Pier body concrete curing device capable of recycling water
By designing a concrete curing device for the pier body that recirculates water, the ridges and slopes are used to recover the water flowing down, and the pier body is evenly sprayed and cured through water pumps and moving mechanisms, which solves the problem of water waste and improves water resource utilization. And the maintenance effect of the pier body.
Patent Information
- Application Number
- CN202420024464.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-03
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-01-03
AI Technical Summary
Water resources cannot be recycled and utilized during the spraying and curing process of the existing concrete pier body, resulting in a waste of water resources.
A concrete curing device for the pier body that circulates water is designed, including a dam, a reservoir, a slope, a water pump and a water pipe around the pier body. By intercepting the flowing water and returning it to the reservoir, the water pump is used to pump the water. It is pumped to water pipes for spray maintenance, and measures such as moving mechanisms and waterproof membranes are used to ensure the recycling and effective protection of water resources.
It realizes the recycling of water resources, reduces water waste, improves the uniform spray effect on the surface of the pier body, reduces labor costs, and ensures the safety of water resources through protective nets and waterproof measures.
Smart Images

Figure CN221822750U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pier body construction and maintenance equipment, and in particular to a pier body concrete maintenance device using circulating water. Background Art
[0002] At present, elevated bridges are developing rapidly. After the pier body concrete is poured, the moisturizing and curing of the concrete becomes the key. In the prior art, after the pier body is poured and the formwork is removed, the pier body concrete is moisturized and cured through an automatic spraying system, thereby better ensuring the curing effect of the concrete and better reducing the input of workers during manual watering.
[0003] However, during the spraying process of the pier body, the water flowing down the pier body can only flow to the ground, and the water resources cannot be recycled, resulting in a certain waste of water resources during the spraying maintenance process. Summary of the invention
[0004] The purpose of the present application is to provide a pier body concrete curing device using recycled water, which is used to solve the problem that water resources cannot be recycled during the spray curing process.
[0005] The present application provides a pier body concrete curing device using circulating water, which adopts the following technical solution:
[0006] A pier body concrete curing device with circulating water comprises a pier body, wherein a water retaining ridge is cast around the pier body, a water reservoir for storing water for curing is provided on the ground between the pier body and the water retaining ridge, a slope is provided at the connection between the water retaining ridge and the water reservoir for facilitating the return of spray water into the water reservoir, a water pump is provided in the water reservoir, a water pipe for spraying and curing the pier body is connected to the water pump, and a water outlet is provided on the water pipe.
[0007] By adopting the above technical scheme, the water in the water reservoir is pumped into the water pipe by a water pump and then sprayed out from the water outlet, thereby reducing the possibility of cracks on the surface of the pier body, which in turn affects the strength of the concrete and easily leaves quality risks; a water retaining ridge is cast under the pier body, so that the water flowing down after the spraying and curing of the pier body can be better intercepted by the water retaining ridge, thereby reducing the infiltration of the flowing water into the ground, thereby better reducing the waste of water resources; the water reservoir is used to provide water for spraying and curing the pier body, and at the same time, a slope is opened between the water retaining ridge and the water reservoir, so that the water intercepted by the water retaining ridge can flow into the water reservoir from the slope, so that the water flowing down after the spraying and curing can flow back to the water reservoir and continue to be used for the spraying and curing of the pier body, thereby enabling the recycling of water resources.
[0008] Optionally, a protective net is hingedly connected to an open portion of the water reservoir close to one side of the pier body.
[0009] By adopting the above technical solution, the protective net is in a covered state, thereby effectively reducing the possibility of people, animals or other impurities falling into the reservoir, thereby better ensuring personal safety.
[0010] Optionally, ceramic tiles fixedly connected to the water pump are laid on the inner wall of the water reservoir, and a waterproof film for reducing water loss is laid between the water reservoir and the ceramic tiles.
[0011] By adopting the above technical solution, the water is contained in the water reservoir, and the possibility of water infiltration in the water reservoir is reduced through the ceramic tiles, thereby better protecting water resources and reducing the waste of water resources; the waterproof film is laid between the water reservoir and the ceramic tiles, thereby better protecting the water resources and further reducing the waste of water resources.
[0012] Optionally, a soft connecting pipe is connected between the water pipe and the water pump, and a moving component for driving the water pipe to move around the pier body is provided at the lower end of the water pipe.
[0013] By adopting the above technical solution, the water in the water reservoir is pumped into the water pipe through the soft connecting pipe by the water pump, and the water is sprayed onto the pier body through the water outlet, thereby playing a better maintenance role on the pier body; at the same time, the water pipe is driven to move by the moving mechanism, so that the water can be sprayed to every corner of the pier body, thereby playing a better maintenance role on the pier body as a whole.
