Energy-saving control system and test equipment
By designing an energy-saving control system in electronic product testing equipment, and using the monitoring unit and main control unit to control the on and off of the power supply unit according to the test status, the problem of energy waste when the equipment is idle is solved and the energy utilization efficiency is improved.
Patent Information
- Application Number
- CN202323393289.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-12
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2033-12-12
AI Technical Summary
In the testing process of electronic products, semi-automated or fully automated equipment remains powered on for a long time even if it is idle, resulting in a waste of energy.
Design an energy-saving control system. By monitoring the test status of the module, the monitoring unit, main control unit and power switch control unit are connected to each other. According to the test status, a control signal is output to turn on or off the power supply unit to avoid energy consumption in the idle state. waste.
It effectively avoids energy waste caused by long-term power-on of the measurement module in idle state, and improves energy utilization efficiency.
Smart Images

Figure CN221804555U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of electronic product detection, and in particular to an energy-saving control system and testing equipment. Background Art
[0002] At present, in order to improve production efficiency and test yield, the testing process of electronic products usually adopts semi-automatic testing or fully-automatic testing. However, after the semi-automatic or fully-automatic equipment is turned on, it will remain powered on for a long time even if it is idle, resulting in unnecessary energy waste. Utility Model Content
[0003] In view of this, it is necessary to provide an energy-saving control system that can turn on or off the power supply unit according to the test status of the measurement module, thereby avoiding energy waste caused by keeping the measurement module powered on for a long time when it is idle.
[0004] An embodiment of the present application discloses an energy-saving control system, which is used to control the on and off of a power supply unit of a measuring module according to a test status of the measuring module, and includes: a monitoring unit, electrically connected to the measuring module, for monitoring the test status of the measuring module and outputting a status signal; a main control unit, electrically connected to the monitoring unit, for receiving the status signal and outputting a control signal according to the status signal; and a power switch control unit, electrically connected to the main control unit and the measuring unit, for receiving the control signal and turning on or off the power supply unit of the measuring module according to the control signal.
[0005] Preferably, the monitoring unit includes: a first monitoring unit, electrically connected to the measuring module, for monitoring whether there is an operator within a preset range of the measuring module, and outputting a first status signal to the main control unit; a second monitoring unit, electrically connected to the measuring module, for monitoring whether the measuring module is connected to the device to be tested, and outputting a second status signal to the main control unit.
[0006] Preferably, the main control unit is also used to: receive the first status signal, and when it is determined based on the first status signal that there is an operator on the measurement module within the preset range, output a first control signal to the power switch control unit; receive the second status signal, and when it is determined based on the second status signal that the measurement module is connected to the device under test and confirms that the device under test needs to be measured, output a second control signal to the power switch control unit.
[0007] Preferably, the power switch control unit is further used for: turning on the total power of the measuring module according to the first control signal; and turning on the channel power of the measuring module according to the second control signal, so that the measuring module starts measuring.
[0008] Preferably, the main control unit is further used to output a third control signal to the power switch control unit when the measurement module finishes testing; the power switch control unit is further used to disconnect the channel power supply of the measurement module according to the third control signal.
[0009] An embodiment of the present application also discloses a testing device, including an energy-saving control system and a measurement module, wherein the energy-saving control system includes: a monitoring unit, electrically connected to the measurement module, for monitoring the test status of the measurement module and outputting a status signal; a main control unit, electrically connected to the monitoring unit, for receiving the status signal and outputting a control signal according to the status signal; a power switch control unit, electrically connected to the main control unit and the measurement module, for receiving the control signal and outputting a switch control signal to the measurement module according to the control signal to control the on and off of the power unit of the measurement module.
[0010] Preferably, the measurement module includes: the power supply unit, including a main power supply and a plurality of channel power supplies; a first sensor, electrically connected to the monitoring unit, for detecting whether there is an operator within a preset range, and outputting a first detection signal to the monitoring unit; a plurality of test slots, each test slot is provided with a channel power supply, and each test slot includes a second sensor and a data acquisition unit, and the channel power supply is electrically connected to the power switch control unit and the data acquisition unit, and is used to supply power to the data acquisition unit; the second sensor is electrically connected to the monitoring unit, for detecting whether the device to be tested is connected to the corresponding test slot, and outputting a second detection signal to the monitoring unit; the data acquisition unit is used to connect to the device to be tested and measure the device to be tested; a measurement control unit, electrically connected to the data acquisition unit and the main control unit, for determining whether the device to be tested needs to be tested, and outputting a test signal to the main control unit.
