Construction method of integrated aluminum single panel metal curtain wall
The integrated aluminum single-panel metal curtain wall construction method solves the problems of aluminum single panels flying out during explosions and high maintenance costs in traditional curtain walls. It achieves rapid explosion venting, decoration and heat insulation effects, and improves construction quality and safety.
Patent Information
- Application Number
- CN202611536932.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-30
- Publication Date
- 2026-11-17
AI Technical Summary
Traditional curtain walls lack the ability to vent explosions, and aluminum panels may fly out, causing secondary damage. Moreover, the repair costs are high. Ordinary explosion-venting curtain walls have failed to effectively solve the problem of panels flying out, and their decorative and thermal insulation properties are insufficient.
The integrated aluminum single-panel metal curtain wall construction method is adopted. Through the combination of post-embedded plates, curtain wall keel frame, fiber reinforced cement board, modified polystyrene board insulation layer, explosion relief bolts and traction cables, a reliable connection is formed to ensure that the aluminum single panel detaches from the keel frame and is limited from flying out in the event of an explosion.
It enables rapid pressure release during an explosion, preventing aluminum panels from scattering, improving construction quality and safety, reducing maintenance costs, and providing decorative, insulation, and sealing functions.
Smart Images

Figure CN123109403A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building curtain wall construction technology, and in particular relates to a construction method for integrated aluminum single-panel metal curtain walls. Background Technology
[0002] In industrial plants, warehouses, and other buildings storing explosive materials, the exterior walls need to have explosion-proof capabilities. Currently, traditional curtain walls generally lack explosion-proof capabilities; during an explosion, the wall material shatters into pieces and scatters in all directions, easily causing secondary injuries. While ordinary explosion-proof curtain walls can relieve pressure, they typically only focus on pressure release and do not address the issue of panels flying out after an explosion. Aluminum panels, even after detaching from the frame, may still fly out and cause secondary damage. Furthermore, traditional explosion-proof walls often use materials such as stone-painted surfaces, fiber-reinforced cement boards, and insulation boards, requiring extensive material replacement after an explosion, resulting in high maintenance costs. Summary of the Invention
[0003] In view of this, the present invention aims to overcome the defects in the prior art and proposes an integrated aluminum single-panel metal curtain wall construction method.
[0004] To achieve the above objectives, the technical solution created by this invention is implemented as follows: The construction method for integrated aluminum single-panel metal curtain walls includes the following steps: S1. Based on the reference axis and design drawings, determine the curtain wall positioning line, grid line and the position of the post-embedded plate on the wall to be constructed; S2. Drill holes in the wall, clean the debris from the holes, insert the rear-expanding mechanical anchor bolts, fix the rear-mounted embedded plate to the rear-expanding mechanical anchor bolts, and perform anti-corrosion treatment on the rear-mounted embedded plate. S3. Weld the main keel to the main steel structure and fix it. Weld vertical secondary keels and horizontal secondary keels between adjacent main keels to form the curtain wall keel frame. S4. The aluminum single-panel columns are welded to the rear embedded plate through the adapter, and aluminum single-panel beams are welded between adjacent aluminum single-panel columns to form an aluminum single-panel keel frame. Traction cable fixing holes are set on the aluminum single-panel keel frame. S5. Fix the fiber-reinforced cement board to the outside of the aluminum single-panel keel frame with self-tapping screws. The upper and lower layers of fiber-reinforced cement boards are arranged in a staggered manner, and a board gap is reserved between adjacent fiber-reinforced cement boards. The board gap is filled with elastic putty. S6. A modified polystyrene insulation layer is attached to the outside of the fiber-reinforced cement board. S7. Provide explosion-proof bolts and traction cables; the explosion-proof bolt includes a screw and a nut; fix the first end of the traction cable to the traction cable fixing hole on the aluminum single-panel keel frame; pass the second end of the traction cable through the horizontal folded edge openings of two adjacent aluminum single-panels and lock it with fasteners; use the explosion-proof bolt to fix the aluminum single-panel to the aluminum single-panel keel frame; when the explosive impact force acting on the aluminum single-panel reaches the explosion-proof pressure value of the explosion-proof bolt, the nut disconnects from the screw, the aluminum single-panel separates from the aluminum single-panel keel frame, and the traction cable maintains the connection between the aluminum single-panel and the aluminum single-panel keel frame and restricts the aluminum single-panel from flying out; S8. Fill the gaps between adjacent aluminum panels with foam rods and inject sealant into the gaps to complete the curtain wall sealing. S9. Inspect the curtain wall keel, aluminum single-panel keel, fiber reinforced cement board, insulation layer, aluminum single panel, explosion relief bolts, traction cable and sealant joint; the process ends after the inspection is qualified; if the inspection is unqualified, rework and rectification are required before re-inspection.
