Automatic control method and system for no-load switching of three-phase flexible DC connected transformers

By automatically identifying the direction of power transmission and reception, adjusting the excitation voltage in real time, and controlling the switching sequence, the problems of cumbersome operation and safety hazards in the no-load switch switching test of flexible DC transformers have been solved, and efficient and safe automated control has been achieved.

CN123122031APending Publication Date: 2026-11-17CHANGZHOU XIDIAN TRANSFORMER CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611633893.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-10-21
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

The existing no-load switch switching test for flexible DC transformers is cumbersome and time-consuming, lacks automated control, makes it difficult to accurately maintain the excitation voltage stability, poses safety hazards, and cannot complete the full-stroke test of two products at once.

Method used

Two three-phase flexible DC-connected transformers with the same parameters are connected in parallel on the grid side and connected on the valve side. The controller automatically identifies the direction of power supply and reception, monitors the excitation voltage in real time and adjusts it to the rated value, drives the tap changer to switch in a preset sequence, and monitors electrical parameters during the switching process, and has abnormal protection functions.

Benefits of technology

It realizes automated control of the no-load switching of flexible DC transformers, improves test efficiency and safety, eliminates the need for high-voltage intermediate transformers, completes the switching of two products at one time, avoids equipment damage, and meets the reliability requirements of factory testing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123122031A_ABST
    Figure CN123122031A_ABST
Patent Text Reader

Abstract

This invention discloses an automatic control method and system for no-load switch switching of a three-phase flexible DC-coupled transformer, belonging to the field of power system testing and computer control technology. Two identical three-phase flexible DC-coupled transformers are connected in parallel on the grid side and directly connected on the valve side. The rated tap of one transformer is used as the power supply terminal. The controller automatically identifies the power supply and receiving directions, monitors the excitation voltage in real time, and adjusts it to the rated value in a closed loop. Then, the tap switches of the two transformers are driven alternately in a preset sequence to complete the full-stroke switching. No high-voltage intermediate transformer is required during the entire test, and the no-load switch switching test is completed in one step, significantly improving test efficiency and safety. The system integrates continuous voltage monitoring, automatic excitation regulation, switching sequence interlock control, and multi-parameter abnormality protection functions, effectively avoiding equipment damage caused by excitation voltage fluctuations or tap switch malfunctions, providing a reliable and automated technical solution for the factory testing of flexible DC-coupled transformers.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention discloses an automatic control method and system for the no-load switching of a three-phase flexible DC-connected transformer, belonging to the field of power system testing and computer control technology. Background Technology

[0002] In flexible DC transmission systems, the connecting transformer is one of the core devices for AC-DC conversion, and its valve side is directly connected to the converter valve. Before leaving the factory, the flexible DC transformer must undergo a no-load switch switching test to verify the reliability of the tap changer operation at different tap positions and the transformer's excitation characteristics. Traditional testing methods typically involve testing each transformer one by one, i.e., first performing no-load switching on one transformer, then disconnecting and switching on another. This is not only cumbersome and time-consuming, but also requires a high-voltage intermediate transformer to simulate valve-side voltage matching conditions, increasing the complexity and cost of the testing equipment.

[0003] Existing technologies have attempted to connect two transformers in parallel on the grid side and connected on the valve side for joint commissioning, but automated control schemes are lacking. Test personnel need to manually switch the power supply and receiving directions, manually adjust the excitation voltage to the rated value, and then operate the tap changers sequentially. This method relies on operational experience, making it difficult to precisely maintain a stable excitation voltage, and is prone to core saturation or overvoltage surges due to voltage fluctuations. Furthermore, the sequence of manual tap changer operation is prone to errors; if the tap changers of the two transformers switch out of sync, circulating currents or equipment damage may occur, resulting in low safety.

[0004] Furthermore, existing methods lack real-time voltage monitoring and anomaly protection mechanisms during testing. When the excitation voltage deviates from the rated value or the tap changer jams, the test cannot be automatically interrupted, posing a significant safety hazard. The entire testing cycle is long and inefficient, and it cannot complete the full-stroke no-load switch switching test of two products in one go, failing to meet the reliability and efficiency requirements of flexible DC transformer factory testing. Therefore, there is an urgent need for an intelligent control method that can automatically identify the power supply and receiving direction, adjust the excitation voltage in real time, sequentially control the tap changer switching, and provide anomaly protection functions. Summary of the Invention

[0005] To achieve the above objectives, this application provides the following technical solution: An automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer, applied to a controller, includes the following steps: Step A: Connect the grid sides of two three-phase flexible DC-connected transformers with the same parameters in parallel according to their phases, and connect the valve sides of the two transformers to each other, using the rated tap of one of the transformers as the power supply terminal. Step B: The controller automatically identifies and sets the power supply direction and power receiving direction, and determines the transformer that performs the power supply operation and the transformer that performs the power receiving operation; Step C: The controller monitors the excitation voltage value at the connection point in real time and adjusts the excitation voltage to the rated value by adjusting the voltage amplitude at the power supply end; Step D: The controller drives the tap changer to perform switching actions according to the preset switching sequence, wherein the switching sequence includes switching the tap changer of the power transmission transformer first and then switching the tap changer of the power receiving transformer. Step E: During the switching process, the controller continuously monitors electrical parameters. When any electrical parameter exceeds the safety threshold, the switching is immediately stopped and a protection signal is output. Step F: After all preset switching actions are completed, the controller determines that the no-load switch switching test is over.

[0006] Furthermore, the controller automatically identifies and sets the power supply direction and power receiving direction in the following specific way: The controller detects which of the two transformers has an electrical connection between its rated tap and the power output terminal, sets that transformer as the power supply terminal, and sets the other transformer as the power receiving terminal. The controller confirms the electrical connection status by reading the current detection signal or voltage detection signal in the rated tap connection circuit. If the current signal or voltage signal is detected, the transformer is determined to be the power supply end; otherwise, it is determined to be the power receiving end.

[0007] Furthermore, the controller monitors the excitation voltage value in real time and adjusts it to the rated value in the following specific manner: The controller collects instantaneous voltage values ​​from the common connection point between the power supply end and the power receiving end at preset sampling intervals, and calculates the effective value of the excitation voltage. The controller compares the calculated effective value of the excitation voltage with the rated voltage value. If the effective value of the excitation voltage is less than the rated voltage value, the controller increases the voltage output amplitude at the power supply end. If the effective value of the excitation voltage is greater than the rated voltage value, the controller decreases the voltage output amplitude at the power supply end. The controller repeats the above process of acquisition, calculation, comparison and adjustment until the absolute value of the difference between the effective value of the excitation voltage and the rated voltage value is less than the preset allowable deviation range.

