A method for roof collapse and coordinated support treatment in water-rich fractured rock roadways
By employing a multi-process collaborative operation method, the support problem of roof collapse accidents in water-rich and fractured surrounding rock roadways was solved, thereby improving the stability and durability of the roadways and ensuring construction safety.
Patent Information
- Application Number
- CN202611526896.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-29
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies are insufficient to effectively handle roof collapse accidents in water-rich, fractured surrounding rock roadways. Conventional support methods are ill-suited to the geological characteristics of such roadways, posing risks of support structure instability, secondary roof collapse, and poor construction safety.
A multi-stage collaborative operation method was adopted, including advanced bracing and protection, cyclic erection of U-shaped steel arch frames, filling of timber slabs, anchoring and reinforcement, and double-layer sprayed and anchored mesh sealing, to form a safety protection shed, gradually reinforcing the roof collapse area, and achieving overall sealing through grouting and sprayed concrete filling.
It improves the stability and durability of roadway support structures, adapts to the geological characteristics of water-rich fractured surrounding rock, ensures safe and controllable construction, and is suitable for the treatment of fractured surrounding rock roadways in underground mines.
Smart Images

Figure FT_1 
Figure FT_2
Abstract
Description
Technical Field
[0001] This invention relates to the field of mine roadway construction technology, specifically to a method for coordinated support treatment of roof collapse in water-rich fractured surrounding rock roadways. Background Technology
[0002] Underground mine roadways are prone to deformation and cracking of the support structure due to mining activities and ground pressure. This is especially true when the surrounding rock is mixed rock with well-developed joints and expands upon contact with water due to seepage. In such cases, the rock's self-stabilizing ability is extremely poor, making roof falls highly likely. These types of roof fall zones are characterized by severe water seepage, rapid deformation of the surrounding rock, large fall areas, and high support difficulty. Conventional single-anchor shotcrete or steel arch support methods are difficult to adapt to these geological characteristics, easily leading to problems such as support structure instability and secondary roof falls. At the same time, traditional treatment methods lack the operational concept of advanced protection and cyclic advancement, resulting in high safety risks during construction and poor filling and reinforcement effects on the arch fall voids, making it difficult to guarantee the long-term stability of the roadway.
[0003] Currently, while existing technologies include support methods combining U-shaped steel arches with anchor spraying (such as CN207620819U), they lack specific water-guiding, filling, and grouting processes designed for the water-rich, fractured surrounding rock's characteristics of water seepage and water-induced expansion. Some advanced grouting support methods (such as CN103628894A) are suitable for fault fracture zones, but their complex procedures make them unsuitable for rapid roof collapse treatment in small to medium-sized tunnels. Therefore, there is an urgent need for a roof collapse treatment method for tunnels that is adapted to the geological characteristics of water-rich, fractured surrounding rock, offers controllable construction safety, and provides stable support effects. Summary of the Invention
[0004] The purpose of this invention is to overcome the shortcomings of the existing technology and provide a method for the coordinated support treatment of roof fall in water-rich fractured surrounding rock roadways. Through multi-process coordinated operation, it achieves advanced protection, gradual reinforcement and overall closure of the roof fall area of the roadway, effectively inhibits the expansion and deformation of water-rich surrounding rock when exposed to water, and improves the stability and durability of the roadway support structure.
