Externally-hung sandwich board parapet wall structure

By adopting the combined design of connectors, fixings and parapets in the external sandwich board parapet structure, using the combination of hook anchors and fixed seats, combined with adhesive slurry and leak-proof plug joints, prefabrication and modularization are achieved The installation solves the problem of complicated installation steps in the existing technology, significantly speeds up the construction and ensures the sealing effect.

CN221798934UActive Publication Date: 2024-10-01北京宏德光展新能源科技有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420273615.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2024-10-01
Estimated Expiration
2034-02-05

AI Technical Summary

Technical Problem

In the existing technology, the installation steps of external prefabricated wall panels are cumbersome, resulting in long on-site construction time, and time cannot be saved through prefabricated modularization.

Method used

Adopt a structure including connectors, fixings and parapets, where the fixings are fixed to the building through the connectors, the connectors cover the top of the building, and the fixings are wrapped between the concrete laminate and the roof insulation layer In the gap, the parapet wall is installed through fasteners, using the combined design of hook anchors and fixed seats, combined with adhesive slurry and leak-proof plugs, to achieve prefabricated and modular installation.

Benefits of technology

Through prefabrication and modular design, the installation process is simplified, the construction speed is significantly accelerated, the on-site construction time is reduced, and the sealing effect is achieved through anti-leak plug joints to avoid cement leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221798934U_ABST
    Figure CN221798934U_ABST
Patent Text Reader

Abstract

The utility model provides an externally-hung sandwich plate parapet wall structure, which relates to the technical field of parapet walls, and comprises a connecting piece, a fixing piece and a parapet wall, and the fixing piece is fixed on a building through the connecting piece. According to the externally-hung sandwich plate parapet wall structure, through the arrangement of the fixing pieces, the parapet wall is prefabricated and modularized by splicing and combining the connecting part, the heat preservation plate and the surface layer, the site construction time can be saved, when the parapet wall is installed, hook head anchor bolts are aligned to the fixing seats which are installed in advance, preliminary positioning installation is conducted, and the installation efficiency is improved. One side of the plate layer is brushed with the adhesion slurry so that the parapet wall can be fixed in an auxiliary mode, the upper end, corresponding to the bin mold cavity, of the roof heat preservation layer is drilled, cement is injected into the cavity through the drilled hole so that the cement can completely cover the hook-headed anchor bolt and the fixing base, and after the cement is completely solidified, installation of the parapet wall can be completed; the installation process is simple and fast, and the construction speed of the parapet wall is greatly increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of parapet walls, in particular to an external sandwich board parapet wall structure. Background Art

[0002] A parapet is a wall structure that is set along the outer contour of a building on the edge of a building's roof or on a fence. Using sandwich panels to prefabricate parapets can save time and cost. Prefabricated parapets can be manufactured in a factory environment away from on-site construction, thereby reducing on-site construction time. Parapets made of sandwich panels have a lighter weight and modular design, making them easier to install.

[0003] After searching, the patent document with the number "CN219931440U" mentioned, "An assembled steel structure external prefabricated wall and roof parapet structure, which reduces the difficulty of installing the prefabricated top-level external prefabricated wall panels and ensures the convenience and safety of parapet construction." The device adopts an assembled steel structure to enable the parapet to be stably fixed on the building. However, the installation steps of the device are relatively cumbersome, resulting in a long on-site construction time, and the device cannot save time through prefabricated modularization. Utility Model Content

[0004] The utility model aims to provide an external sandwich board parapet structure to solve the problem that the above-mentioned installation steps are relatively complicated and result in a long on-site construction time.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an external sandwich panel parapet structure, comprising a connecting piece, a fixing piece and a parapet, wherein the fixing piece is fixed to a building through the connecting piece, the connecting piece covers the top of the building, the connecting piece comprises a concrete laminate layer and a roof insulation layer, the fixing piece is coated in the gap between the concrete laminate layer and the roof insulation layer, the fixing piece comprises a bin mold and a fixing seat, and the parapet is installed on one side of the building through the fixing piece.

[0006] Preferably, a leak-proof plug is fixedly connected in the gap at the connection between the concrete laminated layer and the parapet.

[0007] Preferably, the anti-leakage plugging seam can be made of materials such as PE foam rods and foamed rubber and plastics with anti-leakage effect.

