Construction methods for secondary lining inside shield tunnels
By using a modular prefabrication and assembly method for secondary lining, the problem of low construction efficiency in shield tunnel secondary lining has been solved. This method enables efficient and reliable construction of nuclear power tunnel linings, adapting to confined spaces and highly corrosive environments, and meeting the long-term service requirements of nuclear power tunnels.
Patent Information
- Application Number
- CN202611299706.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-08-26
- Publication Date
- 2026-11-17
AI Technical Summary
Existing shield tunnel secondary lining construction has low efficiency, poor equipment adaptability, and long maintenance cycle. Furthermore, the traditional prefabricated lining construction process is unreasonable and difficult to adapt to the high corrosion, small space, and high standard construction conditions of nuclear power tunnels.
The method of prefabricated secondary lining is adopted. The shield tunnel facilities are dismantled, the ventilation ducts are rearranged, and the prefabricated lining blocks are transported and installed from the outside to the inside using transport rails. The rails are dismantled section by section to form the installation space. The blocks are assembled using chemical bonding, flange connection or hot melt process, and finally grouting is performed to solidify them and form a complete inner lining layer.
It enables efficient and reliable secondary lining construction in confined spaces, shortens the construction cycle, improves the tunnel's corrosion resistance and water pressure resistance, and meets the requirements for the ultra-long service life of nuclear power tunnels.
Smart Images

Figure CN123109701A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of tunnel construction, and more particularly to a construction method for secondary lining in shield tunnels. Background Technology
[0002] With the rapid development of the nuclear power clean energy industry, the number of underwater and seabed shield tunnels for water intake and drainage in nuclear power projects is continuously increasing. These tunnels operate under high water pressure, highly corrosive seawater, and complex geological environments for extended periods. According to the relevant specifications in the "Design Standard for Shield Tunnel Engineering" (GB / T 51438-2021), shield tunnels containing corrosive media must be equipped with secondary lining to meet the design requirements for a 60-100 year service life of nuclear power tunnels and ensure the long-term safe operation of the project.
[0003] Currently, secondary lining of shield tunnels mostly adopts the cast-in-place formwork trolley construction process. This method has obvious technical shortcomings: the dust and noise pollution caused by working in narrow tunnels is severe, construction efficiency is low, and large trolley equipment is difficult to adapt to the construction scenarios of tunnels with small diameters and small radii of curvature. At the same time, the curing period of cast-in-place concrete is long, resulting in high overall construction schedule pressure. Existing prefabricated lining technology is mostly used for the initial lining of tunnels. The assembly process for the internal secondary lining of pre-formed shield tunnels is still imperfect, with problems such as poor alignment accuracy in narrow spaces, insufficient equipment adaptability, and lack of quality control measures for anti-corrosion grouting and process connection.
[0004] In summary, existing construction techniques are difficult to adapt to the highly corrosive, confined, and high-standard construction conditions of nuclear power tunnels. The industry urgently needs a shield tunnel segmented prefabrication secondary lining construction method that is highly adaptable, efficient in construction, and reliable in forming quality. Summary of the Invention
[0005] The purpose of this invention is to provide a construction method for secondary lining in shield tunnels, which solves the technical problems of low efficiency, poor equipment adaptability, long curing period, unreasonable construction procedures, difficult construction in confined spaces, and difficulty in ensuring the quality of the finished product in existing shield tunnel secondary lining cast-in-place construction.
[0006] A construction method for secondary lining inside a shield tunnel includes:
[0007] (a) The supporting facilities for shield tunneling construction are removed from the tunnel wall, and the ventilation ducts are rearranged to create a first installation space above the tunnel wall. The bottom of the shield tunnel has a precast bottom block, on which a transport track is installed.
[0008] (b) A first liner precast block is transported from the outside to the inside via the transport track and installed in the first installation space. The two ends of the first liner precast block abut against the bottom precast block along its radial cross-section.
