barrier is laid, the insulation layer is laid on top. The insulation layer uses extruded polystyrene board (XPS board) with a thickness of 250mm. XPS board has a closed-cell honeycomb structure, extremely low thermal conductivity, and excellent insulation performance. When laying XPS boards, the joints between the boards are joined using a tongue-and-groove joint technique. This effectively reduces heat loss through the joints. After joining, a special waterproof adhesive is applied to the joints to bond the adjacent boards together. At joints such as walls and columns, L-shaped XPS boards are used for wrapping. The L-shaped boards cover the corners of walls and columns, preventing cold bridges that could reduce insulation performance. The gaps between the L-shaped boards and the walls / columns are sealed with expansion rubber strips. These strips expand when wet, completely filling the gaps and further blocking heat transfer.
[0031] Furthermore, during the construction phase of the two-way waterproofing structure, a 15mm thick 1:3 cement mortar layer is first used to level the surface above the insulation layer. After the leveling layer has cured, a cold primer is applied to its surface, and then the waterproof membrane is laid. The waterproof membrane is also a 4mm thick SBS modified bitumen membrane. A full-adhesion construction process is used during laying, meaning the membrane is completely bonded to the substrate without gaps. Full-adhesion construction prevents moisture from seeping under the membrane, avoiding localized failure of the waterproofing layer. An additional layer of waterproof membrane is added within 200mm on both sides of the expansion joint as a reinforcement layer. Expansion joints are weak points in the floor; concrete shrinkage can easily create tiny cracks at these joints, allowing moisture to seep in. Therefore, adding an additional layer on both sides of the expansion joint enhances the waterproofing capability of this area. At the corners where the wall meets the floor, a 45-degree diagonal laying method is used for reinforcement. Diagonal application allows the membrane to better adhere to corners, preventing air pockets caused by excessively steep angles. At the interface between the waterproofing layer and the ventilation duct, where the duct penetrates the waterproofing layer, a seepage channel can easily form. In this embodiment, a custom-made rubber sleeve is used for sealing at the interface. The rubber sleeve tightly wraps around the duct, ensuring no water leakage at the interface.
[0032] Furthermore, during the deformation-resistant treatment of the insulation layer, because XPS boards expand and contract with temperature changes, if the insulation layer is constrained and cannot deform freely, significant temperature stress will be generated, leading to cracking of the insulation board. To release this temperature stress, elastic expansion joints are installed at 6-meter intervals during insulation layer construction. The width of the expansion joints is 10mm, and they are filled with closed-cell foam rods. Closed-cell foam rods are a soft and elastic material; when the insulation layer expands due to heat, the foam rods are compressed, and when the insulation layer contracts due to cold, the foam rods rebound, always ensuring a tight seal in the expansion joints. After the foam rods are filled, waterproof sealant is applied to the surface to prevent moisture from seeping into the insulation layer from the expansion joints. In addition to setting elastic expansion joints, fiberglass mesh is also adhered to the splicing surfaces of the insulation boards. Fiberglass mesh has good tensile strength and alkali resistance; when adhered to the splicing surfaces of the insulation boards, it connects adjacent insulation boards into a whole, increasing the overall integrity of the insulation layer. The overlap width of the mesh fabric should be no less than 100mm, and it should be fixed to the insulation board with a special adhesive. Through the above treatment, a stress-relieving mesh is formed, which can effectively absorb and release the deformation stress caused by temperature changes.
[0033] Further, after the insulation and waterproofing layers are completed, the reinforcing mesh is laid and the concrete is poured. Placing a reinforcing mesh in the floor improves its crack resistance and load-bearing capacity. This method uses 12mm diameter steel bars, arranged bidirectionally at 150mm intervals, forming a double-sided, bidirectional reinforcing mesh. The laying is done in two steps: first, the first layer of reinforcing mesh is tied, located at the bottom of the floor. After the first layer is tied, various pipelines are pre-embedded, including cable conduits and signal conduits. After the pipelines are pre-embedded, the second layer of reinforcing mesh is tied. The two layers of reinforcing mesh are supported by stirrups, small supports made of steel bars, which separate the upper and lower layers of reinforcing mesh to ensure the spacing between them meets design requirements. The stirrup spacing is no more than 1.8m to ensure the upper layer of reinforcing mesh does not sink due to construction loads during concrete pouring. For the bottom layer of reinforcing steel, concrete spacers are used to control the thickness of the protective layer at the bottom. The protective layer refers to the distance from the outer surface of the reinforcing steel to the concrete surface; a sufficient protective layer thickness can prevent the reinforcing steel from corroding. After the reinforcing steel is tied, concrete is poured using a pump. The concrete strength grade is C25 fine aggregate concrete, and the thickness is 120mm. During pouring, the 1-meter control elevation line marked on the wall is used as a reference to control the pouring elevation of the concrete. After the concrete is poured, a plate vibrator is used for compaction. Vibration can remove air bubbles in the concrete and make the concrete dense. After vibration, the original slurry leveling is performed, that is, using the concrete's own slurry to smooth the surface. During the concrete pouring process, it is strictly forbidden to add water to change the concrete mix ratio, because adding water will reduce the strength of the concrete. At the same time, it is necessary to ensure the continuity of concrete supply. The interval between the supply of two adjacent truckloads of concrete should not exceed 40 minutes. If it exceeds 40 minutes, the concrete poured earlier will have begun to set, and a construction cold joint will form between the first and second poured concrete, which will affect the integrity of the floor.
