A BIM-based method for rapid modeling and layout of construction sites

By using a BIM-based rapid construction site layout modeling method, construction site layout schemes are automatically generated, solving the problems of low efficiency and insufficient compliance assessment in existing technologies, and achieving efficient and safe construction site layout.

CN123116793APending Publication Date: 2026-11-17ROAD & BRIDGE INT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611234298.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-08-14
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

Existing technologies suffer from problems such as low efficiency in manual modeling, disconnect between multi-source data, lack of automated layout generation mechanisms, and lack of intelligent compliance assessment methods in construction site layout, resulting in low efficiency and insufficient safety in the early planning stage of construction.

Method used

A BIM-based rapid construction site layout modeling method is adopted. By acquiring basic project data, a three-dimensional site base environment is generated. A parametric component library is called and a layout generation algorithm is used to automatically generate an initial layout scheme. Conflict points are identified and adjusted, compliance assessment and quantitative scoring are carried out, optimization suggestions are output, and finally an optimized layout scheme is generated.

Benefits of technology

It has achieved automation and intelligence in construction site layout, improved modeling efficiency, ensured the compliance and safety of the plan, reduced rework and rectification, and realized the integrated generation of two-dimensional drawings, three-dimensional models and cost data.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123116793A_ABST
    Figure CN123116793A_ABST
Patent Text Reader

Abstract

This invention discloses a BIM-based rapid construction site layout modeling method, belonging to the field of intelligent design technology for building engineering information systems. The method includes: acquiring basic project data and standardizing it to generate a three-dimensional site base environment; based on the three-dimensional site base environment, calling a parametric component library and generating an initial layout scheme through a layout generation algorithm; identifying and displaying conflict points in the initial layout scheme, receiving adjustment operations for component parameters to obtain an adjusted layout scheme; conducting compliance assessment and quantitative scoring on the adjusted layout scheme, outputting an assessment report and optimization suggestions, receiving update operations based on the optimization suggestions to generate an optimized layout scheme; and outputting deliverables based on the optimized layout scheme. This invention enables fully automated generation and intelligent compliance assessment of construction site layout schemes, effectively improving planning efficiency and scheme security, and supporting multi-deliverable linkage output and multi-terminal sharing and collaboration.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of information-based intelligent design technology for building engineering, and in particular to a method for rapid modeling and layout of construction site based on BIM. Background Technology

[0002] In traditional construction site layout planning, the industry mainstream uses Computer-Aided Design (CAD) technology to complete site layout design. However, two-dimensional planar technology has significant limitations and is difficult to adapt to the needs of modern construction site planning. Two-dimensional CAD drawings cannot accurately simulate the three-dimensional spatial positions and safety distances between tower cranes, temporary facilities, proposed buildings, and existing external buildings. This easily leads to problems such as tower cranes touching high-voltage lines within their operating range and insufficient safety distances for temporary facilities, posing significant safety risks. Furthermore, site layout requires integrating multi-source information such as topography, underground pipelines, site boundaries, and proposed buildings. CAD drawing requires manual input, layer-by-layer drawing, and synchronization of various data, making the drawing process cumbersome, inefficient, and prone to information omissions and layer data inconsistencies. In addition, the quality of traditional site layout schemes relies entirely on the subjective experience of technical personnel, lacking quantitative evaluation criteria. This results in a low safety compliance rate for site layout schemes and makes it difficult to meet the needs of project visualization and scheme review, leading to high overall planning rework rates and low decision-making efficiency.

[0003] To overcome the shortcomings of 2D CAD technology, Building Information Modeling (BIM) technology has been gradually introduced into the field of construction site layout. Existing BIM tools can achieve 3D spatial simulation and visualization, which can compensate for the spatial representation deficiencies of CAD technology to a certain extent. Through BIM software, staff can build 3D models of proposed buildings, construction equipment, and temporary facilities on the site, and perform basic spatial location observation and clash checks.

[0004] However, existing BIM-based construction site layout technologies still have many core shortcomings, failing to achieve intelligent and automated planning of construction site layouts. Current BIM software's built-in family libraries primarily consist of building structural components, lacking standardized parametric components specifically designed for construction site planning. The compatibility with components for temporary facilities and large construction equipment is extremely poor, requiring users to create or modify components manually, consuming significant time. Furthermore, existing BIM software has low levels of parametric and automation capabilities; site layout schemes still require manual dragging and dropping, resulting in a large and time-consuming modeling workload, and the inability to automatically generate initial layout schemes based on project constraints. Similar BIM applications both domestically and internationally largely focus on static model display, unable to quickly generate layout schemes by linking raw data such as site survey point clouds and oblique photography. They also generally lack intelligent assessment and quantitative analysis functions for site layout rationality, failing to automatically verify construction code compliance and output optimization suggestions; the quality of the scheme still relies on human experience for judgment.

[0005] In summary, existing CAD and conventional BIM technologies cannot meet the demands for efficient, accurate, and compliant intelligent construction site layout planning, indicating a significant gap in industry technology upgrades. Specifically, the pressing technical issues include: slow manual modeling and delayed visualization output during construction site layout planning; disconnect between 2D drawings, 3D models, and cost data, leading to frequent contradictions among multiple deliverables; a lack of dedicated parametric components and automated layout generation mechanisms for construction site layout; a lack of intelligent compliance verification and quantitative evaluation methods integrating construction standards; and inconvenient multi-terminal result sharing and collaboration methods, making it difficult to adapt to the multi-party collaborative review requirements of modern projects. These problems severely restrict the efficiency and security of pre-construction planning, urgently requiring a fully automated, parametric, and intelligent construction site layout planning solution. Summary of the Invention