[0005] To achieve its purpose, the present invention adopts the following technical solution: This invention provides a method for roof collapse and coordinated support treatment in water-rich, fractured rock roadways, comprising the following steps: (1) Pre-treatment of the roof fall area: On-site measurement of the roof fall area of the water-rich broken surrounding rock roadway to determine the fall range, clear the dangerous rocks around the roof fall area, and carry out water diversion treatment on the water-spraying parts; (2) Advance drill shed protection: The first U-shaped steel arch frame is erected at a position 0.8m-1m away from the roof fall area. The size of the U-shaped steel arch frame is determined according to the cross-sectional specifications of the roadway. The drill bit and drill rod are inserted into the fallen rubble at an angle of 15°-20° with the direction of roadway advance. The spacing between the drill rods is 150mm-200mm. At least 20 drill rods are constructed on the top of the arch frame to form an advance safety drill shed. (3) Cyclic erection of U-steel arch frames: 0.8m-1m away from the first U-steel arch frame, erect the second U-steel arch frame of the same specification and construct the same standard anchorage. After removing and clearing the rubble under the anchorage, reserve the position for the third U-steel arch frame. Erect and construct the anchorage at 0.8m intervals. Repeat the above operation to advance in a cyclical manner until the entire roof fall area is covered. Each U-steel arch frame is anchored to the rock wall cement roll along its entire length by a hook threaded steel anchor. (4) Filling the void in the arch and laying pipelines: If there is a void in the arch, first use shotcrete to seal the rock wall of the void. After solidification, dig out the beam socket and fill the void using the "stacked frame timber" method. The bottom support of the frame timber is made of round timber with a diameter of not less than φ200mm. The bottom support and frame timber are fastened to the rock wall with bracing timber. At least 4 PE conveying pipes are buried in the frame timber, and anchor rods made of seamless steel pipes are also buried. (5) Grouting reinforcement: Inject 32.5 grade pure cement grout into the roof collapse area through anchor bolts. The water-cement ratio of the grout is controlled at 0.65-0.8. If grout leakage occurs, sprayed concrete is used to seal the leakage point. (6) Filling the voids: Pour C25 shotcrete through the PE conveying pipe until the voids are completely filled; (7) Double-layer shotcrete and anchor mesh closed support: Double-layer shotcrete and anchor mesh support is carried out around the roadway in the roof fall area. Each layer is sprayed with 90mm-100mm of C25 concrete. The spacing between the anchor bolts is 1.0m and the cement roll is anchored along the entire length. The metal mesh is equipped with a pad plate. The overlap rate of the metal mesh joint is 100% and the welding is firm.
[0006] As a further preferred embodiment of the technical solution of the present invention, in step (2), a YT-28 pneumatic rock drill is used to insert the drill bit and drill rod into the fallen rubble.
[0007] Furthermore, in step (3), each U-shaped steel arch is anchored to the rock wall cement roll along its entire length by 6 sets of a total of 12 φ22mm×2250mm hooked threaded steel anchor rods.
[0008] Furthermore, in step (4), when spraying concrete to seal the rock wall, the workers stand on the surface of the fallen rubble to operate, and the construction of the frame timber is carried out after the concrete has fully solidified.
[0009] Furthermore, in step (4), the PE conveying pipe has a size of φ50mm×4.5m, the anchor bolt has a size of φ32mm×6mm×3.0m, and the burial spacing is 2.0m.
[0010] Furthermore, in step (5), the anchor rod and the advanced bracing form a cross protection structure. During grouting, the grouting is advanced from both sides of the roof fall area to the middle to avoid grouting blind spots.
[0011] Furthermore, in step (5), the grouting pressure is 4.5 MPa or the grouting volume per hole reaches 250 kg, and the grouting time is maintained for 5 minutes.
[0012] Furthermore, in step (7), after the first layer of the double-layer shotcrete and anchor mesh support has solidified, the second layer is constructed, and the two layers of anchor rods are arranged in a quincunx pattern.
[0013] Furthermore, in step (7), the anchor rod is made of φ22mm×2250mm threaded steel, the metal mesh is a 150mm×150mm mesh structure welded from φ6.5mm round steel, and the pad is a 200mm×200mm×10mm steel plate.
