Geopolymer grouting raw material preparing and feeding equipment

By using auger conveying hoses and transmission mechanisms in the geopolymer grouting material batching equipment, non-artificial lifting and continuous filling of raw materials are realized, which solves the problems of high labor intensity and long mixing time in the existing technology. , improve production efficiency.

CN221816020UActive Publication Date: 2024-10-11NANJING HUIHE TRANSPORTATION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420352051.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-26
Publication Date
2024-10-11
Estimated Expiration
2034-02-26

AI Technical Summary

Technical Problem

When using geopolymer grouting materials to repair foundation sinking and road surface subsidence, existing batching equipment requires workers to lift heavier raw materials, resulting in high labor intensity and long mixing time, which affects production efficiency.

Method used

A kind of geopolymer grouting raw material is equipped with feeding equipment. It adopts auger conveying hose and transmission mechanism. The motor drives the auger conveying hose and stirring shaft to realize non-artificial lifting and continuous filling of raw materials, reducing work. It reduces personnel labor intensity and improves mixing efficiency.

Benefits of technology

It reduces the labor intensity of staff, reduces the assembly cost of equipment, improves the production efficiency of geopolymer grouting materials, and avoids the problem of prolonged mixing time caused by accumulation of raw materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221816020U_ABST
    Figure CN221816020U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of material preparation and feeding, in particular to geopolymer grouting raw material preparation and feeding equipment, which comprises a preparation barrel, an auger conveying hose, a temporary storage bin, a transmission mechanism and a material distribution auger, a stirring shaft is arranged in the preparation barrel, and the lower end of the stirring shaft is connected with an output shaft of a motor. The temporary storage bin is arranged at the upper end of the batching barrel, a conveying hole is formed in the bottom of the temporary storage bin, the distribution auger is arranged in the temporary storage bin and right faces the conveying hole, and the auger conveying hose is arranged on the side edge of the batching barrel; the packing auger conveying hose is arranged, non-manual lifting and filling of raw materials are achieved, the current situation that at least two workers cooperatively lift the raw materials is changed, the labor intensity of the workers is reduced, the transmission mechanism is additionally arranged and can be connected with the packing auger conveying hose and the stirring shaft so that the packing auger conveying hose can be controlled to work under the work of the motor, and the work efficiency is improved. And the arrangement of driving equipment is reduced, and the assembly cost of the device is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of material preparation and feeding, in particular to a material preparation and feeding device for geopolymer grouting raw materials. Background Art

[0002] In order to quickly solve the problems of foundation sinking, ground hollowing, road subsidence, etc., the repair method of injecting geopolymer grouting material is generally adopted. In this way, geopolymer grouting material can be injected into the hollowing and collapsed area without excavating the road surface, and the geopolymer grouting material can quickly fill all holes and gaps, becoming an important repair solution.

[0003] When repairing with geopolymer grouting, it is necessary to transport batching equipment, grouting machines and various raw materials by transporting vehicles. After arriving at the workplace, the staff put various raw materials into the batching equipment according to scientific proportions, and fully mix the raw materials through the batching equipment to form geopolymer grouting. The prepared geopolymer grouting is transported to the grouting machine, and the grouting machine is used to force the geopolymer grouting to fill the hollow and collapsed areas.

[0004] Because the batching equipment is high and the raw materials are heavy, when preparing geopolymer grouting materials, at least two workers are required to lift the raw materials to the upper end of the batching equipment and pour them into the batching equipment. This method causes the workers to be overworked. Although there are feeding devices for geopolymer grouting materials on the market, such as a feeding device for geopolymer grouting raw materials disclosed in a Chinese patent with patent publication number CN215655023U, it mainly realizes quantitative filling of raw materials and requires workers to lift the raw materials, which cannot reduce the labor intensity of the workers. Utility Model Content

[0005] The utility model aims to provide a feeding device for geopolymer grouting raw materials, aiming to improve the problem of excessive fatigue of workers when they lift raw materials to make geopolymer grouting materials.

