A protective cover for tunnel monitoring and measurement piles and its manufacturing and installation method

The design of a three-dimensional frame, a metal protective top plate, and a fixing sleeve solves the protection problem of monitoring and measuring piles in tunnel construction, achieving structural stability, convenient installation, and reusability, and adapting to the needs of the tunnel environment.

CN123124243APending Publication Date: 2026-11-17CHINA RAILWAY TUNNEL GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202611346494.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2026-09-01
Publication Date
2026-11-17

AI Technical Summary

Technical Problem

During tunnel construction, monitoring and measurement piles are susceptible to damage from flying rocks, mechanical collisions, shotcrete, and moisture corrosion. Existing protective structures are not stable enough, are inconvenient to install and dismantle, and are difficult to reuse.

Method used

It adopts a three-dimensional frame, triangular reinforcement structure and metal protective top plate, combined with fixed sleeve and locking mechanism, equipped with buffer layer and anti-corrosion coating, designed with detachable connection structure, and standardized manufacturing and installation methods.

Benefits of technology

It effectively protects monitoring and measurement piles from flying rocks, mechanical impacts, and shotcrete damage, ensures the stability of the protective structure, simplifies installation, disassembly, and reuse, adapts to humid environments, and improves identification and corrosion resistance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN123124243A_ABST
    Figure CN123124243A_ABST
Patent Text Reader

Abstract

This invention discloses a protective cover for tunnel monitoring and measurement piles, and its manufacturing and installation method, relating to the field of tunnel protection technology. It includes a three-dimensional frame, a metal protective top plate, and a fixing sleeve. The three-dimensional frame is formed by connecting longitudinal, transverse, vertical, and diagonal rods. The diagonal rods, longitudinal and vertical rods form a triangular reinforcing structure. The fixing sleeve allows the monitoring and measurement pile to pass through. During manufacturing, material pretreatment, frame welding, top plate welding, sleeve connection, and anti-corrosion treatment are completed sequentially. During installation, site cleaning, protective cover insertion, fixing, leveling, and condition inspection are completed sequentially. This invention can reduce the impact of flying rocks, mechanical collisions, shotcrete, and moisture corrosion on monitoring and measurement piles, and is easy to install, disassemble, and reuse.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of tunnel protection technology, specifically to a protective cover for tunnel monitoring and measurement piles and its manufacturing and installation method. Background Technology

[0002] During tunnel construction, monitoring and measurement piles are typically installed to establish measuring points or serve as monitoring benchmarks to obtain deformation data of the tunnel's surrounding rock and support structure. The stability of these monitoring and measurement piles directly affects the continuity and reliability of the monitoring data; therefore, it is essential to minimize the risk of pile displacement, bending, or damage during construction and monitoring. Due to the limited working space inside the tunnel, and the accompanying blasting excavation, muck removal, shotcreting, and mechanical equipment operations during construction, the monitoring and measuring piles are susceptible to impacts from flying rocks, falling objects, and construction machinery. They may also be covered by shotcrete, dust, and debris. Furthermore, the relatively humid environment inside the tunnel makes the long-term exposed monitoring and measuring piles and their protective components prone to corrosion. Frequent passage of construction personnel and equipment may also cause accidental contact or interference with the monitoring and measuring piles. Existing protective measures, in practical use, also need to consider the impact resistance of the protective structure, installation stability, and avoidance requirements for monitoring and measurement piles. If the stability of the protective structure is insufficient, it is prone to swaying under construction vibration or external forces. If the protective structure makes unintended rigid contact with the pile, it may affect the stability of the pile. In addition, the protective structure needs to be adaptable to the humid and dusty environment of the tunnel and be easy to fabricate, install, dismantle, and reuse on site. Therefore, there is a need for a monitoring and measurement pile protection structure that is structurally stable, can be installed on the outside of the monitoring and measurement pile, and takes into account the requirements of impact resistance, corrosion resistance, on-site installation and reuse. At the same time, there is also a need to develop a manufacturing and installation method that is compatible with the protection structure. Summary of the Invention

[0003] To solve the above-mentioned technical problems, a protective cover for tunnel monitoring and measurement piles and its manufacturing and installation method are provided. This technical solution solves the problems that the tunnel monitoring and measurement piles are susceptible to flying rocks, mechanical collisions, shotcrete and moisture corrosion, and that the existing protective structures are not stable enough, inconvenient to install and disassemble and difficult to reuse.

[0004] To achieve the above objectives, the technical solution adopted by the present invention is as follows: A protective cover for tunnel monitoring and measurement piles, comprising: A three-dimensional frame includes a pair of longitudinal bars arranged along a first direction, a pair of transverse bars arranged along a second direction, a pair of vertical bars arranged along a third direction, and at least a pair of diagonal bars connecting the longitudinal bars and the vertical bars. The first direction, the second direction, and the third direction are perpendicular to each other. The longitudinal bars, the transverse bars, and the vertical bars are connected to form a frame body with a top opening. The diagonal bars form a triangular reinforcing structure with the longitudinal bars and the vertical bars. A metal protective top plate is fixedly installed to cover the top opening; At least one fixed sleeve is connected to the bottom of the three-dimensional frame. A channel is formed inside the fixed sleeve that runs through the third direction. The cross-sectional dimension of the channel is larger than the cross-sectional dimension of the monitoring and measuring pile so that the pile can pass through, thereby covering the outside of the monitoring and measuring pile with the three-dimensional frame and the metal protective top plate.

[0005] Preferably, the horizontal bar, the vertical bar, and the diagonal bar are all circular cross-section threaded steel bars with a diameter of 16mm to 20mm, and the metal protective top plate is a carbon structural steel plate with a thickness of 4mm to 6mm.

[0006] Preferably, the length of the three-dimensional frame along the first direction is 220mm to 240mm, the width along the second direction is 130mm to 150mm, and the height along the third direction is 110mm to 130mm.