[0005] Furthermore, in step S2, the diameter of the drilled hole is φ19mm and the hole depth is not less than 80mm; the depth of the post-expansion mechanical anchor bolt embedded in the wall is not less than 90mm, excluding the thickness of the wall finishing layer or plaster layer.
[0006] Furthermore, in step S3, the welding of the main keel to the main steel structure is to first spot weld for positioning, adjust accurately, and then fully weld; the height of the fillet weld is not less than 5mm, and after welding, the weld area is coated with two coats of anti-rust paint, with an interval of not less than 12 hours between the two coats of anti-rust paint.
[0007] Furthermore, in step S4, both the aluminum single-panel columns and the aluminum single-panel beams are prefabricated using a groove-shaped and fixed-length processing tool. The groove-shaped and fixed-length processing tool is equipped with a prefabricated groove that matches the cross-section of the keel. After the keel to be processed is placed in the prefabricated groove for positioning, it is welded.
[0008] Furthermore, in step S5, the distance between the self-tapping screw and the edge of the fiber-reinforced cement board is 10mm to 16mm, the spacing between the self-tapping screws on the edge of the board is 200mm, and the spacing between the self-tapping screws in the middle of the board is 300mm; the width of the gap between adjacent fiber-reinforced cement boards is 4mm to 5mm.
[0009] Furthermore, in step S6, the length of the modified polystyrene board insulation layer does not exceed 1200mm, and the bonding area between the modified polystyrene board and the fiber-reinforced cement board is not less than 40% of the total area.
[0010] Furthermore, in step S7, the explosion relief bolts include M5×25 explosion relief dovetail bolts and M5×118 explosion relief bolts; the destructive load of the traction cable is not less than 3000 kg.
[0011] Furthermore, in step S7, the traction cable is fixed to the reserved fixing hole of the aluminum single-panel keel frame by bolts, and the other end of the traction cable passes through the horizontal folded edge opening of two adjacent aluminum single panels and is locked by fasteners, so that the adjacent aluminum single panels are mutually constrained by the same traction cable when the explosion is vented.
[0012] Furthermore, in step S8, the ambient temperature for adhesive injection is 15℃~30℃, and the relative humidity is not less than 50%; the adhesive is injected continuously from top to bottom and from left to right in one go, and after injection, the adhesive is scraped to the bottom in one go, with the scraping speed at the corners being less than the scraping speed on the straight sections.
[0013] Furthermore, in step S2, when the drilling position cannot avoid the concrete reinforcement, a reinforcing steel plate is set next to the drilling hole. The reinforcing steel plate is welded to the rear embedded plate, and the weld height of the contact surface between the reinforcing steel plate and the rear embedded plate is not less than 6mm.
[0014] Compared with existing technologies, the present invention has the following advantages: This invention, through a series of steps including measurement and layout, installation of embedded plates, welding of the curtain wall keel and aluminum panel keel, staggered laying of fiber-reinforced cement boards and filling with elastic putty, pasting of modified polystyrene insulation layer, installation of aluminum panels using explosion-proof bolts and traction cables, filling with foam rods and injecting sealant, and inspection and rework, forms an integrated metal curtain wall that combines decoration, insulation, sealing, and reliable connection under normal conditions. When an explosion occurs and the impact force reaches the explosion-proof pressure value of the explosion-proof bolts, the bolt nuts and bolts disconnect, and the aluminum panels detach from the aluminum panel keel frame, thus rapidly releasing the explosion pressure. Simultaneously, the traction cables still connect the aluminum panels to the aluminum panel keel frame and restrict their flight, preventing secondary damage caused by the scattering of aluminum panels. This invention solves the problems of traditional curtain walls lacking explosion-proof capabilities, ordinary explosion-proof curtain walls failing to prevent panel flight, and insufficient decoration and insulation. It effectively improves the construction quality, safety, and ease of maintenance of the curtain wall. Attached Figure Description
[0015] The accompanying drawings, which form part of this invention, are used to provide a further understanding of the invention. The illustrative embodiments and descriptions of the invention are used to explain the invention and do not constitute an undue limitation of the invention. In the drawings: Figure 1 A flowchart illustrating the construction method created for this invention. Detailed Implementation
[0016] It should be noted that, unless otherwise specified, the embodiments and features described in the present invention can be combined with each other.