[0014] Optionally, the moving component includes a support frame that surrounds the pier body, the support frame is fixed to the ground, a rack matching the support frame is installed on the upper surface of the support frame, a moving block fixed to the water pipe is provided above the rack, a gear that meshes with the rack is rotatably connected to the moving block, and a rotating motor fixed to the moving block is fixed to one side of the gear.
[0015] By adopting the above technical scheme, when it is necessary to spray and maintain the pier body, the water pump is turned on to spray the water in the water reservoir from the water outlet, and the rotating motor is started to rotate the gear. Since the gear is meshed with the rack, the gear moves horizontally around the pier body along the rack while rotating. At the same time, the moving block moves horizontally around the pier body together with the gear, and the water pipe is driven to move horizontally around the pier body through the moving block, so that the water pipe can spray the pier body as a whole, reducing the possibility of cracks on the local surface of the pier body due to uneven spray maintenance of the pier body; when the gear moves horizontally around the pier body for one circle, the rotating motor is driven in the reverse direction, so that the rotating motor drives the gear to rotate in the reverse direction, so that the gear drives the water pipe to move horizontally around the pier body in the reverse direction through the moving block, thereby reducing the possibility that the moving block cannot move too many circles around the pier body due to the short soft connecting pipe, thereby improving the effect of spray maintenance of the pier body.
[0016] Optionally, slide rails identical to the rack tracks are provided on both sides of the rack, the slide rails are mounted on the support frame, and pulleys rotatably connected to the moving block are slidably connected to the slide rails.
[0017] By adopting the above technical solution, since the pulley is always slidably connected to the slide rail, during the process of meshing and moving of the gear and the rack, the gear and the rack are always kept in meshing through the guiding effect of the pulley and the slide rail, thereby reducing the possibility of the gear disengaging from the rack during the movement around the pier body, and at the same time better ensuring that the moving block drives the water pipe to move smoothly around the pier body, thereby better improving the effect of spraying maintenance on the pier body.
[0018] Optionally, the water pump is connected to a timer for controlling the water pump to be turned on and off.
[0019] By adopting the above technical solution, the water pump switch is controlled by the timer, so that the spraying maintenance of the pier body can be automatically controlled at a fixed time, the effect of the spraying maintenance is improved, and the labor cost required for the spraying maintenance of the pier body is reduced.
[0020] Optionally, an atomizing nozzle corresponding to the water outlet is installed on the water pipe.
[0021] By adopting the above technical solution, water is sprayed from the atomizing nozzle, thereby increasing the spraying range of the sprayed water, thereby better enabling spray maintenance to be carried out in every corner of the pier body, reducing the possibility of local cracks on the surface of the pier body, and improving the overall quality of the pier body.
[0022] In summary, the present application includes at least one of the following beneficial technical effects:
[0023] 1. The water flowing down from the pier body is intercepted by the water retaining embankment, and the water flows into the reservoir through the slope, and then the water is pumped to the water pipe by the water pump for spraying and curing the pier body, thereby realizing the recycling of water resources;
[0024] 2. The water pipe is driven to move horizontally around the pier body through the moving mechanism, so as to better realize the spray maintenance of every corner of the pier body, reduce the possibility of cracks on the surface of the pier body, and improve the overall quality of the pier body;
[0025] 3. The waterproof film and tiles work together to reduce the possibility of water stored in the reservoir from seeping. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the overall structure of an embodiment of the present application;
[0027] Figure 2 is a schematic cross-sectional structural diagram of an embodiment of the present application;
[0028] Figure 3 yes Figure 2A partial enlarged schematic diagram of part A;
[0029] Figure 4 yes Figure 2 A partial enlarged schematic diagram of part B in the middle
[0030] In the figure, 1, pier body; 2, water retaining embankment; 21, slope; 3, water reservoir; 31, waterproof film; 32, ceramic tile; 33, protective net; 4, water pump; 5, flexible connecting pipe; 6, water pipe; 61, water outlet; 62, atomizing nozzle; 7, moving mechanism; 71, moving block; 711, mounting groove; 72, rotating motor; 73, gear; 74, rack; 75, support frame; 76, slide rail; 77, pulley; 8, timer. DETAILED DESCRIPTION
[0031] The following is combined with Figure 1 -Attached Figure 4 , further details of this application are given.