[0007] Preferably, the fixing sleeve is a circular cross-section steel pipe, and the nominal outer diameter of the fixing sleeve is 18mm to 22mm, and the length is 90mm to 110mm.

[0008] Preferably, the fixing sleeve is detachably connected to the three-dimensional frame, and the fixing sleeve and the three-dimensional frame are connected by threaded connection, snap-fit ​​connection or flange bolt connection; The fixed sleeve includes a first half-cylinder and a second half-cylinder. The first half-cylinder and the second half-cylinder are connected on one side by a hinge, and a locking mechanism is provided on the other side. The locking mechanism is used to adjust the cross-sectional size of the channel so that the channel allows the pile to pass through in the open state and clamps the pile in the locked state.

[0009] Preferably, the protective cover for the tunnel monitoring and measurement piles further includes a buffer layer, which is disposed on at least one of the upper surface of the metal protective top plate and at least a portion of the outer surface of the three-dimensional frame, and the buffer layer is made of rubber, polyurethane or engineering plastic; The upper surface of the metal protective top plate is provided with raised anti-slip textures or reflective marking areas. The surfaces of the three-dimensional frame, the metal protective top plate, and the fixing sleeve are all provided with an anti-corrosion coating, which is at least one of a zinc plating layer, an epoxy zinc-rich primer layer, or a fluorocarbon topcoat layer.

[0010] A method for manufacturing a protective cover for tunnel monitoring and measurement piles includes: S1. Prepare metal rods, metal plates and pipes according to the design specifications of the protective cover, and straighten, remove rust, cut and grind the cut edges of the metal rods, metal plates and pipes. S2. Position the longitudinal rod, the transverse rod, and the vertical rod on the welding fixture and weld them together to form a frame body with a top opening. Weld the diagonal rod between the longitudinal rod and the vertical rod to form the three-dimensional frame. S3. Cut the metal sheet to a predetermined size, cover and position it at the top opening of the three-dimensional frame, and weld the edge of the metal sheet to the three-dimensional frame to form the metal protective top plate; S4. Position at least one of the fixing sleeves at a predetermined position at the bottom of the three-dimensional frame, and connect the fixing sleeves to the three-dimensional frame; S5. Clean the weld seams, grind the sharp edges and burrs of the completed protective cover, and perform surface anti-corrosion treatment on the protective cover.

[0011] Preferably, when welding the three-dimensional frame, the longitudinal rods, the transverse rods and the vertical rods are first spot welded for positioning, and then full welding is performed after the diagonal dimensions and verticality of the frame body meet the design requirements. The two ends of the diagonal rods are connected by full welding. When welding the metal protective top plate, intermittent welding is performed along the edge of the metal protective top plate; The welding of the three-dimensional frame and the metal protective top plate is carried out by carbon dioxide gas shielded welding or manual arc welding, and the welding current, welding voltage and welding speed are set according to the material thickness. After the welding is completed, the welds at both ends of the inclined rod are subjected to non-destructive testing. The surface anti-corrosion treatment includes sandblasting or shot blasting the protective cover to remove rust, so that the surface cleanliness of the protective cover reaches Sa2.5 level, then applying an anti-rust primer, and applying a topcoat after the anti-rust primer dries. The manufacturing method also includes a buffer layer installation step. After the metal protective top plate is welded and before the fixing sleeve is connected, the buffer layer is bonded or mechanically fixed to the upper surface of the metal protective top plate. The buffer layer is made of rubber, polyurethane or engineering plastic.

[0012] A method for installing a protective cover for tunnel monitoring and measurement piles includes: S1. Determine the location of the monitoring and measuring piles inside the tunnel, clear the floating debris and obstacles around the monitoring and measuring piles, and measure and mark the installation reference of the protective cover; S2. Insert the protective cover from the top of the monitoring and measuring pile, so that the pile body of the monitoring and measuring pile passes through the channel of the fixed sleeve, and move the protective cover downward until the bottom of the protective cover contacts the tunnel wall or foundation. S3. Connect the protective cover to a stable structure adjacent to the monitoring and measuring pile using at least one fastener to initially limit the position of the protective cover; S4. Detect the installation posture of the metal protective top plate. When the metal protective top plate is not in a horizontal state, adjust the position of the protective cover by using shims. After the position adjustment is completed, add auxiliary fixing points or increase the fastening force to keep the protective cover stable along the first direction, the second direction and the third direction. S5. Detect the shaking and abnormal noise of the protective cover, and check the fit between the protective cover and the monitoring and measuring pile. When the protective cover has no shaking or abnormal noise, and the other parts of the protective cover, except for the fixed sleeve, have no rigid contact with the monitoring and measuring pile, record the installation pile number, installation time, and post-installation status.

[0013] Preferably, the fixing element is a steel bar pin, expansion bolt or chemical anchor. An installation hole is drilled on the tunnel initial support structure adjacent to the monitoring and measuring pile, and the fixing element is inserted into the installation hole and anchored. When the fixed sleeve includes a first half-cylinder, a second half-cylinder and a locking mechanism, the clamping distance between the first half-cylinder and the second half-cylinder can be changed by adjusting the locking mechanism, so that the fixed sleeve clamps the pile body of the monitoring and measuring pile. When the monitoring task is completed or the monitoring point needs to be relocated, the fixing component is released, and the locking mechanism is released when the fixing sleeve is equipped with the locking mechanism. The protective cover is then removed from the monitoring and measuring pile. The protective cover is then inspected for structural integrity, cleaned and maintained, and the processed protective cover is transferred to another monitoring point for reuse.