[0006] The technical problem this invention aims to solve is to address the shortcomings of existing technologies, specifically the low efficiency of manual modeling, the disconnect between multi-source data, the lack of automated layout generation mechanisms, and the lack of intelligent compliance assessment methods in traditional construction site layout planning. Specifically, it provides a BIM-based rapid construction site layout modeling method, as follows: 1) In a first aspect, the present invention provides a method for rapid modeling and layout of construction sites based on BIM, the specific technical solution of which is as follows: S1. Obtain basic project data, standardize the basic project data, and generate a three-dimensional site base environment. S2, based on the three-dimensional site base environment, call the parameterized component library and generate an initial layout scheme through the layout generation algorithm; S3, identify conflict points in the initial layout scheme and display the conflict points; receive adjustment operations for component parameters in the parameterized component library, adjust the component parameters according to the adjustment operations, and obtain an adjusted layout scheme; S4, perform compliance assessment and quantitative scoring on the adjusted layout scheme, output an assessment report and optimization suggestions; receive update operations based on the optimization suggestions, and generate an optimized layout scheme; S5. Based on the optimized layout scheme, output the delivery results.

[0007] The beneficial effects of the BIM-based rapid modeling and layout method for construction site layout provided by this invention are as follows: By acquiring basic project data and generating a 3D site base environment, a standardized data foundation is provided, resolving the tedious problem of inconsistent coordinates and the need for manual integration of multi-source heterogeneous data. By calling a parametric component library and utilizing a layout generation algorithm to automatically generate an initial layout scheme, replacing the traditional method of manually dragging and dropping components one by one, the workload of manual modeling is significantly reduced, scheme generation efficiency is improved, and project cycle is shortened. Simultaneously, calling the parametric component library enables multi-source data interoperability, eliminating information discrepancies. By identifying and displaying conflict points, users can precisely adjust component parameters, effectively eliminating conflicts between tower cranes and high-voltage lines, and between temporary facilities and proposed structures. The project addressed fundamental compliance issues such as insufficient safety distances between buildings and substandard fire lane widths, improving the overall compliance of the plan. By conducting compliance assessments and quantitative scoring of the adjusted layout, and generating assessment reports and optimization suggestions, users can update their plans based on objective quantitative indicators. This replaces the traditional decision-making method that relies on subjective experience, improving the overall quality and safety compliance rate of the plan, reducing construction costs, and minimizing rework and rectification. Furthermore, by linking the optimized layout with the output of deliverables, the project achieved the integrated generation of 2D drawings, 3D models, visualizations, and cost estimates, avoiding data discrepancies and information contradictions caused by creating multiple deliverables separately.

[0008] Based on the above solution, the present invention can be further improved as follows.

[0009] Furthermore, each component in the parameterized component library adopts a three-layer parameterized family file, the three-layer structure including a bottom layer, a middle layer, and an upper layer; The bottom layer stores two-dimensional drawing data; the middle layer stores BIM three-dimensional geometric models and construction parameters; the top layer stores three-dimensional rendering materials and texture information; and the data between the bottom layer, the middle layer, and the top layer are updated in a two-way linkage.

[0010] Furthermore, the layout generation algorithm includes a site path planning algorithm, a three-dimensional spatial conflict detection algorithm, and a multi-stage layout iteration algorithm; the site path planning algorithm is used to plan construction roads and transportation routes within the site; the three-dimensional spatial conflict detection algorithm is used to detect spatial position conflicts between components in real time; and the multi-stage layout iteration algorithm is used to generate layout schemes for corresponding stages based on the constraints of different construction stages.

[0011] Furthermore, the conflict points include locations where the spatial distance between the tower crane and the high-voltage line is illegal, locations where the safety distance between temporary facilities and the proposed building is insufficient, and locations where the width of the fire lane does not meet the standard; the judgment conditions for identifying the conflict points include the equipment hoisting radius, safety distance, and component size in the component parameters; The evaluation indicators used for the compliance assessment and quantitative scoring include: safety distance compliance indicators, fire safety compliance indicators, logistics and transportation efficiency indicators, secondary handling cost indicators, and site utilization rate indicators.

[0012] 2) In a second aspect, the present invention also provides a BIM-based rapid modeling and layout system for construction site layout, the specific technical solution of which is as follows: a data acquisition module, a layout generation module, a conflict handling module, a compliance assessment module, and a result output module; The data acquisition module is used to acquire basic project data, standardize the basic project data, and generate a three-dimensional site base environment. The layout generation module is used to generate an initial layout scheme based on the three-dimensional site base environment by calling the parameterized component library and using the layout generation algorithm. The conflict handling module is used to identify conflict points in the initial layout scheme and display the conflict points; receive adjustment operations for component parameters in the parameterized component library, adjust the component parameters according to the adjustment operations, and obtain an adjusted layout scheme. The compliance assessment module is used to assess and quantify the compliance of the adjusted layout scheme, output an assessment report and optimization suggestions; receive update operations based on the optimization suggestions, and generate an optimized layout scheme. The output module is used to output deliverables based on the optimized layout scheme.

[0013] Based on the above solution, the present invention can be further improved as follows.

[0014] Furthermore, each component in the parameterized component library adopts a three-layer parameterized family file, the three-layer structure including a bottom layer, a middle layer, and an upper layer; The bottom layer stores two-dimensional drawing data; the middle layer stores BIM three-dimensional geometric models and construction parameters; the top layer stores three-dimensional rendering materials and texture information; and the data between the bottom layer, the middle layer, and the top layer are updated in a two-way linkage.

[0015] Furthermore, the layout generation algorithm includes a site path planning algorithm, a three-dimensional spatial conflict detection algorithm, and a multi-stage layout iteration algorithm; the site path planning algorithm is used to plan construction roads and transportation routes within the site; the three-dimensional spatial conflict detection algorithm is used to detect spatial position conflicts between components in real time; and the multi-stage layout iteration algorithm is used to generate layout schemes for corresponding stages based on the constraints of different construction stages.