[0017] In the description of this invention, it should be understood that the terms "center," "longitudinal," "lateral," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," and "outer," etc., indicating orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, are only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation, and therefore should not be construed as a limitation on this invention. Furthermore, the terms "first," "second," etc., are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, features defined with "first," "second," etc., may explicitly or implicitly include one or more of that feature. In the description of this invention, unless otherwise stated, "a plurality of" means two or more.
[0018] In the description of this invention, it should be noted that, unless otherwise explicitly specified and limited, the terms "installation," "connection," and "linking" should be interpreted broadly. For example, they can refer to a fixed connection, a detachable connection, or an integral connection; they can refer to a mechanical connection or an electrical connection; they can refer to a direct connection or an indirect connection through an intermediate medium; and they can refer to the internal connection of two components. Those skilled in the art will understand the specific meaning of the above terms in this invention based on the specific circumstances.
[0019] The invention will now be described in detail with reference to the accompanying drawings and embodiments.
[0020] like Figure 1 As shown, the integrated aluminum single-panel metal curtain wall construction method provided by the present invention includes the following steps: S1. Measurement and layout: Based on the reference axis and design drawings, determine the curtain wall positioning line, grid line and the position of the post-embedded plate on the wall to be constructed.
[0021] S2. Install the rear-mounted embedded plate: Drill holes in the wall, clean the debris from the holes, insert the rear-expanding mechanical anchor bolts, fix the rear-mounted embedded plate to the rear-expanding mechanical anchor bolts, and perform anti-corrosion treatment on the rear-mounted embedded plate.
[0022] S3. Install the curtain wall keel: Weld the main keel to the main steel structure and fix it in place. Weld vertical secondary keels and horizontal secondary keels between adjacent main keels to form the curtain wall keel frame.
[0023] S4. Install aluminum panel keel: Weld the aluminum panel columns to the rear embedded plate through adapters, weld aluminum panel beams between adjacent aluminum panel columns to form an aluminum panel keel frame, and set traction cable fixing holes on the aluminum panel keel frame.
[0024] S5. Install fiber-reinforced cement board: Fix the fiber-reinforced cement board to the outside of the aluminum single-panel keel frame with self-tapping screws. The upper and lower layers of fiber-reinforced cement boards are arranged in a staggered manner, and a board gap is reserved between adjacent fiber-reinforced cement boards. The board gap is filled with elastic putty.
[0025] S6. Install modified polystyrene insulation layer: attach modified polystyrene insulation layer to the outside of the fiber reinforced cement board.
[0026] S7. Install aluminum single-panel and explosion-proof connection assembly: Provide explosion-proof bolts and traction cables; the explosion-proof bolt includes a screw and a nut; fix the first end of the traction cable to the traction cable fixing hole on the aluminum single-panel keel frame; pass the second end of the traction cable through the horizontal folded edge opening of two adjacent aluminum single panels and lock it with fasteners; use the explosion-proof bolt to fix the aluminum single panel to the aluminum single-panel keel frame; when the explosive impact force acting on the aluminum single panel reaches the explosion-proof pressure value of the explosion-proof bolt, the nut disconnects from the screw, the aluminum single panel separates from the aluminum single-panel keel frame, and the traction cable maintains the connection between the aluminum single panel and the aluminum single-panel keel frame and restricts the aluminum single panel from flying out.
[0027] S8. Sealing and Glue Application: Fill the gaps between adjacent aluminum panels with foam rods and inject sealant into the gaps to complete the curtain wall sealing.
[0028] S9. Inspection: Inspect the curtain wall keel, aluminum single-panel keel, fiber reinforced cement board, insulation layer, aluminum single panel, explosion relief bolts, traction cable and sealant joints; the process ends after the inspection is qualified; if the inspection is unqualified, rework and rectification are required and then re-inspected.
