Control methods for stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden
By arranging working faces and section coal pillars in the coal seam, and using directional top-cutting drilling and grouting filling technology to control the slurry flow range, the problems of increased mine pressure and resource waste during coal seam mining were solved. This achieved efficient grouting filling of mining-induced overburden fracture zones and caving zones, reducing construction costs and time.
Patent Information
- Application Number
- CN202611496256.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-09-24
- Publication Date
- 2026-11-17
AI Technical Summary
Existing technologies, when the coal seam thickness exceeds the limit of full height mining in a single operation, cause severe fracturing of the overlying strata, increase the mine pressure in adjacent working faces, and are prone to rock bursts. Furthermore, leaving section coal pillars results in resource waste, and controlling the flow range of grout during goaf filling is difficult, increasing construction costs and time.
By arranging working faces and section coal pillars in the coal seam, and using directional top-cutting boreholes to form rotating rock blocks, the amount of coal released is controlled. Combined with cemented and non-cemented grouting filling slurry, a partition wall filling body is constructed to control the slurry flow range and share the stress of the overlying strata.
It effectively reduces the width of coal pillars in sections, lowers mine pressure, reduces construction costs and time, improves grouting and filling efficiency, provides support for overlying rock strata, prevents rock bursts, and saves resources.
Smart Images

Figure CN123109773A_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of coal mine goaf filling, specifically involving a method for controlling stress migration induced by grouting filling in the fracture zone and caving zone of the overlying rock during mining. Background Technology
[0002] When the coal seam thickness exceeds the limit that can be mined using full-capacity mining technology, top-coal caving mining is generally employed. Top-coal caving mining involves mining a large total coal seam thickness in a single operation, resulting in intense fracturing of the overlying strata and significant impact on surface structures. To address this, existing technologies propose leaving wide-section coal pillars between adjacent working faces to reduce the degree of full mining in the width direction of each working face, thereby mitigating the intensity of overlying strata fracturing after mining and protecting surface structures. However, when a mined working face is in a state of incomplete mining, its goaf cannot provide sufficient support for the fracturing overlying strata. A significant portion of the gravity of the fracturing overlying strata on the mined working face will transfer to adjacent working faces and coal pillars, increasing stress on adjacent working faces, increasing mine pressure during mining, and increasing the risk of rockbursts. Furthermore, for thick coal seams, leaving wide-section coal pillars also results in a huge waste of resources.
[0003] Goaf grouting and backfilling technology involves filling the fractured and caving zones of the working face after mining. Grouting and backfilling the goaf can increase its support to the overlying fractured strata, reduce or eliminate stress transferred to adjacent working faces and coal pillars, thereby reducing the width of the coal pillar and lowering the mining pressure during adjacent working face mining. It can also absorb gangue. However, controlling the grout flow range during goaf grouting and backfilling is difficult. Reducing or eliminating stress transferred to adjacent working faces and coal pillars only requires grouting and backfilling in the goaf area near the coal pillar. Grouting and backfilling the entire goaf would increase backfilling costs, lengthen the construction period, and hinder the rapid commissioning of adjacent working faces. Therefore, how to control the grout flow range during goaf grouting and backfilling to more accurately grout and backfill the goaf, thereby reducing construction costs and shortening the construction period, has become a problem that needs to be solved in this field. Summary of the Invention
[0004] To address the shortcomings of the existing technologies, this invention proposes a method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of the overburden, comprising the following steps: S1: Arranging a first working face and a second working face in the coal seam, leaving a section coal pillar between the first working face and the second working face; S2: Cutting off the basic roof of the first working face through directional top-cutting boreholes to form a rotating rock block, the rotating rock block being able to abut one end against the caving boundary and the other end against the caving zone; using top-coal caving mining technology to mine the first working face; during coal release, in the area located below the rotating rock block and away from... S3: As the first working face advances, cemented grouting is used to fill the dense caving zone behind it to form a partition wall filling body; S4: After the first working face is completed, the first filling borehole is drilled from the ground to the caving zone between the partition wall filling body and the section coal pillar, and the second filling borehole is drilled from the ground to the fracture zone; gangue powder grouting is injected into the caving zone through the first filling borehole, and gangue powder grouting is injected into the fracture zone through the second filling borehole.
