Dust collection cover of mining cement mine drilling machine

By using the combined design of rubber sleeves, assembly rings, plastic cloth covers and sliding rods in the dust collection hood of mining cement mine drilling rigs, the problem that the existing dust collection hood cannot be adjusted is solved and the adaptation and stability to sites of different heights are achieved. Dust collection effect.

CN221799674UActive Publication Date: 2024-10-01ANHUI HAILUO CEMENT CO LTD BAIMASHAN CEMENT PLANT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420543940.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-20
Publication Date
2024-10-01
Estimated Expiration
2034-03-20

AI Technical Summary

Technical Problem

The existing dust collection hood of mining cement mine drilling rigs cannot be adjusted according to the height of different sites, resulting in the inability to adapt to different usage environments and affecting the dust collection effect.

Method used

A mining cement mine drilling rig dust collector including a rubber cover, an assembly ring, a plastic cloth cover, a sliding rod and an adjusting column is designed. Through the combination of the sliding rod and the adjusting column, it can adapt to sites of different heights and work on uneven ground. Maintain stability and improve dust collection effect.

Benefits of technology

It realizes the adaptation to sites of different heights, avoids the bending of the dust collection cover, improves the dust collection effect, maintains stability on uneven floors, and enhances the dust extraction capacity.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221799674U_ABST
    Figure CN221799674U_ABST
Patent Text Reader

Abstract

The utility model discloses a mining cement mine drilling machine dust collection cover, which belongs to the technical field of dust collection covers and comprises a rubber sleeve and an assembly ring mounted at the upper end of the rubber sleeve, the lower end of the rubber sleeve is connected with a plastic cloth sleeve, and the outer wall of the plastic cloth sleeve is sequentially provided with a first connecting plate, a second connecting plate and a bottom plate from top to bottom. A plurality of sliding rods are fixedly connected to the bottom plate. The dust collection cover can adapt to places with different heights through the flexibility of the plastic cloth sleeve for connection, when the height is low, the distance between the first connection plate and the bottom plate and the distance between the second connection plate and the bottom plate are reduced, meanwhile, the sliding rods are matched for limiting, the dust collection cover can be prevented from being bent, and the dust collection effect is not affected; and meanwhile, the dust collection effect can be further improved by pressing the plastic cloth sleeve on the lower portion through the movable supporting plate, and if the drilled dust needs to be extracted, a dust collector can be installed through the connecting pipe for dust collection treatment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a dust collecting hood, in particular to a dust collecting hood for a mining cement mine drill, and belongs to the technical field of dust collecting hoods. Background Art

[0002] When a drilling rig is working, it will bring out dust from the ground or under the working surface, causing dust pollution at the construction site and affecting the environment. Therefore, dust hoods and other equipment are often used for protection when the drilling rig is in use.

[0003] The existing dust collecting hood of the existing cement mining drill needs to adjust the position of the drill bit according to the working site when the drill is working, and the existing dust collecting hood is often a rubber sleeve with a fixed height and cannot be adjusted, so it cannot be used for different sites. Utility Model Content

[0004] The main purpose of the utility model is to solve the problem that the dust collecting hood of a mining cement mine drill rig cannot be adjusted and thus cannot be used for different sites, and to provide a dust collecting hood for a mining cement mine drill rig.

[0005] The purpose of the utility model can be achieved by adopting the following technical solutions:

[0006] A dust collecting cover for a mining cement mine drill comprises a rubber sleeve and an assembly ring installed at the upper end of the rubber sleeve, the lower end of the rubber sleeve is connected to a plastic cloth sleeve, the outer wall of the plastic cloth sleeve is provided with a first connecting plate, a second connecting plate and a bottom plate in sequence from top to bottom, and a plurality of sliding rods are fixedly connected to the bottom plate.

[0007] Preferably, the first connecting plate, the second connecting plate and the inner wall of the bottom plate are all bonded to the outer wall of the plastic cloth sleeve by glue.

[0008] Preferably, the distance between the first connecting plate and the second connecting plate is the same as the distance between the bottom plate and the second connecting plate.

[0009] Preferably, the first connecting plate and the second connecting plate are both provided with a plurality of through holes for movement of the sliding rod.

[0010] Preferably, four adjustment columns are provided at the lower end of the base plate.

[0011] Preferably, the lower end of the adjusting column is threadedly connected with a movable supporting plate.

[0012] Preferably, anti-slip studs are provided at the lower end of the movable support plate.

[0013] Preferably, a limiting nut is installed on the upper end of the sliding rod.

[0014] Preferably, a connecting pipe is installed at the lower part of the plastic cloth sleeve.

[0015] Preferably, a valve is installed on the connecting pipe.

[0016] The beneficial technical effects of the utility model are as follows: according to the dust collecting hood of the mining cement mine drilling rig of the utility model, the dust collecting hood is installed on the fixed frame at the drill bit of the drilling rig through the assembly ring, and can be adapted to places of different heights through the flexibility of the plastic cloth cover used for connection. When the height is low, the distance between the first connecting plate and the second connecting plate and the bottom plate is reduced, and the sliding rod is used for limiting at the same time, which can avoid the bending of the dust collecting hood and affect the dust collecting effect. The movable support plate can also be adjusted under the bottom plate, which can also be used in uneven positions. At the same time, the dust collecting effect can be further improved by pressing the lower plastic cloth cover through the movable support plate. If it is necessary to extract the drilled dust, a dust collector can be installed through the connecting pipe for dust collection. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall structure of a preferred embodiment of the utility model;

[0018] Figure 2 A side view of the overall structure of a preferred embodiment of the utility model;

[0019] Figure 3 It is an exploded schematic diagram of the overall structure according to a preferred embodiment of the utility model;

[0020] Figure 4 A schematic diagram of a bottom plate structure according to a preferred embodiment of the utility model;

[0021] Figure 5 A schematic diagram of the structure of a first connecting plate according to a preferred embodiment of the utility model;

[0022] Figure 6 It is a schematic diagram of the sliding rod structure according to a preferred embodiment of the utility model.

