A method and system for aggregated calculation of all resources at the process level for complex electronic product production planning in a multi-level production environment
By automating the division of process stages and performing multi-dimensional resource collaborative calculations, the difficulties in connecting resource data in multi-level planning management of the PBOM system have been resolved. This has enabled the conversion of resource requirements from the process level to the section level, improved the efficiency and accuracy of production planning, eliminated the subjectivity of manual division, and ensured the reproducibility and consistency of resource requirements.
Patent Information
- Application Number
- CN202611058208.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2026-07-16
- Publication Date
- 2026-11-17
AI Technical Summary
The existing PBOM system, when supporting macro-level planning management such as monthly and weekly plans, has excessively fine-grained process-level resource requirement data, which cannot be directly adapted to weekly material pre-allocation and monthly capacity planning. It also lacks objective quantitative standards, and the decentralized calculation of resource requirements makes it difficult to connect resource data between multi-level plans.
By automating the division of process stages and coordinating the calculation of multi-dimensional resources, process-level resource requirements are automatically converted into section-level resource requirements. Unsupervised clustering is used to divide process stages, and the optimal number of stages is determined by combining the K-means clustering algorithm and the elbow rule. The actual shortest completion time of process stages is calculated using a graph traversal algorithm. Coordinative verification of resources such as instruments, personnel, and workstations and continuous comparison of material requirements are performed to form a unified section-level resource requirement view.
It enables automatic conversion of data granularity from process level to section level, improves the efficiency of multi-level planning, eliminates the subjectivity of manual division, ensures the reproducibility and consistency of resource requirements, reduces resource mismatch and conflict events, and improves the accuracy and coordination of production planning.
Smart Images

Figure CN123117584A_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the fields of manufacturing and information management technology, specifically to resource requirement calculation technology in the manufacturing process of complex electronic products, and more particularly to a method for aggregated calculation of all elements of resources at each process stage based on the Bill of Materials (PBOM). This application can be applied to multi-level production planning and overall management of manufacturing resources in enterprises manufacturing complex electronic equipment such as aerospace, aviation, radar, and communications. Background Technology
[0002] Complex electronic products (such as radar systems, communication equipment, and avionics equipment) are characterized by a wide variety of components, long process chains, and high technology intensity. Their production management typically employs a multi-level planning system of monthly, weekly, and daily plans. The Bill of Materials (BOM) is the core data system in manufacturing, and Chinese industrial enterprises mainly adopt a three-stage construction model: EBOM-PBOM-MBOM. The Process Bill of Materials (PBOM), based on the Engineering Design EBOM, integrates key elements such as process routes, process divisions, time quotas, and manufacturing resource allocation to form core process data guiding production. Currently, manufacturers of complex electronic products have largely achieved process data management based on PBOM at the process level. PBOM can provide minute-level process information to support the formulation of daily production plans.
[0003] However, the existing PBOM system has significant shortcomings in supporting macro-level planning management such as monthly and weekly plans. First, the granularity of process-level resource requirements data is too fine, making it unsuitable for macro-level control needs such as weekly material pre-allocation and monthly capacity planning. Data aggregation from the process level to the section level currently relies primarily on manual work, resulting in low efficiency and a lack of standardization. Second, existing technologies lack objective quantitative standards for process stage division, relying mainly on the subjective experience of process engineers, leading to significant differences in division results among different personnel and poor reproducibility. Third, manufacturing resource requirements such as instruments, personnel, workstations, and materials are scattered across different management departments, calculated separately without collaboration, making it difficult to form a unified section-level resource requirements view, thus hindering the connection of resource data between multi-level plans.
[0004] To address the aforementioned issues, existing technical solutions primarily focus on modeling and demand calculation for single resource types, or on optimization at the production scheduling level. However, none of these solutions systematically solve the problem of data granularity conversion from the process level to the work section level, nor do they achieve integrated calculation of all elements of multiple manufacturing resources. Therefore, this invention provides a method for aggregating and calculating all elements of resources at the process stage based on PBOM. Through automated division of process stages and collaborative calculation of multi-dimensional resources, process-level resource requirements are automatically converted into work section-level resource requirements. This effectively connects macro-strategic planning with micro-execution plans, improving the planning and control efficiency of multi-model mixed-line production systems. Summary of the Invention
[0005] The purpose of this invention is to provide a method and system for the aggregation and calculation of all resources at the process stage for complex electronic products, oriented towards multi-level production planning. This aims to overcome the problem that process data at the process stage for complex electronic products cannot meet the varying requirements of different levels of planning management regarding product and manufacturing resource content and granularity, resulting in poor continuity between different levels. This method can divide process stages according to process characteristics, achieve integration of process-level manufacturing resources, improve the multi-level production planning management capabilities of the workshop, and ensure the orderly control of complex electronic product production activities.
[0006] The technical solution of the present invention is as follows: A method for aggregated calculation of all resources at the process level for complex electronic products in multi-level production planning includes the following steps: Step 1: Obtain the PBOM information of the specified complex electronic product. The PBOM information includes process information, process method, personnel requirements, material requirements, instrument requirements, workstation requirements, and working hours. Step 2: Based on the process name and process overview information in the PBOM, the process is divided into process stages using an unsupervised clustering method, and the process stages are named. Step 3: Calculate the instrument requirements for each process stage based on the PBOM instrument requirements and the mapping relationship between processes and process stages; Step 4: Calculate the station requirements for each process stage based on the PBOM station requirements and the mapping relationship between processes and process stages; Step 5: Calculate the personnel requirements for each process stage based on the personnel requirements in the PBOM and the mapping relationship between processes and process stages; Step 6: Calculate the material requirements for each process stage based on the PBOM material requirements and the mapping relationship between processes and process stages; Step 7: Calculate the time for each process stage based on the PBOM time and the mapping relationship between processes and process stages.
[0007] Addressing the core deficiency of the mismatch between process-level data granularity and macro-level planning management needs as pointed out in the background technology, this paper achieves fully automated resource aggregation from the process level to the section level within a unified computing framework. This enables the connection between monthly, weekly, and daily plans, making it possible to link macro-strategic planning with micro-level execution plans. At the same time, the five types of resources are calculated based on the same data source and unified classification results, laying a data consistency foundation for subsequent collaborative verification.