[0005] Preferably, in step S1, the width of the coal pillar section is 10-15m.
[0006] Preferably, in step S1, a mining roadway is constructed on the side of the section coal pillar within the first working face; several drilling sites are constructed at intervals along the working face advancement direction from the mining roadway within the first working face, and two directional roof-cutting boreholes are constructed from the drilling sites toward the cutting direction, with the horizontal section of the directional roof-cutting borehole located within the basic roof.
[0007] Preferably, in step S2, the rotating rock block is the rock block closest to the collapse boundary formed by the basic top fracture, and the rock blocks adjacent to the rotating rock block fall on the collapse zone in a basically horizontal manner.
[0008] Preferably, in step S2, the area with no or minimal coal release is 3-5m wide and entirely located under the rotating rock block; the remaining areas in the width direction of the first working face are all normally coal-released to form a normal caving zone.
[0009] Preferably, in step S3, a backfill pipe is installed on the hydraulic support for top coal caving directly opposite the dense caving zone, and the backfill pipe is connected to the underground filling pipeline. Grouting is then performed on the dense caving zone through the backfill pipe.
[0010] Preferably, in step S3, the grout used for grouting and filling the dense collapse zone is a cementitious grouting and filling grouting ...
[0011] Preferably, in step S4, a number of first filling boreholes are constructed at intervals along the working face advancing direction, and the first filling boreholes are constructed entirely outside the collapse boundary.
[0012] Preferably, in step S4, a number of second filling boreholes are constructed at intervals along the working face advancing direction. The second filling boreholes are constructed entirely within the collapse boundary and located directly above the rotating rock block.
[0013] Preferably, in step S4, the gangue powder grouting filling slurry is a non-cemented grouting filling slurry made by mixing gangue powder ground into powder with water.
[0014] The key technical means and beneficial effects of this invention are as follows: This invention uses directional top-cutting drilling to perform controlled-width fracturing and top-cutting of the basic roof, ensuring that the cut-off rotating rock block abuts at both ends of the caving boundary and the caving zone. This creates a grouting and filling space of a certain width under the rotating rock block, the width of which can be determined based on the required support force or the stress of adjacent working faces to be controlled. Furthermore, by controlling the coal release volume through a top-coal caving hydraulic support, a dense caving zone is formed on one side of the rotating rock block. The backfilling pipe on the top-coal caving hydraulic support is used to cement and grout the dense caving zone, forming a partition wall filling body. This creates a basically closed caving grouting space between the partition wall filling body and the section coal pillar, allowing water to pass through but not gangue powder. After the working face is mined, when injecting gangue powder grouting into this space, the grout flow range can be controlled, improving the grouting density and efficiency, and reducing grouting costs and construction time. Furthermore, gangue powder grout is injected into the delamination zone within the fracture zone directly above the rotating rock block to further enhance the support capacity for the overlying strata. This invention can provide excellent support for the overlying strata, share the stress of the coal pillar section and adjacent working faces, thereby reducing the width of the coal pillar section and regulating the stress of adjacent working faces. Attached Figure Description
[0015] Figure 1 This is a schematic cross-sectional view of the working face layout and top-cutting drilling construction of the present invention.
[0016] Figure 2 This is a schematic diagram of the working face layout and top-cutting drilling construction plan of the present invention.
[0017] Figure 3 This is a schematic diagram of the strata dip profile after the first working face of the present invention has been mined.
[0018] Figure 4 This is a schematic diagram of the plan view of the partition wall filling body constructed on the first working surface of the present invention.
[0019] Figure 5 This is a schematic cross-sectional view of the grouting and filling tendency of the fracture zone and collapse zone in the first working face of the present invention.
[0020] Figure 6 This is a schematic diagram of the grouting and filling plan of the first working face collapse zone of the present invention.