[0029] In step S1, during the measurement and layout, due to the relatively large allowable error in civil construction and the high precision requirements of aluminum panel construction, the civil construction horizontal baseline cannot be relied upon entirely. It is necessary to remeasure using the baseline axis and leveling points, and then correct and verify the measurements. The curtain wall positioning lines and grid lines are determined on the ground floor according to the design drawings; a theodolite is used to draw plumb lines upwards to determine the corner positions and facade dimensions of the curtain wall; the positions of the embedded parts are determined based on the grid lines. Measurement and layout are carried out under wind conditions not exceeding level 4. After layout, timely verification is conducted to control the accumulation of errors and ensure the accuracy of the curtain wall's verticality and the column positions.
[0030] In step S2, during drilling, use an impact drill to drill φ19mm holes in the concrete structure, with a hole depth of not less than 80mm. Use a special brush to remove concrete debris generated during drilling, and use a special blower to blow away concrete chips from the drill hole. Avoid drilling into the concrete reinforcement bars as much as possible; if unavoidable, place a reinforcing steel plate next to the steel plate, using steel plates of the same thickness and material. Weld the reinforcing steel plate to the post-installed embedded plate, with a weld height of not less than 6mm and a full, uniform weld surface. When installing the anchor bolts and post-installed embedded plates, use a hammer to strike the special sleeve, causing the head of the post-expanding mechanical anchor bolt to expand and form a locking mechanism with the expanded concrete cavity. After the anchor bolts have been struck to the specified depth, install the post-installed steel plate. The anchor bolts should be embedded into the wall to a depth of not less than 90mm, excluding the thickness of the wall finish or plaster layer. Fit each bolt with a nut to fix the anchor plate in the correct position. After confirming the anchor plate is in the correct position, spot weld the bolts and nuts to prevent them from loosening. Once the embedded parts are confirmed to be correctly placed, remove slag and rust, and apply two coats of anti-rust paint. The installation quality of the post-installed embedded plate should meet the following requirements: the type, specifications, dimensions, performance, plate wall thickness, and surface treatment of the embedded plate should meet the design requirements and have a factory certificate of conformity; the embedded parts should be installed upright, avoiding any tilting; the depth of the four post-expansion mechanical anchors should be uniform; the square washers should be placed upright; and the nuts should be tightened; the insertion depth of the post-expansion mechanical anchors should be strictly controlled; before placing the embedded plate, the finishing layer or plaster layer on the structural surface should be removed to ensure the iron plate is placed flat; it is essential to use a hammer to strike the special sleeve to expand the anchor head and form a locking mechanism with the expanded concrete cavity.
[0031] In step S3, when installing the main keel, the welding points between the main keel and the steel column are ground according to the measurement and layout markings. Spot welding is performed first, followed by adjustment. After accurate adjustment, full welding is performed, and anti-rust paint is applied for corrosion protection after welding. Before installing the vertical secondary keel, the embedded iron parts are cleaned, their positions are checked one by one, and cement residue is removed. Then, the vertical secondary keel is connected to the connectors, and adjusted and fixed. When installing the horizontal secondary keel, the installation position of the horizontal beam is determined on the vertical material, and the horizontal beam is installed. The curtain wall frame is adjusted and calibrated as a whole, using an independent work surface as a unit. After leveling and calibration, the connectors are welded. Keel welding requirements: fillet weld height is not less than 5mm; welds must be free of slag inclusions, porosity, weld beads, and other defects; welds must be aesthetically pleasing and neat, without any missed welds, incomplete welds, cracks, etc.; the anti-corrosion treatment of the welded parts meets the design requirements, and the anti-rust paint is applied evenly without omissions. After welding damages the galvanized layer of the main keel, embedded parts, and various galvanized angle steels, two coats of anti-rust paint are applied for rust prevention, with an interval of no less than 12 hours between the first and second coats. After welding, a slag removal inspection is conducted. Following successful inspection, a concealed acceptance inspection is organized. After acceptance by the supervising engineer, anti-corrosion treatment is applied to the welded areas. In one embodiment, the main keel of the curtain wall can be made of 200×100×6mm steel rectangular tubes, the secondary keels can be made of 50×100×3mm steel rectangular tubes, and the edge keels can be made of 100×100×3mm steel rectangular tubes. The steel used is Q235-B, and the hot-dip galvanizing thickness is greater than 70μm. The verticality of the keel's vertical frames shall be based on the fixed frame, and the deviation shall not exceed 1.5mm; the deviation between two adjacent vertical frames shall not exceed 1.5mm; the deviation between two adjacent horizontal frames shall not exceed 1mm; when the grid size is not greater than 2 meters, the deviation of the grid diagonal size shall not exceed 2mm; the step difference between two adjacent horizontal frames shall not exceed 0.5mm; and the deviation of horizontal frames at the same elevation within a range not exceeding 20 meters shall not exceed 2mm.