[0023] In the figure: 1. rubber sleeve; 2. assembly ring; 3. first connecting plate; 4. sliding rod; 5. second connecting plate; 6. bottom plate; 7. plastic cloth sleeve; 8. connecting pipe; 9. valve; 10. movable support plate; 11. anti-slip spikes; 12. adjusting column. DETAILED DESCRIPTION

[0024] In order to make the technical solution of the present invention more clear and specific to those skilled in the art, the present invention is further described in detail below in conjunction with embodiments and drawings, but the implementation methods of the present invention are not limited thereto.

[0025] like Figure 1-Figure 6As shown, the dust collecting cover of the mining cement mine drilling rig provided in this embodiment includes a rubber sleeve 1 and an assembly ring 2 installed on the upper end of the rubber sleeve 1, the lower end of the rubber sleeve 1 is connected to a plastic cloth sleeve 7, the outer wall of the plastic cloth sleeve 7 is provided with a first connecting plate 3, a second connecting plate 5 and a bottom plate 6 from top to bottom, a plurality of sliding rods 4 are fixedly connected to the bottom plate 6, the inner walls of the first connecting plate 3, the second connecting plate 5 and the bottom plate 6 are all bonded to the outer wall of the plastic cloth sleeve 7 by glue, the spacing between the first connecting plate 3 and the second connecting plate 5 is the same as the spacing between the bottom plate 6 and the second connecting plate 5, a plurality of through holes for the movement of the sliding rods 4 are opened on the first connecting plate 3 and the second connecting plate 5, the lower end of the bottom plate 6 is provided with four adjusting columns 12, the lower end of the adjusting column 12 is threadedly connected with a movable support plate 10, the lower end of the movable support plate 10 The end is provided with anti-slip nails 11, the upper end of the slide rod 4 is installed with a limiting nut, the lower part of the plastic cloth cover 7 is installed with a connecting pipe 8, and the connecting pipe 8 is installed with a valve 9. The dust hood is installed on the fixed frame at the drill bit of the drilling rig through the assembly ring 2. The flexibility of the plastic cloth cover 7 used for connection can adapt to places of different heights. When the height is low, the distance between the first connecting plate 3 and the second connecting plate 5 and the bottom plate 6 is reduced. At the same time, the slide rod 4 is used for limiting, which can avoid the dust hood from bending and affecting the dust collection effect. The movable support plate 10 can also be adjusted under the bottom plate 6, which can also be used in uneven positions. At the same time, the dust collection effect can be further improved by pressing the lower plastic cloth cover 7 by the movable support plate 10. If it is necessary to extract the drilled dust, a dust collector can be installed through the connecting pipe 8 for dust collection.

[0026] The above is only a further embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the scope disclosed by the present invention according to the technical solution and concept of the present invention, which fall within the protection scope of the present invention.

Claims

1. A dust collecting hood for a cement mining rig. It is characterized in that The invention comprises a rubber sleeve (1) and an assembly ring (2) mounted on the upper end of the rubber sleeve (1); the lower end of the rubber sleeve (1) is connected to a plastic cloth sleeve (7); the outer wall of the plastic cloth sleeve (7) is provided with a first connecting plate (3), a second connecting plate (5) and a bottom plate (6) in sequence from top to bottom; and a plurality of sliding rods (4) are fixedly connected to the bottom plate (6).

2. A dust collecting hood for a cement mining drill according to claim 1, It is characterized in that The inner walls of the first connecting plate (3), the second connecting plate (5) and the bottom plate (6) are all bonded to the outer wall of the plastic cloth sleeve (7) by glue.

3. A dust collecting hood for a cement mining drill according to claim 2, It is characterized in that The distance between the first connecting plate (3) and the second connecting plate (5) is the same as the distance between the bottom plate (6) and the second connecting plate (5).

4. A dust collecting hood for a cement mining drill according to claim 3, It is characterized in that The first connecting plate (3) and the second connecting plate (5) are both provided with a plurality of through holes for the movement of the sliding rod (4).

5. A dust collecting hood for cement mining drilling rig according to claim 1, It is characterized in that Four adjustment columns (12) are arranged at the lower end of the bottom plate (6).

6. A dust collecting hood for a cement mining drill according to claim 5, It is characterized in that The lower end of the adjusting column (12) is threadedly connected to a movable supporting plate (10).

7. A dust collecting hood for a cement mining drill according to claim 6, It is characterized in that The lower end of the movable support plate (10) is provided with anti-slip studs (11).

8. A dust collecting hood for a cement mining drill according to claim 1, It is characterized in that A limiting nut is installed on the upper end of the sliding rod (4).

9. A dust collecting hood for a cement mining drill according to claim 1, It is characterized in that A connecting pipe (8) is installed at the lower part of the plastic cloth sleeve (7).

10. A dust collecting hood for a cement mining drill according to claim 9, It is characterized in that A valve (9) is installed on the connecting pipe (8).