[0009] (c) The second liner prefabricated block is conveyed inward via the transport track, and the transport track is disassembled segment by segment from the inside out to form a second installation space on the bottom prefabricated block. The second liner prefabricated block is then installed in the second installation space, and a prefabricated pressure block is placed above the second liner prefabricated block. The second liner prefabricated block and the first liner prefabricated block are joined together to form a radially complete liner layer.
[0010] (d) Grout is delivered via the precast blocks and injected into the grouting space between the tunnel wall and the inner lining.
[0011] In some embodiments, the rearranged ventilation duct is positioned at a distance greater than the thickness of the first lining precast block from the tunnel wall, and is located on the side of the first lining precast block away from the tunnel wall.
[0012] In some embodiments, the first liner prefabricated block and the second liner prefabricated block are installed by chemical bonding, flange connection or hot melt process.
[0013] In some embodiments, the second liner prefabricated block is installed on the bottom prefabricated block by a chemical bonding process.
[0014] In some embodiments, the installation of the second lining precast block further includes the installation of a dosing pipe, which is in communication with the grouting space.
[0015] In some embodiments, the lengths of the first and second precast lining blocks are determined according to the turning radius of the shield tunnel, and are 6 to 10 meters.
[0016] In some embodiments, in step (d), ventilation is continuously provided to the work surface through the ventilation duct.
[0017] In some embodiments, grouting is performed in stages in the grouting space between the tunnel wall and the inner lining.
[0018] In some embodiments, each grouting section is 90-110m long, and each section is grouted in three layers.
[0019] In some embodiments, during the grouting process, the inner lining is limited by the central bolt holes of the pipe segment and fixed by a cross brace inside.
[0020] The aforementioned construction method for secondary lining in shield tunnels employs a zoned spatial arrangement, prefabricated blocks assembled from the outside in and from top to bottom, combined with a construction mode that uses a track-based disassembly and assembly process. This completely eliminates the need for traditional cast-in-place trolley construction techniques, eliminating the need for large formwork trolleys. It effectively adapts to the confined construction space of small-diameter, small-radius-of-curvature shield tunnels, solving the problems of difficult access and limited turning for traditional equipment. This invention, through preliminary facility clearing and ventilation rearrangement, stably reserves the upper first installation space, allowing for priority installation of the upper inner lining prefabricated blocks. Then, by dismantling the transport tracks segment by segment to form the lower second installation space, it achieves full-section segmented prefabricated secondary lining assembly. The process is tightly integrated, with high space utilization, significantly shortening the construction cycle and eliminating the need for prolonged concrete curing. Meanwhile, the precast blocks form a complete inner lining with good integrity and high forming precision, which can quickly form a closed protective structure on the inner wall of the tunnel. Combined with subsequent grouting and filling, it can achieve a tight bond between the primary lining and the secondary lining, effectively improving the tunnel structure's resistance to corrosion and water pressure, and meeting the quality requirements for the ultra-long service life of nuclear power tunnels. Attached Figure Description
[0021] To more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the drawings used in the description of the embodiments or the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on the structures shown in these drawings without creative effort.
[0022] Figure 1 This is a schematic diagram of the shield tunnel before the removal of supporting facilities according to one embodiment of this application.
[0023] Figure 2 This is a schematic diagram of a shield tunnel after the removal of its supporting facilities, according to one embodiment of this application.
[0024] Figure 3 This is a schematic diagram of the installation of the first precast inner lining block in a shield tunnel according to one embodiment of this application.
[0025] Figure 4 This is a schematic diagram of the installation of a second prefabricated inner lining block in a shield tunnel according to one embodiment of this application.
[0026] Figure 5 This is a schematic diagram of shield tunnel grouting according to one embodiment of this application.
[0027] The realization of the objective, functional characteristics and advantages of the present invention will be further explained in conjunction with the embodiments and with reference to the accompanying drawings.