[0032] In step S4, when installing the uprights, the adapter and the embedded plate are connected by welding. The process involves spot welding first, then adjustment, and finally full welding after accurate adjustment. The fillet weld height should be no less than 5mm. After welding, anti-rust paint is applied for corrosion protection. When installing the vertical frames below the reference frame, they are connected to the vertical frames and then inserted into the lower cavity of the reference frame, maintaining the designed expansion joint. The accuracy of the vertical frame position is adjusted, and finally, a secure connection is made. The installation of the lower frames follows the same procedure. When connecting the vertical and horizontal frames, they are connected by welding. In one embodiment, the main keel can be made of 100×50×3mm steel rectangular tubing as the uprights, and the horizontal beams can be made of 50×50×3mm steel rectangular tubing. The steel used is Q235-B, and the hot-dip galvanized thickness is greater than 70μm. The horizontal keel is welded to the uprights, ensuring that the outer surface of the horizontal frame and the outer surface of the reference surface of the vertical frame are on the same vertical plane. The vertical position of the horizontal frame is adjusted, and the levelness of the horizontal frame is checked with a level to ensure that the position of the horizontal frame meets the requirements of the design drawings' grid dimensions. During welding, spot welding is performed first, followed by adjustment, and then full welding after accurate adjustment. The height of the fillet weld is not less than 5mm. After welding, anti-rust paint is applied for corrosion protection. During installation, inspectors constantly check the surface protection of the profiles. A comprehensive inspection is carried out during the installation of the frame, especially the center lines of the horizontal and vertical beams, which must be aligned using instruments. In this embodiment, both the aluminum single-panel columns and aluminum single-panel beams are prefabricated using a channel-shaped, fixed-length processing tool. The channel-shaped, fixed-length processing tool has a prefabricated groove adapted to the cross-section of the keel. The keel to be processed is placed in the prefabricated groove for positioning before welding. This tool can be a U-shaped groove structure with a groove width adapted to the keel cross-section, such as 50mm or 100mm; or it can be a V-shaped groove structure. Adjustable positioning blocks can be set on the tool to adjust the groove width via bolts; angle positioning plates can be set to ensure a welding angle of 90°; quick clamps can be set to achieve rapid positioning of the keel. The tool can be made of Q235 steel with a galvanized surface. This tool enables rapid welding, improves precision, increases construction speed, and saves raw materials. Traction cable fixing holes are set on the aluminum single-panel keel frame. The positions of the traction cable fixing holes are determined according to the aluminum panel layout diagram, and the fixing ends are installed and tightened at the reserved positions using standard bolts. The destructive load of the traction cable is not less than 3000 kg.
[0033] In step S5, when installing fiber-reinforced cement boards, start from one end of the wall. The fiber-reinforced cement boards are generally fixed with self-tapping screws. The screw spacing at the edge of the board is 200mm, and the spacing in the middle of the board is 300mm. The distance between the screw and the edge of the board should not be less than 10mm or more than 16mm. When fixing with self-tapping screws, the fiber-reinforced cement board must be tightly against the joists. The upper and lower layers of fiber-reinforced cement boards should be staggered, leaving a 4mm-5mm gap between the boards. The gap should be filled with elastic putty to reduce the risk of cracks appearing after the putty and paint are applied. When the fiber-reinforced cement board is close to the joists at areas other than the edges, fix it with self-tapping screws spaced 300mm apart to prevent the fiber-reinforced cement board from falling off later. When installing the fiber-reinforced cement board, fix it from the middle of the board outwards to the four sides, with the screw heads slightly embedded in the board, but without damaging the surface. The screw holes should be smoothed with putty. In one embodiment, the fiber-reinforced cement board can be 1220×2440×12mm in size. The staggered joint method can be 1 / 2 staggered or 1 / 3 staggered. The joint width can be 4mm, 5mm or 6mm. The elastic putty can be acrylic, polyurethane or silicone based.
