Water stopping and seepage preventing structure for engineering construction
By using water-proof and anti-seepage structures such as sewage pumps, water suction pipes, and waterproof membrane layers at the construction site, the problem of construction sewage flowing into the water system and underground pollution has been solved, and effective sewage management and environmental protection have been achieved.
Patent Information
- Application Number
- CN202420295784.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-18
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2034-02-18
AI Technical Summary
During the construction process, it is difficult to effectively prevent construction sewage from flowing into the water system with existing technology, resulting in the infiltration of ground sewage and contamination of underground water bodies.
It adopts a water-proof and anti-seepage structure including a sewage pump, water suction pipe, collection water tank, water tank filter top plate, waterproof membrane layer, clay layer and protective layer. The liquid level sensor is used to automatically control the sewage pump. The waterproof membrane layer and protective layer prevent sewage from penetrating. And discharge the permeated wastewater through the sewage pump.
It effectively prevents surface sewage and oily sewage from penetrating into the ground, prevents groundwater pollution, reduces the pressure on the waterproof layer, and improves the environmental protection effect of the construction site.
Smart Images

Figure CN221822835U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of engineering waterproof structures, in particular to a water-stopping and anti-seepage structure used in engineering construction. Background Art
[0002] At present, China Patent No.: CN202310095678.1 discloses a water-stopping and anti-seepage structure, which relates to the technical field of water conservancy project construction. The present invention includes an outer body device, a control device and a protective device. The outer body device includes a fixed plate, an elastic waterproof pad, a horizontal plate, a mobile base and a triangular plate. The control device is arranged inside the fixed plate, including a driving wheel, a driven wheel, a rotating rod, a screw rod, a cylinder, a mobile plate and a connecting end. The surface of one side of the driving wheel is connected to the surface of one side of the driven wheel. A threaded cylinder is provided in the middle of the mobile plate. The protective device includes a heat dissipation frame, a hinge, a door panel, a heat dissipation hole and a rain shelter. The present invention is a water-stopping and anti-seepage structure. The motor controls the rotation of the internal screw rod to drive the movement of the mobile base to meet the needs of using water channels of different widths. The heat of the motor is discharged through the heat dissipation hole to ensure the normal use of the motor. Compared with the traditional anti-seepage structure, it is more practical, has a wider range of use, less manual labor and higher work efficiency. However, during the construction process, it is necessary to explore nearby rivers and groundwater to prevent construction sewage from flowing into the water system. For the infiltration of the ground downward, the treatment effect of the existing technology needs to be improved. Utility Model Content
[0003] Therefore, in response to the above-mentioned problems, the utility model proposes a water-stopping and anti-seepage structure for engineering construction, which solves the technical problems that the prior art still has in actual use, that is, during the engineering construction process, it is necessary to explore nearby rivers and groundwater to prevent construction wastewater from flowing into the water system, and the treatment effect of the prior art needs to be improved as it seeps downwards into the ground.
[0004] To achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a water-stopping and anti-seepage structure for engineering construction, which structure includes a sewage pump, a suction pipe, a water collection tank, a water tank filter top plate, a first protective layer, a second protective layer, a waterproof membrane layer, and a clay layer. The sewage pump is arranged on the ground and its rear end is connected to a closed sewage tank, the front end of the sewage pump is connected to the suction pipe, the front end of the suction pipe is connected to the water collection tank, a water tank filter top plate is arranged on the top of the water collection tank, an inclined waterproof membrane layer is arranged around the top of the water collection tank, a first protective layer and a second protective layer are arranged below the waterproof membrane layer, and a first protective layer and a second protective layer are also arranged above the waterproof membrane layer.
[0005] Furthermore, the water collection tank is made of metal and is located 3-5 m underground.
[0006] Furthermore, a liquid level sensor for detecting the position of the liquid is disposed inside the collection water tank, and the liquid level sensor is a structure for automatically controlling the operation of the sewage pump by detecting the liquid level.
[0007] Furthermore, the water collection tank is a rectangular parallelepiped structure with a capacity of 500-1000L.
[0008] Furthermore, the waterproof membrane layer is made of HDPE waterproof membrane material.
[0009] Furthermore, the first protective layer and the second protective layer below the HDPE waterproof membrane are arranged from bottom to top, the first protective layer is a puncture-resistant protective layer, the second protective layer is a thermal insulation layer, and the first protective layer and the second protective layer above the HDPE waterproof membrane are arranged from top to bottom.
[0010] Furthermore, the waterproof membrane layer is provided with 1-2 layers.
[0011] Furthermore, a 5-10 cm thick clay layer is laid on top of the waterproof membrane layer.
[0012] By adopting the above-mentioned technical scheme, the beneficial effects of the utility model are as follows: the water-stopping and anti-seepage structure of the construction of this project improves the existing technology. In actual use, there is still the situation that ground sewage seeps in the construction site without completely hardened ground. The setting of waterproof membrane layer can effectively prevent ground oil, domestic sewage, etc. from penetrating into the underground and avoid polluting the groundwater. The setting of water tank and drainage pump can effectively discharge the infiltrated wastewater and avoid excessive pressure on the waterproof layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 It is a structural schematic diagram of the utility model;
[0014] In the figure: 1. Sewage pump; 2. Suction pipe; 3. Collection tank; 4. Water tank filter top plate; 5. First protective layer; 6. Second protective layer; 7. Waterproof membrane layer; 8. Clay layer. DETAILED DESCRIPTION
[0015] The utility model is now further described in conjunction with the accompanying drawings and specific implementation methods.