[0008] Furthermore, step 2 specifically includes: Step 21: Obtain the process information set from the PBOM, for each process. It includes the process name, process overview, set of preceding processes, set of following processes, and process method type; Step 22: Construct a multi-dimensional feature vector for each process. The multi-dimensional feature vector includes: features based on the process name and process overview. The semantic features extracted by the method, the topological features formed by the in-degree and out-degree calculated based on the relationship between the preceding and following processes, and the resource complexity features formed by the number of instrument types, workstation types, and personnel roles associated with the process. Step 23: Normalize the semantic features, topological structure features, and resource complexity features, then concatenate them to form a multi-dimensional feature vector for each process. ; Step 24: Use the K-means clustering algorithm to cluster the multidimensional feature vectors of all processes, and the number of clusters is... Determined using the elbow rule; Step 25: For each cluster, name the stages according to the common characteristics of the processes within the cluster, and output the mapping relationship between processes and process stages. ,in For process sequence number, This refers to the process stage number.
[0009] To address the issues raised in the background technology regarding the reliance on manual experience and lack of objective quantitative standards in process stage division, this invention achieves data-driven and reproducible standardized stage division, fundamentally eliminating the subjectivity of manual division and the differences in results due to individual variations, enabling the same product to obtain completely consistent division results at different times and under different operators.
[0010] To address the issue raised in the background technology that the process-level resource aggregation is simply accumulated and fails to fully consider the parallel relationships between processes, a graph traversal algorithm is used to accurately calculate the actual shortest completion time of each process stage in terms of time sequence. This avoids the overestimation of time caused by simply adding up the process cycles, and provides a more accurate and realistic time benchmark for production planning and scheduling.
[0011] Furthermore, step 7 specifically includes: Step 71: Initialize process stage number ; Step 72: Obtain the process stage All process sets And the instrument working hours, cycle time, and man-hours of this process; Step 73: Sum the instrument working hours, cycle time, and man-hours for this section. Step 74: Construct process stages based on the process pre- and post-process relationships in the PBOM. Directed acyclic graph ,in For the stage All process nodes within, Dependency edges between processes; identification stage The set of initial processes within That is, all the preceding processes are not in the stage. Internal processes; Step 75: For each starting process ,by Starting from the first position, a depth-first search is used for traversal. All from For each reachable process node, record the sum of the process cycles on each traversal path, and take the maximum time among all paths as the process stage. Critical path cycle; Step 76: Process Stage Number Determine whether the calculation of all process stages has been completed. If it has, end the process; otherwise, return to sub-step 72.
[0012] To address the issues raised in the background technology, such as the dispersed calculation and lack of collaboration in the demand for manufacturing resources like instruments, personnel, and workstations, which makes it difficult to form a unified resource demand view, a spatial constraint verification mechanism is used to ensure the matching and compatibility between the number of instruments, personnel, and workstation capacity. This effectively avoids resource mismatches such as "having instruments but no workstations" or "having workstations but no personnel" in the traditional distributed computing model.
[0013] Furthermore, after calculating the number of instruments, workstations, and personnel for each process stage in steps 3, 4, and 5 respectively, resource collaboration verification is also included: For each process stage To obtain the set of instruments required for this stage. Workstation Collection and personnel role set ; Construct the resource-space occupancy matrix for this stage Each row corresponds to a workstation type, and each column corresponds to an instrument type or personnel role. Matrix elements Indicates the workstation type Simultaneous use of instruments / personnel types Maximum concurrency; If workstation type exists The number of instruments and personnel used simultaneously at that workstation exceeds its physical capacity. ,Right now If this is the case, resource quantity adjustment will be triggered: according to the priority of instruments first and personnel second, the number of workstations will be increased or the process stages will be split until the space capacity constraint is met.
[0014] To address the issue raised in the background section that the existing PBOM system is unable to support the pre-allocation requirements of weekly planning materials, this paper effectively identifies abnormal breakpoints in material requirements caused by stage division by comparing the continuity of material requirements between adjacent stages, ensuring the continuity and integrity of material requirements between process stages, and providing reliable data support for the pre-allocation of weekly planning materials.
[0015] Furthermore, after calculating the material requirements in step 6, the process also includes verifying the continuity of material requirements across different stages: For adjacent process stages and Compare the material requirements sets of the two sets, if the material type In the stage There is demand in the middle, at the stage If there is no demand, then mark the material as being in the appropriate stage. This will cause intermittent supply disruptions and trigger an early warning.
[0016] Furthermore, step 3 specifically includes: Step 31: Initialize process stage number ; Step 32: Obtain the process stage All processes And all the instrument requirements for this process; Step 33: Deduplicate the instrument requirements by instrument type to obtain the instrument set. ; Step 34: Obtain the process set Instrument working hours for each process Calculate the instrument working hours for this section. ; Step 35: Assign instrument type , Screen the set of processes that require this type of instrument. Calculate the instrument working hours of this set. ; Step 36: Calculate the type of instrument The percentage of time within the segment is ; Step 37: Calculate the instrument type according to the following formula. Number of instruments:
[0017] in Planned operating time indicates the estimated daily operating duration for this type of instrument; For operational efficiency, this data is based on historical statistics. For the planned number of days, , This refers to the daily working hours. Step 38: Process Stage Number Determine whether the instrument requirements calculation for all process stages has been completed. If completed, proceed to step 4; otherwise, return to sub-step 32.
[0018] Furthermore, step 5 specifically includes: Step 51: Initialize process stage sequence number ; Step 52: Obtain the process stage All processes And the total personnel requirements for this process; Step 53: Deduplicate personnel requirements by role to obtain the personnel set. ; Step 54: Obtain the process set Work hours of personnel in each process Calculate the working hours of the workers in this section. ; Step 55: Assign roles to personnel , Filter the set of processes that require this person's role. Calculate the employee hours of this set. ; Step 56: Calculate personnel roles The percentage of time within the segment is ; Step 57: Calculate personnel roles according to the following formula Number of personnel:
[0019] in The planned operating time indicates the daily shift duration for personnel; For operational efficiency, this data is based on historical statistics. For the planned number of days, , This refers to the daily working hours. Step 58: Process Stage Number Determine whether the personnel requirements calculation for all process stages has been completed. If completed, proceed to step 6; otherwise, return to sub-step 52.
[0020] Furthermore, step 4 specifically includes: Step 41: Initialize process stage number ; Step 42: Obtain the process stage All processes and the total workstation requirements for this process set; Step 43: Deduplicate the workstation requirements by workstation type to obtain a set of workstations. ; Step 44: Obtain the process set Cycle of each process Calculate the cycle time of this section. ; Step 45: Assign workstation type , Filter the set of processes that require this workstation type. Calculate the period of the set. ; Step 46: Calculate the workstation type The percentage of time within the segment is ; Step 47: Calculate the workstation type The number of workstations is ; Step 48: Process Stage Number Determine whether the workstation requirements for all process stages have been calculated. If so, proceed to step 5; otherwise, return to sub-step 42.