[0016] Furthermore, the conflict points include locations where the spatial distance between the tower crane and the high-voltage line is illegal, locations where the safety distance between temporary facilities and the proposed building is insufficient, and locations where the width of the fire lane does not meet the standard; the judgment conditions for identifying the conflict points include the equipment hoisting radius, safety distance, and component size in the component parameters; The evaluation indicators used for the compliance assessment and quantitative scoring include: safety distance compliance indicators, fire safety compliance indicators, logistics and transportation efficiency indicators, secondary handling cost indicators, and site utilization rate indicators.

[0017] 3) In a third aspect, the present invention also provides a computer device, the computer device including a processor coupled to a memory, the memory storing at least one computer program, the at least one computer program being loaded and executed by the processor to enable the computer device to implement any of the above methods.

[0018] 4) In a fourth aspect, the present invention also provides a computer-readable storage medium storing at least one computer program, which is loaded and executed by a processor to enable a computer to implement any of the above methods.

[0019] It should be noted that the beneficial effects of the technical solutions of the second to fourth aspects of the present invention and their corresponding possible implementations can be found in the above description of the technical effects of the first aspect and its corresponding possible implementations, and will not be repeated here. Attached Figure Description

[0020] Other features, objects, and advantages of the invention will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings: Figure 1 This is a flowchart illustrating the steps of a BIM-based rapid construction site layout method according to an embodiment of the present invention. Figure 2This is a schematic diagram of the overall architecture of a BIM-based rapid construction site layout method according to an embodiment of the present invention. Figure 3 This is a schematic diagram of a three-layer structure parametric family file for a BIM-based rapid construction site layout method according to an embodiment of the present invention. Figure 4 This is a schematic diagram of the construction site layout planning process for a BIM-based rapid construction site layout method according to an embodiment of the present invention. Figure 5 This is a schematic diagram of the structure of a computer device according to an embodiment of the present invention. Detailed Implementation

[0021] To make the objectives, technical solutions, and advantages of the present invention clearer, the embodiments of the present invention will be described in further detail below with reference to the accompanying drawings.

[0022] BIM, or Building Information Modeling, refers to an information-based digital carrier that integrates the three-dimensional geometry, engineering parameters, cost information, and performance data of buildings or site facilities. Construction site layout refers to the spatial planning and layout design of various facilities within the construction site, such as proposed buildings, construction roads, processing sheds, tower cranes, living areas, and material storage yards, in the early stages of a construction project.

[0023] like Figure 1 as well as Figure 2 As shown in the figure, a method for rapid modeling and layout of construction sites based on BIM according to an embodiment of the present invention includes the following steps: S1. Obtain basic project data, standardize the data, and generate a 3D site baseline environment. The specific implementation method is as follows: Project foundational data refers to the various original input data upon which construction site layout modeling and planning rely, including survey data and project constraints. Survey data reflects the actual topography and existing spatial environment of the site, including topographic point clouds, oblique photogrammetry models, and computer-aided design (CAD) drawings. Topographic point clouds are a massive set of three-dimensional coordinate points on the site surface obtained through laser scanning or photogrammetry; oblique photogrammetry models are measurable three-dimensional mesh models generated using photogrammetry technology after photographing the site with a drone equipped with a multi-angle camera; and site CAD drawings are two-dimensional vector maps containing information on site boundaries, underground pipelines, surrounding existing buildings, and roads. Project constraints refer to the restrictive requirements and parameters imposed by the project itself and the client on the site layout, including information on restricted areas designated by the client, construction phase requirements, tower crane parameters, and safety standard thresholds. The restricted area designation information refers to the area where construction facilities are prohibited, as clearly defined by the construction unit or owner; the construction stage requirements information refers to the different site usage requirements for each stage of the project, such as the foundation pit construction stage, the main structure construction stage, and the decoration and finishing construction stage; the tower crane equipment parameters refer to the technical data such as the model, lifting radius, lifting capacity, and installation height of the tower crane to be used; the safety standard thresholds refer to the mandatory values ​​such as various safety distances and fire lane widths specified in national standards and industry specifications, such as the requirements for fire separation distances for temporary buildings and the net width of fire lanes specified in the national standard GB 50720 "Technical Specification for Fire Safety at Construction Sites".

[0024] Standardization processing refers to the operations of data cleaning, format unification, and coordinate system unification for multi-source heterogeneous data. Since terrain point clouds, oblique photogrammetry models, and site CAD drawings originate from different acquisition methods and employ different data formats and spatial coordinate systems, they cannot be directly overlaid. Therefore, data cleaning is necessary to remove noise and redundant data, unify data formats, and convert all data to the same spatial coordinate system, thereby integrating them to form a three-dimensional site base environment. The three-dimensional site base environment refers to a three-dimensional spatial scene that integrates the site's surface undulations, the spatial occupancy of existing buildings, the distribution of underground pipelines, the site boundary, and surrounding road information, serving as the basic geospatial carrier for all subsequent layout generation and spatial analysis operations.

[0025] Standardized processing solves the problems of inconsistent coordinates and formats of multi-source heterogeneous data. It eliminates the need for staff to manually input, draw in layers, and synchronize various survey data one by one. It provides a standardized and directly usable 3D site base environment for subsequent automated layout generation, avoiding the problems of information omission and layer data contradictions caused by manually integrating multi-source data in the traditional CAD drawing process.

[0026] S2, based on the 3D site environment, calls the parametric component library and generates an initial layout scheme through a layout generation algorithm. The specific implementation is as follows: A parametric component library is a database collection that systematically stores, manages, and retrieves various standardized components specifically designed for construction site layout. A component is a digital 3D model unit of each facility or equipment with independent function on the site, including temporary construction facilities and construction equipment components. Temporary construction facilities include prefabricated houses (used as dormitories and offices), rebar processing sheds, cement mixing plants, material storage yards, site fencing, and gates; construction equipment components include tower cranes and construction hoists. Each component carries adjustable parameter information, including dimensional parameters (length, width, height), positional parameters (spatial coordinates), and engineering attribute parameters (equipment hoisting radius, safety distance requirements, quantity measurement parameters, etc.). By modifying these parameter values, component instances of different specifications can be quickly generated.