[0021] In the diagram: 1-Coal seam; 11-Mining roadway; 12-First working face; 13-Second working face; 14-Section coal pillar; 15-Drilling site; 2-Weak rock strata; 31-First key stratum; 32-Second key stratum; 33-Third key stratum; 41-Dense caving zone; 42-Rotating rock block; 43-Caving boundary; 44-Caving zone; 51-Inclined section; 52-Horizontal section; 61-Backfilling pipe; 62-Partition wall filling body; 63-First filling borehole; 64-Gange filling body; 65-Second filling borehole; 7-Top coal caving hydraulic support. Detailed Implementation
[0022] The specific embodiments of the present invention will now be described in conjunction with the accompanying drawings.
[0023] The No. 3-5 coal seam of the Tongxin Coal Mine of Jineng Holding Group is buried at a depth of approximately 500m with an average dip angle of 3°. Top-coal caving mining technology is used for mining. The designed working face width is 200m, and the original design section coal pillar width is 38m. By controlling the working face width to be in a state of insufficient mining, the intensity of the overlying strata fracturing after mining is reduced, thus protecting the surface power transmission towers. However, when the mined working face is in a state of insufficient mining, its goaf cannot provide sufficient support for the overlying fracturing strata. A large portion of the gravity of the overlying fracturing strata on the mined working face will be transferred to adjacent working faces and section coal pillars, causing increased stress in adjacent working faces, increased mine pressure during mining, and a higher risk of rockbursts. Furthermore, the recovery rate of the 38m wide section coal pillar is only 84%, resulting in a huge waste of resources. To address this, this invention proposes a method for controlling stress migration induced by grouting and filling in the mining-induced overlying strata fracture zone and caving zone, such as... Figures 1-6 As shown, the steps include the following.
[0024] S1: As Figure 1 and Figure 2As shown, working faces are arranged in coal seam 1, including a first working face 12 and a second working face 13. A section coal pillar 14 is left between the first working face 12 and the second working face 13, and the width of the section coal pillar 14 is 10-15m. A mining runway 11 is constructed in the first working face 12 near the section coal pillar 14, and a mining runway 11 is constructed in the second working face 13 near the section coal pillar 14. The first working face 12 is mined first, and then the second working face 13 is mined. In the first working face 12, several drilling sites 15 are constructed at intervals along the working face advancement direction (in this embodiment, the working face advances along the strike) from the mining runway 11. The spacing of the drilling sites 15 along the working face advancement direction is 400-800m. Directional roof cutting boreholes are constructed from drilling site 15 toward the cutting direction; the directional roof cutting boreholes include two, of which the one closer to the section coal pillar 14 is the first directional roof cutting borehole, and the one relatively farther away from the section coal pillar 14 is the second directional roof cutting borehole; each directional roof cutting borehole includes a sloping section 51 and a horizontal section 52, the horizontal section 52 being located within the first key layer 31, the first key layer 31 being the basic roof.
[0025] S2: As Figure 3 and Figure 4 As shown, the first key layer 31 is hydraulically fracturing and cut through the horizontal section 52 of the directional top-cutting borehole, causing the rock blocks cut off by the two horizontal sections 52 of the directional top-cutting borehole to form rotating rock blocks 42. The rotating rock blocks 42 are the rock blocks closest to the collapse boundary 43 formed by the fracture of the first key layer 31. The rotating rock blocks 42 can abut one end on the collapse boundary 43 and the other end on the collapse zone 44 formed after the first working face 12 is mined. The rock blocks adjacent to the rotating rock blocks 42 fall on the collapse zone 44 in a basically horizontal manner. The length of the rotating rock blocks 42 can be controlled by constructing directional top-cutting boreholes, which is conducive to controlling the filling range of the collapse zone 44 after the first working face 12 is mined, and to controlling one end of the rotating rock blocks 42 abutting the collapse boundary 43 formed after the first working face 12 is mined and the other end abutting the collapse zone 44.
[0026] The first working face 12 is mined using top coal caving mining technology. As the first working face 12 advances, the rock strata above the coal seam 1, including the first key layer 31, the second key layer 32, the third key layer 33, the weak rock strata 2 between the three key layers, and the weak rock strata 2 between the first key layer 31 and the coal seam 1, collapse and break. Among them, the collapse and breakage of the first key layer 31 and the weak rock strata 2 between it and the coal seam 1 forms a collapse zone 44; the collapse of the rock strata between the third key layer 33 and the first key layer 31 forms a fracture zone; the third key layer 33 and its overlying rock strata form a curved subsidence zone (not shown in the figure).