[0034] Furthermore, after the concrete pouring is completed, surface finishing and curing treatments are carried out. The finishing and curing treatments include four aspects: multiple rounds of mechanical finishing, moisture retention curing and stress release, temperature compensation curing, and pre-curing treatment of expansion joints.
[0035] In the multiple mechanical finishing stages, a metal roller is used for the initial finishing before the concrete initially sets. The metal roller has grips on both sides and is rolled back and forth along the top of the formwork to compact and smooth the concrete surface. This initial finishing eliminates air bubbles and laitance on the concrete surface, making it initially smooth. Before the concrete finally sets, a low-speed grinder and a high-speed grinder are used for finishing in sequence. The low-speed grinder rotates at 150 to 200 revolutions per minute and is used for coarse grinding, mainly to remove surface protrusions and large particles. The high-speed grinder rotates at 500 to 800 revolutions per minute and is used for fine grinding, mainly to make the surface smooth and dense. During the coarse and fine grinding processes, three different grit grinding discs are used: 50 grit, 150 grit, and 300 grit. The higher the grit number, the finer the grinding disc, which can gradually refine the surface texture. Through multiple rounds of mechanical finishing, a dense hardened layer with a thickness of 0.5 to 1 mm can be formed on the concrete surface. The strength and wear resistance of the dense hardened layer are much higher than those of the internal concrete.
[0036] Furthermore, during the moisture retention and stress release phase, immediately cover the concrete with a breathable plastic film after finishing. The plastic film prevents moisture evaporation from the concrete, providing sufficient moisture for cement hydration. The film overlap should be at least 150mm, and the edges should be secured with sandbags to prevent the film from being blown away by the wind. For the first three days, water should be applied every two hours, maintaining a 1-2mm depth of water underneath the film. The first three days are the most active period for cement hydration, requiring a sufficient water supply. From the fourth day onwards, the watering frequency should be increased to four times daily. Simultaneously, damp straw mats should be laid within a 200mm radius on both sides of the expansion joints. The straw mats have a water-retaining effect, keeping the area moist for an extended period. Concrete undergoes drying shrinkage during hardening, i.e., volume shrinkage due to moisture evaporation. Maintaining moisture at the expansion joints beforehand utilizes the properties of concrete's drying shrinkage and wet expansion, releasing shrinkage stress in the area and reducing the occurrence of drying shrinkage cracks.
[0037] Furthermore, during the temperature-compensated curing stage, the low temperature in the cold storage environment slows down the hydration reaction of cement, extending the curing time. To ensure sufficient cement hydration, two layers of extruded polystyrene (XPS) boards, each 50mm thick, are placed on the concrete surface. The seams of the XPS boards are sealed with aluminum foil tape to prevent heat loss. Simultaneously, one temperature sensor is installed every 500㎡ of floor space to monitor the concrete surface temperature in real time. When the monitored temperature drops below 5℃, an electric heat tracing system is activated. The electric heat tracing system has a power of 20W / ㎡, maintaining the curing environment temperature between 15 and 25℃ through heating. Within this temperature range, the cement hydration reaction is fastest, significantly shortening the curing period.
[0038] Furthermore, during the pre-curing stage of the expansion joint, 24 hours before cutting the expansion joint, a 100mm area on each side of the joint is pre-moistened. The specific operation of pre-moistening curing involves evenly spraying a curing agent using a sprayer, with a dosage of 0.2L / ㎡. After spraying, the curing agent forms a hardening film on the concrete surface, locking in the moisture inside the concrete and preventing shrinkage cracks on both sides of the joint due to moisture evaporation. Then, a 20mm wide PVC guide strip is pasted along the marked line, and the cutting machine operates along the edge of the PVC guide strip during cutting. The guide strip provides precise guidance for cutting, ensuring accurate positioning and straight lines for the expansion joint. The cutting depth is controlled at 20mm, approximately 1 / 6 of the floor thickness, while also avoiding dust contamination of the curing concrete surface during cutting, improving the cutting accuracy to ±2mm.
[0039] Further, after the concrete surface layer has cured to its designed strength, the epoxy wear-resistant surface layer is applied. The application is done in two coats. For the first coat, wear-resistant quartz sand is mixed into the epoxy material. Quartz sand is a very hard granular material, and its inclusion significantly improves the wear resistance of the coating. The second coat is applied using the normal rolling process, without the addition of quartz sand, resulting in a smooth and even surface. Both coats must be applied evenly to avoid inconsistent thickness or color differences.