[0008] Preferably, the parapet comprises a connecting portion, an insulation board and a surface layer, and the parapet is formed by sequentially arranging, splicing and merging the connecting portion, the insulation board and the surface layer.

[0009] Preferably, the connecting portion comprises a plate layer and a hook anchor bolt, the hook anchor bolt is embedded and fixed in the plate layer, and the plate layer is fixed to a fixing seat through the hook anchor bolt.

[0010] Preferably, a slurry having an adhesive effect is laid on the side of the board layer facing the building.

[0011] Preferably, a cavity is formed between the bin mold and the roof insulation layer, and the hook anchor bolt can be reinforced by cast-in-place cement in the bin mold.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] The parapet is composed of the connection part, the insulation board and the surface layer, and is prefabricated and modularized by splicing, which can save time for on-site construction. The interlayer of the parapet can be customized freely during prefabrication. The concrete superposition layer is laid flat on the top of the building, and then the roof insulation layer is fixed on the concrete superposition layer. When installing the parapet, the hook anchor bolt is aligned to the central circular hole of the fixing seat installed in advance, and a preliminary positioning installation is performed so that one side of the board layer of the parapet is in contact with the building. Brushing the adhesive slurry on one side of the board layer helps to assist in fixing the parapet. A hole is drilled at the upper end of the corresponding warehouse mold cavity on the roof insulation layer, and cement is added into the cavity through the drilling hole so that the cement completely covers the hook anchor bolt and the fixing seat. After the cement is completely solidified, the installation of the parapet is completed. The installation process is simple and fast, which greatly speeds up the construction speed of the parapet. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 This is a schematic diagram of the structure of the external sandwich panel parapet of the utility model;

[0015] Figure 2 This is a schematic diagram of the fixing structure of the utility model;

[0016] Figure 3 This is a schematic diagram of the parapet structure of the utility model;

[0017] Figure 4 It is a schematic diagram of the cross-sectional structure of the parapet installation of the utility model.

[0018] Numbers in the figure: 1, building; 2, connecting part; 21, concrete superposition layer; 211, leak-proof plugging; 22, roof insulation layer; 3, fixing part; 31, warehouse mold; 32, fixing seat; 4, parapet; 41, connecting part; 411, board layer; 412, hook anchor bolt; 42, insulation board; 43, surface layer. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0020] See also Figure 1-4 As shown, the utility model provides a technical solution: an external sandwich panel parapet structure, comprising a connecting member 2, a fixing member 3 and a parapet 4, wherein the fixing member 3 is fixed to a building 1 through the connecting member 2, the connecting member 2 covers the top of the building 1, the connecting member 2 comprises a concrete laminated layer 21 and a roof insulation layer 22, the fixing member 3 is wrapped in a gap between the concrete laminated layer 21 and the roof insulation layer 22, the fixing member 3 comprises a bin mold 31 and a fixing seat 32, the inside of the bin mold 31 is provided with a fixing seat 32, and the parapet 4 is installed on one side of the building 1 through the fixing member 3.

[0021] Furthermore, a leak-proof plugging seam 211 is fixedly connected in the gap at the connection between the concrete superimposed layer 21 and the parapet 4. When the parapet 4 is installed, there will be cracks between the parapet 4 and the building 1. By plugging the leak-proof plugging seam 211 into the cracks, a sealing effect can be achieved to prevent cement from leaking through the cracks when grouting cement.

[0022] Furthermore, the leak-proof plugging seam 211 is made of materials such as PE foam rods and foamed rubber and plastics that have a leak-proof effect. The material of the leak-proof plugging seam 211 should be selected from materials with good leak-proof effect.

[0023] Furthermore, the parapet 4 includes a connecting portion 41, an insulation board 42 and a surface layer 43. The parapet 4 is formed by the connecting portion 41, the insulation board 42 and the surface layer 43 being arranged, spliced ​​and combined in sequence. The parapet 4 is prefabricated and modularized by splicing and combining the connecting portion 41, the insulation board 42 and the surface layer 43, which can save time for on-site construction, and the interlayer of the parapet 4 can be freely customized during prefabrication.