[0027] When coal is released via the top coal caving hydraulic support 7, no coal or only a small amount of coal is released on the side located below the rotating rock block 42 and away from the caving boundary 43. The area where no coal is released or only a small amount of coal is released is 3-5m wide and is entirely located below the rotating rock block 42. The rest of the entire first working face 12 is released normally in all directions (in this embodiment, it refers to the dip direction) to form a normal caving zone 44. Because no coal is released or only a small amount of coal is released, the amount of caving coal and rock blocks in the area is large, the density of coal and rock blocks is high, and the voids are small, forming a dense caving zone 41. Because the width of the dense caving zone 41 is small, it will not significantly hinder the movement of the rotating rock block 42 and the fractured rock layer above it. Furthermore, the dense caving zone 41 can provide good support for the rotating rock block 42, which is conducive to the rotating rock block 42 engaging with the caving boundary 43. This reduces the compression of the caving zone 44 between the dense caving zone 41 and the section coal pillar 14 by the rotating rock block 42, resulting in a large void in this part of the caving zone 44, which is conducive to grouting and filling using gangue powder grout.
[0028] S3: As Figure 4 As shown, a backfill pipe 61 is installed on the hydraulic support 7 for top coal caving, which is directly opposite the dense caving zone 41, and the backfill pipe 61 is connected to the underground filling pipeline. As the first working face 12 advances, grouting is continuously performed on the dense caving zone 41 behind it to form a partition wall filling body 62. The grouting slurry used for grouting the dense caving zone 41 is a cementitious grouting slurry made of cement, gangue powder of different particle size gradations and water. Because the coal and rock blocks in the dense caving zone 41 are highly concentrated and have small voids, it has the following advantages: First, it requires less grouting material, is low in cost, and is quick to construct, with minimal impact on the mining of the first working face 12; Second, it uses cemented grouting material with poor fluidity, and the cemented grouting material can solidify after a certain period of time, so the flow range of the cemented grouting material can be basically controlled within the dense caving zone 41, further reducing the loss of cemented grouting material; Third, the partition wall filling body 62 formed by the cemented grouting material and the dense caving zone 41 has greater strength and will not collapse when exposed to water, which is beneficial for subsequent filling of the caving zone 44 with non-cemented gangue powder grouting material.
[0029] S4: As Figure 5 and Figure 6As shown, after the first working face 12 is completed according to the above steps, a partition wall filling body 62 will be formed in the caving zone 44 of the first working face 12 along the working face advancement direction; a number of first filling boreholes 63 are constructed from the ground to the caving zone 44, and the number of first filling boreholes 63 are constructed at intervals along the working face advancement direction. The first filling boreholes 63 are located between the partition wall filling body 62 and the section coal pillar 14, and are completely constructed outside the caving boundary 43 (coal wall support area); a number of second filling boreholes 65 are constructed from the ground to the fracture zone, and the number of second filling boreholes 65 are constructed at intervals along the working face advancement direction. The second filling boreholes 65 are completely constructed inside the caving boundary 43 and are located directly above the rotating rock block 42.
[0030] Gangue powder grouting material is injected into the collapse zone 44 through the first filling borehole 63. This gangue powder grouting material is a non-cemented grouting material made by mixing gangue powder (ground into powder) with water. The gangue powder grouting material has a large diffusion range, which facilitates flow in the large-void collapse zone 44, thereby reducing the amount of work required in the first filling borehole 63. Due to the presence of the partition wall filling body 62, it will hinder the flow of gangue. The gangue powder in the grout flows through the partition wall filling body 62 and remains in the caving zone 44 between the partition wall filling body 62 and the section coal pillar 14. However, the partition wall filling body 62 is not absolutely sealed; water can flow through it to the caving zone 44 on the other side, thus facilitating the compaction of the caving zone 44 between the partition wall filling body 62 and the section coal pillar 14 into a gangue filling body 64. The gangue filling body 64 and the partition wall filling body 62 can provide good support for the overlying strata, share the stress of the section coal pillar 14 and the subsequent second working face 13, thereby reducing the width of the section coal pillar 14 and regulating the stress of the subsequent second working face 13.