[0008] Furthermore, the controller drives the tap changer to perform switching actions according to a preset switching sequence, specifically including the following steps: The controller reads the current tap changer position number of the power transmission transformer and the current tap changer position number of the power receiving transformer, and confirms that the tap changers of both transformers are in the rated tap position. The controller generates a switching instruction queue, which alternately arranges step instructions for the tap changer of the power transmission transformer and the tap changer of the power receiving transformer. The step instructions include a movement direction parameter. The movement direction of the power transmission transformer is to move step by step from the rated tap position to an extreme tap position, and the movement direction of the power receiving transformer is to move step by step from the rated tap position to the opposite extreme tap position. The controller retrieves a step instruction from the switching instruction queue and sends the step instruction to the corresponding tap changer drive module, driving the tap changer to move from one tap position to the next adjacent tap position. The controller waits for a signal feedback that the step instruction has been completed. After receiving the feedback that the execution has been completed, the controller collects the current excitation voltage value and executes the adjustment steps to stabilize the excitation voltage back to the rated value. The controller checks if the switching instruction queue is empty. If it is not empty, it returns to retrieve the next step instruction. If it is empty, it proceeds to the next step. The controller confirms that the tap changer of the power transmission transformer has been moved to the upper limit tap position or the lower limit tap position, and at the same time confirms that the tap changer of the receiving transformer has been moved to the opposite limit position to the power transmission transformer, thus completing the full-stroke switching.

[0009] Furthermore, the electrical parameters continuously monitored by the controller include the output current at the power supply end, the instantaneous peak value of the excitation voltage, the tap changer position feedback signal, and the temperature signals of the two transformers; The controller presets corresponding safety thresholds for each electrical parameter, including upper limit thresholds for current, peak voltage, position deviation, and temperature. When the controller detects that the output current of the power supply end exceeds the current upper limit threshold, or the instantaneous peak value of the excitation voltage exceeds the voltage peak upper limit threshold, or the deviation between the tap changer position feedback signal and the expected position exceeds the position deviation threshold, or the temperature signal of any transformer exceeds the temperature upper limit threshold, the controller immediately cuts off the power output of the power supply end, locks the drive modules of all tap changers, and outputs a protection signal containing an abnormality type identifier to the external monitoring interface.

[0010] Furthermore, the specific method for interconnecting the valve sides of the two transformers in step A is as follows: Connect the valve-side three-phase leads of one transformer to the valve-side three-phase leads of the other transformer respectively to form a three-phase valve-side closed loop. No switching or measuring equipment is connected at the valve-side connection point; only a direct wire connection is used. After completing the valve-side connection, the controller performs a continuity test by applying a test voltage signal to the power supply terminal. The controller determines whether the valve-side connection is correct by detecting whether there is a circulating current in the valve-side closed loop. If a circulating current is detected, the valve-side connection is confirmed to be normal; otherwise, a connection fault alarm is output and the test is stopped.

[0011] Furthermore, in step A, when the rated tap of one of the transformers is used as the power supply terminal, the controller performs the following initialization operations: The controller disconnects all external high-voltage power supply circuits, confirming that the power supply end is directly connected to the rated tap via the power module inside the controller, without passing through any voltage transformation device; The controller reads the nameplate parameters of the two transformers to obtain the rated voltage value, the rated tap position number, and the voltage ratio corresponding to each tap position; The controller sends a reset command to the tap changer drive modules of the two transformers, moves the tap changers of both transformers to the rated tap position, and confirms that each tap changer is accurately stopped at the rated tap position through the feedback signal of the position sensor. The controller activates the internal power module to increase the output voltage at the power supply end in a continuous and slow manner, while monitoring the excitation voltage value in real time. When the excitation voltage value approaches the rated voltage value, the controller switches to a slower, fine-tuning method to increase the voltage until the excitation voltage value stabilizes at the rated voltage value. The controller records the voltage change curve and excitation current change curve throughout the entire boost process and stores this data in its internal memory; During the above initialization process, if the controller detects abnormal fluctuations in the excitation voltage or sudden changes in the excitation current, it will immediately stop boosting the voltage and disconnect the power supply terminal, outputting an initialization failure alarm.

[0012] Furthermore, when the controller drives the tap changer to perform the switching action according to the preset switching sequence, it also performs interlock control: After the controller sends a switching command to the tap changer of the power transmission transformer, it immediately locks the tap changer drive module of the power receiving transformer, prohibiting the tap changer of the power receiving transformer from receiving any switching command during this period. After the tap changer of the power transmission transformer completes the switching and sends back the signal of arrival, the controller releases the lock on the tap changer drive module of the power receiving transformer, sends a switching command to the tap changer of the power receiving transformer, and locks the tap changer drive module of the power transmission transformer at the same time. The controller repeats the above alternating locking and unlocking process, and at any given time, at most only one tap switch receives a switching command.

[0013] Furthermore, the controller determines the end of the no-load switch switching test after all preset switching actions are completed in the following specific way: The controller cumulatively records the number of switching operations of the power transmission transformer tap changer and the power receiving transformer tap changer. When the number of complete round trips of the power transmission transformer tap changer from the rated tap position to the extreme tap position and back to the rated tap position reaches the preset number of cycles, or when the power receiving transformer tap changer completes the same number of cycles of switching, the controller determines that the switching action is complete. The controller then performs test termination operations: Gradually reduce the output voltage at the power supply end to zero, disconnect the power supply end from the power source, send a homing command to the tap changer drive modules of the two transformers, move the tap changers to the rated tap position, generate a test report and save it to non-volatile memory; The controller internally maintains a state machine, which includes the following states: Initialization status, direction confirmation status, excitation adjustment status, switching execution status, protection shutdown status, test completion status; After power-on, the controller enters the initialization state, performing hardware self-test and parameter loading; After the self-test is passed, the system enters the direction confirmation state and performs the identification of the power supply direction and power receiving direction. After the direction is confirmed, the system enters the excitation adjustment state and performs the excitation voltage adjustment to the rated value. After the excitation voltage stabilizes, the system enters the switching execution state and performs the switching action. If an abnormal protection is triggered during the switching execution state, the system enters the protection shutdown state; otherwise, the system enters the test completion state after the switching is completed. When the controller switches between states, it records the timestamp of the state transition and the reason for the transition.

[0014] According to a second aspect of the present invention, the present invention claims protection for an automatic control system for the no-load switching of a three-phase flexible DC-connected transformer, comprising: One or more processors; A memory storing one or more programs, which, when executed by one or more processors, enable the one or more processors to implement the automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer.

[0015] This invention discloses an automatic control method and system for no-load switch switching of a three-phase flexible DC-coupled transformer, belonging to the field of power system testing and computer control technology. Two identical three-phase flexible DC-coupled transformers are connected in parallel on the grid side and directly connected on the valve side. The rated tap of one transformer is used as the power supply terminal. The controller automatically identifies the power supply and receiving directions, monitors the excitation voltage in real time, and adjusts it to the rated value in a closed loop. Then, the tap switches of the two transformers are driven alternately in a preset sequence to complete the full-stroke switching. No high-voltage intermediate transformer is required during the entire test, and the no-load switch switching test of both products is completed in one go, significantly improving test efficiency and safety. The system integrates continuous voltage monitoring, automatic excitation regulation, interlocking control of the switching sequence, and multi-parameter abnormality protection functions, effectively avoiding equipment damage caused by excitation voltage fluctuations or tap switch malfunctions. This provides a reliable and automated technical solution for factory testing of flexible DC-coupled transformers. Attached Figure Description

[0016] Figure 1 A flowchart illustrating the automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer, as claimed in an embodiment of the present invention. Figure 2 The second working flowchart of an automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer, as claimed in an embodiment of the present invention, is shown below. Figure 3 The third working flowchart of an automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer, as claimed in an embodiment of the present invention, is shown in the figure. Detailed Implementation

[0017] The technical solutions of the embodiments of this application will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of the embodiments. Based on the embodiments of this application, all other embodiments obtained by those of ordinary skill in the art without creative effort are within the scope of protection of this application.