[0014] Compared with the prior art, the beneficial effects of the present invention are as follows: This invention addresses the problems of monitoring and measuring piles being susceptible to damage from flying stones, falling objects, mechanical collisions, and shotcrete through a three-dimensional frame, triangular reinforcement structure, and metal protective top plate; it solves the problems of unstable positioning and easy shaking after installation by using a fixed sleeve and locking mechanism; it solves the problems of inconvenient installation, disassembly, and sleeve replacement by using a detachable connection structure; it solves the problems of insufficient impact cushioning, difficulty in identification in dim environments, and susceptibility to corrosion in humid environments by using a buffer layer, reflective markings, and anti-corrosion coating; and it solves the problems of insufficient consistency in on-site construction and difficulty in reusing the protective cover by standardizing the manufacturing, fixing, leveling, inspection, and disassembly steps. Attached Figure Description

[0015] Figure 1 A schematic diagram of the structure of the protective cover for the tunnel monitoring and measurement piles; Figure 2 A flowchart illustrating the method for fabricating protective covers for tunnel monitoring and measurement piles; Figure 3 This is a flowchart illustrating the installation method of protective covers for tunnel monitoring and measurement piles. Detailed Implementation

[0016] The following description is intended to disclose the invention and enable those skilled in the art to implement it. The preferred embodiments described below are merely examples, and other obvious variations will occur to those skilled in the art.

[0017] In this embodiment, the first direction is the length direction of the protective cover, the second direction is the width direction of the protective cover, and the third direction is the height direction of the protective cover after installation. The first direction, the second direction, and the third direction are perpendicular to each other.

[0018] Example 1 Reference Figure 1 As shown, a protective cover for tunnel monitoring and measurement piles includes: A three-dimensional frame includes a pair of longitudinal bars arranged along a first direction, a pair of transverse bars arranged along a second direction, a pair of vertical bars arranged along a third direction, and at least a pair of diagonal bars connecting the longitudinal bars and the vertical bars. The first direction, the second direction, and the third direction are perpendicular to each other. The longitudinal bars, the transverse bars, and the vertical bars are connected to form a frame body with a top opening. The diagonal bars form a triangular reinforcing structure with the longitudinal bars and the vertical bars. A metal protective top plate is fixedly installed to cover the top opening; At least one fixed sleeve is connected to the bottom of the three-dimensional frame. A channel is formed inside the fixed sleeve that runs through the third direction. The cross-sectional dimension of the channel is larger than the cross-sectional dimension of the monitoring and measuring pile so that the pile can pass through, thereby covering the outside of the monitoring and measuring pile with the three-dimensional frame and the metal protective top plate.

[0019] In this embodiment, two longitudinal rods extend along a first direction and are spaced apart along a second direction; two transverse rods extend along the second direction and are respectively disposed at the ends of the two longitudinal rods along the first direction, so that the two longitudinal rods and the two transverse rods together form a top opening. Two vertical rods are disposed along a third direction and are respectively connected to the two sides of the three-dimensional frame that are disposed opposite each other along the second direction. Two diagonal rods are respectively disposed on the two sides of the three-dimensional frame that are disposed opposite each other along the second direction, and each diagonal rod connects to the longitudinal rod and the vertical rod on the same side, so that the diagonal rod and the corresponding longitudinal rod and vertical rod form a triangular reinforcement structure.

[0020] A metal protective top plate covers the top opening formed by two longitudinal bars and two transverse bars. A fixing sleeve is connected to the bottom of the three-dimensional frame, allowing the channel of the fixing sleeve to be unobstructed along a third direction. After installation, the monitoring and measuring pile passes through the channel of the fixing sleeve, with the three-dimensional frame located outside the pile and the metal protective top plate located above the pile.

[0021] The longitudinal, transverse, vertical, and diagonal bars are all made of circular cross-section threaded steel with a diameter of 16mm to 20mm, and the metal protective top plate is made of carbon structural steel plate with a thickness of 4mm to 6mm.

[0022] Circular cross-section threaded steel bars, used as a material for three-dimensional frames, can control the overall weight of the protective cover while providing the frame with the ability to withstand flying stones, falling objects, and construction collisions. The threaded structure on the surface of the threaded steel bars also increases the contact area at the connection points of the members, facilitating welding and fixing.

[0023] Carbon structural steel plates, used as metal protective roofs, can shield the protective cover from flying rocks, falling tools, and shotcrete. When the thickness of the metal protective roof is less than 4mm, it is prone to deformation that affects protection after being subjected to concentrated impact; when the thickness is greater than 6mm, it increases the overall weight of the protective cover, which is not conducive to on-site installation, disassembly, and relocation.

[0024] In a preferred embodiment, the longitudinal bars, transverse bars, vertical bars, and diagonal bars are all made of HRB400 threaded steel with a diameter of 18mm, and the metal protective top plate is made of Q235B carbon structural steel plate with a thickness of 5mm.

[0025] When the above materials are used, the three-dimensional frame has the load-bearing capacity to meet the protection requirements of tunnel construction, and the Q235B carbon structural steel plate also has the characteristics of being easy to cut and weld.

[0026] The three-dimensional frame has a length of 220mm to 240mm along the first direction, a width of 130mm to 150mm along the second direction, and a height of 110mm to 130mm along the third direction.

[0027] The length in the first direction is used to determine the protection range of the protective cover along the length direction, the width in the second direction is used to determine the protection range of the protective cover along the width direction, and the height in the third direction is used to adapt to the exposed height of the monitoring and measuring pile.

[0028] When determining the above dimensions, the exposed part of the monitoring and measurement stake should be located within the protective space formed by the three-dimensional frame and the metal protective top plate, while avoiding the protective cover occupying too much of the working space in the tunnel.

[0029] In a preferred embodiment, the three-dimensional frame has a length of 230 mm along the first direction, a width of 140 mm along the second direction, and a height of 120 mm along the third direction.