[0011] Preferably, the monitoring unit includes: a first monitoring unit, electrically connected to the first sensor, and used to output a first status signal to the main control unit according to the first detection signal; a second monitoring unit, including a plurality of monitoring sub-units, and the plurality of monitoring sub-units are connected one-to-one to the second sensors in the plurality of test slots, and are used to output a second status signal to the main control unit according to the second detection signal output by the corresponding sensor.
[0012] Preferably, the main control unit is also used to: receive the first status signal, and when it is determined based on the first status signal that there is an operator within the preset range of the measurement module, output a first control signal to the power switch control unit; receive the second status signal and the test signal, and when it is determined based on the second status signal and the test signal that the measurement module is connected to the device under test and confirms that the measurement module needs to be measured, output a second control signal to the power switch control unit.
[0013] Preferably, the power switch control unit includes: a main power switch control unit, electrically connected between the main power supply and the main control unit, and used to turn on the main power supply of the measurement module according to the first control signal; a plurality of channel power control units, one-to-one connected to the channel power supplies in the plurality of test slots, and used to turn on the corresponding channel power supplies according to the second control signal so that the corresponding data acquisition unit starts measurement.
[0014] Compared with the prior art, the energy-saving control system and testing equipment provided in the embodiments of the present application monitor the test status of the measuring module through the monitoring unit, and then output a control signal to the power switch control unit according to the current test status of the measuring module through the main control unit, so that the power switch control unit turns on or off the power unit of the measuring module according to the control signal, avoiding energy waste caused by keeping the measuring module powered on for a long time when it is idle. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a functional module diagram of an implementation scheme of the energy-saving control system of the present application.
[0016] Figure 2 It is a circuit diagram of an implementation of the testing device of the present application.
[0017] Main component symbols
[0018] 1- Test equipment
[0019] 10.10a-Energy-saving control system
[0020] 20, 20a-Measurement module
[0021] 101, 101a-Monitoring unit
[0022] 1011, 1011a- first monitoring unit
[0023] 1012, 1012a- second monitoring unit
[0024] 102, 102a-main control unit
[0025] 103, 103a- power switch control unit
[0026] 201-First sensor
[0027] 202-Measurement control unit
[0028] P, Pa - power supply unit
[0029] P0-Main power supply
[0030] P1~P3-channel power supply
[0031] T1~T3-Test slot
[0032] C1~C3-Data Acquisition Unit
[0033] S1~S3-Second sensor
[0034] M1~M3-Monitoring subunit DETAILED DESCRIPTION
[0035] The technical solutions in the embodiments of the present application will be clearly described below in conjunction with the drawings in the embodiments of the present application.
[0036] It is understandable that the connection relationship described in this application refers to direct or indirect connection. For example, the connection between A and B can be either a direct connection between A and B or an indirect connection between A and B through one or more other electrical components. For example, A and C can be directly connected, and C and B can be directly connected, so that A and B are connected through C. It is also understandable that the "A connects B" described in this application can be a direct connection between A and B, or an indirect connection between A and B through one or more other electrical components.
[0037] In the description of this application, unless otherwise specified, " / " means "or", for example, A / B can mean A or B. "And / or" in this article is only a way to describe the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone.
[0038] In the description of this application, words such as "first" and "second" are only used to distinguish different objects, and do not limit the quantity and execution order, and words such as "first" and "second" do not necessarily limit differences. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions.
[0039] The technical solution of the present application is further described in detail below in conjunction with the accompanying drawings.
[0040] See also Figure 1 , Figure 1This is a functional module diagram of an embodiment of the energy-saving control system of the present application. The energy-saving control system 10 can be used to monitor the test status of the measuring module 20. The measuring module 20 can be connected to the device under test and measure the product parameters of the device under test as required. The energy-saving control system 10 controls the on and off of the power supply unit of the measuring module 20 according to the test status of the measuring module 20, so that the power supply unit is turned on when the measuring module 20 needs to measure the device under test, and the power supply unit is turned off when the measuring module 20 does not measure the device under test or the measurement is completed. The device under test can be a circuit in an electronic device, and the embodiment of the present application does not limit the type of electronic device.