[0028] 100. First inner lining precast block; 200. First inner lining precast block; 300. Ventilation duct; 400. Bottom precast block; 500. Precast compacted block; 600. Grouting space; 700. Star-shaped support; 800. Supporting ancillary facilities;
[0029] 410. Transport track; 510. Dosing tube. Detailed Implementation
[0030] The technical solutions of the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present invention, and not all of them. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0031] It should be noted that all directional indicators (such as up, down, etc.) in the embodiments of the present invention are only used to explain the relative positional relationship and movement of each component in a certain specific posture (as shown in the figure). If the specific posture changes, the directional indicator will also change accordingly.
[0032] Furthermore, in this invention, descriptions involving "first," "second," etc., are for descriptive purposes only and should not be construed as indicating or implying their relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined with "first" or "second" may explicitly or implicitly include at least one of that feature.
[0033] Furthermore, the technical solutions of the various embodiments of the present invention can be combined with each other, but only if they are based on the ability of those skilled in the art to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be considered that such combination of technical solutions does not exist and is not within the scope of protection claimed by the present invention.
[0034] The embodiments of this application provide a construction method for secondary lining in a shield tunnel, including:
[0035] Reference Figure 1 and Figure 2 (a) The supporting facilities 800 for shield tunneling are removed from the tunnel wall, and the ventilation ducts 300 are rearranged to create a first installation space above the tunnel wall. The bottom of the shield tunnel has a bottom precast block 400, on which a transport track 410 is provided.
[0036] In this embodiment, the overall construction process can be divided into four major stages: preliminary space preparation, upper precast block assembly, lower space expansion and closure assembly, and gap grouting and consolidation. Each stage is connected sequentially and does not interfere with each other, which is suitable for the narrow and enclosed working environment of the tunnel.
[0037] Step (a) involves the preliminary space preparation stage, which mainly involves clearing temporary facilities inside the tunnel and optimizing the layout of the ventilation system. This is achieved by removing the remaining shield tunneling auxiliary facilities 800 from the tunnel walls, thus eliminating installation obstructions and construction obstacles.
[0038] For example, during tunneling, the branch tunnels and relay pumps at the standard cross-section are removed, ventilation pipes are rearranged on the sides, and the original ventilation pipes, lighting, and pipelines are dismantled to restore a one-way lane. The trolley is then removed from the tunnel in sections.
[0039] Simultaneously, the existing ventilation ducts 300 were relocated, reorganized, and rearranged to free up space in the upper part of the tunnel, creating a stable first installation space that can be used for the installation of the upper lining. The precast blocks 400 at the bottom of the tunnel are the permanent bottom structure of the tunnel, and the transport rails 410 laid on them serve as the only channel for the transfer of precast blocks within the tunnel, enabling the deep transport of large precast components and solving the problem of difficult component transfer in narrow tunnels.
[0040] Reference Figure 3 (b) The first liner prefabricated block 100 is transported from the outside to the inside via the transport track 410 and installed in the first installation space. The two ends of the first liner prefabricated block 100 abut against the bottom prefabricated block 400 along its radial cross section.
[0041] Step (b) is the upper precast block assembly stage. Using the transport rail 410 on the bottom precast block 400, the first inner lining precast block 100 is transported from the tunnel entrance to the tunnel depth, and positioned and installed using the pre-designated first installation space. Specifically, using the existing rail on the bottom precast block 400, a transport vehicle transports the first inner lining precast block 100 from the starting shaft to the tunnel end, where it is assembled section by section. In this step, the ventilation duct 300 can be installed on temporary supports.
[0042] The first inner lining precast block 100 has an Ω-shaped cross-section and can also be called an Ω-shaped inner lining. After installation, the first inner lining precast block 100 abuts against the bottom precast block 400 at both radial ends, forming a stable upper support structure. It is firmly positioned and not easily shifted, providing an upper reference structure for subsequent overall assembly.
[0043] Reference Figure 4(c) The second liner prefabricated block 200 is conveyed inward via the transport track 410, and the transport track 410 is disassembled segment by segment from the inside out to form a second installation space on the bottom prefabricated block 400. The second liner prefabricated block 200 is then installed in the second installation space, and a prefabricated pressure block 500 is placed above the second liner prefabricated block 200. The second liner prefabricated block 200 and the first liner prefabricated block 100 are joined together to form a radially complete liner layer.