[0018] The terms "first," "second," and "third" in this application are for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of technical features indicated. Therefore, a feature defined as "first," "second," or "third" may explicitly or implicitly include at least one of those features. In the description of this application, "multiple" means at least two, such as two, three, etc., unless otherwise explicitly specified. All directional indications in the embodiments of this application, such as up, down, left, right, front, back, etc., are only used to explain the relative positional relationships and movements between components in a specific orientation as shown in the accompanying drawings. If the specific orientation changes, the directional indications will change accordingly. Furthermore, the terms "including" and "having," and any variations thereof, are intended to cover non-exclusive inclusion. For example, a process, method, system, product, or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units not listed, or may optionally include other steps or units inherent to these processes, methods, products, or devices.

[0019] References to embodiments herein mean that a particular feature, structure, or characteristic described in connection with an embodiment may be included in at least one embodiment of this application. The appearance of this phrase in various places throughout the specification does not necessarily refer to the same embodiment, nor is it a mutually exclusive, independent, or alternative embodiment. It will be explicitly and implicitly understood by those skilled in the art that the embodiments described herein can be combined with other embodiments.

[0020] According to the first embodiment of the present invention, referring to Figure 1 This invention claims protection for an automatic control method for the no-load switching of a three-phase flexible DC-connected transformer, applied to a controller, comprising the following steps: Step A: Connect the grid sides of two three-phase flexible DC-connected transformers with the same parameters in parallel according to their phases, and connect the valve sides of the two transformers to each other, using the rated tap of one of the transformers as the power supply terminal. Step B: The controller automatically identifies and sets the power supply direction and power receiving direction, and determines the transformer that performs the power supply operation and the transformer that performs the power receiving operation; Step C: The controller monitors the excitation voltage value at the connection point in real time and adjusts the excitation voltage to the rated value by adjusting the voltage amplitude at the power supply end; Step D: The controller drives the tap changer to perform switching actions according to the preset switching sequence, wherein the switching sequence includes switching the tap changer of the power transmission transformer first and then switching the tap changer of the power receiving transformer. Step E: During the switching process, the controller continuously monitors electrical parameters. When any electrical parameter exceeds the safety threshold, the switching is immediately stopped and a protection signal is output. Step F: After all preset switching actions are completed, the controller determines that the no-load switch switching test is over.

[0021] In this embodiment, the controller uses a programmable logic controller (PLC) paired with an industrial control computer. The controller integrates a voltage sampling module, a digital input / output module, and a tap changer drive interface.

[0022] Step A is implemented as follows: The operator first connects the grid-side three-phase busbars of the first and second three-phase flexible DC-connected transformers in parallel to the same 10kV AC busbar. Then, the valve-side three-phase leads U1, V1, and W1 of the first transformer are directly connected to the valve-side three-phase leads U2, V2, and W2 of the second transformer in the same phase sequence, i.e., U1 connects to U2, V1 connects to V2, and W1 connects to W2, forming a closed valve-side circuit. The operator then connects the cable from the rated tap of the first transformer to the power supply terminal block. This power supply terminal block is connected to the output terminal of the solid-state relay inside the controller, and the input terminal of the solid-state relay is connected to the low-voltage distribution cabinet in the laboratory.

[0023] In step B, after the controller is powered on, it automatically scans the secondary side signals of the current transformers in the two rated tap connection circuits. If a power frequency current of more than 0.5A is detected in the first circuit, the first transformer is determined to be the power supply end and the second transformer to be the power receiving end. If there is no current in either circuit, the controller outputs an alarm indicating that the power supply end is not identified and stops the test.

[0024] In step C, the controller collects the effective value of the line voltage in real time through a voltage transformer installed at the common connection point on the valve side of the two transformers. The sampling period is 20 milliseconds, and the arithmetic mean is calculated every 10 periods as the excitation voltage value. The controller has a preset rated voltage of 400V. If the current excitation voltage is 380V, the controller increases the conduction angle of the solid-state relay to increase the output voltage at the power supply end; if the excitation voltage is 420V, the conduction angle is decreased. This adjustment is made every 200 milliseconds, with each adjustment step not exceeding 1% of the rated value, until the deviation of the excitation voltage from 400V is less than ±2V.

[0025] In step D, the controller's internal memory stores a switching sequence table. This table specifies that the tap changer of the power transmission transformer is first instructed to go up one level, and after waiting 500 milliseconds, the position feedback signal is read to confirm that the action is completed. Then, the tap changer of the power receiving transformer is instructed to go down one level, and so on alternately.

[0026] In step E, the controller continuously monitors the current transformer value at the power supply end after each switching command is issued. If the current exceeds 15A, the solid-state relay is immediately disconnected, and an emergency stop signal is sent to the tap changer drive motor. In addition, the controller monitors the winding temperature of the two transformers through temperature sensors. If either temperature exceeds 85°C, the same protection action is triggered.

[0027] In step F, when the controller has accumulated 9 records of the power supply transformer tap changer moving from the rated position to the highest position and the power receiving transformer moving from the rated position to the lowest position, and there are no more switching instructions to be executed, the controller determines that the test is over, automatically disconnects the power supply at the power supply end, and outputs a test completion indication.

[0028] Furthermore, the controller automatically identifies and sets the power supply direction and power receiving direction in the following specific way: The controller detects which of the two transformers has an electrical connection between its rated tap and the power output terminal, sets that transformer as the power supply terminal, and sets the other transformer as the power receiving terminal. The controller confirms the electrical connection status by reading the current detection signal or voltage detection signal in the rated tap connection circuit. If the current signal or voltage signal is detected, the transformer is determined to be the power supply end; otherwise, it is determined to be the power receiving end.

[0029] In this embodiment, the controller internally sets up two independent electrical connection detection circuits. Each circuit includes a Hall current sensor and an optocoupler-isolated voltage detection circuit. At the beginning of step B, the controller sequentially closes contactor K1, which is connected in series with the rated tap of the first transformer, while keeping contactor K2, which is connected in series with the rated tap of the second transformer, open. Then, the controller collects current signals through the current sensor of the first circuit. If the effective value of the collected power frequency current is greater than 0.1A for five consecutive cycles, it is determined that the first transformer has an electrical connection. If the current is less than 0.05A and the voltage detection circuit detects that the voltage of the rated tap of the transformer to ground is less than 10V, it is determined that there is no electrical connection. Subsequently, the controller opens K1 and closes K2, and detects the second transformer in the same way. If electrical connection is detected in both transformers, the controller compares the two current values ​​and selects the one with the larger current value as the power supply end and the other as the power receiving end. If only one transformer detects an electrical connection, it is directly set as the power supply end. After the controller completes the identification, it records the result in the internal register and illuminates the corresponding indicator light on the control panel: red for the power supply end and green for the power receiving end. If no electrical connection is detected in either unit, the controller stops all outputs and displays a message on the human-machine interface indicating that no power input has been detected and to check the wiring of the rated taps. The operator is then required to rewire the taps before restarting the identification process. The entire identification process takes no more than 2 seconds and does not issue any drive commands to any tap switches during the process, ensuring safety.