[0006] The utility model is implemented as follows: a feeding device for geopolymer grouting raw materials includes a batching barrel, a stirring shaft is arranged in the batching barrel, the lower end of the stirring shaft is connected to the output shaft of the motor, and also includes an auger conveying hose, a temporary storage bin, a transmission mechanism and a material distribution auger. The temporary storage bin is arranged at the upper end of the batching barrel, and a feeding hole is arranged at the bottom. The material distribution auger is arranged in the temporary storage bin and is opposite to the feeding hole. The auger conveying hose is arranged on the side of the batching barrel, and the end portion is communicated with the upper end of the temporary storage bin. The transmission mechanism is arranged through the bottom of the temporary storage bin, the upper end is connected to the material distribution auger and the auger conveying hose, and the lower end is connected to the stirring shaft.

[0007] Preferably, the transmission mechanism includes a transmission shaft, a first bevel gear and a second polygonal column. The transmission shaft is connected through a bearing and passes through the bottom of the temporary storage bin. The first bevel gear is sleeved on the upper end of the transmission shaft and is meshed with the second bevel gear at the end of the fabric auger. The second polygonal column is arranged at the lower end of the transmission shaft and can be inserted into the second polygonal groove at the upper end of the stirring shaft.

[0008] Preferably, the lower end face of the transmission shaft is provided with a first polygonal groove, a connecting column is fixedly provided at the upper end of the second polygonal column, a first polygonal column is fixedly provided at the upper end of the connecting column, and the first polygonal column is lifted and inserted into the first polygonal groove.

[0009] Preferably, a lifting plate is provided on the connecting column through a bearing sleeve, and a limit rod and an adjusting screw are provided below the storage bin. The limit rod passes through the lifting plate, and the adjusting screw thread passes through the lifting plate.

[0010] Preferably, the upper end of the temporary storage bin is arranged as an opening, a cover plate is arranged at the opening, a feed hole is arranged on the cover plate, the upper end of the auger conveying hose is communicated with the feed hole, and the internal auger is connected with the transmission shaft.

[0011] Preferably, the material feeding holes are arranged along the length direction of the temporary storage bin, and there are two of them. Two sets of material augers are provided. The ends of the two sets of material augers close to each other are provided with brackets, and the ends away from each other are respectively inserted into the end walls of the temporary storage bin, and the brackets are connected to the temporary storage bin.

[0012] Preferably, limiting plates are provided at both ends below the temporary storage bin, and balls are inlaid on the sides of the limiting plates close to each other. An annular groove is provided at the upper end of the dispensing barrel, and the balls are located in the annular groove.

[0013] Preferably, a quantitative bin is further included, the bottom of the quantitative bin is arranged as a structure with a low middle and high ends, and a scale is arranged on the side wall of the quantitative bin.

[0014] Compared with the prior art, the beneficial effects of the utility model are:

[0015] 1. The utility model is provided with an auger conveying hose to realize non-artificial lifting and filling of raw materials, which changes the current situation that at least two workers need to cooperate in lifting the raw materials, thereby reducing the labor intensity of the workers. In addition, a transmission mechanism is provided to connect the auger conveying hose and the stirring shaft so as to control the operation of the auger conveying hose under the operation of the motor, thereby reducing the setting of the driving equipment and reducing the assembly cost of the device.

[0016] 2. The utility model is provided with a material distribution auger, which can be controlled to rotate under the operation of the transmission mechanism, so as to move the raw materials falling into the middle of the temporary storage bin to the two ends of the temporary storage bin, and in the process of movement, the raw materials fall into the material distribution barrel from the feeding hole, avoiding the problem of long mixing time caused by the accumulation of raw materials at one time, and improving the production efficiency of geopolymer grouting. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the first three-dimensional structure of an embodiment of the utility model;

[0018] Figure 2 This utility model Figure 1 Schematic diagram of the three-dimensional structure of the Zhonglin storage warehouse and the material distribution auger;

[0019] Figure 3 This utility model Figure 1 Schematic diagram of the three-dimensional structure of Zhonglin storage warehouse;

[0020] Figure 4 This utility model Figure 2 Schematic diagram of the three-dimensional structure of the middle fabric auger and transmission mechanism;

[0021] Figure 5 This utility model Figure 4 A three-dimensional structural diagram of the middle transmission mechanism;

[0022] Figure 6 This utility model Figure 2 Schematic diagram of the structure of the middle transmission mechanism and the temporary storage bin;

[0023] Figure 7 This utility model Figure 2 A schematic diagram of the three-dimensional structure of the middle limiting plate;

[0024] Figure 8 It is a schematic diagram of the second three-dimensional structure of the embodiment of the utility model;

[0025] Fig. 9 This utility model Figure 8 Schematic diagram of the three-dimensional structure of the medium quantitative warehouse.