[0041] In this embodiment, the energy-saving control system 10 includes a monitoring unit 101, a main control unit 102 and a power switch control unit 103. The monitoring unit 101 is electrically connected to the measurement module 20, and is used to monitor the test status of the measurement module 20 and output a status signal. The main control unit 102 is electrically connected to the monitoring unit 101, and is used to receive the status signal and output a control signal according to the status signal. The power switch control unit 103 is electrically connected to the main control unit 102 and the measurement unit 20, and is used to receive the control signal and turn on or off the power supply unit P of the measurement module 20 according to the control signal. The power supply unit P may include a main power supply and a channel power supply, the main power supply is used to power on the measurement module 20, and the channel power supply is used to power the test slot of the measurement module 20, which is described in detail below.
[0042] In the present embodiment, the monitoring unit 101 may include a first monitoring unit 1011 and a second monitoring unit 1012. The first monitoring unit 1011 is electrically connected to the measuring module 20, and is used to monitor whether there is an operator within a preset range of the measuring module 20, and output a first state signal to the main control unit 102. The second monitoring unit 1012 is electrically connected to the measuring module 20, and is used to monitor whether the measuring module 20 is connected to the device under test, and output a second state signal to the main control unit 102. The main control unit 102 may include a microcontroller (Microcontroller Unit, MCU) with control and signal processing capabilities. The main control unit 102 may be an STM32 chip based on the ARM Cortex core. The first monitoring unit 1011 and the second monitoring unit 1012 may be chips with signal processing capabilities. In other embodiments of the present invention, the first monitoring unit 1011 and the second monitoring unit 1012 may be integrated in the main control unit 102.
[0043] In this embodiment, the main control unit 102 receives the first state signal output by the first monitoring unit 1011, and determines whether the measuring module 20 has an operator within the preset range according to the first state signal. When it is determined that the measuring module 20 has an operator within the preset range according to the first state signal, the main control unit 102 outputs a first control signal to the power switch control unit 103. The main control unit 102 also receives the second state signal output by the second monitoring unit 1012, and determines whether the measuring module 20 is connected to the device under test according to the second state signal. When it is determined that the measuring module 20 is connected to the device under test and it is confirmed that the measuring module 20 needs to be measured according to the second state signal, the main control unit 102 outputs a second control signal to the power switch control unit 103. The power switch control unit 103 turns on the total power supply of the measuring module 20 according to the first control signal. The power switch control unit 103 turns on the channel power supply of the measuring module 20 according to the second control signal, so that the measuring module 20 starts measuring. The power switch control unit 103 includes electronic switch components, such as any one of a relay, a MOS tube or a triode, which is not limited here.
[0044] In a specific embodiment of the present application, when the first monitoring unit 1011 does not detect an operator within a preset range, it outputs a first state signal of a first level to the main control unit 102, and the main control unit 102 outputs a first control signal of a first level according to the first state signal of the first level to keep the power switch control unit 103 disconnected from the main power supply. When the first monitoring unit 1011 detects an operator, it outputs a first state signal of a second level to the main control unit 102, and the main control unit 102 outputs a first control signal of a second level to the power switch control unit 103 according to the first state signal of the second level, and the power switch control unit 103 conducts the main power supply of the measurement module 20 according to the first control signal of the second level, and powers on the measurement module 20. In practical applications, a first preset time can be set, and when the first monitoring unit 1011 detects no operator for multiple times within the first preset time, it outputs a first state signal of a first level; and when the first monitoring unit 1011 detects an operator for multiple times within the first preset time, it outputs a first state signal of a second level. After the measurement module 20 is powered on, the second monitoring unit 1012 starts to monitor whether the measurement module 20 is connected to the device under test. When the second monitoring unit 1012 detects that the measurement module 20 is not connected to the device under test within the second preset time, it outputs a second state signal of the first level to the main control unit 102, and the main control unit 102 outputs a second control signal of the first level according to the second state signal of the first level to control the power switch control unit 103 to keep the channel power off; when the second detection unit 1012 detects that the measurement module 20 is connected to the device under test within the second preset time, it outputs a second state signal of the second level to the main control unit 102, and the main control unit 102 outputs a second control signal of the second level according to the second state signal of the second level to make the power switch control unit 103 turn on the channel power, and the measurement module 20 starts measuring. In other embodiments, when the main control unit 102 determines that the measurement module is connected to the device under test based on the second status signal, it further confirms whether the device under test needs to be measured. When it is confirmed that the device under test needs to be measured, the main control unit 102 outputs a second control signal to the power switch control unit 103.
[0045] In this embodiment, the first level is a low level, and the second level is a high level. In other embodiments, the first level may be a high level, and the second level may be a low level.