[0014] By adopting the above technical solution, the beneficial effects of the present invention are as follows: This invention employs a multi-stage collaborative operation involving advanced safety protection via a pre-construction shed, cyclical erection of U-shaped steel arch frames, compaction of timber frames, anchoring reinforcement, and double-layer sprayed and anchored mesh sealing. First, an advanced safety protection shed is formed. Then, fallen rubble is gradually cleared and U-shaped steel arch frames are erected. Empty areas in the arch are sealed and filled using a combination of timber frames and sprayed concrete. Simultaneously, pipelines are laid to achieve grouting and sprayed concrete filling. Finally, the overall support is completed using a double-layer sprayed and anchored mesh. This method is adapted to the geological characteristics of water-rich, fractured surrounding rock. The support structure combines rigidity and flexibility, effectively inhibiting the expansion and deformation of the surrounding rock upon contact with water, improving the overall stability of the roadway in the roof fall area, and ensuring safe and controllable construction. It is suitable for roof fall treatment in fractured surrounding rock roadways of various underground mines affected by mining and ground pressure. Attached Figure Description
[0015] Figure 1 A schematic diagram of the layout of the advanced bracing shed and U-shaped steel arch frame in the roof fall area; Figure 2 A schematic diagram showing the arch cavity and pipeline installation; Attached reference numerals: 1. Drill rod; 2. U-shaped steel arch; 3. Conveyor pipe; 4. Concrete layer; 5. Roof collapse zone. Detailed Implementation
[0016] Reference Figure 1-2 This embodiment addresses the treatment of roof collapse in underground mine roadways, where the surrounding rock is mixed rock with well-developed joints and fractured zones, resulting in severe water seepage, expansion upon contact with water, and rapid pressure build-up in the roadway. The collaborative support treatment method is as follows: 1. Pre-treatment of the roof fall zone Based on the actual measured area of the collapse, loose rocks around the collapse area were cleared, and water pipes were installed at the water-spraying locations to direct the seepage water to the roadway drainage system to prevent the seepage water from continuously soaking the surrounding rock.
[0017] 2. Advanced wire mesh protection The first U-shaped steel arch frame 2 was erected 1m away from the collapse zone. A YT-28 pneumatic rock drill was used to construct the drill shed. The drill rod 1 consisted of a φ38mm drill bit and a 3.0m long rod body, which was at a 15° angle to the direction of the roadway and spaced 200mm apart. 22 drill rods 1 were used to form a safety protection shed on the arch roof to prevent rubble from falling during construction.
[0018] 3. Circular erection of U-shaped steel arch frames The second and third U-shaped steel arch frames 2 were erected sequentially at 0.8m intervals, and each frame was constructed with the same standard anchorage. The rubble under the anchorage was manually removed and transported to the designated location using a shovel, leaving space for the subsequent arch frame erection. Each U-shaped steel arch frame 2 was anchored to the rock wall with 12 φ22mm×2250mm hook anchor rods along its full length using cement rolls. A total of 10 U-shaped steel arch frames 2 were erected to cover the entire roof fall area 5.
[0019] 4. Filling the void in the arch and laying pipelines The fifth arch section of the collapse zone contained irregular voids. First, C20 shotcrete was used to seal the voids in the rock wall. After curing and solidification, beam recesses were manually excavated from the rock wall. φ220mm round logs were used to make frame timber base supports. The voids were filled using the "stacked frame timber" method. The base supports were tightly wedged into the rock wall with bracing timber. Six φ50mm×4.5m PE conveying pipes were buried in the frame timbers, and eight φ32mm×6mm×3.0m anchor bolts were buried at 2.0m intervals to ensure that the pipelines and anchor bolts were evenly distributed without blind spots.
[0020] 5. Grouting reinforcement A grouting machine was used to inject 32.5 grade pure cement grout through anchor bolts with a water-cement ratio of 0.7. The grouting pressure was gradually increased to 4.5 MPa and maintained for 5 minutes before the grouting valve was closed. If grout leakage occurred at one point during construction, C20 shotcrete was used to seal the leakage point in time, and grouting was continued after solidification.
[0021] 6. Filling the voids caused by collapse Connect the shotcrete machine through the PE conveying pipe and pour C20 shotcrete into the collapsed void. Fill the void in layers from bottom to top until the concrete overflows from the top of the void, confirming that the void is completely filled.
[0022] 7. Double-layer shotcrete and anchor mesh closed support Double-layer shotcrete and anchor mesh support was constructed around the tunnel in the collapse zone: The first layer consisted of 150mm×150mm metal mesh welded from φ6.5mm round steel with 100% overlap and secure welding. φ22mm×2250mm anchor rods were installed at 1.0m intervals, with cement cartridges anchored along the entire length, and steel plate pads were used as accessories. 100mm of C25 concrete was then sprayed. After the concrete layer 4 had solidified, the second layer of anchor rods was arranged in a quincunx pattern. The above metal mesh laying and shotcrete operation were repeated to complete the double-layer support.