[0030] Furthermore, the controller monitors the excitation voltage value in real time and adjusts it to the rated value in the following specific manner: The controller collects instantaneous voltage values ​​from the common connection point between the power supply end and the power receiving end at preset sampling intervals, and calculates the effective value of the excitation voltage. The controller compares the calculated effective value of the excitation voltage with the rated voltage value. If the effective value of the excitation voltage is less than the rated voltage value, the controller increases the voltage output amplitude at the power supply end. If the effective value of the excitation voltage is greater than the rated voltage value, the controller decreases the voltage output amplitude at the power supply end. The controller repeats the above process of acquisition, calculation, comparison and adjustment until the absolute value of the difference between the effective value of the excitation voltage and the rated voltage value is less than the preset allowable deviation range.

[0031] In this embodiment, the controller incorporates a high-speed analog signal acquisition module. This module acquires the instantaneous voltage waveform from the secondary side of the voltage transformer at the point of common coupling at a sampling rate of 1000 times per millisecond. The controller samples 2000 consecutive points corresponding to two power frequency cycles each time. After removing spike interference through digital filtering, the root mean square value of these 2000 points is calculated as the effective value of the current excitation voltage, denoted as Vrms. The controller's internal non-volatile memory stores the rated excitation voltage value Vnom for this type of transformer, for example, 650V, and the allowable error band δ, for example, ±3V. After calculating Vrms each time, the controller executes the following comparison logic: first, it calculates the difference Δ = Vrms - Vnom. If the absolute value of Δ is less than or equal to δ, the controller maintains the current output voltage at the power supply end unchanged and waits for the next sampling cycle (1 second) before sampling again. If Δ is less than -δ (i.e., Vrms is too low), the controller sends a forward rotation command to the regulator drive motor connected to the power supply end, causing the regulator's output voltage to rise. For each step the regulator's stepper motor rotates, the output voltage changes by approximately 0.5V. The controller controls the motor to rotate continuously until the absolute value of Δ returns to the δ range. During rotation, after each step, it waits 20 milliseconds to reread Vrms. If Δ is greater than +δ (i.e., Vrms is too high), the controller sends a reverse rotation command to the regulator drive motor, causing the output voltage to fall. To prevent oscillations during regulation, the controller also sets a hysteresis interval: the rise regulation is only initiated when Vrms is below Vnom-δ, and once initiated, it only stops when Vrms is above Vnom-δ / 2; conversely, the fall regulation is only initiated when Vrms is above Vnom+δ, and it stops only when Vrms is below Vnom+δ / 2. After each regulation command is executed, the controller stores the current Vrms value, regulation direction, and number of regulation steps in its internal log for later retrieval.

[0032] Furthermore, referring to Figure 2 The controller drives the tap changer to perform switching actions according to a preset switching sequence, specifically including the following steps: The controller reads the current tap changer position number of the power transmission transformer and the current tap changer position number of the power receiving transformer, and confirms that the tap changers of both transformers are in the rated tap position. The controller generates a switching instruction queue, which alternately arranges step instructions for the tap changer of the power transmission transformer and the tap changer of the power receiving transformer. The step instructions include a movement direction parameter. The movement direction of the power transmission transformer is to move step by step from the rated tap position to an extreme tap position, and the movement direction of the power receiving transformer is to move step by step from the rated tap position to the opposite extreme tap position. The controller retrieves a step instruction from the switching instruction queue and sends the step instruction to the corresponding tap changer drive module, driving the tap changer to move from one tap position to the next adjacent tap position. The controller waits for a signal feedback that the step instruction has been completed. After receiving the feedback that the execution has been completed, the controller collects the current excitation voltage value and executes the adjustment steps to stabilize the excitation voltage back to the rated value. The controller checks if the switching instruction queue is empty. If it is not empty, it returns to retrieve the next step instruction. If it is empty, it proceeds to the next step. The controller confirms that the tap changer of the power transmission transformer has been moved to the upper limit tap position or the lower limit tap position, and at the same time confirms that the tap changer of the receiving transformer has been moved to the opposite limit position to the power transmission transformer, thus completing the full-stroke switching.

[0033] In this embodiment, a switching task queue is established within the controller. This queue adopts a first-in, first-out (FIFO) structure, and each queue element is a structure containing a target transformer identifier (0 for the transmitting transformer, 1 for the receiving transformer), a movement direction (+1 for increasing the tap, -1 for decreasing the tap), and the expected stopping position number. Initially, the controller reads the tap position sensor of the transmitting transformer to confirm its position number as N0, the rated tap position, for example, tap 5. Simultaneously, it reads the tap position of the receiving transformer, also confirming it as tap 5. Then, the controller calculates the extreme positions the transmitting transformer needs to move to: according to the transformer nameplate parameters, the highest tap is tap 9, and the lowest is tap 1. The controller pre-sets the transmitting direction for this test to move to the higher tap (from tap 5 to tap 9) and the receiving direction to move to the lower tap (from tap 5 to tap 1). Therefore, the controller generates a queue and sequentially pushes in the following elements: Elements: 1st element: Transformer 0, direction +1, expected position 6; 2nd element: Transformer 1, direction -1, expected position 4; 3rd element: Transformer 0, direction +1, expected position 7; 4th element: Transformer 1, direction -1, expected position 3; 5th element: Transformer 0, direction +1, expected position 8; 6th element: Transformer 1, direction -1, expected position 2; 7th element: Transformer 0, direction +1, expected position 9; 8th element: Transformer 1, direction -1, expected position 1; After the queue is generated, the controller enters the loop execution phase. First, the controller retrieves the first element from the head of the queue and sends a pulse signal to the tap changer drive module of the power transmission transformer, with a pulse width of 200 milliseconds. Then, the controller starts a timer with a timeout of 5 seconds, while monitoring the feedback signal from the tap changer position sensor. When the sensor reports that the current tap has changed from 5 to 6, the controller confirms the switch is complete and immediately stops the timer. If no tap change signal is received within 5 seconds, the controller determines that the switch has timed out and enters the abnormal protection process. After the first element is retrieved, the controller immediately calls the excitation adjustment process: it collects the current excitation voltage, and if it deviates from the rated value, it makes a fine adjustment through the voltage regulator, which generally takes 1 to 2 seconds until the deviation is less than the allowable value. Then, the controller retrieves the second element, sends a pulse signal to the tap changer of the power receiving transformer to decrease the tap, waits for the position sensor to change from 5 to 4, and then performs excitation adjustment. This process is repeated. After each switching action is completed, the controller checks whether the current queue is empty. After executing the 8th element, the controller reconfirms that the power supply transformer is at position 9 and the power receiving transformer is at position 1, then clears the queue and exits the loop. During any of the above switching processes, if the controller detects that the position feedback signal does not match the expected position, for example, the position jumps from 5 to 7 after issuing an upshift command, or stays in an illegal gear, it immediately stops the queue execution, outputs a tap changer position abnormal signal, and executes protection steps.