[0046] In this embodiment, when the measuring module 20 finishes measuring, the main control unit 102 further outputs a third control signal to the power switch control unit 103. The power switch control unit 103 disconnects the channel power of the measuring module 20 according to the third control signal.
[0047] In this embodiment, the monitoring unit 101 monitors the test status of the measurement module 20, and then the main control unit 102 controls the power switch control unit 103 to disconnect or turn on the power of the measurement module 20 according to the status signal output by the monitoring unit 101, thereby avoiding energy waste caused by keeping the measurement module 20 powered on for a long time when it is in an idle state.
[0048] See also Figure 2 , Figure 2 This is a functional module diagram of an embodiment of the test device of the present application. In this embodiment, the test device 1 includes an energy-saving control system 10a and a measuring module 20a, and the energy-saving control system 10a is used to monitor the test status of the measuring module 20a. The measuring module 20a can be connected to the device under test and measure the product parameters of the device under test as required. The energy-saving control system 10a controls the on and off of the power supply unit Pa of the measuring module 20a according to the test status of the measuring module 20a, so as to turn on the power supply unit Pa when the measuring module 20a measures the device under test, and turn off the power supply unit Pa when the measuring module 20a does not measure the device under test or the measurement is completed. The device under test can be a circuit in an electronic device, and the embodiment of the present application does not limit the type of electronic device. The energy-saving control system 10a includes a monitoring unit 101a, a main control unit 102a and a power switch control unit 103a, wherein the connection relationship and working principle of the monitoring unit 101a, the main control unit 102a and the power switch control unit 103a are similar to those of the monitoring unit 101, the main control unit 102 and the power switch control unit 103 in the above-mentioned embodiment, and are not repeated here.
[0049] In this embodiment, the measurement module 20a includes a first sensor 201, a measurement control unit 202, a power supply unit Pa and a plurality of test slots. The number of test slots can be determined according to actual test requirements. In this embodiment, three test slots T1, T2, and T3 are used as examples, but are not limited to this. The first sensor 201 is electrically connected to the monitoring unit 101a, and is used to detect whether there is an operator within a preset range, and output a first detection signal to the monitoring unit 101a. The power supply unit Pa includes a total power supply P0 and a plurality of channel power supplies. The total power supply 2031 is electrically connected to the measurement control unit 202. The number of channel power supplies is the same as the number of test slots. In this embodiment, three channel power supplies P1, P2, and P3 are used as examples. Each test slot is provided with an independent channel power supply, and each test slot can independently complete the measurement of the device under test. Take the test slot T1 as an example. The test slot T1 is provided with a channel power supply P1, and the test slot T1 includes a second sensor S1 and a data acquisition unit C1. The channel power supply P1 is electrically connected to the power switch control unit 103a and the data acquisition unit C1, and is used to supply power to the data acquisition unit C1. The second sensor S1 is electrically connected to the monitoring unit 101a, and is used to detect whether the device under test is connected to the test slot T1, and output a second detection signal to the monitoring unit 101a. The data acquisition unit C1 is used to connect the device under test and measure the device under test. The measurement control unit 202 is electrically connected to the data acquisition units C1, C2, C3 and the main control unit 102a, and is used to determine whether the device under test needs to be tested, and output a test signal to the main control unit 102a.
[0050] In this embodiment, the monitoring unit 101a includes a first monitoring unit 1011a and a second monitoring unit 1012a. The first monitoring unit 1011a is electrically connected to the first sensor 201, and is used to output a first state signal to the main control unit 102a according to the first detection signal. The second monitoring unit 1012a includes a plurality of monitoring sub-units, and the plurality of monitoring sub-units are connected to the second sensors in the plurality of test slots one by one, and are used to output a second state signal to the main control unit 102a according to the second detection signal output by the corresponding sensor. Figure 2 As shown, taking the monitoring subunits M1, M2, and M3 as an example, the monitoring subunits M1, M2, and M3 are connected to the second sensors S1, S2, and S3 in the test slots T1, T2, and T3 in a one-to-one correspondence. The measurement control unit 202 is electrically connected to the data acquisition units C1, C2, and C3 and the main control unit 102a, and is used to determine whether the device under test needs to be tested, and output a test signal to the main control unit 102a.