[0032] A pier concrete curing device using circulating water, referring to Figure 1 , Figure 2 , including a pier body 1, with a water retaining ridge 2 cast around the pier body 1, a water reservoir 3 for spraying and maintaining the pier body 1 is provided in the water retaining ridge 2, a slope 21 is provided at the connection between the water retaining ridge 2 and the water reservoir 3, the slope 21 gradually slopes downward from the water retaining ridge 2 to the water reservoir 3, a water pump 4 is provided in the water reservoir 3, a soft connecting pipe 5 is fixedly connected to the water pump 4, a water pipe 6 for spraying and maintaining the pier body 1 is fixedly connected to the end of the soft connecting pipe 5 away from the water pump 4, the water pipe 6 is connected to the soft connecting pipe 5, and a water outlet is provided on the water pipe 6.
[0033] When the pier body 1 is to be sprayed and maintained, the water pump 4 is turned on, the water in the water reservoir 3 is pumped to the water pipe 6 by the water pump 4, and the water is sprayed out from the water outlet, so that the pier body 1 can be sprayed and maintained better. During the spraying process, the water flowing down from the pier body 1 is collected by the water retaining ridge 2, and the water in the water retaining ridge 2 flows into the water reservoir 3 through the slope 21, and then the water pump 4 pumps the water to the water pipe 6 for spraying and maintaining the pier body 1, so that the water flowing down from the pier body 1 can be recycled again, thereby improving the utilization rate of water resources and better saving water resources.
[0034] Reference Figure 2 and Figure 3 A waterproof film 31 is laid in the water reservoir 3, and ceramic tiles 32 are laid on the waterproof film 31. The waterproof film 31 and the ceramic tiles 32 can effectively reduce the possibility of water infiltration in the water reservoir 3, thereby playing a better role in protecting water resources and reducing the waste of water resources. The open part of the water reservoir 3 is covered with a protective net 33 hinged to the water reservoir 3, thereby reducing the possibility of people, animals or other impurities accidentally falling into the water reservoir 3.
[0035] Reference Figure 2 An atomizing nozzle 62 corresponding to the water outlet hole 61 is fixedly installed on the water pipe 6, so that the water sprayed from the water outlet hole 61 is sprayed out in a mist form after passing through the atomizing nozzle 62, and at the same time, the spraying range of the sprayed water is expanded, the spraying effect on the pier body 1 is improved, and the possibility of cracks on the local surface of the pier body 1 is reduced.
[0036] Reference Figure 2 and Figure 4 A moving mechanism 7 is provided on the side of the water pipe 6 close to the ground, and the moving mechanism 7 includes a moving block 71 fixedly connected to the water pipe 6, and a rotating motor 72 is fixedly installed on the side of the moving block 71 away from the pier body 1. A mounting groove 711 is provided below the moving block 71, and a gear 73 rotatably connected to the moving block 71 is provided in the mounting groove 711. The gear 73 is fixedly connected to the driving end of the rotating motor 72, and a rack 74 that surrounds the pier body 1 is meshed below the gear 73. A support frame 75 matching the rack 74 is fixedly connected below the rack 74. The support frame 75 is located on the side of the water retaining dam 2 away from the pier body 1, and the support frame 75 is fixedly installed on the ground.
[0037] When the pier body 1 needs to be sprayed for maintenance, the water pump 4 is turned on to spray the stored water in the water reservoir 3 from the atomizing nozzle 62, and the rotating motor 72 is started to rotate the gear 73. Since the gear 73 is meshed with the rack 74, the gear 73 moves horizontally around the pier body 1 along the rack 74 while rotating. At the same time, the moving block 71 moves horizontally around the pier body 1 together with the gear 73, and the water pipe 6 is driven to move horizontally around the pier body 1 through the moving block 71, so that the water pipe 6 can spray the pier body 1 as a whole, reducing the possibility of cracks on the local surface of the pier body 1 due to uneven spray maintenance of the pier body 1; when the gear 73 moves horizontally around the pier body 1 for one circle, the rotating motor 72 is driven in the reverse direction, so that the rotating motor 72 drives the gear 73 to rotate in the reverse direction, so that the gear 73 drives the water pipe 6 to move horizontally around the pier body 1 in the reverse direction through the moving block 71, thereby reducing the possibility that the moving block 71 cannot move too many circles around the pier body 1 due to the short soft connecting pipe 5, thereby improving the effect of spray maintenance on the pier body 1.
[0038] Slide rails 76 fixed to the support frame 75 are provided on both sides of the rack 74. The track of the slide rail 76 is the same as that of the rack 74. A pulley 77 corresponding to the slide rail 76 is slidably connected to the slide rail 76, and the pulley 77 only slides along the slide rail 76. The pulley 77 is rotatably connected to the moving block 71. Since the pulley 77 only slides along the slide rail 76, during the process of the gear 73 and the rack 74 meshing and moving, the gear 73 and the rack 74 are always kept in meshing through the guiding effect of the pulley 77 and the slide rail 76, thereby reducing the possibility of the gear 73 being separated from the rack 74 during the process of moving around the pier body 1, and at the same time better ensuring that the moving block 71 drives the water pipe 6 to move around the pier body 1 smoothly, thereby better improving the effect of spraying and curing the pier body 1.