[0030] When the exposed height and cross-sectional dimensions of the monitoring and measurement stake to be protected change, the length, width, and height of the three-dimensional frame can be adjusted within the above-mentioned size range so that the protective cover can cover the exposed part of the monitoring and measurement stake.

[0031] The fixing sleeve is a circular cross-section steel pipe with a nominal outer diameter of 18mm to 22mm and a length of 90mm to 110mm.

[0032] The internal space of the circular cross-section steel pipe forms a channel for the pile to pass through. The length of the fixing sleeve is used to increase the guiding and positioning range of the protective cover along the direction of the pile, and reduce the deviation of the protective cover relative to the pile after installation.

[0033] The nominal outer diameter of the fixing sleeve and the cross-sectional dimensions of the internal channel of the fixing sleeve are different parameters. When selecting a fixing sleeve, the channel size should be determined according to the wall thickness of the steel pipe and the cross-sectional dimensions of the pile to be protected, so that the pile can pass through the fixing sleeve when it is not locked or open.

[0034] In a preferred embodiment, the length of the fixing sleeve is 100mm. After the protective cover is manufactured, the channel of the fixing sleeve is inspected to ensure that there is no weld slag, burrs, or local deformation that would obstruct the passage of the pile.

[0035] In a preferred embodiment, the fixing sleeve is detachably connected to the three-dimensional frame, and the fixing sleeve and the three-dimensional frame are connected by threaded connection, snap-fit ​​connection or flange bolt connection.

[0036] With detachable connection, when the fixed sleeve is damaged, it can be removed and replaced separately; when the protective cover needs to be used for monitoring and measuring piles with different cross-sectional sizes, a fixed sleeve with the corresponding channel size can also be replaced without replacing the entire three-dimensional frame.

[0037] When using threaded connection, the fixed sleeve is connected to the bottom of the three-dimensional frame through the interlocking thread structure; when using snap-fit ​​connection, the fixed sleeve is installed and removed by closing and releasing the snap; when using flange bolt connection, the fixed sleeve is replaced by removing and installing the bolts at the flange position.

[0038] Furthermore, the fixed sleeve includes a first half-cylinder and a second half-cylinder. The first half-cylinder and the second half-cylinder are connected on one side by a hinge, and a locking mechanism is provided on the other side.

[0039] When the first and second semi-cylinders are closed, they form a channel through which the pile body passes. The locking mechanism is used to adjust the cross-sectional dimensions of the channel, allowing the pile body to pass through in the open state and clamping the pile body in the locked state.

[0040] Before installing the protective cover, release the locking mechanism to allow the first and second semi-cylinders to open relative to each other around the hinge, thereby increasing the effective cross-sectional size of the channel. After the pile enters the channel, close the first and second semi-cylinders and gradually adjust the locking mechanism to gradually reduce the clamping distance between them. When the fixed sleeve can limit the vertical and lateral movement of the protective cover relative to the pile, and the pile does not bend, shift, or undergo other visible deformation, stop adjusting the locking mechanism.

[0041] After adjustment, the fixed sleeve limits the relative position between the protective cover and the pile body, and no longer increases the tightness of the locking mechanism to avoid excessive clamping of the pile body by the fixed sleeve.

[0042] When disassembling the protective cover, release the locking mechanism to allow the first and second half-cylinders to open relative to each other, and then remove the protective cover from the outside of the pile.

[0043] The protective cover for the tunnel monitoring and measurement piles also includes a buffer layer, which is disposed on at least one of the upper surface of the metal protective top plate and at least part of the outer surface of the three-dimensional frame. The buffer layer is made of rubber, polyurethane or engineering plastic.

[0044] When the buffer layer is installed on the upper surface of the metal protective roof, flying stones or falling objects will first come into contact with the buffer layer, which is used to reduce the direct impact of flying stones or falling objects on the metal protective roof.

[0045] When a buffer layer is placed on part of the outer surface of a three-dimensional frame, it can reduce local damage caused by direct collisions between construction machinery, tools, or personnel and the three-dimensional frame.

[0046] In a preferred embodiment, the buffer layer is made of polyurethane material and is fixed to the upper surface of the metal protective top plate by adhesive bonding.

[0047] Furthermore, the upper surface of the metal protective top plate is provided with raised anti-slip textures or reflective marking areas.

[0048] Raised anti-slip textures can be formed by pressing steel plates, surface forming, or welding anti-slip strips to increase the friction on the upper surface of metal protective top plates.

[0049] Reflective marking areas can be created by attaching reflective film to the upper surface of a metal protective roof. In environments with insufficient tunnel lighting, reflective marking areas are used to improve the visibility of the protective cover and remind construction workers and machinery operators to avoid the area where monitoring and measurement stakes are located.

[0050] In one embodiment, raised anti-slip textures are provided on the metal protective top plate; in another embodiment, reflective marking areas are provided on the metal protective top plate; when it is necessary to simultaneously meet the requirements of anti-slip and warning, raised anti-slip textures and reflective marking areas can be provided in different areas of the metal protective top plate respectively.

[0051] Furthermore, the surfaces of the three-dimensional frame, the metal protective top plate, and the fixing sleeve are all provided with an anti-corrosion coating, which is at least one of a zinc plating layer, an epoxy zinc-rich primer layer, or a fluorocarbon topcoat layer.

[0052] A zinc coating can be formed on the metal surface of the protective cover through a zinc plating process; an epoxy zinc-rich primer layer can be applied to the metal surface as an anti-corrosion undercoat; and a fluorocarbon topcoat layer can be used as the outer surface layer of the protective cover to improve its corrosion resistance in humid, dusty, and shotcrete environments.

[0053] In a preferred embodiment, the surfaces of the three-dimensional frame, the metal protective top plate, and the fixing sleeve are first coated with an epoxy zinc-rich primer, and then a topcoat is applied over the epoxy zinc-rich primer.