[0044] Step (c) is the lower assembly stage. First, the second inner lining precast block 200 is transported longitudinally via transport track 410. Then, the track is disassembled segment by segment from the inside out, gradually expanding the bottom working area as construction progresses to form a second installation space suitable for the installation of the second inner lining precast block 200. The cross-sectional shape of the second inner lining precast block 200 is "I" shaped, which can also be called "I" shaped facing.
[0045] This segmented dismantling and forming method effectively solves the problem of insufficient working space in narrow tunnels, ensuring that component transportation and installation are carried out simultaneously. After the second inner lining precast block 200 is installed, it is precisely joined with the upper first inner lining precast block 100 to form a complete inner lining layer. At the same time, precast pressing blocks 500 are arranged above the second inner lining precast block 200, which not only realizes the compaction and positioning of the components, but also reserves grouting channels, providing a structural foundation for subsequent grouting operations.
[0046] In this step, the ventilation duct 300 may be installed on the first lining precast block 100.
[0047] Reference Figure 5 (d) Grout is delivered via the precast block 500 and grouting is performed in the grouting space 600 between the tunnel wall and the inner lining.
[0048] Step (d) is the grouting consolidation stage. Using the grouting channel reserved in the precast block 500, grout is injected into the annular grouting space 600 between the tunnel wall and the inner lining to fill the gap between the primary and secondary linings, eliminate voids and gaps, and make the inner lining tightly bonded to the original tunnel structure to form an integral load-bearing structure, thereby improving the overall sealing, impermeability and corrosion resistance of the tunnel.
[0049] In some embodiments, the rearranged ventilation duct 300 is at a distance greater than the thickness of the first lining prefabricated block 100 from the cavity wall, and is located on the side of the first lining prefabricated block 100 away from the cavity wall.
[0050] In this embodiment, the ventilation duct 300 arrangement structure can be divided into two parts: a space avoidance structure and an operational ventilation structure. Through position optimization, the dual functions of installation avoidance and safe ventilation are achieved.
[0051] After the ventilation duct 300 is rearranged, it is completely away from the tunnel wall, and the clear distance is greater than the structural thickness of the first precast lining block 100. This allows the ventilation duct 300 to be completely placed inside the lining structure, thus completely avoiding spatial interference between the ventilation duct 300 and the first precast lining block 100. This ensures that the precast lining block is installed in place and the structure fits tightly, eliminating the need for secondary relocation of pipelines later. At the same time, the pipeline's inner-side arrangement can continuously provide fresh air to the working face in depth, improving the construction environment for the assembly and grouting operations of the enclosed tunnel and ensuring construction safety.
[0052] In some embodiments, the first liner prefabricated block 100 and the second liner prefabricated block 200 are installed by chemical bonding, flange connection or hot-melt process.
[0053] In this embodiment, the precast block connection system can flexibly select three connection processes according to the tunnel corrosion level and structural stress requirements to adapt to the sealing and consolidation requirements of different working conditions.
[0054] Among them, chemical bonding technology is convenient to construct and has good sealing performance, effectively sealing gaps between components and adapting to highly corrosive water environments; flange connection technology has high positioning accuracy, high structural rigidity, and is convenient for disassembly, assembly, and maintenance, making it suitable for sections with high requirements for structural integrity; hot-melt technology has good integrated molding effect, seamless splicing, and excellent impermeability, which can further improve the overall airtightness of the lining. Multiple connection methods can be used individually or in combination, greatly improving construction adaptability and structural reliability.
[0055] In some embodiments, the second liner prefabricated block 200 is installed on the bottom prefabricated block 400 by a chemical bonding process.