[0031] Simultaneously, gangue powder grouting material is injected into the fracture zone through the second filling borehole 65. This gangue powder grouting material is a non-cemented grouting material made by mixing gangue powder (ground into powder) with water. Overall, the injectable space in the fracture zone is much smaller than that in the collapse zone 44. The rock strata in the fracture zone generally collapse in the form of large, regular cuboids, with very small gaps between the rock blocks. Only a small amount of delamination exists directly above the rotating rock block 42, meaning the injectable space is basically concentrated in the area directly above the rotating rock block 42. Therefore, using gangue powder grouting material can increase the diffusion range and facilitate its flow within the delaminations in the fracture zone. After filling the fracture zone with gangue powder, the integrity of the fracture zone near the coal wall support area (the area directly above the rotating rock block 42) will be better, which can provide better support for the overlying strata, further share the stress of the section coal pillar 14 and the subsequent second working face 13, and thus further reduce the width of the section coal pillar 14 and regulate the stress of the subsequent second working face 13.
[0032] This invention is not limited to the preferred embodiments described above. Anyone can derive other methods in various forms under the guidance of this invention. Any technical solution that is the same as or similar to this application falls within the protection scope of this invention.
Claims
1. A method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden, characterized in that, Includes the following steps: S1: Arrange the first working face and the second working face in the coal seam, and leave a section coal pillar between the first working face and the second working face; S2: The basic top of the first working face is cut off by directional top-cutting borehole to form a rotating rock block. The rotating rock block can abut one end on the caving boundary and the other end on the caving zone. The first working face is mined by top-coal caving mining technology. When releasing coal, no coal or only a small amount of coal is released on the side located below the rotating rock block and away from the caving boundary to form a dense caving zone. S3: As the first working face advances, the dense collapse zone behind it is continuously filled with cemented grout to form a partition wall filling body. S4: After the first working face is completed, the first filling borehole is constructed from the ground to the caving zone between the partition wall filling body and the section coal pillar, and the second filling borehole is constructed from the ground to the fracture zone; gangue powder grouting filling slurry is injected into the caving zone through the first filling borehole, and gangue powder grouting filling slurry is injected into the fracture zone through the second filling borehole.
2. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1, characterized in that, In step S1, the width of the coal pillar in the section is 10-15m.
3. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1, characterized in that, In step S1, a mining roadway is constructed on the side of the section coal pillar in the first working face; several drilling sites are constructed at intervals along the working face advancement direction in the mining roadway in the first working face, and two directional roof cutting boreholes are constructed from the drilling sites toward the cutting direction, with the horizontal section of the directional roof cutting borehole located inside the basic roof.
4. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1, characterized in that, In step S2, the rotating rock block is the rock block closest to the collapse boundary formed by the basic top fracture, and the rock blocks adjacent to the rotating rock block fall on the collapse zone in a basically horizontal manner.
5. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1 or 4, characterized in that, In step S2, the area with no or minimal coal release is 3-5m wide and entirely located under the rotating rock block; the remaining areas along the width of the first working face are released normally to form a normal caving zone.
6. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1, characterized in that, In step S3, a backfill pipe is installed on the hydraulic support for top coal caving directly opposite the dense caving zone, and the backfill pipe is connected to the underground filling pipeline. Grouting is then performed on the dense caving zone through the backfill pipe.
7. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1 or 6, characterized in that, In step S3, the grout used for grouting and filling the dense collapse zone is a cementitious grouting and filling grout made of cement, gangue powder with different particle size gradations and water.
8. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1, characterized in that, In step S4, several first filling boreholes are constructed at intervals along the working face advancing direction, and the first filling boreholes are constructed entirely outside the collapse boundary.
9. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 8, is characterized in that... In step S4, several second filling boreholes are constructed at intervals along the working face advancing direction. The second filling boreholes are constructed entirely within the collapse boundary and located directly above the rotating rock block.
10. The method for controlling stress migration induced by grouting and filling in the fractured zone and caving zone of mining-induced overburden as described in claim 1 or 9, characterized in that, In step S4, the gangue powder grouting filling slurry is a non-cemented grouting filling slurry made by mixing gangue powder ground into powder with water.