[0027] Layout generation algorithms refer to a set of algorithms used to automatically determine the spatial position and dimensions of various components within a site. The specific implementation process for generating the initial layout scheme is as follows: The system reads topographic relief data, site boundary lines, underground pipeline distribution, and existing building occupancy information from the 3D site base environment; it obtains information on the client's restricted areas, construction phase requirements, tower crane parameters, and safety standard thresholds from the project constraints; it automatically plans on-site construction roads and material transportation routes based on site topographic conditions and the principle of optimal logistics paths; and it automatically matches corresponding components from the parameterized component library based on the planned road network and the work surface locations of each construction phase, determines the spatial location and parameter values ​​of each component, and generates an initial layout scheme that includes the spatial location and component parameter information of the proposed buildings, on-site roads, processing sheds, tower cranes, living areas, and stockpiles.

[0028] After the initial layout scheme is generated, a parameter visualization and fine-tuning function is supported. Users can directly drag and drop the model of any component in the 3D scene. The component moves in real time with the mouse drag operation, and the current spatial coordinates of the component and its real-time distance from other components are displayed synchronously. At the same time, the size parameters and engineering attribute parameters of the component can also be finely adjusted in the parameter panel through sliders or numerical input boxes. The above two adjustment methods work together, and the shape and spatial position of the component in the 3D scene and the values ​​in the parameter panel are updated synchronously, without the need for manual data synchronization between the 3D scene and the parameter panel.

[0029] In a preferred embodiment, such as Figure 3As shown, each component in the parametric component library uses a three-layer parametric family file. A family file is a data file used in BIM technology to define component templates with the same set of attributes. Different component instances can be derived by modifying the parameter values ​​in the family file. The three-layer structure includes a bottom layer, a middle layer, and a top layer. The bottom layer stores two-dimensional drawing data, namely standardized CAD lines, layers, and annotation information, used to support the automatic output of two-dimensional construction drawings. The middle layer stores the BIM three-dimensional geometric model and construction parameters, including equipment hoisting radius, safety distance, component dimensions, and quantity measurement parameters, used to support 3D BIM display and automatic quantity calculation. The top layer stores 3D rendering materials and texture information, namely the visual attribute data of the component surface, such as color, texture, and gloss, used to generate high-definition visual rendering scenes and walkthrough animations. The data between the bottom, middle, and top layers is updated bidirectionally; that is, when a user edits or modifies the data in any layer, the data in the other two layers is automatically updated synchronously, ensuring that the data across all three layers remains consistent. The specific implementation of the three-layer structure parametric family file is as follows: In the BIM software secondary development environment, three data storage layers are established for each component family file. Change events of data in each layer are captured through an event listening mechanism. Once a change event is captured, the data synchronization function is triggered, and the changed data is written into the corresponding data fields of the other two layers according to the predefined mapping relationship.

[0030] By using a three-layer parametric family file structure, dynamic linkage updates of 2D drawings, 3D models, rendering effects, and cost data are achieved. A single modification can be synchronized to all three layers of data, completely solving the problems of data disconnect, information omission, and version inconsistencies caused by the need to create and modify 2D drawings, 3D models, rendering effects, and cost data separately in traditional technologies, and ensuring data consistency of all deliverables.

[0031] In a preferred embodiment, the layout generation algorithm includes a site path planning algorithm, a 3D spatial conflict detection algorithm, and a multi-stage layout iteration algorithm. The site path planning algorithm is used to plan construction roads and transportation routes within the site. Specifically, it takes terrain undulation data from the 3D site base environment, site boundary lines, and existing obstacle locations as input, and aims to connect various functional areas of the site (including processing areas, material storage areas, construction work surfaces, and entrances / exits). A path search algorithm is used to automatically generate a network of main roads and branch roads that meet slope and minimum width requirements. The 3D spatial conflict detection algorithm is used to detect spatial position conflicts between components in real time. Specifically, during the layout scheme generation process and the adjustment of component parameters, the spatial overlap volume and minimum spatial distance between the bounding boxes of each component in 3D space are calculated in real time. When the spatial distance between two components is less than the corresponding safety standard threshold or spatial overlap occurs, a conflict marker is immediately triggered and the conflict location is recorded. The multi-stage layout iteration algorithm is used to generate layout schemes for corresponding stages based on the constraints of different construction stages, including the foundation pit construction stage, the main structure construction stage, and the decoration and finishing construction stage. The constraints for different construction stages come from: the construction stage requirements information in the project constraints and the differentiated specification clauses corresponding to each stage in the built-in national construction specifications and standards. The specific implementation of the multi-stage layout iteration algorithm is as follows: the constraints of each construction stage are read sequentially, the layout generation process in S2 is re-executed for the current stage to generate the initial layout scheme for the corresponding stage, and the data consistency between the initial layout schemes of each stage is maintained through the three-layer linkage update of the parameterized component library. That is, the initial layout schemes of each stage share the same set of bottom-level 2D drawing data, middle-level 3D model data, and upper-level rendering data. The differences are only made in the spatial position of components and parameter values ​​according to the constraints of different stages, ensuring the continuity and traceability of the results of each stage.

[0032] By automatically matching and arranging the parametric component library and layout generation algorithm, the traditional manual modeling method of dragging and dropping components one by one is replaced, which greatly reduces the amount of manual modeling work and solves the technical defects of existing BIM tools such as low automation, large modeling workload and long time consumption, and significantly improves the generation efficiency of site layout schemes.