[0016] refer to Figure 1The present embodiment provides a water-stopping and anti-seepage structure for engineering construction, which includes a sewage pump 1, a water suction pipe 2, a water collection tank 3, a water tank filter top plate 4, a first protective layer 5, a second protective layer 6, a waterproof membrane layer 7, and a clay layer 8. The sewage pump 1 is arranged on the ground and its rear end is connected to a closed sewage tank, the front end of the sewage pump 1 is connected to the water suction pipe 2, the front end of the water suction pipe 2 is connected to the water collection tank 3, the top of the water collection tank 3 is provided with a water tank filter top plate 4, the top of the water collection tank 3 is provided with an inclined waterproof membrane layer 7, the first protective layer 5 and the second protective layer 6 are provided below the waterproof membrane layer 7, and the first protective layer 5 and the second protective layer 6 are also provided above the waterproof membrane layer 7.
[0017] Furthermore, the water collection tank 3 is made of metal and is disposed at a position 3-5 m underground.
[0018] Furthermore, a liquid level sensor for detecting the position of the liquid is disposed inside the water collection tank 3 , and the liquid level sensor is a structure for automatically controlling the operation of the sewage pump 1 by detecting the liquid level.
[0019] Furthermore, the water collection tank 3 is a rectangular parallelepiped structure with a capacity of 500-1000L.
[0020] Furthermore, the waterproof membrane layer 7 is made of HDPE waterproof membrane material.
[0021] Furthermore, the first protective layer 5 and the second protective layer 6 below the HDPE waterproof membrane are arranged from bottom to top, the first protective layer 5 is a puncture-resistant protective layer, the second protective layer 6 is a thermal insulation layer, and the first protective layer 5 and the second protective layer 6 above the HDPE waterproof membrane are arranged from top to bottom.
[0022] Furthermore, the waterproof membrane layer 7 is provided with 1-2 layers.
[0023] Furthermore, a clay layer 8 with a thickness of 5-10 cm is laid on the waterproof membrane layer 7 .
[0024] The water-stopping and anti-seepage structure of the construction of this project has improved the existing technology. In actual use, there is still the situation of ground sewage infiltration in the construction site without completely hardened ground. The waterproof membrane layer 7 is set to effectively prevent the ground oil, domestic sewage, etc. from penetrating into the ground and avoid polluting the groundwater. The water tank and drainage pump are set to effectively discharge the infiltrated wastewater and avoid excessive pressure on the waterproof layer.
[0025] The first protective layer 5, the second protective layer 6, and the waterproof membrane layer 7 used in this solution do not contain preservatives, and their effective life is 2-3 years. Their natural degradation rate is 20-50% in 5-10 years. After the construction is completed, the first protective layer 5, the second protective layer 6, and the waterproof membrane layer 7 can be perforated using a puncture device.
[0026] The above shows and describes the basic principles and main features of the utility model and the advantages of the utility model. For those skilled in the art, it is obvious that the utility model is not limited to the details of the above exemplary embodiments, and can be implemented in other specific forms without departing from the spirit or basic features of the utility model. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the utility model is limited by the attached claims rather than the above description, and it is intended to include all changes within the meaning and scope of the equivalent elements of the claims. Any figure mark in the claims should not be regarded as limiting the claims involved.
[0027] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A water-stopping and anti-seepage structure for engineering construction, characterized in that: Its structure includes a sewage pump, a suction pipe, a water collection tank, a water tank filter top plate, a first protective layer, a second protective layer, a waterproof membrane layer, and a clay layer. The sewage pump is arranged on the ground and its rear end is connected to a closed sewage tank. The front end of the sewage pump is connected to the suction pipe, and the front end of the suction pipe is connected to the water collection tank. A water tank filter top plate is arranged on the top of the water collection tank. Inclined waterproof membrane layers are arranged around the top of the water collection tank. A first protective layer and a second protective layer are arranged below the waterproof membrane layer, and a first protective layer and a second protective layer are also arranged above the waterproof membrane layer.
2. A water-stopping and anti-seepage structure for engineering construction according to claim 1, characterized in that: The water collection tank is made of metal and is located 3-5 m underground.
3. The waterproof and anti-seepage structure for engineering construction according to claim 1, characterized in that: A liquid level sensor for detecting the position of the liquid is arranged inside the collection water tank, and the liquid level sensor is a structure for automatically controlling the operation of the sewage pump by detecting the liquid level.
4. The waterproof and anti-seepage structure for engineering construction according to claim 1, characterized in that: The collecting water tank is a rectangular parallelepiped structure with a capacity of 500-1000L.
5. The waterproof and anti-seepage structure for engineering construction according to claim 1, characterized in that: The waterproof membrane layer is made of HDPE waterproof membrane material.
6. A water-stopping and anti-seepage structure for engineering construction according to claim 5, characterized in that: The first protective layer and the second protective layer below the HDPE waterproof membrane are arranged from bottom to top, the first protective layer is a puncture-resistant protective layer, the second protective layer is a thermal insulation layer, and the first protective layer and the second protective layer above the HDPE waterproof membrane are arranged from top to bottom.
7. The waterproof and anti-seepage structure for engineering construction according to claim 1, characterized in that: The waterproof membrane layer is provided with 1-2 layers.