Reinforced concrete member assembled wind-shield wall for operating railway in strong wind area
Through the assembly technology of prefabricated reinforced concrete components, the safety risks and construction period extension problems of railway windshield wall construction in windy areas have been solved, and a fast and stable windshield wall structure has been achieved, which is suitable for railway operations under strong wind conditions.
Patent Information
- Application Number
- CN202420312500.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-20
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2034-02-20
AI Technical Summary
In windy areas, the existing railway windbreak walls have insufficient wind protection capabilities, leading to construction safety risks and extended construction periods. Especially under severe weather conditions, it is difficult to achieve rapid construction with existing technology.
Prefabricated reinforced concrete components are used, and gaps and lifting rings are reserved at the factory to assemble the components into an integral wind-shielding wall. The connection holes are filled with cement mortar to form a stable structure, and the I-beam is hammered to the base to improve stability. .
It avoids the safety risks of on-site construction, achieves rapid construction and a stable windshield wall structure, facilitates the transportation and hoisting of small machinery, and is suitable for operating railways with heavy wind and sand.
Smart Images

Figure CN221798202U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of railway construction in windy areas, and in particular relates to a windbreak wall assembled from reinforced concrete components of railways in operation in windy areas. Background Art
[0002] During the operation of railways in windy areas, windbreaks are set up to prevent trains from being overturned by strong winds. With the opening of the "Green Giant" EMU, the windbreaks of existing railways are insufficient to protect against winds and cannot meet the normal operation of the "Green Giant" EMU under strong winds. Therefore, it is necessary to strengthen the existing railway windbreaks and windbreaks, or to add windbreaks and windbreaks in some sections.
[0003] For operating railways, foreign objects are not allowed to enter the railway limit. The existing technology is to set up concrete cast-in-place windbreak walls and steel component windbreak walls. If the windbreak wall structure adopts concrete cast-in-place structure, the formwork must be supported above the ground during construction. In order to ensure that the poured concrete reaches the necessary strength, the span of the formwork above the ground is relatively long. Once a strong wind occurs, the construction formwork will inevitably be blown into the railway limit, causing a safety accident. In addition, in order to ensure construction safety, according to construction regulations, on-site construction can only be carried out during the time period when the wind force is less than level 6. The number of days that can be constructed throughout the year is limited. Affected by bad weather, the construction period is uncontrollable. If the windbreak wall structure adopts a steel component windbreak wall, the steel component windbreak wall can also be assembled on site, but after the windbreak wall is assembled, the overall weight is relatively light, and reinforced concrete anchor piles need to be set underground as the foundation, and connected to the upper steel component through anchor bolts to resist the wind load borne by the steel component windbreak wall. The underground anchor pile foundation requires on-site excavation of pile pits and pouring of concrete. The on-site engineering volume is large and the construction period is long. Both structures cannot fully achieve the purpose of rapid construction. Utility Model Content
[0004] In order to make up for the deficiencies of the prior art, the utility model provides a windbreak wall assembled of reinforced concrete components for railways operating in windy areas, which can avoid the safety risks existing in on-site construction and can be constructed quickly.
[0005] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0006] A windbreak wall assembled of reinforced concrete components for railways in windy areas, comprising a plurality of reinforced concrete components, with notches arranged on both sides of the reinforced concrete components, and the notches of two adjacent reinforced concrete components forming a closed connection hole;
[0007] Components are arranged in the connection holes, and the connection holes are filled with cement mortar to connect the reinforced concrete components into an integral windbreak wall.
[0008] Furthermore, the notch is rectangular in shape.
[0009] Furthermore, a lifting ring is provided on the top of the reinforced concrete component, and the lifting ring is a steel bar ring.
[0010] Furthermore, the components are two 20A I-beams.
[0011] Furthermore, the bottom of the component is arranged at a position 1 m below the base of the windbreak wall.
[0012] Furthermore, the weight of a single reinforced concrete component is 1 to 1.25 tons.
[0013] Furthermore, in the height direction, the connection holes of each layer are aligned up and down.
[0014] Beneficial effects of the utility model:
[0015] 1) The utility model adopts factory prefabricated reinforced concrete components. After the individual reinforced concrete components are transported to the site, they are assembled into an integral windbreak wall structure, which can avoid the safety risks of supporting formwork on site construction and enable rapid construction;
[0016] 2) The reinforced concrete component of the utility model weighs 1 to 1.25 tons, which is convenient for small-scale mechanical transportation and lifting;
[0017] 3) The utility model uses an I-beam that is hammered to 1m below the base of the windbreak wall, thereby improving the stability of the entire windbreak wall and being suitable for operating railways with heavy sandstorms. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 Cross-sectional view of windbreak wall assembled from reinforced concrete components;
[0019] Figure 2 It is a plan view of reinforced concrete components;
[0020] Figure 3 It is the side view of reinforced concrete member;
[0021] Figure 4 It is the plane assembly drawing of reinforced concrete components;
[0022] Figure 5 Elevation drawing of windbreak wall assembled from reinforced concrete elements;
[0023] In the figure: 1- reinforced concrete component, 2- notch, 3- lifting ring, 4- connecting hole, 5- two 20A I-beams, 6- cement mortar. DETAILED DESCRIPTION
[0024] The present invention is described in detail below in conjunction with specific implementation methods.