[0024] Furthermore, the connecting part 41 includes a plate layer 411 and a hook anchor 412. The hook anchor 412 is embedded and fixed in the plate layer 411. The plate layer 411 is fixed to the fixing seat 32 through the hook anchor 412. When installing the parapet 4, the hook anchor 412 is aligned with the central circular hole of the fixing seat 32 installed in advance for preliminary positioning and installation.

[0025] Furthermore, a slurry with an adhesive effect is laid on the side of the board layer 411 facing the building 1 , and brushing the adhesive slurry on one side of the board layer 411 of the parapet 4 helps to assist in fixing the parapet 4 .

[0026] Furthermore, a cavity is formed between the chamber mold 31 and the roof insulation layer 22, and cement is poured into the cavity of the chamber mold 31 so that the cement completely covers the hook anchor bolt 412 and the fixing seat 32. After the cement is completely solidified, the installation of the parapet 4 can be completed. The installation process is simple and quick, which greatly speeds up the construction speed of the parapet 4.

[0027] Working principle: First, an external sandwich board parapet structure is moved to the working position. In the first step, the parapet 4 is prefabricated and modularized by splicing the connecting part 41, the insulation board 42 and the surface layer 43, which can save the time of on-site construction, and the interlayer of the parapet 4 can be freely customized during prefabrication. In the second step, the concrete superposition layer 21 is laid on the top of the building 1, and then the roof insulation layer 22 is fixed on the concrete superposition layer 21. In the third step, when installing the parapet 4, the hook anchor 412 is aligned with the central circular hole of the pre-installed fixing seat 32 for preliminary positioning and installation, so that one side of the board layer 411 of the parapet 4 is in contact with the building 1, and one side of the board layer 411 is brushed The adhesive slurry helps to assist in fixing the parapet 4. In the fourth step, a hole is drilled on the roof insulation layer 22 at the upper end of the cavity of the bin mold 31, and cement is added into the cavity through the drilling hole so that the cement completely covers the hook anchor bolt 412 and the fixing seat 32. After the cement is completely solidified, the installation of the parapet 4 can be completed. The installation process is simple and fast, which greatly speeds up the construction speed of the parapet 4. In the fifth step, when the parapet 4 is installed, there will be cracks between the parapet 4 and the building 1. By plugging the cracks with leak-proof plugs 211, a sealing effect can be achieved to prevent cement from leaking through the cracks when grouting cement, thus completing the use process of an external sandwich board parapet structure.

Claims

1. An external sandwich panel parapet structure, characterized in that: The invention comprises a connecting piece (2), a fixing piece (3) and a parapet (4); the fixing piece (3) is fixed to a building (1) through the connecting piece (2); the connecting piece (2) covers the top of the building (1); the connecting piece (2) comprises a concrete laminate layer (21) and a roof insulation layer (22); the fixing piece (3) is covered in a gap between the concrete laminate layer (21) and the roof insulation layer (22); the fixing piece (3) comprises a bin mold (31) and a fixing seat (32); the bin mold (31) is provided with a fixing seat (32); and the parapet (4) is installed on one side of the building (1) through the fixing piece (3).

2. The external sandwich panel parapet structure according to claim 1 is characterized in that: A leak-proof plugging seam (211) is fixedly connected in the gap at the connection between the concrete laminated layer (21) and the parapet wall (4).

3. The external sandwich panel parapet structure according to claim 1 is characterized in that: The parapet (4) comprises a connecting portion (41), a heat-insulating plate (42) and a surface layer (43); the parapet (4) is formed by sequentially arranging, splicing and merging the connecting portion (41), the heat-insulating plate (42) and the surface layer (43).

4. The external sandwich panel parapet structure according to claim 3 is characterized in that: The connecting portion (41) comprises a plate layer (411) and a hook anchor bolt (412), wherein the hook anchor bolt (412) is embedded and fixed in the plate layer (411), and the plate layer (411) is fixed on the fixing seat (32) via the hook anchor bolt (412).

5. The external sandwich panel parapet structure according to claim 4 is characterized in that: The side of the board layer (411) facing the building (1) is paved with slurry having an adhesive effect.

6. The external sandwich panel parapet structure according to claim 1, characterized in that: A cavity is formed between the bin mold (31) and the roof insulation layer (22).