[0054] After the protective cover is put into use, the metal protective top plate shields the flying rocks, falling objects and sprayed concrete from above, the three-dimensional frame supports the metal protective top plate, the triangular reinforcement structure formed by the diagonal rods restricts the lateral deformation of the three-dimensional frame, and the fixing sleeve limits the relative position between the protective cover and the pile body, so that the protective cover is continuously installed on the outside of the monitoring and measuring pile.

[0055] Example 2 A method for manufacturing a protective cover for tunnel monitoring and measurement piles includes: S1. Prepare metal rods, metal plates and pipes according to the design specifications of the protective cover, and straighten, remove rust, cut and grind the cut edges of the metal rods, metal plates and pipes. S2. Position the longitudinal rod, the transverse rod, and the vertical rod on the welding fixture and weld them together to form a frame body with a top opening. Weld the diagonal rod between the longitudinal rod and the vertical rod to form the three-dimensional frame. S3. Cut the metal sheet to a predetermined size, cover and position it at the top opening of the three-dimensional frame, and weld the edge of the metal sheet to the three-dimensional frame to form the metal protective top plate; S4. Position at least one of the fixing sleeves at a predetermined position at the bottom of the three-dimensional frame, and connect the fixing sleeves to the three-dimensional frame; S5. Clean the weld seams, grind the sharp edges and burrs of the completed protective cover, and perform surface anti-corrosion treatment on the protective cover.

[0056] Through the above steps, the pretreatment of the frame material, top plate material and sleeve material is completed respectively. Then, the welding of the three-dimensional frame, the welding of the metal protective top plate, the connection of the fixed sleeve and the post-treatment of the surface are completed in sequence, so as to obtain the finished protective cover that can be used for monitoring and measuring pile protection.

[0057] When welding the three-dimensional frame, the longitudinal, transverse and vertical members are first spot welded for positioning. After the diagonal dimensions of the main frame and the verticality of the members meet the design requirements, full welding is carried out. The two ends of the diagonal members are connected by full welding.

[0058] By employing a method of spot welding followed by full welding, the conditions for adjusting the position of the members can be preserved before a permanent connection is formed. After spot welding is completed, the two diagonals of the main frame are measured, and the perpendicularity of the vertical members relative to the longitudinal and transverse members is checked.

[0059] When the dimensions of the two diagonals of the main frame and the verticality of the members meet the design requirements, full welding is performed at each connection point. If the inspection results do not meet the design requirements, the positions of the corresponding members are adjusted before full welding, and full welding is performed after re-inspection.

[0060] After the diagonal bar is positioned between the longitudinal bar and the vertical bar, both ends of the diagonal bar are fully welded to form a stable connection between the diagonal bar and the longitudinal bar and the vertical bar.

[0061] Furthermore, when welding the metal protective top plate, intermittent welding is performed along the edge of the metal protective top plate.

[0062] Before welding, cover the top opening of the frame body with the cut metal sheet and adjust the position of the metal sheet so that it completely covers the top opening.

[0063] Subsequently, multiple weld segments are formed at intervals along the edge of the metal sheet, and these weld segments are used to fix the metal sheet to the three-dimensional frame. Intermittent welding can reduce the concentrated heat input generated by continuous welding, thereby reducing the possibility of warping of the metal protective top plate and deformation of the three-dimensional frame.

[0064] In a preferred embodiment, the spacing between adjacent weld segments is 50 mm, and the length of each weld segment is 20 mm.

[0065] Furthermore, the welding of the three-dimensional frame and metal protective top plate adopts carbon dioxide gas shielded welding or manual electric arc welding, and the welding current, welding voltage and welding speed are matched and set according to the material thickness. After the welding is completed, the welds at both ends of the inclined rod are subjected to non-destructive testing.

[0066] In a preferred embodiment, the three-dimensional frame is welded using carbon dioxide gas shielded welding with ER50-6 welding wire and a welding current of 180A to 220A.

[0067] During the welding process, the welding voltage and welding speed are adjusted according to the diameter of the rebar, the thickness of the metal protective top plate, and the welding position to ensure that the weld can cover the connection position and avoid obvious burn-through, slag inclusion, or lack of fusion.

[0068] When using manual arc welding, the corresponding welding current and welding speed should be set according to the electrode specifications, rod diameter and steel plate thickness.

[0069] After welding is completed, non-destructive testing is performed on the welds at both ends of the diagonal bar. In a preferred embodiment, magnetic particle testing is used to inspect the surface and near-surface of the welds at both ends of the diagonal bar for cracks or other welding defects that may affect the stability of the connection.

[0070] Furthermore, the surface anti-corrosion treatment includes sandblasting or shot blasting the protective cover to remove rust, so that the surface cleanliness of the protective cover reaches Sa2.5 level, followed by applying an anti-rust primer, and then applying a topcoat after the anti-rust primer has dried.

[0071] After completing the frame welding, top plate welding, and fixed sleeve connection, first remove the welding slag from each welding position, and then grind the weld surface, sharp edges, and burrs.

[0072] After grinding, the protective cover is sandblasted or shot blasted to remove oxide scale, rust and other deposits from the metal surface, so that the metal surface reaches Sa2.5 cleanliness level.

[0073] After sandblasting or shot blasting, remove dust and abrasive residue from the surface of the protective cover, and then apply an anti-rust primer. After the anti-rust primer dries, apply a topcoat over it.

[0074] In a preferred embodiment, the anti-rust primer is an epoxy zinc-rich primer with a dry film thickness of not less than 60 μm; the topcoat is an acrylic polyurethane topcoat with a total dry film thickness of not less than 120 μm formed by the primer and topcoat.

[0075] Furthermore, the manufacturing method also includes a buffer layer installation step. After the metal protective top plate is welded and before the fixing sleeve is connected, the buffer layer is bonded or mechanically fixed to the upper surface of the metal protective top plate. The buffer layer is made of rubber, polyurethane or engineering plastic.