[0025] like Figure 1As shown, the utility model comprises a plurality of reinforced concrete components 1, and notches 2 are arranged on both sides of the reinforced concrete components 1, and the notches 2 of two adjacent reinforced concrete components 1 form a closed connection hole 4, and the shape of the notch 2 is rectangular; a lifting ring 3 is arranged on the top of the reinforced concrete component 1, and the lifting ring 3 is a steel bar ring;
[0026] A component 5 is arranged in the connecting hole 4, and the component 5 is two 20A I-beams. The bottom of the component 5 is arranged at a position 1m below the base of the windbreak wall; the cement mortar 6 is filled in the connecting hole 4 to connect the reinforced concrete component 1 into an integral windbreak wall; the weight of the single reinforced concrete component 1 is 1 to 1.25 tons, and in the height direction, the connecting holes 4 of each layer are aligned up and down.
[0027] The construction method of the utility model is as follows: firstly, the structural dimensions of the windbreak wall are determined, the windbreak wall is disassembled into reinforced concrete components 1, the reinforced concrete components 1 are prefabricated, and after the single reinforced concrete components 1 are transported to the site, they are assembled into an integral windbreak wall structure.
[0028] The specific steps include:
[0029] Step 1: Determine the wind force that the windbreak wall bears according to the design wind speed, and determine the overall structural dimensions of the windbreak wall according to the wind force;
[0030] Step 2: according to the overall structural size of the windbreak wall, the windbreak wall is disassembled into a single reinforced concrete component 1, and the single reinforced concrete component 1 is prefabricated in a factory;
[0031] Step 3: Reserving interconnected gaps 2 for the single prefabricated reinforced concrete components 1;
[0032] Step 4: transporting the single reinforced concrete component 1 to the site for assembly, and forming a closed connection hole 4 after plane assembly;
[0033] Step 5: insert steel sections into the connection holes 4 and pour in cement mortar 6. After the cement mortar 6 hardens, connect the individual reinforced concrete components 1 into an integral windbreak wall.
[0034] The specific embodiments are as follows:
[0035] The utility model is described in detail below in conjunction with an implementation method for adding a windbreak wall in a reinforcement project for the first 100 kilometers of a railway section from K9+755 to K108+680.
[0036] According to the wind speed v = 60m / s, the wind pressure on the windbreak wall was calculated and the overall structural dimensions of the windbreak wall were determined, such as Figure 1 As shown, when the windbreak wall is 3.5m high, the windbreak wall width is 1m;
[0037] According to the overall structural size of the windbreak wall, it is disassembled into component 1, which is a reinforced concrete of 1m (length) × 1m (width) × 0.5m (height), such as Figure 2 , Figure 3 As shown; component 1 is prefabricated in the factory, and component 1 weighs 1.25t, which is convenient for small machinery transportation and lifting; gaps 2 are reserved on the left and right sides, and lifting rings 3 (lifting steel bar rings) are reserved, as shown Figure 2 , Figure 3 As shown;
[0038] After the component 1 is transported to the site, it is hoisted and seamlessly spliced. Figure 4 As shown, the notches 2 of two adjacent components 1 form a connecting hole 4; Figure 5 As shown, the 3.5m high windbreak wall is composed of 7 layers of reinforced concrete components 1, and the closed connection holes 4 of each layer should be aligned up and down;
[0039] After the components 1 are spliced to the predetermined height and length, two 20A I-beams are placed in the connection holes 4, and the I-beams are hammered to 1m below the base of the windbreak wall. The closed connection holes are filled with cement mortar to connect the components 1 into an integral windbreak wall. At this point, the construction of the windbreak wall assembled with reinforced concrete components is completed. Figure 4 , Figure 5 shown.
[0040] In the description of the present invention, unless otherwise clearly specified and limited, the terms "set", "install", "connect", "connect", and "fix" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0041] The content of the utility model is not limited to the examples listed, and any equivalent changes made to the technical solution of the utility model by ordinary technicians in this field after reading the specification of the utility model are covered by the claims of the utility model.
Claims
1. A windbreak wall assembled from reinforced concrete components for railways in windy areas, characterized by: It comprises a plurality of reinforced concrete components (1), each reinforced concrete component (1) being provided with notches (2) on both sides, and the notches (2) of two adjacent reinforced concrete components (1) forming a closed connection hole (4); A component (5) is arranged in the connection hole (4), and the connection hole (4) is filled with cement mortar (6) to connect the reinforced concrete component (1) into an integral windbreak wall.
2. The windbreak wall assembled from reinforced concrete components of railways in windy areas according to claim 1 is characterized by: The notch (2) has a rectangular shape.
3. The windbreak wall assembled from reinforced concrete components for railways in windy areas according to claim 1 is characterized by: A lifting ring (3) is provided at the top of the reinforced concrete component (1), and the lifting ring (3) is a steel bar ring.
4. The windbreak wall assembled from reinforced concrete components for railways in windy areas according to claim 3 is characterized by: The components (5) are two 20A I-beams.
5. The windbreak wall assembled from reinforced concrete components for railways in windy areas according to claim 4, characterized in that: The bottom of the component (5) is arranged at a position 1 m below the base of the windbreak wall.
6. The windbreak wall assembled from reinforced concrete components for railways in windy areas according to claim 5, characterized in that: The weight of a single reinforced concrete component (1) is 1 to 1.25 tons.
7. The windbreak wall assembled from reinforced concrete components for railways in windy areas according to claim 6, characterized in that: In the height direction, the connection holes (4) of each layer are aligned vertically.
Citation Information
Cited By
Reinforced concrete member assembled wind-shield wall for operating railway in strong wind area and construction method
CN117888473A