[0034] In step S6, the base layer should be treated before applying the insulation layer. Remove impurities and hollow areas from the fiber-reinforced cement board and repair them; slope window sills and eaves; and fill all openings in the exterior wall tightly. The surface flatness deviation of the modified polystyrene board to be applied should not exceed 4mm. Grind any protruding areas left during roughening and fill any recessed areas; ensure the flatness of the entire wall surface is within 4mm, with square corners and smooth vertical alignment. Prepare a layout diagram of the modified polystyrene boards based on the design dimensions of the entire exterior wall facade. The modified expanded polystyrene boards should be laid horizontally along their length to ensure continuous bonding. According to the insulation board layout diagram, the length of a single insulation board should not exceed 1200mm. Place them between the base steel frame and firmly bond them with special adhesive. The modified polystyrene boards must be firmly bonded to the cement pressure board, without loosening or incomplete adhesion. During inspection, randomly check one location every 20m (3 linear meters per location), but no less than three locations. Inspection methods include observation and manual pushing and pulling. The bonding area between each modified polystyrene board and the cement pressure board shall not be less than 40% of the total area. In one embodiment, the modified polystyrene insulation board may be 1200×550×90mm in size. The insulation board may also be replaced with rock wool board, extruded polystyrene board, or graphite polystyrene board. The bonding method may be spot bonding, strip bonding, or full bonding, and the bonding area may be 40%, 50%, 60%, or 70%.
[0035] In step S7, the traction cable is first installed. The first end of the traction cable is fixed to the traction cable fixing hole on the aluminum panel keel frame; the second end of the traction cable passes through the horizontal folded edge openings of two adjacent aluminum panels and is locked with fasteners. In one embodiment, each aluminum panel is equipped with an independent traction cable, with the first end fixed to the aluminum panel keel frame and the second end fixed to the folded edge opening of the aluminum panel. In another embodiment, two adjacent aluminum panels share a single traction cable. After passing through the horizontal folded edge openings of the two panels, the cable is locked with fasteners, so that adjacent aluminum panels are mutually restrained by the same traction cable during explosion venting. In yet another embodiment, four aluminum panels share a single traction cable, forming a cross-shaped restraint. The traction cable can be made of 304 stainless steel, with a diameter of 4mm, 5mm, or 6mm, and a breaking tensile strength of not less than 3000kg. The cable is covered with a transparent plastic hose to prevent abrasion of the aluminum panel surface. The tension of the cable connected to the keel can be adjusted using turnbuckles. Then, the aluminum panels are installed. Aluminum panels should be installed according to the panel numbers on the panel allocation diagram. Angle brackets should be installed at the adhesive joints, and it should be checked that the angle brackets of adjacent panels are staggered. A trial assembly should be performed to check the horizontal and vertical alignment. Then, explosion-proof dovetail screws should be used for assembly and trial fixing to the main and secondary keels. The horizontal and vertical gaps should be adjusted to meet requirements before final fixing. At the concealed adhesive joints, concealed joint clamps should be used for fixing. The gaps between the clamps should be checked to ensure consistency. Specifically, the horizontal and vertical deviation of the aluminum panels should be ±1.5mm. Sealant should be applied to the joints of the concealed joint clamps, and the joint should be greater than 5mm to ensure a tight seal. The gap between aluminum panels should be 20mm. Explosion-proof bolts include a bolt and a nut. Explosion-proof bolts are used to fix the aluminum panels to the aluminum panel keel frame. Explosion-relief bolts are known explosion-relief fasteners in the art. When the explosive impact force applied to the aluminum panel reaches the explosion-relief pressure value of the bolt, the nut and bolt disconnect, the aluminum panel detaches from the aluminum panel frame, and the pressure is released; simultaneously, the traction cable tightens the aluminum panel to prevent it from flying out and avoid secondary damage. After an explosion, the aluminum panel can be reused. In one embodiment, the explosion-relief bolts include M5×25 explosion-relief dovetail screws and M5×118 explosion-relief bolts. The explosion-relief pressure value can be selected according to the building design requirements, such as 5kPa, 10kPa, 15kPa, or 20kPa. The explosion-relief bolts are evenly arranged around the perimeter of the aluminum panel, with a spacing of 200mm, 300mm, or 400mm. In one embodiment, one M5×25 explosion-relief dovetail screw is provided at each of the four corners of each aluminum panel, for a total of four. In another embodiment, two M5×118 explosion-relief bolts are provided at the top and bottom edges of each aluminum panel, for a total of four. In another embodiment, M5×25 explosion-proof dovetail screws are used at the corners, and M5×118 explosion-proof bolts are used at the edges. In another embodiment, the explosion-proof bolts are only arranged at the top and bottom ends of the aluminum panel, while ordinary bolts are used on the left and right sides to cooperate with the traction cable. In one embodiment, the aluminum panel can be a 2.5mm thick roller-coated perfluorocarbon printed aluminum plate or a 2.5mm thick smooth fluorocarbon sprayed brick-red aluminum plate.The thickness of the aluminum panels can be 2.0mm, 2.5mm, or 3.0mm; the surface treatment can be fluorocarbon spraying, roller coating, or powder coating. The width of the panel seams can be 15mm, 20mm, or 25mm.