[0051] The main control unit 102a receives the first state signal, and determines whether the measuring module 20a has an operator within the preset range according to the first state signal. When it is determined that the measuring module 20a has an operator within the preset range according to the first state signal, the first control signal is output to the power switch control unit 103a. The main control unit 102a also receives the second state signal output by the second monitoring unit 1012a, and determines whether the measuring module 20a is connected to the device under test according to the second state signal. When it is determined that the measuring module 20a is connected to the device under test and it is confirmed that the measuring module 20a needs to be measured according to the second state signal, the second control signal is output to the power switch control unit 103a. The power switch control unit 103a turns on the total power of the measuring module 20a according to the first control signal. The power switch control unit 103a turns on the channel power of the measuring module 20a according to the second control signal, so that the measuring module 20a starts measuring. The power switch control unit 103a includes an electronic switch component, such as any one of a relay, a MOS tube or a triode, which is not limited here.
[0052] In a specific embodiment of the present application, when the first sensor 201 does not detect an operator within a preset range, it outputs a first detection signal of a first level to the first monitoring unit 1011a; when an operator is detected within the preset range, it outputs a first detection signal of a second level to the first monitoring unit 1011a. When the first monitoring unit 1011a receives the first detection signal of the first level, it outputs a first state signal of the first level to the main control unit 102a, and the main control unit 102a outputs a first control signal of the first level according to the first state signal of the first level to keep the power switch control unit 103a disconnected from the main power supply. When the first monitoring unit 1011a receives the first detection signal of the second level, it outputs a first state signal of the second level to the main control unit 102a, and the main control unit 102a outputs a first control signal of the second level to the power switch control unit 103a according to the first state signal of the second level, so as to control the power switch control unit 103a to conduct the main power supply of the measurement module 20a and power on the measurement module 20a. In practical applications, a first preset time can be set. When the first monitoring unit 1011a detects no operator for multiple times within the first preset time, a first state signal of a first level is output; when the first monitoring unit 1011a detects an operator for multiple times within the first preset time, a first state signal of a second level is output. After the measurement module 20a is powered on, the second sensors S1, S2, and S3 respectively detect whether the test slots T1, T2, and T3 are connected to the device to be tested, and output second detection signals to the monitoring subunits M1, M2, and M3 respectively. Taking the test slot T1 as an example, when the second sensor S1 detects that the data acquisition unit C1 in the test slot T1 is not connected to the device to be tested, a second detection signal of a first level is output to the monitoring subunit M1; when the second sensor S1 detects that the test slot T1 is connected to the device to be tested, a second detection signal of a second level is output to the monitoring subunit M1. If the monitoring subunit M1 receives a second detection signal of the first level within the second preset time, it outputs a second state signal of the first level to the main control unit 102a, and the main control unit 102a outputs a second control signal of the first level according to the second state signal of the first level to make the power switch control unit 103a keep the channel power P1 disconnected; if the monitoring subunit M1 detects that the test slot T1 is connected to the device under test within the second preset time, it outputs a second state signal of the second level to the main control unit 102a, and the main control unit 102a confirms that the test slot T1 is connected to the device under test according to the second state signal of the second level and confirms that the device under test needs to be measured according to the test signal output by the measurement control unit 202, and outputs a second control signal of the second level to make the power switch control unit 103a turn on the channel power P1, and the data acquisition unit C1 starts measurement.
[0053] In this embodiment, when the main control unit 102a receives the second state signal of the second level, it can first send a notification signal to the measurement control unit 202, and the measurement control unit 202 then determines whether the connected device under test needs to be measured according to the notification signal, and then sends a test signal to the main control unit 102a. The working principle of the test slot T2 and the test slot T3 is the same as that of the test slot T1, which will not be repeated here.
[0054] In this embodiment, the first level is a low level, and the second level is a high level. In other embodiments, the first level may be a high level, and the second level may be a low level.
[0055] In this embodiment, when any data acquisition unit finishes measuring, the main control unit 102a further outputs a third control signal to the power switch control unit 103a. The power switch control unit 103a disconnects the corresponding channel power supply according to the third control signal.
[0056] In this embodiment, the measuring module 20a may further include a display unit for displaying the on / off status of the total power supply and each channel power supply, so that the staff can understand the testing process of the measuring module 20a in real time.
[0057] Compared with the prior art, the energy-saving control system and testing equipment provided in the embodiments of the present application monitor the test status of the measuring module through the monitoring unit, and then output a control signal to the power switch control unit according to the current test status of the measuring module through the main control unit, so that the power switch control unit turns on or off the power unit of the measuring module according to the control signal, avoiding energy waste caused by keeping the measuring module powered on for a long time when it is idle.
[0058] Those skilled in the art should recognize that the above embodiments are only used to illustrate the present application and are not intended to be limiting of the present application. As long as they are within the spirit and scope of the present application, appropriate changes and modifications to the above embodiments are within the scope of protection claimed in the present application.