[0026] In the figure: 1. batching barrel; 11. stirring shaft; 12. annular groove; 2. auger conveying hose; 3. temporary storage bin; 31. feeding hole; 32. limit rod; 33. adjusting screw; 34. limiting plate; 35. cover plate; 36. feeding hole; 37. ball bearing; 4. material distribution auger; 41. bracket; 5. transmission mechanism; 51. transmission shaft; 52. first bevel gear; 53. first polygonal groove; 54. lifting plate; 55. first polygonal column; 56. second polygonal column; 6. quantitative bin; 61. scale. DETAILED DESCRIPTION

[0027] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0028] The following is a further description with reference to the accompanying drawings and specific embodiments:

[0029] Example 1

[0030] like Figure 1 or Figure 8 As shown, the batching equipment used in the preparation of geopolymer grouting includes a batching barrel 1, the bottom of which is set as a conical structure, and the output pipe (i.e., the lower end of the batching barrel 1) deviates from the center of the batching barrel 1, a stirring shaft 11 is set inside the batching barrel 1, and a motor is set at the lower outside, and the lower end of the stirring shaft 11 is connected to the output shaft of the motor. When the batching equipment is used to make geopolymer grouting with multiple raw materials, the multiple raw materials are put into the batching barrel 1, and the stirring shaft 11 is driven to rotate under the operation of the motor, forcing the multiple raw materials to be fully mixed. However, this method requires at least two workers to cooperate in lifting materials, which is a large workload and high work cost.

[0031] like Figure 1 , Figure 2As shown, in order to reduce the labor intensity of the staff, an auger conveying hose 2, a temporary storage bin 3, a transmission mechanism 5 and a material distribution auger 4 are arranged on the outside of the batching barrel 1. The temporary storage bin 3 is arranged above the batching barrel 1, and a feeding hole 31 is arranged at the bottom. The upper end of the auger conveying hose 2 (the same as the hose of the auger grain suction machine) is connected to the temporary storage bin 3, and the lower end can be inserted into the storage bag of each raw material. The material distribution auger 4 is arranged in the temporary storage bin 3 and is opposite to the feeding hole 31. The transmission mechanism 5 is arranged through the bottom of the temporary storage bin 3, the upper end is connected to the material distribution auger 4 and the auger conveying hose 2, and the lower end is connected to the stirring shaft 11. When geopolymer grouting is required, the motor is started, and the stirring shaft 11, the material distribution auger 4 and the auger conveying hose 2 are controlled by the motor to work. Since the end of the auger conveying hose 2 can be extended into the raw material storage bag, the raw materials can be controlled to be transported to the temporary storage bin 3 along the auger conveying hose 2. The raw materials falling into the temporary storage bin 3 are then distributed in the temporary storage bin 3 through the material distribution auger 4. Finally, the raw materials pass through the feeding hole 31 and fall into the batching barrel 1. The falling raw materials are quickly mixed under the action of the stirring shaft 11. This method not only changes the current situation of high labor intensity and high work cost for workers to lift raw materials, but also avoids the problem of long mixing time due to accumulation of raw materials when they are added once due to continuous input of raw materials, thereby improving the production efficiency of geopolymer grouting.