[0036] In step S8, when bonding and fixing components with silicone structural sealant, the sealant application should be carried out at a temperature above 15°C and below 30°C, and a relative humidity above 50%. Tear off the folded edge of the protective film on the aluminum panel, and apply masking tape at the 90° corner fold. The masking tape should be folded at a 90° angle at the four corners of the adhesive seam, and the entire panel should be covered with masking tape in one go, smoothing it firmly to avoid wrinkles. Fill with foam rods, ensuring a dense and straight application. Apply the sealant in a straight line, from top to bottom and from left to right, completing the application in one go. When scraping the sealant, follow the application steps to the bottom in one stroke, slowing down the scraping speed slightly at the corners. Remove the masking tape at a 45° outward angle, and dispose of the removed masking tape properly to avoid environmental pollution. In one embodiment, the sealant can be silicone structural adhesive, silicone weather-resistant adhesive, modified silane adhesive, or polyurethane adhesive. The dispensing temperature can be 15℃, 20℃, 25℃ or 30℃; the relative humidity can be 50%, 60% or 70%.
[0037] In step S9, the inspection items include: pull-out test of the post-embedded plate, the number of samples, test load, and qualification standards should meet the design requirements; weld inspection, the weld height, appearance quality, and anti-rust paint application should meet the requirements; allowable deviations in the installation of fiber-reinforced cement board, insulation layer, and aluminum single panel should meet the design requirements; the sealant joint should be subjected to a water spray test or a sealing test; the explosion relief function should be verified to confirm that the explosion relief bolts reliably disconnect under the set pressure and that the traction cable effectively restricts the aluminum single panel from flying out.
[0038] This invention, through a series of steps including measurement and layout, installation of embedded plates, welding of the curtain wall keel and aluminum panel keel, staggered laying of fiber-reinforced cement boards and filling with elastic putty, pasting of modified polystyrene insulation layer, installation of aluminum panels using explosion-proof bolts and traction cables, filling with foam rods and injecting sealant, and inspection and rework, forms an integrated metal curtain wall that combines decoration, insulation, sealing, and reliable connection under normal conditions. When an explosion occurs and the impact force reaches the explosion-proof pressure value of the explosion-proof bolts, the bolt nuts and bolts disconnect, and the aluminum panels detach from the aluminum panel keel frame, thus rapidly releasing the explosion pressure. Simultaneously, the traction cables still connect the aluminum panels to the aluminum panel keel frame and restrict their flight, preventing secondary damage caused by the scattering of aluminum panels. This invention solves the problems of traditional curtain walls lacking explosion-proof capabilities, ordinary explosion-proof curtain walls failing to prevent panel flight, and insufficient decoration and insulation. It effectively improves the construction quality, safety, and ease of maintenance of the curtain wall.