[0021] Furthermore, step 6 specifically includes: Step 61: Initialize process stage number ; Step 62: Obtain the process stage All process sets and all material requirements for this process; Step 63: Deduplicate materials according to material type to obtain the material collection. ; Step 64: According to material type Select the processes that require this material, and calculate the quantity of this type of material. ; Step 65: Determine if there is a demand for this type of material before this process stage. If there is, mark the material as no; if not, mark it as yes. Step 66: Process Stage Number Determine whether the calculation of all process stages has been completed. If it has, proceed to step 7; otherwise, return to sub-step 62.
[0022] In response to the problem mentioned in the background technology that the various manufacturing resource requirements are calculated separately by different management departments, the above method reflects that the calculation of the four types of resources is based on a unified PBOM data source and a unified process-stage mapping relationship, which ensures the comparability, consistency and composability of the calculation results of various resources, and provides a data foundation for the subsequent formation of a unified section-level resource requirement view.
[0023] This application also includes a complex electronic product section-level full resource aggregation calculation system for multi-level production planning, and implements a method for complex electronic product section-level full resource aggregation calculation for multi-level production planning, including: The data acquisition module is used to acquire the PBOM information of a specified model of complex electronic product; The process stage segmentation module is used to divide processes into the same process stage based on PBOM process information using an unsupervised clustering method. The instrument requirement calculation module is used to calculate the instrument requirements for each process stage based on the PBOM instrument requirements and the mapping relationship between processes and process stages. The workstation requirement calculation module is used to calculate the workstation requirements for each process stage based on the PBOM workstation requirements and the mapping relationship between processes and process stages. The personnel requirement calculation module is used to calculate the personnel requirements for each process stage based on the personnel requirements in the PBOM and the mapping relationship between processes and process stages. The Material Requirements Calculation module is used to calculate the material requirements for each process stage based on the PBOM material requirements and the mapping relationship between processes and process stages. The time calculation module is used to calculate the time for each process stage based on the PBOM time and the mapping relationship between processes and process stages; The output module is used to output the resource requirements data for each process stage, including five categories: instruments, workstations, personnel, materials, and working hours.
[0024] Compared with existing technologies, the advantages of this invention are: 1. This application enables automatic conversion of data granularity from the process level to the section level, eliminating barriers to multi-level planning. Through automatic process segmentation and automated resource aggregation calculation, minute-level resource data scattered across dozens or even hundreds of processes is automatically integrated into section-level resource requirement data in five categories: instruments, workstations, personnel, materials, and working hours. This directly meets the data requirements for monthly planned capacity planning and weekly planned material pre-allocation, achieving data connectivity between multi-level plans. In a practical application in a workshop of a complex electronic product manufacturing enterprise, section resource calculations for over 3,000 sets of products across 5 models were completed. The calculation time per set of products decreased from approximately 4.5 hours manually to 0.8 hours, an efficiency improvement of approximately 82%. Monthly plan preparation time was shortened from an average of 3 days to 1 day, and weekly planned material pre-allocation time was shortened from an average of 8 hours to 2 hours, resulting in an overall improvement of approximately 65% in multi-level plan preparation efficiency.
[0025] 2. Achieving standardization and reproducibility in process stage division, eliminating reliance on manual experience. This application constructs multi-dimensional feature vectors for each process and automatically determines the optimal number of stages using the K-means clustering algorithm and the elbow rule, achieving data-driven and standardized process stage division. Taking product K0001 as an example, this application automatically divides 13 processes into four stages: "assembly, commissioning, testing, and acceptance," which is completely consistent with the division results independently reviewed by three senior process experts (100% overlap of stage boundaries), proving the objectivity and accuracy of the division results. For the same product model, the division results are completely consistent when the method is run by different operators at different times (100% reproducibility), fundamentally eliminating the problems of inconsistent and unstandardized traditional manual division, and providing a standardized data foundation for horizontal comparison and unified scheduling of resource requirements among multiple product models.
[0026] 3. Achieve integrated collaborative computing for multiple types of manufacturing resources, eliminating information silos. This application uses the same PBOM data and process stage mapping relationships for calculations at the data source level, ensuring comparability and consistency of results for the five resource categories. At the spatial level, collaborative verification is performed through a resource-space occupancy matrix to ensure that the number of instruments, personnel, and workstations matches and is compatible in terms of physical capacity (this mechanism increases the rate of resource requirement schemes passing on-site review from approximately 65% to approximately 95%). At the temporal level, the critical path cycle is fed back to the calculation of instrument and personnel numbers, dynamically configuring redundant resources based on process parallelism. These collaborative mechanisms enable this application to output complete section-level resource requirement data packages for the five categories at once, overcoming the resource mismatch problem caused by information silos in traditional decentralized management models. Actual verification shows that the output resource requirement scheme achieves 100% consistency in type with the results of human expert review, and a consistency rate of over 86% in quantity. The differences are verified in actual production to be better redundant configuration schemes.
[0027] 4. The above effects are superimposed and enhanced through a closed-loop mechanism of "division → calculation → feedback". The process stage is automatically divided into multi-resource calculations, providing a unified aggregation unit. Multi-resource collaborative verification ensures the engineering rationality of various resource allocation ratios. Periodic feedback on the critical path optimizes resource quantity allocation. These three elements work together to systematically solve all the defects pointed out in the background technology from three dimensions: data granularity transformation, division standardization, and resource collaboration. Practical application verification shows that, while ensuring calculation accuracy, this application reduces the occurrence rate of resource conflict events in multi-model mixed-line production scenarios by approximately 40%, effectively verifying the feasibility and practicality of this application in actual production environments. Attached Figure Description
[0028] Figure 1 This is a flowchart of the resource calculation method for the process stage in this application.
[0029] Figure 2 This is a flowchart illustrating the method for calculating instrument requirements at each process stage in this application.
[0030] Figure 3 This is a flowchart illustrating the method for calculating the workstation requirements at each process stage in this application.
[0031] Figure 4 This is a flowchart illustrating the method for calculating personnel requirements at each process stage in this application.
[0032] Figure 5 This is a flowchart illustrating the material requirements calculation method for each process stage in this application.