[0032] like Figure 3 , Figure 4 As shown, in order to achieve the falling of raw materials in a larger range, two feeding holes 31 are provided, and each feeding hole 31 is provided along the length direction of the temporary storage bin 3, and a through hole is provided in the middle of the two feeding holes 31. At the same time, two sets of fabric augers 4 are provided, and the fabric augers 4 are matched with the feeding holes 31 one by one, and the ends of the two sets of fabric augers 4 close to each other are provided with brackets 41, and the ends away from each other are respectively inserted into the interior of the temporary storage bin 3, and the brackets 41 are connected to the temporary storage bin 3. Therefore, under the action of the two sets of fabric augers 4, the raw materials falling in the middle of the temporary storage bin 3 can be moved to both ends, and in the process of moving, they pass through the feeding holes 31 and fall into the batching barrel 1, avoiding the concentrated accumulation of raw materials. At the same time, in order to limit the movement of raw materials in the temporary storage bin 3, a cover plate 35 is provided at the opening of the upper end of the temporary storage bin 3, and a feed hole 36 is provided on the cover plate 35. The upper end of the auger conveying hose 2 is connected to the feed hole 36, and the internal auger is connected to the transmission shaft 51.

[0033] like Figure 5As shown, in order to simultaneously control the operation of the stirring shaft 11, the material distribution auger 4 and the auger conveying hose 2, the transmission mechanism 5 includes a transmission shaft 51, a first bevel gear 52, a first polygonal column 55 and a second polygonal column 56. The transmission shaft 51 is connected to the through hole at the bottom of the temporary storage bin 3 through a bearing, and a first polygonal groove 53 is provided on the lower end surface of the transmission shaft 51. The first bevel gear 52 is sleeved on the upper end of the transmission shaft 51, and a second bevel gear is provided at one end of the two sets of material distribution auger 4 close to each other. The first bevel gear 52 and the second bevel gear are meshed. Therefore, when the transmission shaft 51 rotates, the material distribution auger 4 is controlled to rotate through the cooperation of the bevel gears. The second polygonal column 56 is arranged below the transmission shaft 51. At the same time, a second polygonal groove is arranged on the upper end surface of the stirring shaft 11. The second polygonal column 56 can be inserted into the second polygonal groove. In addition, a connecting column is fixedly arranged on the upper end of the second polygonal column 56. The upper end of the connecting column is fixedly arranged with a first polygonal column 55. The first polygonal column 55 is lifted and inserted into the first polygonal groove 53 to realize the connection between the transmission shaft 51 and the stirring shaft 11. Therefore, when the stirring shaft 11 rotates, the transmission shaft 51 is driven to rotate.

[0034] like Figure 5 , Figure 6 As shown, in order to be able to control the stirring shaft 11, the material auger 4 and the auger conveying hose 2 to work in a staggered manner, a lifting plate 54 is provided on the connecting column through a bearing sleeve, and a limit rod 32 and an adjusting screw 33 are arranged under the temporary storage bin 3. The limit rod 32 penetrates the lifting plate 54, and the adjusting screw 33 threadably penetrates the lifting plate 54. When the raw material filling is completed, the staff can rotate the adjusting screw 33 to control the lifting plate 54 to drive the polygonal column to rise and fall, thereby providing support for the second polygonal column 56 to separate from the stirring shaft 11, and then control whether the transmission shaft 51 and the stirring shaft 11 are connected or not.

[0035] Example 2

[0036] like Figure 1 , Figure 2 , Figure 7 As shown, on the basis of Example 1, in order to be able to adjust the orientation of the temporary storage bin 3 according to actual needs and to make the temporary storage bin 3 stably connected to the batching barrel 1, limiting plates 34 are provided at both ends below the temporary storage bin 3, and the sides of the limiting plates 34 close to each other are inlaid with balls 37, and the upper end of the batching barrel 1 is provided with an annular groove 12, and the ball 37 is located in the annular groove 12. With the cooperation of the ball 37 and the annular groove 12, the temporary storage bin 3 is stably and movably connected to the batching barrel 1, so that the staff can adjust the orientation of the temporary storage bin 3 according to needs.

[0037] Example 3

[0038] like Figure 8 , Fig. 9As shown, on the basis of Example 1 or Example 2, in order to realize the quantitative filling of raw materials, a quantitative bin 6 is arranged at the lower end of the auger delivery hose 2, and the bottom of the quantitative bin 6 is arranged as a structure with a low middle and high two ends, and the low end of the quantitative bin 6 is communicated with the auger delivery hose 2. At the same time, the end of the auger of the auger delivery hose 2 extends into the quantitative bin 6, and a scale 61 is arranged on the side wall of the quantitative bin 6. The quantitative bin 6 can be used to quantitatively fill raw materials to realize the scientific ratio of geopolymer grouting.