[0040] Further, after the epoxy wear-resistant surface layer is applied, the expansion joints are cut and caulking is performed. Cutting is done according to pre-marked lines, with a depth of 18-22mm and a width of 3-6mm. After cutting, the joints are cleaned and then filled with antifreeze sealant. Antifreeze sealant is a sealing material with good elasticity and low-temperature performance; it will not become brittle or crack in low-temperature environments and can maintain its sealing effect for a long time. After caulking, the floor forms a complete segmented structure, with each segment isolated from the others by expansion joints. The shrinkage stress of the concrete can be effectively released at the expansion joints, thus preventing cracking of the floor.
[0041] It should be noted that the specific values involved in the above embodiments are merely examples, and can be appropriately adjusted according to engineering needs in practical applications. Those skilled in the art, based on their understanding of the principles of this invention, can make various modifications or variations to the above embodiments, and all such modifications or variations should be covered within the protection scope of this invention. The protection scope of this invention should be determined by the claims.
Claims
1. A method of segmented construction of a freezer wear floor, characterised by, Includes the following steps: S1: Grind and roughen the base plate, moisten it with water, and then mark the position of the partition joint according to the compartment layout diagram. S2: Erect and level the formwork, and bury ventilation pipes in the base sand layer to form a ventilation and antifreeze system; S3: Construct the vapor barrier layer, insulation layer and waterproof layer in sequence to form a composite insulation and waterproof structure, and set an anti-deformation structure in the insulation layer; S4: Lay a double-layer steel mesh and tie it in place. Pour concrete using a pumping method, vibrate it to compact it, and then level it. S5: Perform multiple mechanical finishing processes on the concrete surface, cover with a film for moisture retention and curing, and combine with temperature compensation curing measures. S6: After the concrete has cured to the design strength, apply epoxy wear-resistant surface material by roller. S7: Cut the dividing seam according to the marked line, clean the seam opening and fill it with antifreeze sealant.
2. The method of claim 1, wherein the cold storage warehouse wear floor is constructed in segments, and S3 includes the following steps: S31. Lay an air barrier layer on the surface of the concrete leveling layer, then lay an insulation layer. The joints of the boards are spliced with tongue and groove and coated with adhesive. The wall and column joints are wrapped with L-shaped insulation boards and filled with expansion rubber strips for sealing. S32. Construct and cure a leveling layer above the insulation layer, lay waterproof membrane, and fully adhere the membrane to the base layer. Add an additional layer on both sides of the expansion joint, reinforce the inside and outside corners with diagonal laying, and seal the interface between the waterproof layer and the ventilation pipe with a sealing sleeve to form a two-way waterproof and airtight structure. S33. Set elastic expansion joints at set intervals in the insulation layer, fill the joints with elastic sealing material, and attach fiberglass mesh to the splicing surface of the insulation board and fix it with adhesive to form a stress-relieving mesh.
3. The segmented construction method for cold storage wear-resistant flooring as described in claim 2, characterized in that, The air barrier layer is made of SBS modified bitumen membrane, the insulation layer is made of extruded polystyrene board, and the overlap length of the SBS modified bitumen membrane is 100~150mm.
4. The method of claim 1, wherein the cold storage warehouse wear floor is constructed in segments. Step S5 specifically includes: S51. Before the initial setting of the concrete, it is first compacted and polished with a metal roller. Before the final setting, it is coarsely ground with a low-speed polisher and finely ground with a high-speed polisher, and then layered with multi-grit grinding discs to form a dense hardened layer on the surface. S52. After finishing, cover with breathable plastic film and press the edges firmly. Use intermittent watering for curing. Lay damp straw mats on both sides of the separation joint to release shrinkage stress. S53. The concrete surface is covered with an insulation board, and temperature sensors are installed to monitor the surface temperature in real time. When the temperature is lower than the set value, the electric heat tracing system is activated to maintain the curing environment within the set temperature range. S54. Before cutting the dividing joint, spray a curing agent on both sides of the joint to form a hardened film. Attach a guide strip along the marked line. When cutting, operate along the edge of the guide strip to control the joint depth.
5. The segmented construction method for cold storage wear-resistant flooring as described in claim 4, characterized in that, In step S51, the low-speed polishing machine rotates at 150-200 rpm, and the high-speed polishing machine rotates at 500-800 rpm.
6. The segmented construction method for cold storage wear-resistant flooring as described in claim 4, characterized in that, The thickness of the dense hardened layer is 0.5~1mm.
7. The segmented construction method for cold storage wear-resistant flooring as described in claim 4, characterized in that, The insulation board is an extruded polystyrene board.
8. The segmented construction method for cold storage wear-resistant flooring as described in claim 4, characterized in that, The concrete is C25 fine aggregate concrete, and the thickness of the concrete is 115mm~125mm.
9. The segmented construction method for cold storage wear-resistant flooring as described in claim 4, characterized in that, The temperature sensor is installed at a density of one sensor per 500 square meters, and the maintenance environment temperature is 15~25℃.
10. The segmented construction method for cold storage wear-resistant flooring as described in claim 9, characterized in that, The cutting depth of the separation joint is 1 / 6 of the floor thickness, and the width is 3~6mm.