[0076] After the metal protective top plate is welded, clean the upper surface of the metal protective top plate to remove weld slag and debris that may affect the connection of the buffer layer.

[0077] When using an adhesive bonding method, adhesive material is applied at the contact point between the buffer layer and the metal protective top plate, and then the buffer layer is pressed onto the upper surface of the metal protective top plate.

[0078] When using a mechanical fixing method, the buffer layer is fixed to the upper surface of the metal protective top plate through mechanical connectors.

[0079] After the buffer layer is installed, check for any warping, partial separation, or loosening. Once the inspection is passed, install the fixing sleeve connection.

[0080] Before sandblasting or shot blasting and painting the protective cover after the fixed sleeve connection is completed, use masking material to cover the exposed surface of the buffer layer and the connection edge between the buffer layer and the metal protective top plate, so that the sandblasting abrasive, shot blasting medium, anti-rust primer and topcoat do not come into contact with the buffer layer.

[0081] After sandblasting or shot blasting to remove rust and applying anti-rust primer and topcoat, wait for the anti-corrosion coating to cure before removing the masking material on the outside of the buffer layer and inspecting the surface of the buffer layer and its joints. If the buffer layer is free from damage, contamination, warping, or loosening, proceed to the finished product inspection step.

[0082] After the protective cover is manufactured, the finished product is inspected. The inspection includes the length, width, and height of the three-dimensional frame; the diagonal dimensions of the main frame; the verticality of the vertical rods; the coverage and warping of the metal protective top plate; the unobstructed state of the fixing sleeve channel; the opening and locking status of the locking mechanism; and the appearance of the anti-corrosion coating.

[0083] The qualified protective cover should meet the following requirements: the three-dimensional frame should not have any obvious twists that affect the installation; the metal protective top plate should be able to completely cover the top opening; there should be no welding slag or burrs in the fixed sleeve channel that would obstruct the pile body from passing through; the first half-cylinder, the second half-cylinder and the locking mechanism should be able to open, close and lock normally; the anti-corrosion coating should be continuous and there should be no obvious omissions or peeling.

[0084] Example 3 A method for installing a protective cover for tunnel monitoring and measurement piles includes: S1. Determine the location of the monitoring and measuring piles inside the tunnel, clear the floating debris and obstacles around the monitoring and measuring piles, and measure and mark the installation reference of the protective cover; S2. Insert the protective cover from the top of the monitoring and measuring pile, so that the pile body of the monitoring and measuring pile passes through the channel of the fixed sleeve, and move the protective cover downward until the bottom of the protective cover contacts the tunnel wall or foundation. S3. Connect the protective cover to a stable structure adjacent to the monitoring and measuring pile using at least one fastener to initially limit the position of the protective cover; S4. Detect the installation posture of the metal protective top plate. When the metal protective top plate is not in a horizontal state, adjust the position of the protective cover by using shims. After the position adjustment is completed, add auxiliary fixing points or increase the fastening force to keep the protective cover stable along the first direction, the second direction and the third direction. S5. Detect the shaking and abnormal noise of the protective cover, and check the fit between the protective cover and the monitoring and measuring pile. When the protective cover has no shaking or abnormal noise, and the other parts of the protective cover, except for the fixed sleeve, have no rigid contact with the monitoring and measuring pile, record the installation pile number, installation time, and post-installation status.

[0085] Furthermore, the fasteners are steel pins, expansion bolts, or chemical anchors. Installation holes are drilled in the initial support structure of the tunnel adjacent to the monitoring and measurement piles, and the fasteners are inserted into and anchored.

[0086] Before installation, confirm that the monitoring and measurement piles have been anchored and clear away any loose debris, shotcrete, and other obstructions around the monitoring and measurement piles.

[0087] In a preferred embodiment, debris and loose material are cleared from a range of at least 30 cm around the monitoring and measurement pile, and the exposed height and cross-sectional dimensions of the pile are measured.

[0088] Based on the installation location of the protective cover and the connection location of the fasteners, mark the installation hole positions on the tunnel's initial support structure adjacent to the monitoring and measuring pile. The installation holes are located on the tunnel's initial support structure; no holes are drilled in the monitoring and measuring pile itself.

[0089] When using reinforcing bar pins, insert the reinforcing bar pins into the installation holes and complete the anchoring; when using expansion bolts, insert the expansion bolts into the installation holes and tighten them to form an anchor between the expansion part and the inner wall of the installation hole; when using chemical anchors, clean the installation holes and install the chemical anchors, and make subsequent adjustments to the protective cover after the anchoring connection is formed.

[0090] After the fasteners are installed, the protective cover is initially limited, making it less likely to fall off from the location of the monitoring and measuring stakes during the adjustment of the installation posture of the metal protective top plate.

[0091] Furthermore, when the fixed sleeve includes a first half-cylinder, a second half-cylinder, and a locking mechanism, the clamping distance between the first half-cylinder and the second half-cylinder can be changed by adjusting the locking mechanism, so that the fixed sleeve clamps the pile body of the monitoring and measuring pile.

[0092] Before inserting the protective cover, open the locking mechanism to allow the first and second half-cylinders to open relative to each other. Move the protective cover to the monitoring and measuring stake, allowing the stake to enter the channel formed by the first and second half-cylinders.

[0093] Subsequently, the first and second half-cylinders are closed, and the locking mechanism is gradually adjusted to gradually reduce the clamping gap between the first and second half-cylinders.

[0094] During the adjustment process, after each adjustment is completed, gently push the protective cover along the first, second, and third directions to check whether there is any perceptible relative movement between the protective cover and the pile body, and at the same time observe whether the pile body bends, shifts, or undergoes other visible deformation.