[0039] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may be modified and varied in various ways. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A feeding device for geopolymer grouting raw materials, comprising a feeding barrel (1), a stirring shaft (11) is arranged in the feeding barrel (1), and the lower end of the stirring shaft (11) is connected to the output shaft of a motor, characterized in that: It also includes an auger conveying hose (2), a temporary storage bin (3), a transmission mechanism (5) and a material distribution auger (4). The temporary storage bin (3) is arranged at the upper end of the batching barrel (1) and is provided with a material delivery hole (31) at the bottom. The material distribution auger (4) is arranged in the temporary storage bin (3) and is directly opposite to the material delivery hole (31). The auger conveying hose (2) is arranged on the side of the batching barrel (1) and its end is communicated with the upper end of the temporary storage bin (3). The transmission mechanism (5) is arranged through the bottom of the temporary storage bin (3), and its upper end is connected to the material distribution auger (4) and the auger conveying hose (2), while its lower end is connected to the stirring shaft (11).

2. The feeding device for geopolymer grouting raw materials according to claim 1, characterized in that: The transmission mechanism (5) comprises a transmission shaft (51), a first bevel gear (52) and a second polygonal column (56); the transmission shaft (51) is connected through a bearing and is arranged at the bottom of the temporary storage bin (3); the first bevel gear (52) is sleeved on the upper end of the transmission shaft (51) and is meshed with the second bevel gear at the end of the material distribution auger (4); the second polygonal column (56) is arranged at the lower end of the transmission shaft (51) and can be inserted into the second polygonal groove at the upper end of the stirring shaft (11).

3. The feeding device for geopolymer grouting raw materials according to claim 2, characterized in that: The lower end surface of the transmission shaft (51) is provided with a first polygonal groove (53), the upper end of the second polygonal column (56) is fixedly provided with a connecting column, the upper end of the connecting column is fixedly provided with a first polygonal column (55), and the first polygonal column (55) is lifted and inserted into the first polygonal groove (53).

4. The feeding device for geopolymer grouting raw materials according to claim 3 is characterized in that: A lifting plate (54) is sleeved on the connecting column via a bearing, and a limit rod (32) and an adjusting screw (33) are arranged below the temporary storage bin (3). The limit rod (32) passes through the lifting plate (54), and the adjusting screw (33) is threadedly arranged to pass through the lifting plate (54).

5. The feeding device for geopolymer grouting raw materials according to claim 2, characterized in that: The upper end of the temporary storage bin (3) is arranged as an opening, a cover plate (35) is arranged at the opening, a feed hole (36) is arranged on the cover plate (35), the upper end of the auger conveying hose (2) is communicated with the feed hole (36), and the internal auger is connected to the transmission shaft (51).

6. A feeding device for geopolymer grouting raw materials according to claim 5, characterized in that: The feeding holes (31) are arranged along the length direction of the temporary storage bin (3), and there are two of them. The material distribution screws (4) are arranged in two sets. The ends of the two sets of material distribution screws (4) close to each other are provided with brackets (41), and the ends away from each other are respectively inserted into the end walls of the temporary storage bin (3). The brackets (41) are connected to the temporary storage bin (3).

7. A feeding device for geopolymer grouting raw materials according to claim 6, characterized in that: Both ends of the temporary storage bin (3) are provided with limiting plates (34), and the sides of the limiting plates (34) close to each other are inlaid with balls (37). The upper end of the dispensing barrel (1) is provided with an annular groove (12), and the balls (37) are located in the annular groove (12).

8. The feeding device for geopolymer grouting raw materials according to claim 1, characterized in that: In addition, a quantitative bin (6) is arranged at the lower end of the auger delivery hose (2), the bottom of the quantitative bin (6) being arranged in a structure with a lower middle and higher ends, and a scale (61) is arranged on the side wall of the quantitative bin (6).