[0056] In this embodiment, the second inner lining precast block 200 serves as the bottom closing component and is connected to the bottom precast block 400 using a chemical bonding process. This ensures complete filling of gaps and tight bonding, effectively preventing problems such as water seepage, dampness, and media corrosion at the bottom joint. The chemical bonding layer forms a continuous anti-corrosion and sealing structure, suitable for the highly corrosive service environment of submarine and riverbed nuclear power tunnels. Furthermore, it allows for rapid construction and eliminates the need for cumbersome bolt tightening, effectively improving assembly efficiency.
[0057] In some embodiments, the first liner prefabricated block 100 and the second liner prefabricated block 200 are prefabricated in a factory and processed in a standardized manner. The materials include, but are not limited to, fiberglass pipes, HDPE and other polymer materials.
[0058] Reference Figure 4 In some embodiments, when installing the second lining precast block 200, a dosing pipe is also installed inside the precast block 500, and the dosing pipe is connected to the grouting space 600.
[0059] In this embodiment, the dosing pipe can be divided into two parts: a chemical delivery channel and an auxiliary grouting channel, serving as an auxiliary functional pipeline for the grouting space 600.
[0060] The dosing pipe is connected to the grouting space 600 on the outside of the inner lining throughout the entire process. During construction, anti-corrosion agents, consolidation aids and other functional media can be delivered to the grouting space 600 through the dosing pipe as needed to improve the consolidation strength and corrosion resistance of the grout. At the same time, it can assist in venting and grouting, avoid air accumulation and voids in the grouting space 600, ensure the density of gap filling, and further improve the quality of the secondary lining.
[0061] In some embodiments, the precast blocks 500 are prefabricated in a factory and processed in a standardized manner. They are installed simultaneously during the shield tunnel segment assembly process and are combined with the permanent structure. While ensuring the efficiency of shield tunneling and transportation, this also provides a transportation channel for the subsequent installation of components such as the dismantling of tunnel sections, Ω-shaped inner lining pipes, "I"-shaped facing pipes, chemical dosing pipes, and precast blocks 500.
[0062] In some embodiments, the lengths of the first precast lining block 100 and the second precast lining block 200 are determined according to the turning radius of the shield tunnel, and are 6 to 10 meters in length.
[0063] In this embodiment, the length of the precast block adopts a modular segmented design that adapts to the tunnel alignment, which can meet the construction needs of straight tunnels and small radius of curvature curve tunnels.
[0064] By controlling the length of precast blocks to the range of 6 to 10 meters, it is possible to ensure that the size of a single component is moderate, which is suitable for the narrow tunnel track transportation and hoisting assembly space. At the same time, the short modules can be adapted to the curve of the tunnel, effectively reducing the problems of misalignment and poor fit during assembly on curves, and ensuring that the overall lining has a smooth line and regular structure.
[0065] In some embodiments, in step (d), ventilation is continuously provided to the work surface through the ventilation duct 300.
[0066] In this embodiment, the continuous ventilation system enables air replacement and moisture removal at the work surface, effectively improving the enclosed environment of the grouting operation. Continuous ventilation can quickly remove water vapor, harmful gases, and dust generated during the grouting operation, ensuring the safety of workers. At the same time, it can moderately regulate the temperature and humidity of the work surface, which is conducive to the stable solidification and formation of the grout, avoiding quality defects such as poor grout consolidation and low strength caused by a humid and enclosed environment.
[0067] In some embodiments, grouting is performed in stages in the grouting space 600 between the tunnel wall and the inner lining.
[0068] In this embodiment, the segmented and layered grouting process can be divided into longitudinal segmented grouting and radial upper and lower layer grouting to achieve a uniform, full, and void-free grouting process. For example, wheeled grout transport vehicles can be grouped together and travel on the precast blocks 500 to perform the filling and grouting operation.
[0069] Compared to single-stage grouting, segmented and layered grouting can effectively avoid problems such as uneven grout settlement, local voids, and lining displacement and deformation caused by excessive pressure. It can precisely control the grouting pressure and volume, ensuring that each segment and each layer of grout is densely filled, and improving the overall bonding between the primary and secondary linings.