[0095] When the fixing sleeve can limit the vertical and lateral movement of the protective cover relative to the pile body, and the pile body does not bend, shift, or undergo other visible deformation, the adjustment of the locking mechanism should be stopped. At this point, the fixing sleeve is used to position the protective cover, and the tightening degree of the locking mechanism is no longer increased.

[0096] If bending, displacement or other visible deformation of the pile is found during the adjustment process, the locking mechanism is adjusted in the opposite direction to increase the clamping distance between the first half-cylinder and the second half-cylinder until the pile returns to its original state, and then the stability of the protective cover is rechecked.

[0097] After the bottom of the protective cover contacts the tunnel wall or foundation, use a level to check the installation posture of the metal protective top plate along the first and second directions.

[0098] When the metal protective top plate is not in a horizontal position, shims are placed between the bottom of the protective cover and the tunnel wall or foundation, and the installation posture of the protective cover is changed by adjusting the position or number of shims.

[0099] After adjusting the position, use a level to check the installation posture of the metal protective top plate again. Once the metal protective top plate is level, add auxiliary fixing points or increase the tightening force of the fasteners to ensure that the protective cover remains stable in the first, second, and third directions.

[0100] For installation areas near the working face or with strong vibrations, auxiliary fixing connections can be added between the three-dimensional frame and the adjacent stable structure to reduce the loosening of the protective cover caused by construction vibrations.

[0101] After installation, shake the protective cover in the first, second, and third directions respectively to check for any perceptible looseness and check for any abnormal noises caused by component collisions during the shaking process.

[0102] At the same time, check the fit between the protective cover and the monitoring and measuring pile. Except for the positioning or clamping position between the fixed sleeve and the pile body, the three-dimensional frame and the metal protective top plate do not form rigid contact with the monitoring and measuring pile.

[0103] If the protective cover is loose, check the fasteners, auxiliary fixing points, and locking mechanism, and eliminate the looseness by increasing the tightening force, adjusting the shims, or adding auxiliary fixing points.

[0104] If there is abnormal noise from the protective cover, check whether the three-dimensional frame or metal protective top plate is in contact with the pile body, and readjust the position of the protective cover.

[0105] After ensuring that the protective cover is stable and makes no abnormal noise, and that the rest of the protective cover, except for the fixing sleeve, is not in rigid contact with the monitoring and measuring pile, record the installation pile number, installation time, installation personnel, and post-installation status.

[0106] Furthermore, when the monitoring task is completed or the monitoring point needs to be relocated, the fasteners are removed, and the locking mechanism is released when the fixed sleeve is equipped with a locking mechanism. The protective cover is then removed from the monitoring and measuring stake, and the structural integrity of the protective cover is checked, cleaned, and maintained. The treated protective cover is then transferred to another monitoring point for reuse.

[0107] During disassembly, first release the anchoring connection between the fastener and the initial support structure of the tunnel, and then release the auxiliary fastening connection between the protective cover and the adjacent stable structure. When the fixed sleeve is equipped with a locking mechanism, release the locking mechanism to release the clamping of the pile body by the first half-cylinder and the second half-cylinder; when the fixed sleeve is not equipped with a locking mechanism, it is not necessary to perform the locking mechanism release operation.

[0108] Then, the protective cover is moved upward along the axis of the pile body, so that the pile body exits the channel of the fixed sleeve, and the protective cover is removed from the outside of the monitoring and measuring pile.

[0109] After the protective cover is removed, check whether the three-dimensional frame is bent, cracked or damaged by welds, check whether the metal protective top plate is deformed in a way that affects the protective effect, and check whether the fixing sleeve, the first half of the cylinder, the second half of the cylinder, the hinge and the locking mechanism can operate normally.

[0110] Remove sprayed concrete, dust, and other debris from the surface of the protective cover, and repair any localized damage to the anti-corrosion coating.

[0111] After completing the structural integrity check, cleaning, and maintenance, the protective cover will be moved to the next monitoring point and reinstalled and used following the above installation steps.

[0112] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely principles of the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of the claimed invention. The scope of protection claimed by the appended claims and their equivalents is defined.

Claims

1. A protective cover for tunnel monitoring and measurement piles, characterized in that, include: A three-dimensional frame includes a pair of longitudinal bars arranged along a first direction, a pair of transverse bars arranged along a second direction, a pair of vertical bars arranged along a third direction, and at least a pair of diagonal bars connecting the longitudinal bars and the vertical bars. The first direction, the second direction, and the third direction are perpendicular to each other. The longitudinal bars, the transverse bars, and the vertical bars are connected to form a frame body with a top opening. The diagonal bars form a triangular reinforcing structure with the longitudinal bars and the vertical bars. A metal protective top plate is fixedly installed to cover the top opening; At least one fixed sleeve is connected to the bottom of the three-dimensional frame. A channel is formed inside the fixed sleeve that runs through the third direction. The cross-sectional dimension of the channel is larger than the cross-sectional dimension of the monitoring and measuring pile so that the pile can pass through, thereby covering the outside of the monitoring and measuring pile with the three-dimensional frame and the metal protective top plate.

2. The protective cover for tunnel monitoring and measurement piles according to claim 1, characterized in that, The longitudinal rod, the transverse rod, the vertical rod, and the diagonal rod are all circular cross-section threaded steel bars with a diameter of 16mm to 20mm, and the metal protective top plate is a carbon structural steel plate with a thickness of 4mm to 6mm.

3. The protective cover for tunnel monitoring and measurement piles according to claim 1, characterized in that, The length of the three-dimensional frame along the first direction is 220mm to 240mm, the width along the second direction is 130mm to 150mm, and the height along the third direction is 110mm to 130mm.

4. A protective cover for tunnel monitoring and measurement piles according to claim 1, characterized in that, The fixing sleeve is a circular cross-section steel pipe with a nominal outer diameter of 18mm to 22mm and a length of 90mm to 110mm.