[0033] S3 identifies conflict points in the initial layout scheme and displays them; it receives adjustment operations for component parameters in the parametric component library, adjusts the component parameters according to the adjustment operations, and obtains an adjusted layout scheme. The specific implementation is as follows: Conflict points refer to locations in the initial layout scheme that violate safety standard thresholds or spatial constraints. The specific process for identifying conflict points is as follows: using a three-dimensional spatial conflict detection algorithm, based on the equipment hoisting radius, safety distance, and component dimensions in the component parameters, the spatial positional relationships between each component in the initial layout scheme are calculated and judged item by item to determine whether there are violations such as insufficient spatial distance or spatial overlap. The safety standard thresholds used for determining conflict points are derived from the safety standard thresholds in the project constraints, such as the minimum safe clearance distance between tower cranes and high-voltage lines, the minimum fire separation distance between temporary facilities and proposed buildings, and the minimum clear width of fire lanes as stipulated by national standards.

[0034] The specific implementation method for displaying conflict points is as follows: In the three-dimensional site base environment, the identified conflict points are marked at the spatial location of the corresponding components using highlighted colors, flashing marks, or warning icons. At the same time, the user interface displays detailed information about all conflict points in a list format, including conflict type, violation value, name of the component involved, and specific regulatory clauses violated, so that users can quickly locate and understand the details of the violation.

[0035] Receiving adjustment operations for component parameters in the parametric component library refers to providing users with a parameter editing interface. After viewing the conflict points, users can select the component to be adjusted through this interface and modify its size parameters (e.g., reducing the component size to increase the distance between it and adjacent facilities), position parameters (e.g., translating the component to adjust the spatial distance), or engineering attribute parameters (e.g., replacing it with a smaller model of equipment). The system receives the above operation input and updates the corresponding component's parameter values ​​in real time. After adjusting the component parameters according to the adjustment operation, the spatial position and geometry of the components in the 3D site base environment are automatically updated to obtain the adjusted layout scheme. During the above adjustment operation, the bottom layer 2D drawing data, the middle layer 3D geometric model, and the upper layer rendering material data in the three-layer structure parametric family file are updated synchronously and in conjunction with each other, without requiring users to modify the drawings, models, or rendering materials separately.

[0036] In a preferred implementation, conflict points include locations where the spatial distance between the tower crane and high-voltage lines violates regulations, locations where the safety clearance between temporary facilities and the proposed building is insufficient, and locations where the width of fire lanes does not meet standards. Locations where the spatial distance between the tower crane and high-voltage lines violates regulations refer to locations where the minimum spatial distance between the tower crane's boom rotation range and high-voltage transmission lines erected around or within the site is less than the minimum safe clearance distance specified in national standards. Locations where the safety clearance between temporary facilities (such as prefabricated houses or processing sheds) and the main body of the proposed building is less than the fire separation distance requirement for temporary housing and construction projects as specified in national standard GB 50720. Locations where the width of fire lanes does not meet standards refer to locations where the actual net width of the planned fire lanes within the site is less than the minimum net width requirement for fire lanes specified in national standards. The criteria for identifying conflict points include the equipment hoisting radius, safety distance, and component size in the component parameters. Specifically, by calculating the spatial distance between the tower crane hoisting radius coverage area and the high-voltage line coordinates, the horizontal distance between the temporary facility boundary and the outline of the proposed building, and the vertical distance between components on both sides of the fire lane, these are compared with the corresponding safety standard thresholds. Spatial locations that do not meet the threshold requirements are identified as conflict points.

[0037] By automatically identifying and visually displaying conflict points, users can quickly locate violations in the layout plan, replacing the inefficient method of traditional manual item-by-item verification. By receiving user adjustments to component parameters, it enables precise correction of hard violations, effectively eliminating safety hazards such as insufficient safety distance between tower cranes and high-voltage lines, substandard fire separation distance between temporary facilities and proposed buildings, and insufficient width of fire lanes, thereby improving the basic compliance and safety of the plan.

[0038] S4 performs compliance assessment and quantitative scoring on the adjusted layout scheme, outputs an assessment report and optimization suggestions; receives update operations based on the optimization suggestions, and generates an optimized layout scheme. The specific implementation method is as follows: Compliance assessment refers to the process of verifying and judging each compliance indicator in the adjusted layout plan based on built-in national construction specifications and standards, determining whether each indicator meets the requirements of national standards and industry specifications. Quantitative scoring refers to the process of calculating a comprehensive score for the adjusted layout plan based on multi-dimensional evaluation indicators, reflecting the overall quality of the plan in quantitative numerical form. The assessment report is a standardized document that includes the judgment results of each compliance indicator, detailed scores for each dimension, and the overall score. Optimization suggestions are automatically generated specific operational suggestions for improving the overall score of the plan or eliminating violations for indicators with low scores or those that failed the compliance judgment.

[0039] The specific implementation process of compliance assessment and quantitative scoring is as follows: A built-in national construction standard database stores the requirements of various mandatory national standards and industry specifications, including GB 50720 "Technical Specification for Fire Safety at Construction Sites". Spatial location data and parameter data of each component in the adjusted layout plan are read and compared item by item with the requirements in the built-in standards to determine whether indicators such as safety distances, fire lanes, and equipment operating range meet the specifications. Simultaneously, a quantitative evaluation model is constructed by integrating a rule engine and a deep learning algorithm. The rule engine is responsible for executing explicit hard rule judgments (such as whether the safety distance is greater than or equal to the specification threshold), while the deep learning algorithm is responsible for learning the weight relationships and non-linear effects between indicators based on historical compliance plan data, thereby performing multi-dimensional quantitative scoring of the adjusted layout plan. The specific implementation of the deep learning algorithm is as follows: The deep learning algorithm adopts a decision tree network structure and a clustering algorithm. The training dataset is based on historical construction site layout compliance schemes and their corresponding evaluation index scores. The training dataset is labeled by experts scoring each evaluation index of the historical compliance schemes and marking the comprehensive score as the label value. After supervised learning training, the decision tree network is used to predict the comprehensive score of new schemes in real time. The clustering algorithm is used to perform cluster analysis on the schemes in the historical compliance scheme database, grouping similar layout schemes into the same category. When evaluating the current scheme, the algorithm automatically identifies the category to which the current scheme belongs and provides a reference benchmark and weight adjustment basis for the scores of various indicators of the current scheme based on the historical scheme score distribution of that category.