[0034] Furthermore, the electrical parameters continuously monitored by the controller include the output current at the power supply end, the instantaneous peak value of the excitation voltage, the tap changer position feedback signal, and the temperature signals of the two transformers; The controller presets corresponding safety thresholds for each electrical parameter, including upper limit thresholds for current, peak voltage, position deviation, and temperature. When the controller detects that the output current of the power supply end exceeds the current upper limit threshold, or the instantaneous peak value of the excitation voltage exceeds the voltage peak upper limit threshold, or the deviation between the tap changer position feedback signal and the expected position exceeds the position deviation threshold, or the temperature signal of any transformer exceeds the temperature upper limit threshold, the controller immediately cuts off the power output of the power supply end, locks the drive modules of all tap changers, and outputs a protection signal containing an abnormality type identifier to the external monitoring interface.

[0035] In this embodiment, the controller has four independent monitoring channels, each equipped with a hardware comparator for rapid response. The first channel monitors the output current of the power supply end, converting the current signal into a 0-10V voltage signal through a current transformer with a range of 0-50A, and sending it to the controller's analog input port. The controller software sets the upper current threshold to 25A. When the sampling value exceeds 25A for three consecutive sampling points with a 10-millisecond interval, the controller immediately triggers a protection output via a hardware interrupt. The second channel monitors the instantaneous peak value of the excitation voltage, recording the maximum voltage value within each power frequency cycle through a peak hold circuit. The controller reads this peak value every 20 milliseconds. If the peak value exceeds 1.2 times the rated voltage peak value (e.g., a rated voltage of 400V corresponds to a peak value of 565V, and 1.2 times is 678V), then protection is triggered. The third channel monitors the tap changer position feedback signal. The controller reads the Gray code encoder value of each tap changer every 50 milliseconds and compares it with the expected position after the last command. If the deviation exceeds one tap (i.e., the code difference is greater than 1), it is determined to be an abnormal position deviation and protection is triggered. The fourth channel monitors the temperature signals of the two transformers. PT100 platinum resistance sensors are installed on the upper surface of the transformer core and the middle of the winding of each transformer. The controller collects the values ​​of four temperature points every 2 seconds and takes the maximum value as the current temperature. If the maximum value exceeds 85℃, protection is triggered. The specific execution method of the protection action is as follows: the controller performs three operations simultaneously—first, outputs a high-level signal to the power supply end. First, the trip coil of the main circuit contactor causes the contactor to disconnect instantly. Second, the enable pin of the tap changer drive module is pulled low via a separate hardwired connection, causing all drive motors to stop immediately and become unrestartable. Third, a 16-bit digital signal containing an anomaly type identifier is generated, such as 0x0001 for current over-limit, 0x0002 for peak voltage over-limit, 0x0004 for position deviation, and 0x0008 for temperature over-limit. This signal is sent to an external monitoring touchscreen via an RS485 bus, and the specific cause of the anomaly and the time of occurrence are displayed on the screen with a flashing red bar, accurate to milliseconds. After the protection is triggered, the controller enters a non-automatically recoverable shutdown state and must be manually reset by the operator before the test can be restarted.

[0036] Furthermore, the specific method for interconnecting the valve sides of the two transformers in step A is as follows: Connect the valve-side three-phase leads of one transformer to the valve-side three-phase leads of the other transformer respectively to form a three-phase valve-side closed loop. No switching or measuring equipment is connected at the valve-side connection point; only a direct wire connection is used. After completing the valve-side connection, the controller performs a continuity test by applying a test voltage signal to the power supply terminal. The controller determines whether the valve-side connection is correct by detecting whether there is a circulating current in the valve-side closed loop. If a circulating current is detected, the valve-side connection is confirmed to be normal; otherwise, a connection fault alarm is output and the test is stopped.

[0037] In this embodiment, in step A, the operator first places two three-phase flexible DC-coupled transformers side by side, with their valve-side terminal blocks facing each other. A copper busbar with a cross-sectional area of ​​95 square millimeters is used to directly bolt the U1 terminal of the first transformer to the U2 terminal of the second transformer, without connecting any circuit breakers, disconnectors, or ammeters in series. Similarly, V1 connects to V2, and W1 connects to W2. After connection, the surface of the copper busbar is wrapped with insulating heat-shrink tubing. After completing the connection, the operator starts the continuity test program through the controller's human-machine interface. The controller first confirms that the power supply end is not energized, meaning the main circuit contactor is in the open state. Then, a low-voltage signal source inside the controller outputs a frequency of 50Hz, an amplitude of 10V, and a current limited to below 100mA, which is connected to any two phases on the grid side of the power transmission transformer via two relays. Due to the electromagnetic induction characteristics of the transformer, a weak voltage will be induced on the valve side of the power transmission transformer. This voltage is directly transmitted to the valve side of the receiving transformer through the valve side copper busbar, and then induced on the grid side of the receiving transformer. The controller also connects a detection probe to the grid side of the receiving transformer. If a voltage amplitude between 9V and 11V and a frequency of 50Hz is detected, it indicates that the valve side circuit is malfunctioning. The connection is normal. Simultaneously, a clamp-on current transformer is connected to the common connection point on the valve side. When a 10V signal is applied, if a weak circulating current (e.g., between 5mA and 20mA) is generated in the circuit, the connection is further confirmed to be correct. If no voltage or circulating current is detected, the controller determines that there is an open circuit or phase mismatch in the valve side connection. The controller will output a connection fault alarm and display on the screen which specific phase is not connected. This can be resolved by testing phases U, V, and W separately. At this time, the controller automatically locks all subsequent test steps until the operator troubleshoots the fault and performs a continuity test again. If the test is normal, the controller records the valve side connection confirmation flag, allowing the subsequent voltage boosting steps to proceed.

[0038] Furthermore, in step A, when the rated tap of one of the transformers is used as the power supply terminal, the controller performs the following initialization operations: The controller disconnects all external high-voltage power supply circuits, confirming that the power supply end is directly connected to the rated tap via the power module inside the controller, without passing through any voltage transformation device; The controller reads the nameplate parameters of the two transformers to obtain the rated voltage value, the rated tap position number, and the voltage ratio corresponding to each tap position; The controller sends a reset command to the tap changer drive modules of the two transformers, moves the tap changers of both transformers to the rated tap position, and confirms that each tap changer is accurately stopped at the rated tap position through the feedback signal of the position sensor. The controller activates the internal power module to increase the output voltage at the power supply end in a continuous and slow manner, while monitoring the excitation voltage value in real time. When the excitation voltage value approaches the rated voltage value, the controller switches to a slower, fine-tuning method to increase the voltage until the excitation voltage value stabilizes at the rated voltage value. The controller records the voltage change curve and excitation current change curve throughout the entire boost process and stores this data in its internal memory; During initialization, if the controller detects abnormal fluctuations in excitation voltage or sudden changes in excitation current, it will immediately stop boosting and disconnect the power supply terminal, outputting an initialization failure alarm.