5. A protective cover for tunnel monitoring and measurement piles according to claim 1, characterized in that, The fixing sleeve is detachably connected to the three-dimensional frame, and the fixing sleeve and the three-dimensional frame are connected by threaded connection, snap-fit ​​connection or flange bolt connection. The fixed sleeve includes a first half-cylinder and a second half-cylinder. The first half-cylinder and the second half-cylinder are connected on one side by a hinge, and a locking mechanism is provided on the other side. The locking mechanism is used to adjust the cross-sectional size of the channel so that the channel allows the pile to pass through in the open state and clamps the pile in the locked state.

6. A protective cover for tunnel monitoring and measurement piles according to claim 1, characterized in that, The protective cover for the tunnel monitoring and measurement piles also includes a buffer layer, which is disposed on at least one of the upper surface of the metal protective top plate and at least part of the outer surface of the three-dimensional frame. The buffer layer is made of rubber, polyurethane or engineering plastic. The upper surface of the metal protective top plate is provided with raised anti-slip textures or reflective marking areas. The surfaces of the three-dimensional frame, the metal protective top plate, and the fixing sleeve are all provided with an anti-corrosion coating, which is at least one of a zinc plating layer, an epoxy zinc-rich primer layer, or a fluorocarbon topcoat layer.

7. A method for manufacturing a protective cover for tunnel monitoring and measurement piles, applied to the protective cover for tunnel monitoring and measurement piles as described in any one of claims 1-6, characterized in that, include: S1. Prepare metal rods, metal plates and pipes according to the design specifications of the protective cover, and straighten, remove rust, cut and grind the cut edges of the metal rods, metal plates and pipes. S2. Position the longitudinal rod, the transverse rod, and the vertical rod on the welding fixture and weld them together to form a frame body with a top opening. Weld the diagonal rod between the longitudinal rod and the vertical rod to form the three-dimensional frame. S3. Cut the metal sheet to a predetermined size, cover and position it at the top opening of the three-dimensional frame, and weld the edge of the metal sheet to the three-dimensional frame to form the metal protective top plate; S4. Position at least one of the fixing sleeves at a predetermined position at the bottom of the three-dimensional frame, and connect the fixing sleeves to the three-dimensional frame; S5. Clean the weld seams, grind the sharp edges and burrs of the completed protective cover, and perform surface anti-corrosion treatment on the protective cover.

8. A method for manufacturing a protective cover for tunnel monitoring and measurement piles according to claim 7, characterized in that, When welding the three-dimensional frame, the longitudinal rods, the transverse rods and the vertical rods are first spot welded for positioning. After the diagonal dimensions and verticality of the frame body meet the design requirements, full welding is performed. The two ends of the diagonal rods are connected by full welding. When welding the metal protective top plate, intermittent welding is performed along the edge of the metal protective top plate; The welding of the three-dimensional frame and the metal protective top plate is carried out by carbon dioxide gas shielded welding or manual arc welding, and the welding current, welding voltage and welding speed are set according to the material thickness. After the welding is completed, the welds at both ends of the inclined rod are subjected to non-destructive testing. The surface anti-corrosion treatment includes sandblasting or shot blasting the protective cover to remove rust, so that the surface cleanliness of the protective cover reaches Sa2.5 level, then applying an anti-rust primer, and applying a topcoat after the anti-rust primer dries. The manufacturing method also includes a buffer layer installation step. After the metal protective top plate is welded and before the fixing sleeve is connected, the buffer layer is bonded or mechanically fixed to the upper surface of the metal protective top plate. The buffer layer is made of rubber, polyurethane or engineering plastic.

9. A method for installing a protective cover for tunnel monitoring and measurement piles, applied to the protective cover for tunnel monitoring and measurement piles as described in any one of claims 1-6, characterized in that, include: S1. Determine the location of the monitoring and measuring piles inside the tunnel, clear the floating debris and obstacles around the monitoring and measuring piles, and measure and mark the installation reference of the protective cover; S2. Insert the protective cover from the top of the monitoring and measuring pile, so that the pile body of the monitoring and measuring pile passes through the channel of the fixed sleeve, and move the protective cover downward until the bottom of the protective cover contacts the tunnel wall or foundation. S3. Connect the protective cover to a stable structure adjacent to the monitoring and measuring pile using at least one fastener to initially limit the position of the protective cover; S4. Detect the installation posture of the metal protective top plate. When the metal protective top plate is not in a horizontal state, adjust the position of the protective cover by using shims. After the position adjustment is completed, add auxiliary fixing points or increase the fastening force to keep the protective cover stable along the first direction, the second direction and the third direction. S5. Detect the shaking and abnormal noise of the protective cover, and check the fit between the protective cover and the monitoring and measuring pile. When the protective cover has no shaking or abnormal noise, and the other parts of the protective cover, except for the fixed sleeve, have no rigid contact with the monitoring and measuring pile, record the installation pile number, installation time, and post-installation status.

10. The method for installing a protective cover for tunnel monitoring and measurement piles according to claim 9, characterized in that, The fastener is a steel bar pin, expansion bolt or chemical anchor. An installation hole is drilled on the tunnel initial support structure adjacent to the monitoring and measuring pile, and the fastener is inserted into the installation hole and anchored. When the fixed sleeve includes a first half-cylinder, a second half-cylinder and a locking mechanism, the clamping distance between the first half-cylinder and the second half-cylinder can be changed by adjusting the locking mechanism, so that the fixed sleeve clamps the pile body of the monitoring and measuring pile. When the monitoring task is completed or the monitoring point needs to be relocated, the fixing component is released, and the locking mechanism is released when the fixing sleeve is equipped with the locking mechanism. The protective cover is then removed from the monitoring and measuring pile. The protective cover is then inspected for structural integrity, cleaned and maintained, and the processed protective cover is transferred to another monitoring point for reuse.