[0040] The specific implementation process for generating optimization suggestions is as follows: Indicators that fail compliance checks and those with scores below a preset threshold are designated as optimization targets. For each type of violation or low score, a corresponding component operation template is predefined. For example, when the safety distance is not met, the template is "Move component X a distance D in the X direction" or "Adjust the dimension parameter of component X from V1 to V2"; when the fire lane width is insufficient, the template is "Increase the distance between components on both sides of the lane to W meters" or "Remove obstruction component Y in the lane area". Based on the component identifiers and violation values ​​involved in the violation, the specific values ​​are filled into the placeholder positions in the template to generate specific actionable suggestions. When multiple violations exist simultaneously, the optimization suggestions are sorted in descending order of violation severity (i.e., the percentage deviation between the violation value and the standard threshold). The larger the deviation, the higher the priority. A list of optimization suggestions is then output in priority order for user reference and execution.

[0041] Receiving updates based on optimization suggestions means that after the evaluation report and optimization suggestions are presented to the user in a visual manner, the user reads the optimization suggestions and updates the component parameters in the layout plan through the interactive interface based on the specific problems pointed out in the optimization suggestions (such as insufficient safety distance or insufficient width of fire lane) and the corresponding rectification plan (such as "moving the component by a distance D in the X direction" or "increasing the distance between the components on both sides of the passage to W meters"). The system receives the update operation and updates and adjusts the layout plan accordingly to generate an optimized layout plan.

[0042] In a preferred implementation scheme, the evaluation indicators used for compliance assessment and quantitative scoring include: safety distance compliance indicators, fire safety compliance indicators, logistics and transportation efficiency indicators, secondary handling cost indicators, and site utilization rate indicators. Safety distance compliance indicators evaluate whether the safety distances between various facilities and between facilities and the proposed building meet national standards. Fire safety compliance indicators evaluate whether fire lane width, fire truck access road layout, and temporary fire water supply system arrangement meet regulatory requirements. Logistics and transportation efficiency indicators evaluate the connectivity of construction roads within the site, the rationality of transportation routes, and the distance of material transportation, reflecting the efficiency of construction logistics. Secondary handling cost indicators evaluate the distance between material storage areas and construction work areas, indirectly reflecting the additional transportation costs incurred due to multiple material transfers. Site utilization rate indicators evaluate the compactness of the layout of various facilities within the site and the proportion of vacant areas, reflecting the efficiency of site space resource utilization. After calculating scores for each indicator, they are weighted and summed according to predefined weighting coefficients to output a comprehensive score for the adjusted layout scheme. A higher comprehensive score indicates a better overall quality of the adjusted layout scheme. The specific method for determining the weight coefficients of each evaluation indicator is as follows: the initial weight coefficients are preset based on the experience of industry experts. During the operation, the deep learning algorithm continuously learns the correlation between the scores of each indicator and the comprehensive score based on the historical compliance solution dataset, and automatically adjusts the weight coefficients of each indicator to minimize the error between the quantitative scoring results and the expert review conclusions.

[0043] By integrating a rule engine and deep learning algorithms into a multi-dimensional quantitative scoring model, an objective quantitative evaluation of layout solutions is achieved, replacing the traditional decision-making method that relies on the subjective experience of technical personnel to judge the merits of solutions. By automatically generating evaluation reports and targeted optimization suggestions, users are provided with clear directions for solution improvement, reducing the reliance on the experience of senior technical personnel for solution optimization and improving the overall quality and safety compliance rate of the solution.

[0044] S5, based on the optimized layout scheme, outputs the deliverables. The specific implementation method is as follows: Deliverables refer to the final outputs of the construction site layout modeling and planning, including 2D construction drawings, 3D BIM, high-definition visualization rendering scenes and walkthrough animations, and a cost list for temporary construction works. 2D construction drawings are CAD format drawing files containing the overall site layout and layout plans for each construction stage, automatically generated from standardized CAD lines, layers, and annotation data stored at the bottom layer of the parametric component library. 3D BIM refers to interactive 3D model files containing the 3D geometry of each component and complete construction parameters, automatically generated from the 3D geometric model and construction parameters stored in the middle layer. High-definition visualization rendering scenes and walkthrough animations are high-definition image sequences or video files generated after material mapping, lighting rendering, and camera path animation of the 3D BIM, automatically generated from the 3D rendering materials and texture information stored in the upper layer. The cost list for temporary construction works is a bill of quantities and cost calculation report automatically calculated based on the component dimensions and quantity measurement parameters of each temporary facility in the optimized layout scheme.

[0045] It also supports packaging deliverables into standalone executable (.exe) files for local offline sharing. A standalone executable file is a program file that can be directly run by double-clicking on a Windows operating system without installing any BIM or CAD software, allowing users to browse the complete 3D site scene, view 2D drawings, and play walkthrough animations. It also supports uploading optimized layout schemes to a cloud-based collaborative platform for multi-user online viewing and collaborative editing. The cloud-based collaborative platform is a multi-user collaborative work platform deployed on a web server, supporting project teams, construction units, supervision units, and other parties to simultaneously view the same project scheme online through a browser or client, and to annotate, comment on, and iteratively edit the scheme.

[0046] By leveraging optimized layout schemes to deliver a complete set of deliverables, including 2D construction drawings, 3D BIM, high-definition visual rendering scenes and walkthrough animations, as well as a cost list for temporary construction projects, a single modeling process can simultaneously produce multiple types of deliverables without switching between different software or creating duplicates. This completely avoids data disconnect and information contradictions caused by creating multiple deliverables separately. By supporting both local sharing of independent executable files and online sharing on a cloud-based collaborative platform, it adapts to various scenarios such as project review and reporting, multi-party collaborative design, and deliverable presentation, comprehensively improving the efficiency of early-stage project planning and multi-party collaboration.