[0039] In this embodiment, in step A, the operator connects the rated tap cable of the power supply end to a dedicated power interface inside the controller. This interface is directly connected to the output of a solid-state voltage regulator, while the input of the regulator comes from the laboratory distribution cabinet, without passing through any step-down or step-up transformers. Before initialization begins, the controller performs the following sequential actions: First, the controller checks the status of all external high-voltage power supply circuits and reads the position of the main contactor through an auxiliary contact. If the main contactor is in the closed state, the controller first sends a disconnect command and waits 100 milliseconds to confirm that the contact has opened.

[0040] Second, the controller reads the QR code information on the nameplates of the two transformers through the RS232 interface, and deciphers that the rated voltage is 10kV / 400V, the rated tap position is the 5th tap, and there are 9 taps in total. The voltage ratio table corresponding to each tap position changes by 1.25% for each tap.

[0041] Third, the controller sends instructions to the tap changer drive modules of the two transformers to move to the 5th position sequentially, with the power supply transformer first and the receiving transformer second. During the movement of each tap changer, the controller monitors the position change in real time through a Gray code encoder. When the encoded value stabilizes at the code corresponding to the 5th position, such as 1010, and remains unchanged for 0.5 seconds, the position is confirmed to be in place. If there is any jamming or timeout during the movement, the controller stops initialization and reports an error.

[0042] Fourth, the controller activates its internal solid-state voltage regulator, setting the initial output voltage to 0V. It then continuously and slowly increases the voltage at a rate of 0.5V every 20 milliseconds, while simultaneously monitoring the excitation voltage value via a voltage transformer. When the excitation voltage reaches 90% of the rated value of 400V, i.e., 360V, the controller changes its voltage boosting strategy to a fine-tuning method increasing by 0.1V every 100 milliseconds. When the excitation voltage reaches 398V, the controller stops boosting and waits 5 seconds to observe whether it stabilizes. If it stabilizes between 398-402V, initialization is complete; if the overshoot exceeds 405V, the controller will actively reduce the voltage by 0.5V.

[0043] Throughout the voltage boosting process, the controller records the excitation voltage and excitation current every 0.1 seconds via a current transformer and plots the curves in real time, storing them in the internal SD card. If the excitation voltage suddenly drops by more than 10% and lasts for more than 0.2 seconds, or the excitation current suddenly changes by more than twice the rated no-load current, the controller immediately cuts off the trigger signal of the solid-state voltage regulator within 1 millisecond, disconnects the main contactor, and outputs an initialization failure alarm. The alarm information includes the voltage and current values ​​at the time of the abnormality.

[0044] Furthermore, when the controller drives the tap changer to perform the switching action according to the preset switching sequence, it also performs interlock control: After the controller sends a switching command to the tap changer of the power transmission transformer, it immediately locks the tap changer drive module of the power receiving transformer, prohibiting the tap changer of the power receiving transformer from receiving any switching command during this period. After the tap changer of the power transmission transformer completes the switching and sends back the signal of arrival, the controller releases the lock on the tap changer drive module of the power receiving transformer, sends a switching command to the tap changer of the power receiving transformer, and locks the tap changer drive module of the power transmission transformer at the same time. The controller repeats the above alternating locking and unlocking process, and at any given time, at most only one tap switch receives a switching command.

[0045] In this embodiment, the controller internally sets a software enable flag for each transformer's tap changer drive module, while simultaneously cutting off the drive power supply via two independent solid-state relays. Initially, both enable flags are true, and the drive power supply is on. When the controller needs to issue switching commands to the power-transmitting transformer in sequence, it first performs an interlock operation: clearing the software enable flag of the receiving transformer and cutting off the 24V power supply to the receiving transformer drive module via a hardware output pin, ensuring that even erroneous command signals cannot drive the receiving transformer's motor. Then, the controller issues a shift command to the power-transmitting transformer and begins waiting for position feedback. An internal monitoring timer checks the receiving transformer's position sensor for changes every 10 milliseconds during the interlock period, ensuring the receiving transformer's tap changer is completely stationary. When the power-transmitting transformer's position feedback is in place... Afterwards, the controller does not immediately release the lock on the receiving transformer, but waits for an additional 50 milliseconds of debounce time before restoring the software enable flag and hardware power of the receiving transformer. Similarly, before issuing a command to the receiving transformer, the controller locks the drive module of the transmitting transformer. Throughout the test, the controller also maintains an interlock status register, where a value of 0 indicates that no device is locked, a value of 1 indicates that the receiving transformer is locked, and a value of 2 indicates that the transmitting transformer is locked. At any time, if the controller detects that the interlock status register does not match the currently executed command, for example, it is in the state of locking the receiving transformer but receives feedback of a change in the position of the receiving transformer, the controller will immediately trigger a protection action. This interlock mechanism ensures that at any given time, at most only one transformer tap changer is in the operating state, avoiding circulating current impact or mechanical interference that may be caused by two transformers operating simultaneously.

[0046] Furthermore, the controller determines the end of the no-load switch switching test after all preset switching actions are completed in the following specific way: The controller cumulatively records the number of switching operations of the power transmission transformer tap changer and the power receiving transformer tap changer. When the number of complete round trips of the power transmission transformer tap changer from the rated tap position to the extreme tap position and back to the rated tap position reaches the preset number of cycles, or when the power receiving transformer tap changer completes the same number of cycles of switching, the controller determines that the switching action is complete. The controller then performs test termination operations: Gradually reduce the output voltage at the power supply end to zero, disconnect the power supply end from the power source, send a homing command to the tap changer drive modules of the two transformers, move the tap changers to the rated tap position, generate a test report and save it to non-volatile memory; The controller internally maintains a state machine, which includes the following states: Initialization status, direction confirmation status, excitation adjustment status, switching execution status, protection shutdown status, test completion status; After power-on, the controller enters the initialization state, performing hardware self-test and parameter loading; After the self-test is passed, the system enters the direction confirmation state and performs the identification of the power supply direction and power receiving direction. After the direction is confirmed, the system enters the excitation adjustment state and performs the excitation voltage adjustment to the rated value. After the excitation voltage stabilizes, the system enters the switching execution state and performs the switching action. If an abnormal protection is triggered during the switching execution state, the system enters the protection shutdown state; otherwise, the system enters the test completion state after the switching is completed. When the controller switches between states, it records the timestamp of the state transition and the reason for the transition.