[0039] Reference Figure 3 The water pump 4 is connected with a timer 8, and the water pump 4 is controlled to be turned on and off at a fixed time by the timer 8, and the water pump 4 and the rotating motor 72 can be turned on or off at the same time. When it is time to spray the pier body 1, the water pump 4 is controlled by the counter to be turned on, and the rotating motor 72 is started at the same time as the water pump 4 is turned on, so that the rotating motor 72 and the water pump 4 operate together, reducing the possibility of water resource waste caused by the water pump 4 being turned on first; when the spraying time preset on the timer 8 is reached, the water pump 4 is controlled to be turned off by the timer 8, and the rotating motor 72 is turned off together with the water pump 4, thereby reducing the possibility of electricity waste caused by the delayed shutdown of the rotating motor 72.
[0040] The implementation principle of the embodiment of the present application is as follows: when it is time to spray and maintain the pier body 1, the water pump 4 is started by controlling the counter, and the rotating motor 72 and the water pump 4 are started at the same time, so that the water pipe 6 sprays and maintains the pier body 1 while moving horizontally around the pier body 1, thereby better spraying and maintaining the pier body 1 as a whole, improving the maintenance effect of the pier body 1, and reducing the possibility of cracks on the surface of the pier body 1; when the spraying time preset on the timer 8 is reached, the water pump 4 is automatically controlled to start by the timer 8, and the rotating motor 72 and the water pump 4 are turned off at the same time, so that the movement of the water pipe 6 and the spraying maintenance of the pier body 1 are stopped at the same time, thereby better automatically controlling the spraying operation of the water pipe 6 on the pier body 1, improving the maintenance efficiency of the pier body 1, and reducing the labor intensity of manual operation; while the pier body 1 is being sprayed and maintained, the water reservoir 3 collects and reuses the water flowing down from the pier body 1, thereby better saving water resources.
[0041] The embodiments of this specific implementation are all preferred embodiments of the present application, and are not intended to limit the protection scope of the present application. The same components are represented by the same figure marks. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A pier body concrete curing device using circulating water, comprising a pier body (1), characterized in that: A water retaining bank (2) is cast around the pier body (1), a water reservoir (3) for storing water for maintenance is provided on the ground between the pier body (1) and the water retaining bank (2), a slope (21) is provided at the connection between the water retaining bank (2) and the water reservoir (3) to facilitate the return of spray water to the water reservoir (3), a water pump (4) is provided in the water reservoir (3), a water pipe (6) for spraying and maintaining the pier body (1) is connected to the water pump (4), and a water outlet hole (61) is provided on the water pipe (6).
2. A pier shaft concrete curing device using circulating water according to claim 1, characterized in that: A protective net (33) is hingedly connected to an open portion of one side of the water storage tank (3) close to the pier body (1).
3. The pier shaft concrete curing device using circulating water according to claim 1 is characterized in that: The inner wall of the water reservoir (3) is provided with ceramic tiles (32) fixedly connected to the water pump (4), and a waterproof film (31) for reducing water loss is laid between the water reservoir (3) and the ceramic tiles (32).
4. The pier shaft concrete curing device using circulating water according to claim 1 is characterized in that: A soft connecting pipe (5) is connected between the water pipe (6) and the water pump (4), and a moving component is provided at the lower end of the water pipe (6) for driving the water pipe (6) to move around the pier body (1).
5. The pier shaft concrete curing device using circulating water according to claim 4 is characterized in that: The moving assembly comprises a support frame (75) which surrounds the pier body (1), the support frame (75) being fixedly connected to the ground, a rack (74) matching the support frame (75) being installed on the upper surface of the support frame (75), a moving block (71) fixedly connected to the water pipe (6) being arranged above the rack (74), a gear (73) meshing with the rack (74) being rotatably connected to the moving block (71), and a rotating motor (72) fixedly connected to the moving block (71) being fixedly connected to one side of the gear (73).
6. The pier shaft concrete curing device using circulating water according to claim 5 is characterized in that: Slide rails (76) having the same track as the rack (74) are provided on both sides of the rack (74); the slide rails (76) are mounted on the support frame (75); and a pulley (77) rotatably connected to the moving block (71) is slidably connected to the slide rails (76).
7. A pier shaft concrete curing device using circulating water according to claim 6, characterized in that: The water pump (4) is connected to a timer (8) for controlling the opening and closing of the water pump (4).
8. The pier shaft concrete curing device using circulating water according to claim 1 is characterized in that: The water pipe (6) is provided with an atomizing nozzle (62) corresponding to the water outlet hole (61).