[0033] Figure 6 This is a flowchart illustrating the method for calculating the time required for each process stage in this application. Detailed Implementation
[0034] It should be noted that relational terms such as "first" and "second" are used merely to distinguish one entity or operation from another, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Furthermore, the terms "comprising," "including," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements includes not only those elements but also other elements not expressly listed, or elements inherent to such a process, method, article, or apparatus. Without further limitations, an element defined by the phrase "comprising one..." does not exclude the presence of other identical elements in the process, method, article, or apparatus that includes said element.
[0035] The features and performance of the present invention will be further described in detail below with reference to embodiments.
[0036] Please see Figure 1-6 A method for aggregated calculation of all resources at the process level for complex electronic product production planning, oriented towards multi-level production planning, such as... Figure 1 As shown, it includes the following steps: Step 1: Data Acquisition. For a specific model of complex electronic product, acquire the product PBOM information. The PBOM information includes process information, process method, personnel requirements, material requirements, instrument requirements, workstation requirements, and working hours. Step 2: Process Stage Division. Based on the process names and process overview information in the PBOM, unsupervised clustering methods are used to group similar processes into the same process stage, and the process stages are named; specifically, this includes the following steps: Step 21: For a specific model of complex electronic product, obtain the process information set from the PBOM, including each process. This includes the process name, process overview, set of preceding processes, set of following processes, process method type, and material flow characteristic attribute information; Step 22: Construct a multi-dimensional feature vector for each process. Specifically: preprocess the process name and overview text, and extract the text feature vector of the process using the TF-IDF method as the semantic feature of the process; calculate the in-degree and out-degree of each process based on the relationship between the preceding and succeeding processes, and construct the topological position feature of the process in the process network as the structural feature of the process; count the number of instrument types, workstation types, and personnel roles associated with each process to construct the resource complexity feature of the process; and then normalize and concatenate the above semantic features, structural features, and resource complexity features to form the multi-dimensional feature vector of each process.
[0037] Step 23: Use the K-means clustering algorithm to cluster the multidimensional feature vectors of all processes, and the number of clusters is... The elbow rule is used to determine the position. Step 24: For each cluster, name the stage according to the common characteristics of the processes within the cluster. Use the most frequent process method type as the main process feature of the stage, and generate the stage name by combining the process sequence number range of the stage.
[0038] Step 25: Output the mapping relationship between the process and the process stage. ,in, For process sequence number, This refers to the process stage number.
[0039] Step 3: Calculate the instrument requirements for each process stage. Based on the PBOM instrument requirements and the mapping relationship between processes and process stages, calculate the instrument requirements for each process stage. (See Appendix) Figure 2 Specifically, it includes the following steps: Step 31: Initialize process stage number ; Step 32: Obtain the process stage All processes And all the instrument requirements for this process; Step 33: Deduplicate the instrument requirements by instrument type to obtain the instrument set. ; Step 34: Obtain the process set Instrument working hours for each process Calculate the instrument working hours for this section. ; Step 35: Assign instrument type Screening the set of procedures required for the instrument Calculate the instrument working hours of this set. ; Step 36: Calculate the type of instrument The percentage of time within the segment is ; Step 37: Calculate the instrument type using the capacity model. Number of instruments:
[0040] in, Planned operating time indicates the estimated daily operating duration for this type of instrument; For operational efficiency, this data is based on historical statistics. For the planned number of days, , This refers to the daily working hours.
[0041] Step 38: Process Stage Number Determine whether the instrument requirements calculation for all process stages has been completed. If completed, proceed to step 4; otherwise, proceed to step 32. Step 4: Calculate the workstation requirements for each process stage. Based on the PBOM workstation requirements and the mapping relationship between processes and process stages, calculate the workstation requirements for each process stage. (See Appendix) Figure 3 Specifically, it includes the following steps: Step 41: Initialize process stage number ; Step 42: Obtain the process stage All processes and the total workstation requirements for this process set; Step 43: Deduplicate the workstation requirements by workstation type to obtain a set of workstations. ; Step 44: Obtain the process set Cycle of each process Calculate the cycle time of this section. ; Step 45: Assign workstation type Filter the set of processes required for this workstation. Calculate the period of the set. ; Step 46: Calculate the workstation type The percentage of time within the segment is ; Step 47: Calculate the workstation type The number of workstations is ; Step 48: Process Stage Number Determine whether the workstation requirements calculation for all process stages has been completed. If completed, proceed to step 5; otherwise, proceed to step 42. Step 5: Calculate personnel requirements for each process stage. Based on the personnel requirements in the PBOM and the mapping relationship between processes and process stages, calculate the personnel requirements for each process stage. (See appendix) Figure 3 Specifically, it includes the following steps: Step 51: Initialize process stage sequence number ; Step 52: Obtain the process stage All processes And the total personnel requirements for this process; Step 53: Deduplicate personnel requirements by role to obtain the personnel set. ; Step 54: Obtain the process set Work hours of personnel in each process Calculate the working hours of the workers in this section. ; Step 55: Assign roles to personnel Filter the set of processes required for this person. Calculate the employee hours of this set. ; Step 56: Calculate personnel roles The percentage of time within the segment is ; Step 57: Calculate personnel roles using the capacity model Number of personnel:
[0042] in, The planned operating time indicates the daily shift duration for personnel. For operational efficiency, this was determined based on historical data statistics. For the planned number of days, , This refers to the daily working hours.
[0043] Step 58: Process Stage Number Determine whether the personnel requirements calculation for all process stages has been completed. If completed, proceed to step 6; otherwise, proceed to step 52. Step 6: Calculate Material Requirements for Each Process Stage. Based on the PBOM material requirements and the mapping relationship between processes and process stages, calculate the material requirements for each process stage. (See Appendix) Figure 4 Specifically, it includes the following steps: Step 61: Initialize process stage number ; Step 62: Obtain the process stage All process sets and all material requirements for this process; Step 63: Deduplicate materials according to material type to obtain the material collection. ; Step 64: According to material type Select the processes that require this material, and calculate the quantity of this type of material. ; Step 65: Determine if there is a demand for this type of material before this process segment. If it exists, then the material addition requirement is set to "No"; if it does not exist, then the material addition requirement is set to "Yes". Step 66: Process Stage Number Determine whether the calculation of all process stages has been completed. If completed, proceed to step 7; otherwise, proceed to step 62. Step 7: Calculate the time required for each process stage. Based on the PBOM time and the mapping relationship between processes and process stages, calculate the time required for each process stage. (See appendix) Figure 5 Specifically, it includes the following steps: Step 71: Initialize process stage number ; Step 72: Obtain the process stage All process sets And the instrument working hours, cycle time, and man-hours of this process; Step 73: Sum the instrument working hours, cycle time, and man-hours for each work section; Step 74: Construct process stages based on the process pre- and post-process relationships in the PBOM. Directed acyclic graph ,in For the stage All process nodes within, Dependency edges between processes; identification stage The set of initial processes within That is, all the preceding processes are not in the stage. The internal processes.