[0047] Figure 4This invention demonstrates the complete process from data input to output. It gathers heterogeneous data from multiple sources, including red-line CAD drawings, oblique photogrammetry models, underground pipeline survey data, and client constraints, as the project's foundational data. After standardization, a three-dimensional site base environment is generated. Based on this, a parametric component library is used to automatically generate an initial layout scheme, establish the proposed building, and deploy modular temporary facilities. Users can detect and fine-tune spatial conflicts through conflict identification and parameter adjustment functions, and simulate secondary data transfer. The scheme undergoes compliance verification and comprehensive scoring through compliance assessment and quantitative evaluation. If the scheme does not meet the requirements, iterative adjustments are made based on optimization suggestions. Once the requirements are met, the optimized layout scheme outputs deliverables including two-dimensional CAD drawings, a three-dimensional BIM model, a visual rendering scene and walkthrough animation, and a temporary construction cost list. Results are shared through both local distribution via EXE files and online collaboration on a cloud-based platform.

[0048] The general implementation process of this invention is applicable to all building construction projects. It does not require staff to have extensive site layout experience. Relying on automation and intelligent functions, it can quickly produce compliant, efficient and economical construction site layout solutions, effectively solving various pain points of traditional technologies and possessing strong engineering applicability and promotional value.

[0049] In the above embodiments, although the steps are numbered S1, S2, etc., they are only specific embodiments given by the present invention. Those skilled in the art can adjust the execution order of S1, S2, etc. according to the actual situation, and these situations are also within the protection scope of the present invention. It can be understood that in some embodiments, some or all of the above embodiments may be included.

[0050] Furthermore, the acquisition process of the data involved in this application follows the principles of legality, legitimacy, and necessity. Based on obtaining the explicit authorization and consent of the user, only the minimum necessary information required to achieve the purpose is collected, and data security protection obligations are fulfilled in accordance with the law.

[0051] This invention also provides a BIM-based rapid modeling and layout system for construction site layout, the specific technical solution of which includes: a data acquisition module, a layout generation module, a conflict resolution module, a compliance assessment module, and a result output module; The data acquisition module is used to acquire basic project data, standardize the basic project data, and generate a three-dimensional site base environment. The layout generation module is used to generate an initial layout scheme based on the three-dimensional site base environment, by calling the parametric component library and using the layout generation algorithm. The conflict handling module is used to identify conflict points in the initial layout scheme and display the conflict points; it receives adjustment operations for component parameters in the parametric component library, adjusts the component parameters according to the adjustment operations, and obtains an adjusted layout scheme. The compliance assessment module is used to assess and quantify the compliance of the layout adjustment plan, output an assessment report and optimization suggestions; receive update operations based on the optimization suggestions, and generate an optimized layout plan. The deliverables module is used to output deliverables based on the optimized layout scheme.

[0052] It should be noted that the beneficial effects of the BIM-based rapid construction site layout system provided in the above embodiments are the same as those of the BIM-based rapid construction site layout method described above, and will not be repeated here. Furthermore, the system provided in the above embodiments is only illustrated by the division of the above functional modules. In practical applications, the above functions can be assigned to different functional modules as needed, that is, the system can be divided into different functional modules according to the actual situation to complete all or part of the functions described above. In addition, the system and method embodiments provided in the above embodiments belong to the same concept, and their specific implementation process is detailed in the method embodiments, and will not be repeated here.

[0053] like Figure 5 As shown, an embodiment of the present invention provides a computer device 300, which includes a processor 320 coupled to a memory 310. The memory 310 stores at least one computer program 330, which is loaded and executed by the processor 320 to enable the computer device 300 to implement any of the above-described methods. Specifically: The computer device 300 can vary considerably due to differences in configuration or performance. It may include one or more processors 320 (Central Processing Units, CPUs) and one or more memories 310. The one or more memories 310 store at least one computer program 330, which is loaded and executed by the one or more processors 320 to enable the computer device 300 to implement the BIM-based rapid construction site layout method provided in the above embodiments. Of course, the computer device 300 may also have wired or wireless network interfaces, a keyboard, and input / output interfaces for input and output. The computer device 300 may also include other components for implementing device functions, which will not be elaborated upon here.

[0054] An embodiment of the present invention provides a computer-readable storage medium storing at least one computer program, which is loaded and executed by a processor to enable a computer to implement any of the above-described methods.

[0055] Alternatively, the computer-readable storage medium may be a read-only memory (ROM), a random access memory (RAM), a compact disc read-only memory (CD-ROM), magnetic tape, a floppy disk, and an optical data storage device, etc.

[0056] In an exemplary embodiment, a computer program product or computer program is also provided, which includes computer instructions stored in a computer-readable storage medium. A processor of a computer device reads the computer instructions from the computer-readable storage medium and executes the computer instructions, causing the computer device to perform any of the aforementioned BIM-based rapid construction site layout modeling methods.

[0057] It should be noted that the terms "first," "second," etc., used in the specification of this application are used to distinguish similar objects and do not imply a specific order or sequence. Where appropriate, the order of use for similar objects can be interchanged so that the embodiments of this application described herein can be implemented in an order other than that shown in the figures or description.

[0058] Those skilled in the art will recognize that this invention can be implemented as a system, method, or computer program product. Therefore, this disclosure can be specifically implemented in the following forms: it can be entirely hardware, entirely software (including firmware, resident software, microcode, etc.), or a combination of hardware and software, generally referred to herein as a "circuit," "module," or "system." Furthermore, in some embodiments, the invention can also be implemented as a computer program product contained in one or more computer-readable media, which includes computer-readable program code.