[0039] The above description is merely a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A construction method for integrated aluminum single-panel metal curtain walls, characterized in that, Includes the following steps: S1. Based on the reference axis and design drawings, determine the curtain wall positioning line, grid line and the position of the post-embedded plate on the wall to be constructed. S2. Drill holes in the wall, clean the debris from the holes, insert the rear-expanding mechanical anchor bolts, fix the rear-mounted embedded plate to the rear-expanding mechanical anchor bolts, and perform anti-corrosion treatment on the rear-mounted embedded plate. S3. Weld the main keel to the main steel structure and fix it. Weld vertical secondary keels and horizontal secondary keels between adjacent main keels to form the curtain wall keel frame. S4. The aluminum single-panel columns are welded to the rear embedded plate through the adapter, and aluminum single-panel beams are welded between adjacent aluminum single-panel columns to form an aluminum single-panel keel frame. Traction cable fixing holes are set on the aluminum single-panel keel frame. S5. Fix the fiber-reinforced cement board to the outside of the aluminum single-panel keel frame with self-tapping screws. The upper and lower layers of fiber-reinforced cement boards are arranged in a staggered manner, and a board gap is reserved between adjacent fiber-reinforced cement boards. The board gap is filled with elastic putty. S6. A modified polystyrene insulation layer is attached to the outside of the fiber-reinforced cement board. S7. Provide explosion-proof bolts and traction cables; the explosion-proof bolt includes a screw and a nut; fix the first end of the traction cable to the traction cable fixing hole on the aluminum single-panel keel frame; pass the second end of the traction cable through the horizontal folded edge openings of two adjacent aluminum single-panels and lock it with fasteners; use the explosion-proof bolt to fix the aluminum single-panel to the aluminum single-panel keel frame; when the explosive impact force acting on the aluminum single-panel reaches the explosion-proof pressure value of the explosion-proof bolt, the nut disconnects from the screw, the aluminum single-panel separates from the aluminum single-panel keel frame, and the traction cable maintains the connection between the aluminum single-panel and the aluminum single-panel keel frame and restricts the aluminum single-panel from flying out; S8. Fill the gaps between adjacent aluminum panels with foam rods and inject sealant into the gaps to complete the curtain wall sealing. S9. Inspect the curtain wall keel, aluminum single-panel keel, fiber reinforced cement board, insulation layer, aluminum single panel, explosion relief bolts, traction cable and sealant joint; the process ends after the inspection is qualified; if the inspection is unqualified, rework and rectification are required before re-inspection.
2. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S2, the diameter of the drilled hole is φ19mm and the hole depth is not less than 80mm; the depth of the post-expansion mechanical anchor bolt embedded in the wall is not less than 90mm, excluding the thickness of the wall finishing layer or plaster layer.
3. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S3, the welding of the main keel to the main steel structure is to first spot weld for positioning, adjust accurately, and then fully weld; the height of the fillet weld is not less than 5mm, and after the welding is completed, two coats of anti-rust paint are applied to the weld area, with an interval of not less than 12 hours between the two coats of anti-rust paint.
4. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S4, both the aluminum single-panel columns and the aluminum single-panel beams are prefabricated using a groove-shaped and fixed-length processing tool. The groove-shaped and fixed-length processing tool is equipped with a prefabricated groove that matches the cross-section of the keel. After the keel to be processed is placed in the prefabricated groove for positioning, it is welded.
5. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S5, the distance between the self-tapping screw and the edge of the fiber-reinforced cement board is 10mm to 16mm, the spacing between the self-tapping screws on the edge of the board is 200mm, and the spacing between the self-tapping screws in the middle of the board is 300mm; the width of the gap between adjacent fiber-reinforced cement boards is 4mm to 5mm.
6. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S6, the length of the modified polystyrene board insulation layer shall not exceed 1200mm, and the bonding area between the modified polystyrene board and the fiber-reinforced cement board shall not be less than 40% of the total area.
7. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S7, the explosion relief bolts include M5×25 explosion relief dovetail bolts and M5×118 explosion relief bolts; the destructive load of the traction cable is not less than 3000 kg.
8. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S7, the traction cable is fixed to the reserved fixing hole of the aluminum single panel keel frame by bolts. The other end of the traction cable passes through the horizontal folded edge opening of two adjacent aluminum single panels and is locked by fasteners, so that the adjacent aluminum single panels are mutually restrained by the same traction cable when the explosion is vented.
9. The construction method for integrated aluminum single-panel metal curtain wall according to claim 1, characterized in that: In step S8, the ambient temperature for adhesive injection is 15℃~30℃ and the relative humidity is not less than 50%. When injecting adhesive, it should be done continuously from top to bottom and from left to right. After injection, scrape the adhesive to the bottom in one stroke. The scraping speed at the corners should be less than the scraping speed on the straight sections.
10. The construction method for integrated aluminum single-panel metal curtain wall according to any one of claims 1 to 9, characterized in that: In step S2, when the drilling position cannot avoid the concrete reinforcement, a reinforcing steel plate is set next to the drilling hole. The reinforcing steel plate is welded to the post-embedded plate, and the weld height of the contact surface between the reinforcing steel plate and the post-embedded plate is not less than 6mm.