[0044] Step 75: For each starting process ,by Starting from the first position, a depth-first search is used for traversal. All from For each reachable process node, record the sum of the process cycles along each traversal path to obtain the path time corresponding to that starting process; take the maximum value among all path times corresponding to all starting processes as the process stage. Critical path cycle.
[0045] Step 76: Process Stage Number Determine whether the calculation of all process stages has been completed. If it has, end the calculation; otherwise, proceed to step 72.
[0046] After calculating the number of instruments, workstations, and personnel in steps 3, 4, and 5 respectively, resource collaboration verification is also included: For each process stage To obtain the set of instruments required for this stage. Workstation Collection Personnel Roles Construct the resource-space occupancy matrix for this stage. Each row corresponds to a workstation type, and each column corresponds to an instrument type or personnel role. Matrix elements Indicates the workstation type Simultaneous use of instruments / personnel types Maximum concurrency; if a certain workstation type exists The number of instruments and personnel used simultaneously at that workstation exceeds its physical capacity. ,Right now If this is not the case, the resource quantity will be adjusted. The number of workstations will be increased or the process stages will be split according to the priority of instruments first and personnel second, until the space capacity constraint is met.
[0047] After calculating material requirements in step 6, the process also includes a step to verify the continuity of material requirements across different phases. For adjacent process stages and Compare the material requirements sets of the two sets, if the material type In the stage There is demand in the middle, at the stage If there is no demand, then mark the material as being in the appropriate stage. The "intermittent supply disruption" triggered an early warning.
[0048] After calculating the critical path cycle for each process stage in step 7, the process also includes a feedback adjustment step on the critical path's resource quantity: For each process stage Compare its critical path cycle With the work section cycle ,like ,in The preset parallelism threshold has a range of values. This indicates that the parallelism of processes is high in this stage. Therefore, based on the number of instruments calculated in step 37, additional spare instruments are added according to the superposition of instrument requirements in parallel processes; based on the number of personnel calculated in step 57, additional spare personnel are added according to the superposition of personnel requirements in parallel processes.
[0049] The steps in this application are not simply connected in a "pipeline" manner, but rather form a closed-loop collaborative mechanism of "division → calculation → feedback," specifically manifested as follows: Synergistic effect 1: The process stage is divided into multi-resource computing to provide a unified aggregation unit.
[0050] Step 2 output process-stage mapping relationship It serves as the common input for all subsequent resource calculation steps (3-7). Compared to the existing technology where each resource is calculated based on different aggregation rules, this application ensures that the five types of resources—instruments, workstations, personnel, materials, and working hours—are aggregated at the same granularity through a unified process stage division result. This makes the calculation results of each resource comparable and combinable, providing a data foundation for subsequent multi-resource collaborative scheduling.
[0051] Synergistic effect 2: Multi-resource collaborative verification ensures the engineering rationality of resource allocation.
[0052] The resource calculations in steps 3-6 are not completed independently, but rather are mutually constrained by spatial coupling constraints (capacity matching of instruments, workstations, and personnel) and inter-stage continuity constraints (cross-stage connection of material requirements). This calculation paradigm of "independent calculation → collaborative verification → coordinated adjustment" ensures that the final output resource requirement plan achieves a reasonable engineering state of quantity matching, spatial compatibility, and temporal consistency among various resources, avoiding configuration conflicts caused by separate calculations of various resources in traditional methods.
[0053] Synergistic effect three: Critical path periodic feedback optimizes resource allocation.
[0054] The critical path cycle calculated in step 7 not only serves as the time output but also feeds back into the calculations of steps 3 (number of instruments) and 5 (number of personnel), dynamically adjusting the redundancy configuration of instruments and personnel based on the parallelism of the process stages. This two-way coupling mechanism of "time → resources" upgrades resource quantity calculation from static time aggregation to dynamic parallel-aware configuration, significantly improving the accuracy of resource requirement calculation.
[0055] Synergistic Effect 4: Integrated computing across all elements eliminates information silos.
[0056] In existing technologies, instruments, personnel, workstations, materials, and working hours are typically managed and calculated separately by different departments (equipment management, human resources, process, logistics, etc.), resulting in inconsistent data formats and asynchronous updates, creating information silos. This application, based on a unified PBOM data source and unified process stage division results, completes the synchronous calculation and collaborative verification of five types of resources within the same computing framework, outputting a complete section-level resource requirement data package in one go, thus eliminating information barriers between multiple departments at the data level.
[0057] This application also provides a complex electronic product process-level full resource aggregation calculation system for multi-level production planning, including: a data acquisition module for acquiring PBOM information of a specified model of complex electronic product; a process stage division module for dividing similar processes into the same process stage based on PBOM process information using an unsupervised clustering method; an instrument requirement calculation module for calculating the instrument requirement of the process stage based on PBOM instrument requirements and the mapping relationship between processes and process stages; a workstation requirement calculation module for calculating the workstation requirement of the process stage based on PBOM workstation requirements and the mapping relationship between processes and process stages; a personnel requirement calculation module for calculating the personnel requirement of the process stage based on PBOM personnel requirements and the mapping relationship between processes and process stages; a material requirement calculation module for calculating the material requirement of the process stage based on PBOM material requirements and the mapping relationship between processes and process stages; a time calculation module for calculating the time of the process stage based on PBOM time and the mapping relationship between processes and process stages; and an output module for outputting the resource requirement data of five categories: instruments, workstations, personnel, materials, and time for each process stage.
[0058] This implementation example discloses a process resource calculation method used in a workshop of a complex electronic product manufacturing company. The specific steps of the process stage resource calculation method performed in this implementation example are as follows: Step 1: Obtain the PBOM information for product model K0001; Obtain the PBOM information for product model K0001, including the process method table, instrument requirements table, workstation requirements table, personnel requirements table, material requirements table, and time table. The process method table for product K0001 is shown in Table 1, which contains the sequence number, name, preceding process, and following process information for 13 processes.
[0059] Table 1. Processing Method for Product K0001
[0060] Table 2 shows the instrument requirements for product K0001, which records the types and quantities of instruments required for each process.
[0061] Table 2 Instrument Requirements Table
[0062] Table 3 shows the workstation requirements for product K0001, which records the type and quantity of workstations required for each process.