[0070] In some embodiments, refer to Figure 5 Each grouting section is 90-110m long, and each section is grouted in three layers.
[0071] In this embodiment, a segmented, three-layer gradient grouting mode with a 100-meter scale is adopted to meet the needs of continuous grouting construction in long-distance tunnels.
[0072] By controlling the grouting section to 90-110m, standardized continuous construction can be achieved, avoiding problems such as grout loss and large consolidation differences caused by excessively long single construction distances. The three-layer gradient grouting from bottom to top and from inside to outside can gradually fill gaps and expel air, ensuring uniform and stable grout density and significantly improving the overall impermeability and corrosion resistance of the tunnel.
[0073] In some embodiments, refer to Figure 5 During the grouting process, the inner lining layer is limited by the bolt holes in the center of the pipe segment and fixed by a cross brace 700 inside.
[0074] In this embodiment, the inner lining fixing system can be divided into two parts: bolt hole point limiting and cross bracing 700 overall reinforcement, forming an inner and outer double fixing structure.
[0075] Using the existing central bolt holes of the pipe segments for precise positioning can constrain the radial displacement of the inner lining layer. The internal cross bracing can improve the overall structural rigidity, resist the external tension generated by the grouting pressure, effectively prevent the precast inner lining from floating, shifting, or deforming, and ensure the accurate forming line and structural stability of the secondary lining.
[0076] The above technical solutions of the present invention are merely preferred embodiments of the present invention and do not limit the patent scope of the present invention. All equivalent structural transformations made under the technical concept of the present invention using the contents of the present invention specification and drawings, or direct / indirect applications in other related technical fields, are included in the patent protection scope of the present invention.
Claims
1. A construction method for secondary lining inside a shield tunnel, characterized in that, include: (a) Remove the supporting facilities for shield tunneling construction from the tunnel wall and rearrange the ventilation ducts to form a first installation space above the tunnel wall; the bottom of the shield tunnel has a bottom precast block, and the bottom precast block is equipped with a transport track. (b) The first liner precast block is transported from the outside to the inside via the transport track and installed in the first installation space; the two ends of the first liner precast block abut against the bottom precast block along the radial section; (c) The second lining prefabricated block is transported inward via the transport track, and the transport track is disassembled segment by segment from the inside out to form a second installation space on the bottom prefabricated block. The second lining prefabricated block is then installed on the second installation space, and a prefabricated pressure block is set above the second lining prefabricated block. The second lining prefabricated block and the first lining prefabricated block are joined together to form a radially complete lining layer. (d) Grout is delivered via the precast blocks and injected into the grouting space between the tunnel wall and the inner lining.
2. The construction method according to claim 1, characterized in that, The rearranged ventilation duct is positioned at a distance greater than the thickness of the first precast lining block from the tunnel wall, and is located on the side of the first precast lining block away from the tunnel wall.
3. The construction method according to claim 1, characterized in that, The first and second prefabricated inner lining blocks are installed using chemical bonding, flange connection, or hot-melt processes.
4. The construction method according to claim 1, characterized in that, The second inner lining precast block is installed on the bottom precast block by chemical bonding, flange connection or hot melt process.
5. The construction method according to claim 1, characterized in that, When installing the second lining precast block, a dosing pipe is also installed inside the precast block, and the dosing pipe is connected to the grouting space.
6. The construction method according to claim 1, characterized in that, The lengths of the first and second precast lining blocks are determined according to the turning radius of the shield tunnel, and are 6 to 10 meters.
7. The construction method according to claim 1, characterized in that, In step (d), ventilation is continuously provided to the work surface through the ventilation duct.
8. The construction method according to any one of claims 1 to 7, characterized in that, The grouting is carried out in stages in the grouting space between the tunnel wall and the inner lining.
9. The construction method according to claim 7, characterized in that, Each grouting section is 90-110m long, and each section is grouted in three layers.
10. The construction method according to claim 7, characterized in that, During the grouting process, the inner lining layer is limited by the bolt holes in the center of the pipe segment and fixed by a cross brace inside.