[0047] In this embodiment, the controller internally sets up two counters: Counter_Tx and Counter_Rx, which record the number of complete cycles of the tap changers of the power supply transformer and the power receiving transformer from their rated positions to their extreme positions and back to their rated positions, respectively. In the switching queue, a complete cycle is defined as the power supply transformer rising from its rated position to the highest level and then falling back to its rated position, while the power receiving transformer falls from its rated position to the lowest level and then rises back to its rated position. After executing the 8th element of powering to the highest level and powering to the lowest level, the controller does not immediately stop, but continues to generate a reverse queue: first, the power supply transformer is gradually lowered from its highest level to its rated level, while the power receiving transformer is gradually raised from its lowest level to its rated level. Each time a complete round trip is completed, Counter_Tx and Counter_Rx are each incremented by 1. The preset number of cycles is input by the operator through the touch screen, for example, set to 3 times. When Counter_Tx reaches 3 times and Counter_Rx also reaches 3 times, the controller determines that all switching actions are completed. The test then proceeds to its final stages: First, the controller gradually decreases the output voltage at the power supply end by 5V every 100 milliseconds, while simultaneously monitoring the excitation voltage. When the output voltage at the power supply end drops below 10V, the trigger signal of the solid-state voltage regulator is cut off, and the main contactor is disconnected. Second, the controller sends a return-to-rated position command to both tap changer drive modules and monitors the position sensors until both position codes are equal to the value of the 5th position. Third, the controller formats and stores all test data—including the initial excitation voltage, excitation voltage adjustment records after each switch, total number of switches, total test time, highest temperature, and any abnormal events—into a new file in its internal non-volatile memory. The file is named as test date_time_transformer number.dat. Simultaneously, the controller pushes the test report to the host computer database via the Ethernet interface. Finally, the controller illuminates the green completion indicator on the panel and displays the test completed and the tap changers returned to their original positions.

[0048] The controller maintains an 8-bit status register, the value of which corresponds to the following states: 0x01 initialization state, 0x02 direction confirmation state, 0x04 excitation adjustment state, 0x08 switching execution state, 0x10 protection shutdown state, and 0x20 test completion state. After the controller is powered on, the status register is forcibly set to 0x01, and then the initialization state is executed: self-test includes checking whether all analog input channels are open, whether the tap changer drive power supply is normal, whether the communication interface is readable and writable, and internal memory CRC check; if the self-test passes, the controller records the current timestamp as T0, and then the status jumps to 0x02; in the direction confirmation state, the controller calls the method to identify the power supply end and the power receiving end, and after successful identification, records the identification result and completion time T1, and then the status jumps to 0x04; in the excitation regulation state, the controller calls the method to adjust the excitation voltage to the rated value, and at the same time monitors whether the voltage is stable at the rated value for more than 3 seconds, if so, records T2, and the status jumps to 0x08; in the switching execution state, the controller calls the queue execution method, and at the same time continuously checks the external protection request signal; if no protection is triggered during the switching execution process, and all switching instructions are executed, the controller records T3, and the status jumps to 0x20. If a protection signal is received during the switching execution state, the state immediately jumps to 0x10. After entering the protection shutdown state, the controller records T4 and the reason for the protection state transition, such as current over-limit, and executes the protection action. At the same time, the state machine is locked, prohibiting any automatic transitions. Only manual reset of the state machine to 0x01 is possible via the reset button. In the test completion state, the controller performs a cleanup operation. After completion, the state remains at 0x20 and no longer automatically jumps. The controller records the timestamp and reason for each state transition, such as self-test passed, direction recognition successful, excitation stable, switching completed, protection triggered, position deviation, etc., in plaintext in a circular buffer with a capacity of 100 records. When the buffer is full, it automatically overwrites the oldest record. Operators can read the current state value and historical transition records in real time through the debugging interface for fault analysis.

[0049] According to a second embodiment of the present invention, the present invention claims protection for an automatic control system for the no-load switching of a three-phase flexible DC-connected transformer, comprising: One or more processors; A memory storing one or more programs, which, when executed by one or more processors, cause the one or more processors to implement the aforementioned automatic control method for switching the no-load circuit breaker of a three-phase flexible DC-connected transformer. In the several embodiments provided in this application, it should be understood that the disclosed systems, apparatuses, and methods can be implemented in other ways. For example, the apparatus embodiments described above are merely illustrative; for instance, the division of units is only a logical functional division, and in actual implementation, there may be other division methods. For example, multiple units or components may be combined or integrated into another system, or some features may be ignored or not executed. Furthermore, the coupling or direct coupling or communication connection shown or discussed may be through some interfaces, or indirect coupling or communication connection between apparatuses or units, and may be electrical, mechanical, or other forms.

[0050] Furthermore, the functional units in the various embodiments of this application can be integrated into one processing unit, or each unit can exist physically separately, or two or more units can be integrated into one unit. The integrated units described above can be implemented in hardware or as software functional units. The above are merely embodiments of this application and do not limit the patent scope of this application. Any equivalent structural or procedural transformations made based on the description and drawings of this application, or direct or indirect applications in other related technical fields, are similarly included within the patent protection scope of this application.

[0051] The specific embodiments of the invention have been described in detail above, but they are only examples, and this application is not limited to the specific embodiments described above. For those skilled in the art, any equivalent modifications or substitutions to the invention are also within the scope of this application. Therefore, all equivalent changes, modifications, and improvements made without departing from the spirit and principles of this application should be covered within the scope of this application.

Claims

1. An automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer, applied to a controller, characterized in that, Includes the following steps: Step A: Connect the grid sides of two three-phase flexible DC-connected transformers with the same parameters in parallel according to their phases, and connect the valve sides of the two transformers to each other, using the rated tap of one of the transformers as the power supply terminal. Step B: The controller automatically identifies and sets the power supply direction and power receiving direction, and determines the transformer that performs the power supply operation and the transformer that performs the power receiving operation; Step C: The controller monitors the excitation voltage value at the connection point in real time and adjusts the excitation voltage to the rated value by adjusting the voltage amplitude at the power supply end; Step D: The controller drives the tap changer to perform switching actions according to the preset switching sequence, wherein the switching sequence includes switching the tap changer of the power transmission transformer first and then switching the tap changer of the power receiving transformer. Step E: During the switching process, the controller continuously monitors electrical parameters. When any electrical parameter exceeds the safety threshold, the switching is immediately stopped and a protection signal is output. Step F: After all preset switching actions are completed, the controller determines that the no-load switch switching test is over.

2. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, The controller automatically identifies and sets the power supply direction and power receiving direction in the following specific way: The controller detects which of the two transformers has an electrical connection between its rated tap and the power output terminal, sets that transformer as the power supply terminal, and sets the other transformer as the power receiving terminal. The controller confirms the electrical connection status by reading the current detection signal or voltage detection signal in the rated tap connection circuit. If the current signal or voltage signal is detected, the transformer is determined to be the power supply end; otherwise, it is determined to be the power receiving end.

3. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, The controller monitors the excitation voltage value in real time and adjusts it to the rated value in the following specific way: The controller collects instantaneous voltage values ​​from the common connection point between the power supply end and the power receiving end at preset sampling intervals, and calculates the effective value of the excitation voltage. The controller compares the calculated effective value of the excitation voltage with the rated voltage value. If the effective value of the excitation voltage is less than the rated voltage value, the controller increases the voltage output amplitude at the power supply end. If the effective value of the excitation voltage is greater than the rated voltage value, the controller decreases the voltage output amplitude at the power supply end. The controller repeats the above process of acquisition, calculation, comparison and adjustment until the absolute value of the difference between the effective value of the excitation voltage and the rated voltage value is less than the preset allowable deviation range.

4. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, The controller drives the tap changer to perform switching actions according to a preset switching sequence, specifically including the following steps: The controller reads the current tap changer position number of the power transmission transformer and the current tap changer position number of the power receiving transformer, and confirms that the tap changers of both transformers are in the rated tap position. The controller generates a switching instruction queue, which alternately arranges step instructions for the tap changer of the power transmission transformer and the tap changer of the power receiving transformer. The step instructions include a movement direction parameter. The movement direction of the power transmission transformer is to move step by step from the rated tap position to an extreme tap position, and the movement direction of the power receiving transformer is to move step by step from the rated tap position to the opposite extreme tap position. The controller retrieves a step instruction from the switching instruction queue and sends the step instruction to the corresponding tap changer drive module, driving the tap changer to move from one tap position to the next adjacent tap position. The controller waits for a signal feedback that the step instruction has been completed. After receiving the feedback that the execution has been completed, the controller collects the current excitation voltage value and executes the adjustment steps to stabilize the excitation voltage back to the rated value. The controller checks if the switching instruction queue is empty. If it is not empty, it returns to retrieve the next step instruction. If it is empty, it proceeds to the next step. The controller confirms that the tap changer of the power transmission transformer has been moved to the upper limit tap position or the lower limit tap position, and at the same time confirms that the tap changer of the receiving transformer has been moved to the opposite limit position to the power transmission transformer, thus completing the full-stroke switching.

5. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, The electrical parameters continuously monitored by the controller include the output current at the power supply end, the instantaneous peak value of the excitation voltage, the tap changer position feedback signal, and the temperature signals of the two transformers. The controller presets corresponding safety thresholds for each electrical parameter, including upper limit thresholds for current, peak voltage, position deviation, and temperature. When the controller detects that the output current of the power supply end exceeds the current upper limit threshold, or the instantaneous peak value of the excitation voltage exceeds the voltage peak upper limit threshold, or the deviation between the tap changer position feedback signal and the expected position exceeds the position deviation threshold, or the temperature signal of any transformer exceeds the temperature upper limit threshold, the controller immediately cuts off the power output of the power supply end, locks the drive modules of all tap changers, and outputs a protection signal containing an abnormality type identifier to the external monitoring interface.

6. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, The specific method for interconnecting the valve sides of the two transformers in step A is as follows: Connect the valve-side three-phase leads of one transformer to the valve-side three-phase leads of the other transformer respectively to form a three-phase valve-side closed loop. No switching or measuring equipment is connected at the valve-side connection point; only a direct wire connection is used. After completing the valve-side connection, the controller performs a continuity test by applying a test voltage signal to the power supply terminal. The controller determines whether the valve-side connection is correct by detecting whether there is a circulating current in the valve-side closed loop. If a circulating current is detected, the valve-side connection is confirmed to be normal; otherwise, a connection fault alarm is output and the test is stopped.

7. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, In step A, when the rated tap of one of the transformers is used as the power supply terminal, the controller performs the following initialization operations: The controller disconnects all external high-voltage power supply circuits, confirming that the power supply end is directly connected to the rated tap via the power module inside the controller, without passing through any voltage transformation device; The controller reads the nameplate parameters of the two transformers to obtain the rated voltage value, the rated tap position number, and the voltage ratio corresponding to each tap position; The controller sends a reset command to the tap changer drive modules of the two transformers, moves the tap changers of both transformers to the rated tap position, and confirms that each tap changer is accurately stopped at the rated tap position through the feedback signal of the position sensor. The controller activates the internal power module to increase the output voltage at the power supply end in a continuous and slow manner, while monitoring the excitation voltage value in real time. When the excitation voltage value approaches the rated voltage value, the controller switches to a slower, fine-tuning method to increase the voltage until the excitation voltage value stabilizes at the rated voltage value. The controller records the voltage change curve and excitation current change curve throughout the entire boost process and stores this data in its internal memory; During the above initialization process, if the controller detects abnormal fluctuations in the excitation voltage or sudden changes in the excitation current, it will immediately stop boosting the voltage and disconnect the power supply terminal, outputting an initialization failure alarm.

8. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, When the controller drives the tap changer to perform the switching action according to the preset switching sequence, it also performs interlock control: After the controller sends a switching command to the tap changer of the power transmission transformer, it immediately locks the tap changer drive module of the power receiving transformer, prohibiting the tap changer of the power receiving transformer from receiving any switching command during this period. After the tap changer of the power transmission transformer completes the switching and sends back the signal of arrival, the controller releases the lock on the tap changer drive module of the power receiving transformer, sends a switching command to the tap changer of the power receiving transformer, and locks the tap changer drive module of the power transmission transformer at the same time. The controller repeats the above alternating locking and unlocking process, and at any given time, at most only one tap switch receives a switching command.

9. The automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to claim 1, characterized in that, The specific method by which the controller determines the end of the no-load switch switching test after all preset switching actions are completed is as follows: The controller cumulatively records the number of switching operations of the power transmission transformer tap changer and the power receiving transformer tap changer. When the number of complete round trips of the power transmission transformer tap changer from the rated tap position to the extreme tap position and back to the rated tap position reaches the preset number of cycles, or when the power receiving transformer tap changer completes the same number of cycles of switching, the controller determines that the switching action is complete. The controller then performs test termination operations: Gradually reduce the output voltage at the power supply end to zero, disconnect the power supply end from the power source, send a homing command to the tap changer drive modules of the two transformers, move the tap changers to the rated tap position, generate a test report and save it to non-volatile memory; The controller internally maintains a state machine, which includes the following states: Initialization status, direction confirmation status, excitation adjustment status, switching execution status, protection shutdown status, test completion status; After power-on, the controller enters the initialization state, performing hardware self-test and parameter loading; After the self-test is passed, the system enters the direction confirmation state and performs the identification of the power supply direction and power receiving direction. After the direction is confirmed, the system enters the excitation adjustment state and performs the excitation voltage adjustment to the rated value. After the excitation voltage stabilizes, the system enters the switching execution state and performs the switching action. If an abnormal protection is triggered during the switching execution state, the system enters the protection shutdown state; otherwise, the system enters the test completion state after the switching is completed. When the controller switches between states, it records the timestamp of the state transition and the reason for the transition.

10. An automatic control system for switching the no-load switch of a three-phase flexible DC-connected transformer, characterized in that, include: One or more processors; A memory having stored one or more programs that, when executed by one or more processors, cause the one or more processors to implement an automatic control method for switching the no-load switch of a three-phase flexible DC-connected transformer according to any one of claims 1 to 9.