[0063] Table 3 Workstation Requirements
[0064] The personnel requirements table for product K0001 is shown in Table 4, which records the personnel roles and quantities required for each process.
[0065] Table 4 Personnel Requirements
[0066] The material requirements table for product K0001 is shown in Table 5, which records the names and quantities of materials required for each process.
[0067] Table 5 Material Requirements Table
[0068] The timetable for product K0001 is shown in Table 6, which records the cycle, man-hours, and instrument-hours for each process.
[0069] Table 6 Hourly Schedule
[0070] Step 2: Divide the process into stages; Based on PBOM information, K-means clustering is used to group similar processes into the same process stage; the specific implementation is as follows: First, a multi-dimensional feature vector is constructed for each of the 13 processes. Taking process 4, "Debugging," as an example: its semantic features are obtained by TF-IDF extraction of "Debugging" and related process overviews; its structural features are in-degree 2 (preceding processes 2 and 3) and out-degree 1 (following process 5); its resource features are 3 types of instruments (instrument system a, board, electrical instrument), 1 type of workstation (unit debugging), and 1 type of personnel role (debugging personnel). After normalizing the above three types of features, they are concatenated to form the multi-dimensional feature vector of process 4.
[0071] Then, K-means clustering was performed on the feature vectors of all 13 processes. The elbow rule was used to determine the optimal number of clusters. :calculate to The sum of squared errors within the cluster at time, when The downward trend of SSE changed from steep to gentle, therefore, we selected... As the optimal number of clusters.
[0072] After clustering, each cluster was named as a stage. The clustering results are shown in Table 7: Processes 1, 2, and 3 were grouped into the same cluster, with the "assembly" process method appearing most frequently within the cluster, and were named the "assembly" stage; Processes 4, 5, 6, and 7 were grouped into the same cluster, with "debugging," "joint testing," and "testing" processes appearing most frequently within the cluster, and were named the "debugging and testing" stage; Processes 8, 9, and 10 were grouped into the same cluster, with all processes being experimental, and were named the "experiment" stage; Processes 11, 12, and 13 were grouped into the same cluster, with all processes being acceptance-related, and were named the "acceptance" stage. The process stage division results are shown in Table 7.
[0073] Table 7 Results of Process Stage Division
[0074] After comparison with the independent review results of three senior process experts, the above automatic classification results have a 100% consistency rate with the experts.
[0075] Step 3: Calculate the instrument requirements for each process stage.
[0076] Taking process stage 2, "adjustment and testing," as an example, the calculation process for instrument requirements is explained in detail.
[0077] Obtain all processes in process stage 2 And all the instrument requirements for this process.
[0078] The instrument requirements are deduplicated according to instrument type to obtain the instrument set. .
[0079] Obtain the instrument working hours for each process (from Table 6): , , , Calculate the instrument working hours for this section. Hours. Planned number of days. sky.
[0080] Taking instrument type "instrument system a" as an example, filter the set of processes that require this instrument type. Calculate the instrument working hours of this set. Hour, percentage of time within a segment .
[0081] Calculate the number of instruments using a capacity model. Planned operating time. Hours / day, operating efficiency Historical data shows a value of 0.3. Number of instruments tower.
[0082] Similarly, calculate the required quantity of each instrument type. The calculated instrument working hours for each stage of the process are shown in Table 8. Table 8 Work Hour Schedule for Work Section
[0083] The calculation results of the equipment requirements for the work section are shown in Table 9.
[0084] Table 9: Instrument Requirements for Work Section
[0085] Step 4: Calculate the workstation requirements for each process stage; Taking process stage 2, "adjustment and testing," as an example, the calculation process for workstation requirements is explained in detail.
[0086] Obtain all processes in process stage 2 And the requirements for all workstations in this process set.
[0087] The workstation requirements are deduplicated according to workstation type to obtain a workstation set. .
[0088] Obtain the cycle time for each process (from Table 6): , , , Calculate the cycle time for this section. Hour.
[0089] Taking the workstation type "adjustment and testing" as an example, filter the set of processes that require this workstation type. Calculate the period of the set. Hour, percentage of time within a segment .
[0090] The number of workstations of type "Debugging" is calculated as follows: indivual.
[0091] The calculation results for each workstation type are shown in Table 11. The calculation results for the instrument working hours of each process stage are shown in Table 10.
[0092] Table 10: Work Section Cycle Table
[0093] Table 11 Workstation Requirements for Each Section
[0094] Step 5: Calculate the personnel requirements for each process stage; Taking process stage 2, "adjustment and testing," as an example, the process of calculating personnel requirements is explained in detail.
[0095] Obtain all processes in process stage 2 And the total personnel requirements for this process.
[0096] The personnel requirements are deduplicated according to personnel roles to obtain the personnel set. {Debugging personnel, testing personnel, inspection personnel}.
[0097] Obtain the work hours of each process (from Table 6): , , , Calculate the man-hours for this work section. Hour.
[0098] Taking the personnel role "tester" as an example, the set of work processes that require this personnel role is selected. Calculate the employee hours of this set. Hour, percentage of time within a segment .
[0099] Calculate the number of personnel using a capacity model. Planned run time. Hours / day, operating efficiency Based on historical data, the figure is 0.2. (Number of personnel) The calculation results for each personnel role are shown in Table 13. The work hours of each section personnel are shown in Table 12.
[0100] Table 12 Work Hour Schedule for Section 12
[0101] Table 13: Personnel Requirements for Work Section
[0102] Step 6: Calculate material requirements for each process stage; Taking process stage 1, "assembly," as an example, the material requirements calculation process is explained in detail.
[0103] Obtain all processes in process stage 1 And all material requirements for this process.
[0104] Sub-step S63: Deduplicate materials according to their type to obtain a material set. {Module 1, Module 2, Module 3}.
[0105] Filter the set of processes that have a requirement for the material according to the material type "Module 1". Calculate the quantity of this type of material. indivual.
[0106] Since this process is in stage 1, there were no material requirements prior to this stage, so all three materials are newly added.
[0107] The material requirements calculation results for each process stage are shown in Table 14.
[0108] Table 14 Material Requirements for Section 14
[0109] Step 7: Calculate the time required for each process stage; Taking process stage 2, "adjustment and testing," as an example, the process of calculating working hours is explained in detail.
[0110] Obtain all processes in process stage 2 And the instrument working hours, cycle, and manpower working hours of this process.
[0111] Summing them up, we get the instrument working hours for the section as 0.5 + 1 + 0.5 + 2 = 4 hours, the cycle as 0.5 + 1 + 0.5 + 2 = 4 hours, and the personnel working hours as 0.5 + 1 + 0.5 + 2 = 4 hours.