Claims
1. An energy-saving control system, used to control the on and off of a power supply unit of a measuring module according to a test state of the measuring module, characterized in that: include: A monitoring unit, electrically connected to the measuring module, for monitoring the test status of the measuring module and outputting a status signal; A main control unit, electrically connected to the monitoring unit, configured to receive the status signal and output a control signal according to the status signal; The power switch control unit is electrically connected to the main control unit and the measuring module, and is used to receive the control signal and turn on or off the power unit of the measuring module according to the control signal.
2. The energy-saving control system according to claim 1, characterized in that: The monitoring unit comprises: A first monitoring unit, electrically connected to the measuring module, for monitoring whether there is an operator within a preset range of the measuring module, and outputting a first status signal to the main control unit; The second monitoring unit is electrically connected to the measuring module, and is used to monitor whether the measuring module is connected to the device under test, and output a second state signal to the main control unit.
3. The energy-saving control system according to claim 2, characterized in that: The main control unit is also used for: receiving the first state signal, and outputting a first control signal to the power switch control unit when determining according to the first state signal that there is an operator within the preset range of the measurement module; The second state signal is received, and when it is determined according to the second state signal that the measuring module is connected to the device under test and that the device under test needs to be measured, a second control signal is output to the power switch control unit.
4. The energy-saving control system according to claim 3, characterized in that: The power switch control unit is also used for: Turning on the main power supply of the measuring module according to the first control signal; The channel power supply of the measuring module is turned on according to the second control signal, so that the measuring module starts measuring.
5. The energy-saving control system according to claim 4, characterized in that: The main control unit is further used to output a third control signal to the power switch control unit when the measurement module finishes testing; The power switch control unit is further used to disconnect the channel power supply of the measurement module according to the third control signal.
6. A test device, comprising an energy-saving control system and a measurement module, characterized in that: The energy-saving control system comprises: A monitoring unit, electrically connected to the measuring module, for monitoring the test status of the measuring module and outputting a status signal; A main control unit, electrically connected to the monitoring unit, configured to receive the status signal and output a control signal according to the status signal; The power switch control unit is electrically connected to the main control unit and the measuring module, and is used to receive the control signal and output a switch control signal to the measuring module according to the control signal to control the power unit of the measuring module to be turned on or off.
7. The testing device according to claim 6, characterized in that The measurement module comprises: The power supply unit includes a main power supply and a plurality of channel power supplies; A first sensor, electrically connected to the monitoring unit, for detecting whether there is an operator within a preset range and outputting a first detection signal to the monitoring unit; A plurality of test slots, each of which is provided with a channel power supply, each of which includes a second sensor and a data acquisition unit, wherein the channel power supply is electrically connected to the power switch control unit and the data acquisition unit, and is used to supply power to the data acquisition unit; the second sensor is electrically connected to the monitoring unit, and is used to detect whether a device under test is connected to the corresponding test slot, and output a second detection signal to the monitoring unit; the data acquisition unit is used to connect the device under test and measure the device under test; The measurement control unit is electrically connected to the data acquisition unit and the main control unit, and is used to determine whether the device under test needs to be tested, and output a test signal to the main control unit.
8. The testing device according to claim 7, characterized in that The monitoring unit comprises: a first monitoring unit, electrically connected to the first sensor, and configured to output a first status signal to the main control unit according to the first detection signal; The second monitoring unit includes a plurality of monitoring sub-units, which are connected to the second sensors in the plurality of test slots in a one-to-one correspondence, and are used to output a second status signal to the main control unit according to a second detection signal output by the corresponding sensor.
9. The testing device according to claim 8, characterized in that The main control unit is also used for: receiving the first state signal, and outputting a first control signal to the power switch control unit when determining according to the first state signal that there is an operator within the preset range of the measurement module; The second state signal and the test signal are received, and when it is determined that the measuring module is connected to the device under test and that the measuring module needs to be measured according to the second state signal and the test signal, a second control signal is output to the power switch control unit.
10. The test device according to claim 9, characterized in that The power switch control unit comprises: A main power switch control unit, electrically connected between the main power supply and the main control unit, and configured to conduct the main power supply of the measuring module according to the first control signal; A plurality of channel power control units are connected to the channel power supplies in the plurality of test slots one by one, and are used to turn on the corresponding channel power supplies according to the second control signal so that the corresponding data acquisition units start measuring.