Claims
1. A method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway, characterized in that, Includes the following steps: (1) Pre-treatment of the roof fall area: On-site measurement of the roof fall area of the water-rich broken surrounding rock roadway to determine the fall range, clear the dangerous rocks around the roof fall area, and carry out water diversion treatment on the water-spraying parts; (2) Advance drill shed protection: The first U-shaped steel arch frame is erected at a position 0.8m-1m away from the roof fall area. The size of the U-shaped steel arch frame is determined according to the cross-sectional specifications of the roadway. The drill bit and drill rod are inserted into the fallen rubble at an angle of 15°-20° with the direction of roadway advance. The spacing between the drill rods is 150mm-200mm. At least 20 drill rods are constructed on the top of the arch frame to form an advance safety drill shed. (3) Cyclic erection of U-steel arch frames: 0.8m-1m away from the first U-steel arch frame, erect the second U-steel arch frame of the same specification and construct the same standard anchorage. After removing and clearing the rubble under the anchorage, reserve the position for the third U-steel arch frame. Erect and construct the anchorage at 0.8m intervals. Repeat the above operation to advance in a cyclical manner until the entire roof fall area is covered. Each U-steel arch frame is anchored to the rock wall cement roll along its entire length by a hook threaded steel anchor. (4) Filling the void in the arch and laying pipelines: If there is a void in the arch, first use shotcrete to seal the rock wall of the void. After solidification, dig out the beam socket and fill the void using the "stacked frame timber" method. The bottom support of the frame timber is made of round timber with a diameter of not less than φ200mm. The bottom support and frame timber are fastened to the rock wall with bracing timber. At least 4 PE conveying pipes are buried in the frame timber, and anchor rods made of seamless steel pipes are buried at the same time. (5) Grouting reinforcement: Inject 32.5 grade pure cement grout into the roof collapse area through anchor bolts. The water-cement ratio of the grout is controlled at 0.65-0.
8. If grout leakage occurs, sprayed concrete is used to seal the leakage point. (6) Filling the voids: Pour C25 shotcrete through the PE conveying pipe until the voids are completely filled; (7) Double-layer shotcrete and anchor mesh closed support: Double-layer shotcrete and anchor mesh support is carried out around the roadway in the roof fall area. Each layer is sprayed with 90mm-100mm of C25 concrete. The spacing between the anchor bolts is 1.0m and the cement roll is anchored along the entire length. The metal mesh is equipped with a pad plate. The overlap rate of the metal mesh joint is 100% and the welding is firm.
2. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 1, characterized in that, In step (2), a YT-28 pneumatic rock drill is used to insert the drill bit and drill rod into the fallen rubble.
3. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 1, characterized in that, In step (3), each U-shaped steel arch frame is anchored to the rock wall cement roll along its entire length by 6 sets of 12 φ22mm×2250mm hooked threaded steel anchor rods.
4. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 1, characterized in that, In step (4), when spraying concrete to seal the rock wall, the workers stand on the surface of the fallen rubble to operate, and the construction of the wooden frame is carried out after the concrete has fully solidified.
5. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 4, characterized in that, In step (4), the PE conveying pipe has a size of φ50mm×4.5m, the anchor bolt has a size of φ32mm×6mm×3.0m, and the burial spacing is 2.0m.
6. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 1, characterized in that, In step (5), the anchor rod and the advanced bracing form a cross protection structure. During grouting, the grouting is advanced from both sides of the roof fall area to the middle to avoid grouting blind spots.
7. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 6, characterized in that, In step (5), the grouting pressure is 4.5 MPa or the grouting volume per hole reaches 250 kg, and the grouting time is maintained for 5 minutes.
8. The method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 1, characterized in that, In step (7), after the first layer of the double-layer shotcrete and anchor mesh support is solidified, the second layer is constructed, and the two layers of anchor rods are arranged in a quincunx pattern.
9. A method for roof collapse and coordinated support treatment in a water-rich, fractured rock roadway according to claim 8, characterized in that, In step (7), the anchor rod is made of φ22mm×2250mm threaded steel, the metal mesh is a 150mm×150mm mesh structure welded from φ6.5mm round steel, and the pad is a 200mm×200mm×10mm steel plate.
Citation Information
Patent Citations
Water-rich fault fracture zone collapsed roadway repairing method based on angle-variable umbrella-shaped advancing grouting
CN103628894A
Tunnel U shaped steel cover canopy supporting construction
CN207620819U