[0112] Based on the pre- and post-process relationships in Table 1, a directed acyclic graph (DAG) of process stage 2 is constructed. Within stage 2, the post-process of process 4 is 5, the post-process of process 5 is 6, and the post-process of process 6 is 7, forming a chain structure 4→5→6→7. The starting process set is identified: the pre-processes of process 4 are 2 and 3, neither of which are within stage 2. .
[0113] Starting from step 4, a depth-first search is used to traverse all reachable nodes. The unique path is 4→5→6→7, and the path time is 0.5+1+0.5+2=4 hours, which is the critical path cycle for this stage.
[0114] The time calculation results for each process stage are shown in Table 15.
[0115] Table 15 Work Hour Schedule for Work Section
[0116] Resource collaboration verification: After calculating each of the above-mentioned resources separately, a resource collaboration verification is performed. Taking process stage 2, "Adjustment and Testing," as an example: Construct the resource-space occupancy matrix for this phase. This phase involves 4 workstation types (unit commissioning, commissioning, shape and quality measurement, and dedicated room), 9 instrument types, and 3 personnel roles. Verification showed that the "dedicated room" workstation type, simultaneously using 1 dedicated system instrument, 1 antenna, 1 power amplifier, 2 testing personnel, and 1 inspection personnel, totaling 3 devices and 3 personnel, did not exceed the physical capacity of the workstation (calculated based on the workstation area, accommodating no more than 8 units of equipment and personnel simultaneously), and thus passed the verification.
[0117] If the sum of the number of instruments and personnel used simultaneously at a certain workstation type exceeds the physical capacity of that workstation, a resource quantity adjustment is triggered. For example, if a workstation's physical capacity is to accommodate 4 units simultaneously, but calculations show that 3 instruments and 2 personnel (a total of 5 units) need to be placed at that workstation, an adjustment is triggered: prioritizing instruments over personnel, increasing the number of workstations or splitting related processes to other stages until the space capacity constraint is met.
[0118] Inter-stage continuity verification of material requirements: Taking material "Module 1" as an example, it has demand in stages 1, 2, 3, and 4, showing good continuity. Taking material "Rubber" as an example, it has demand in stage 3 but not in stages 2 and 4, so it is marked as newly added in stage 3, and the continuity verification passes (newly added materials do not require prior stages). Taking material "Cable 3" as an example, it has demand in stage 4 but not in stages 1, 2, and 3, so it is marked as newly added in stage 4, and the continuity verification passes.
[0119] If a certain material is in the stage There is demand in the middle, at the stage There is demand, but at this stage If there is no demand, then mark the material as being in the appropriate stage. The scenario of "intermittent supply disruption" triggers an alert, prompting process engineers to confirm whether any material requirements have been missed. This scenario did not occur in this embodiment.
[0120] The critical path adjusts the amount of resources accordingly: Taking process stage 3 "experimentation" as an example, its critical path cycle Hours, work cycle Hour, This indicates that the processes in this stage are sequential and have no parallel relationship, so no additional backup resources are needed.
[0121] Taking process stage 1 "assembly" as an example, its critical path cycle Hours, work cycle Hour, Preset parallelism threshold ,because This indicates that the parallelism at this stage is not high, and no additional backup resources are needed.
[0122] If the ratio of the critical path cycle to the work segment cycle in a certain stage is less than If the value is less than 0.5, it indicates that the parallelism of the processes is high in this stage. Based on the calculation results of the number of instruments and personnel, additional backup resources are added according to the superposition of resource requirements in the parallel processes to improve the robustness of the production system in response to plan fluctuations.
[0123] This embodiment illustrates the application effects of this application on different product models.
[0124] The method described in this application was applied to five complex electronic product models (K0001, K0002, K0003, K0004, and K0005), resulting in the completion of resource calculations for over 3,000 sets of products. The calculation time per set of products was reduced from approximately 4.5 hours using traditional manual operation to 0.8 hours, representing an efficiency improvement of approximately 82%. In one workshop, the monthly planning time was shortened from an average of 3 days to 1 day, and the weekly material pre-allocation time was reduced from an average of 8 hours to 2 hours, resulting in an overall efficiency improvement of approximately 65% in multi-level planning. The incidence of resource conflict events in multi-model mixed-line production scenarios was reduced by approximately 40%.
[0125] The embodiments described above merely illustrate specific implementation methods of this application, and while the descriptions are detailed and specific, they should not be construed as limiting the scope of protection of this application. It should be noted that those skilled in the art can make various modifications and improvements without departing from the concept of the technical solution of this application, and these modifications and improvements all fall within the scope of protection of this application.
Claims
1. A method for aggregated calculation of all resources at the process level for complex electronic products in multi-level production planning, characterized in that, Includes the following steps: Step 1: Obtain the PBOM information of the specified complex electronic product. The PBOM information includes process information, process method, personnel requirements, material requirements, instrument requirements, workstation requirements, and working hours. Step 2: Based on the process name and process overview information in the PBOM, the process is divided into process stages using an unsupervised clustering method, and the process stages are named. Step 3: Calculate the instrument requirements for each process stage based on the PBOM instrument requirements and the mapping relationship between processes and process stages; Step 4: Calculate the station requirements for each process stage based on the PBOM station requirements and the mapping relationship between processes and process stages; Step 5: Calculate the personnel requirements for each process stage based on the personnel requirements in the PBOM and the mapping relationship between processes and process stages; Step 6: Calculate the material requirements for each process stage based on the PBOM material requirements and the mapping relationship between processes and process stages; Step 7: Calculate the time for each process stage based on the PBOM time and the mapping relationship between processes and process stages.
2. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, Step 2 specifically includes: Step 21: Obtain the process information set from the PBOM, for each process. It includes the process name, process overview, set of preceding processes, set of following processes, and process method type; Step 22: Construct a multi-dimensional feature vector for each process. The multi-dimensional feature vector includes: features based on the process name and process overview. The semantic features extracted by the method, the topological features formed by the in-degree and out-degree calculated based on the relationship between the preceding and following processes, and the resource complexity features formed by the number of instrument types, workstation types, and personnel roles associated with the process. Step 23: Normalize the semantic features, topological structure features, and resource complexity features, then concatenate them to form a multi-dimensional feature vector for each process. ; Step 24: Use the K-means clustering algorithm to cluster the multidimensional feature vectors of all processes, and the number of clusters is... Determined using the elbow rule; Step 25: For each cluster, name the stages according to the common characteristics of the processes within the cluster, and output the mapping relationship between processes and process stages. ,in For process sequence number, This refers to the process stage number.
3. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, Step 7 specifically includes: Step 71: Initialize process stage number ; Step 72: Obtain the process stage All process sets And the instrument working hours, cycle time, and man-hours of this process; Step 73: Sum the instrument working hours, cycle time, and man-hours for this section. Step 74: Construct process stages based on the process pre- and post-process relationships in the PBOM. Directed acyclic graph ,in For the stage All process nodes within, Dependency edges between processes; identification stage The set of initial processes within That is, all the preceding processes are not in the stage. Internal processes; Step 75: For each starting process ,by Starting from the first position, a depth-first search is used for traversal. All from For each reachable process node, record the sum of the process cycles on each traversal path, and take the maximum time among all paths as the process stage. Critical path cycle; Step 76: Process Stage Number Determine whether the calculation of all process stages has been completed. If it has, end the process; otherwise, return to sub-step 72.
4. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, After calculating the number of instruments, workstations, and personnel for each process stage in steps 3, 4, and 5, resource collaboration verification is also included: For each process stage To obtain the set of instruments required for this stage. Workstation Collection and personnel role set ; Construct the resource-space occupancy matrix for this stage Each row corresponds to a workstation type, and each column corresponds to an instrument type or personnel role. Matrix elements Indicates the workstation type Simultaneous use of instruments / personnel types Maximum concurrency; If workstation type exists The number of instruments and personnel used simultaneously at that workstation exceeds its physical capacity. ,Right now If this is the case, resource quantity adjustment will be triggered: according to the priority of instruments first and personnel second, the number of workstations will be increased or the process stages will be split until the space capacity constraint is met.
5. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, After calculating the material requirements in step 6, the process also includes verifying the continuity of material requirements across different phases: For adjacent process stages and Compare the material requirements sets of the two sets, if the material type In the stage There is demand in the middle, at the stage If there is no demand, then mark the material as being in the appropriate stage. This will cause intermittent supply disruptions and trigger an early warning.
6. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, Step 3 specifically includes: Step 31: Initialize process stage number ; Step 32: Obtain the process stage All processes And all the instrument requirements for this process; Step 33: Deduplicate the instrument requirements by instrument type to obtain the instrument set. ; Step 34: Obtain the process set Instrument working hours for each process Calculate the instrument working hours for this section. ; Step 35: Assign instrument type , Screen the set of processes that require this type of instrument. Calculate the instrument working hours of this set. ; Step 36: Calculate the type of instrument The percentage of time within the segment is ; Step 37: Calculate the instrument type according to the following formula. Number of instruments: in Planned operating time indicates the estimated daily operating duration for this type of instrument; For operational efficiency, this data is based on historical statistics. For the planned number of days, , This refers to the daily working hours. Step 38: Process Stage Number Determine whether the instrument requirements calculation for all process stages has been completed. If completed, proceed to step 4; otherwise, return to sub-step 32.
7. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, Step 5 specifically includes: Step 51: Initialize process stage sequence number ; Step 52: Obtain the process stage All processes And the total personnel requirements for this process; Step 53: Deduplicate personnel requirements by role to obtain the personnel set. ; Step 54: Obtain the process set Work hours of personnel in each process Calculate the working hours of the workers in this section. ; Step 55: Assign roles to personnel , Filter the set of processes that require this person's role. Calculate the employee hours of this set. ; Step 56: Calculate personnel roles The percentage of time within the segment is ; Step 57: Calculate personnel roles according to the following formula Number of personnel: in The planned operating time indicates the daily shift duration for personnel; For operational efficiency, this data is based on historical statistics. For the planned number of days, , This refers to the daily working hours. Step 58: Process Stage Number Determine whether the personnel requirements calculation for all process stages has been completed. If completed, proceed to step 6; otherwise, return to sub-step 52.
8. The method for aggregated calculation of all resources at the section level for complex electronic products oriented towards multi-level production planning, as described in claim 1, is characterized in that... Step 4 specifically includes: Step 41: Initialize process stage number ; Step 42: Obtain the process stage All processes and the total workstation requirements for this process set; Step 43: Deduplicate the workstation requirements by workstation type to obtain a set of workstations. ; Step 44: Obtain the process set Cycle of each process Calculate the cycle time of this section. ; Step 45: Assign workstation type , Filter the set of processes that require this workstation type. Calculate the period of the set. ; Step 46: Calculate the workstation type The percentage of time within the segment is ; Step 47: Calculate the workstation type The number of workstations is ; Step 48: Process Stage Number Determine whether the workstation requirements for all process stages have been calculated. If so, proceed to step 5; otherwise, return to sub-step 42.
9. The method for calculating the full resource aggregation of complex electronic product production lines according to claim 1, characterized in that, Step 6 specifically includes: Step 61: Initialize process stage number ; Step 62: Obtain the process stage All process sets and all material requirements for this process; Step 63: Deduplicate materials according to material type to obtain the material collection. ; Step 64: According to material type Select the processes that require this material, and calculate the quantity of this type of material. ; Step 65: Determine if there is a demand for this type of material before this process stage. If there is, mark the material as no; if not, mark it as yes. Step 66: Process Stage Number Determine whether the calculation of all process stages has been completed. If it has, proceed to step 7; otherwise, return to sub-step 62.
10. A complex electronic product production line-level full resource aggregation computing system for multi-level production planning, characterized in that, Implementing the method for comprehensive resource aggregation calculation at the process level for complex electronic products oriented towards multi-level production planning as described in any one of claims 1-9, comprising: The data acquisition module is used to acquire the PBOM information of a specified model of complex electronic product; The process stage segmentation module is used to divide processes into the same process stage based on PBOM process information using an unsupervised clustering method. The instrument requirement calculation module is used to calculate the instrument requirements for each process stage based on the PBOM instrument requirements and the mapping relationship between processes and process stages. The workstation requirement calculation module is used to calculate the workstation requirements for each process stage based on the PBOM workstation requirements and the mapping relationship between processes and process stages. The personnel requirement calculation module is used to calculate the personnel requirements for each process stage based on the personnel requirements in the PBOM and the mapping relationship between processes and process stages. The Material Requirements Calculation module is used to calculate the material requirements for each process stage based on the PBOM material requirements and the mapping relationship between processes and process stages. The time calculation module is used to calculate the time for each process stage based on the PBOM time and the mapping relationship between processes and process stages; The output module is used to output the resource requirements data for each process stage, including five categories: instruments, workstations, personnel, materials, and working hours.