[0059] Any combination of one or more computer-readable media may be used. A computer-readable medium can be a computer-readable signal medium or a computer-readable storage medium. A computer-readable storage medium can be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination thereof. More specific examples (a non-exhaustive list) of computer-readable storage media include: an electrical connection having one or more wires, a portable computer disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM or flash memory), optical fiber, portable compact disk read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof. In this document, a computer-readable storage medium can be any tangible medium that contains or stores a program that can be used by or in connection with an instruction execution system, apparatus, or device.

[0060] Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention. Those skilled in the art can make changes, modifications, substitutions and variations to the above embodiments within the scope of the present invention.

Claims

1. A BIM-based method for rapid modeling and layout of construction sites, characterized in that, include: S1. Obtain basic project data, standardize the basic project data, and generate a three-dimensional site base environment. S2, based on the three-dimensional site base environment, call the parameterized component library and generate an initial layout scheme through the layout generation algorithm; S3, identify conflict points in the initial layout scheme and display the conflict points; receive adjustment operations for component parameters in the parameterized component library, adjust the component parameters according to the adjustment operations, and obtain an adjusted layout scheme; S4. Conduct a compliance assessment and quantitative scoring of the proposed layout adjustment scheme, and output an assessment report and optimization suggestions; Receive update operations based on the optimization suggestions and generate an optimized layout scheme; S5. Based on the optimized layout scheme, output the delivery results.

2. The method for rapid modeling and layout of construction sites based on BIM according to claim 1, characterized in that, Each component in the parametric component library adopts a three-layer parametric family file, which includes a bottom layer, a middle layer, and a top layer. The bottom layer stores two-dimensional drawing data; the middle layer stores BIM three-dimensional geometric models and construction parameters; the top layer stores three-dimensional rendering materials and texture information; and the data between the bottom layer, the middle layer, and the top layer are updated in a two-way linkage.

3. The method for rapid modeling and layout of construction sites based on BIM according to claim 1, characterized in that, The layout generation algorithm includes a site path planning algorithm, a three-dimensional spatial conflict detection algorithm, and a multi-stage layout iteration algorithm. The site path planning algorithm is used to plan construction roads and transportation routes within the site. The three-dimensional spatial conflict detection algorithm is used to detect spatial position conflicts between components in real time. The multi-stage layout iteration algorithm is used to generate layout schemes for corresponding stages based on the constraints of different construction stages.

4. The method for rapid modeling and layout of construction sites based on BIM according to claim 1, characterized in that, The conflict points include locations where the spatial distance between the tower crane and the high-voltage line is illegal, locations where the safety distance between temporary facilities and the proposed building is insufficient, and locations where the width of the fire lane does not meet the standard. The judgment criteria for identifying the conflict points include the equipment hoisting radius, safety distance, and component size in the component parameters. The evaluation indicators used for the compliance assessment and quantitative scoring include: safety distance compliance indicators, fire safety compliance indicators, logistics and transportation efficiency indicators, secondary handling cost indicators, and site utilization rate indicators.

5. A BIM-based rapid modeling and layout system for construction site layout, characterized in that, include: The module includes a data acquisition module, a layout generation module, a conflict resolution module, a compliance assessment module, and a results output module. The data acquisition module is used to acquire basic project data, standardize the basic project data, and generate a three-dimensional site base environment. The layout generation module is used to generate an initial layout scheme based on the three-dimensional site base environment by calling the parameterized component library and using the layout generation algorithm. The conflict handling module is used to identify conflict points in the initial layout scheme and display the conflict points; receive adjustment operations for component parameters in the parameterized component library, adjust the component parameters according to the adjustment operations, and obtain an adjusted layout scheme. The compliance assessment module is used to conduct compliance assessment and quantitative scoring of the adjusted layout plan, and output an assessment report and optimization suggestions. Receive update operations based on the optimization suggestions and generate an optimized layout scheme; The output module is used to output deliverables based on the optimized layout scheme.

6. A BIM-based rapid modeling and layout system for construction site layout according to claim 5, characterized in that, Each component in the parametric component library adopts a three-layer parametric family file, which includes a bottom layer, a middle layer, and a top layer. The bottom layer stores two-dimensional drawing data; the middle layer stores BIM three-dimensional geometric models and construction parameters; the top layer stores three-dimensional rendering materials and texture information; and the data between the bottom layer, the middle layer, and the top layer are updated in a two-way linkage.

7. A BIM-based rapid modeling and layout system for construction site layout according to claim 5, characterized in that, The layout generation algorithm includes a site path planning algorithm, a three-dimensional spatial conflict detection algorithm, and a multi-stage layout iteration algorithm. The site path planning algorithm is used to plan construction roads and transportation routes within the site. The three-dimensional spatial conflict detection algorithm is used to detect spatial position conflicts between components in real time. The multi-stage layout iteration algorithm is used to generate layout schemes for corresponding stages based on the constraints of different construction stages.

8. A BIM-based rapid modeling and layout system for construction site layout according to claim 5, characterized in that, The conflict points include locations where the spatial distance between the tower crane and the high-voltage line is illegal, locations where the safety distance between temporary facilities and the proposed building is insufficient, and locations where the width of the fire lane does not meet the standard. The judgment criteria for identifying the conflict points include the equipment hoisting radius, safety distance, and component size in the component parameters. The evaluation indicators used for the compliance assessment and quantitative scoring include: safety distance compliance indicators, fire safety compliance indicators, logistics and transportation efficiency indicators, secondary handling cost indicators, and site utilization rate indicators.

9. A computer device, characterized in that, The computer device includes a processor coupled to a memory, the memory storing at least one computer program, the at least one computer program being loaded and executed by the processor to enable the computer device to implement a BIM-based rapid modeling and layout method for construction site layout as described in any one of claims 1 to 4.

10. A computer-readable storage medium, characterized in that, The computer-readable storage medium stores at least one computer program, which is loaded and executed by a processor to enable the computer to implement a BIM-based rapid modeling and layout method for construction site layout as described in any one of claims 1 to 4.