Double-layer gypsum board suspended ceiling

By using structures such as suspenders, main keels, auxiliary keels and limit plates in the double-layer gypsum board ceiling to disperse the stress area and provide screw movement space, the problem of reduced stability of the double-layer gypsum board connection is solved and the structure is improved. stability and adaptability.

CN221823196UActive Publication Date: 2024-10-11SHENZHEN XINYA CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420368308.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-28
Publication Date
2024-10-11
Estimated Expiration
2034-02-28

AI Technical Summary

Technical Problem

Due to the heavy weight of the double-layer gypsum board ceiling, it is difficult to control the self-tapping screw caps, which leads to a decrease in connection stability and can easily lead to cracking of the gypsum board.

Method used

It adopts structures such as boom, main keel, auxiliary keel and limit plate. Through the design of limit plate and nut, the force-bearing area is dispersed and the possibility of screw detachment is reduced. The movable groove and guide plate are used to provide screw movement space and adjust Limit plate position to improve fit.

Benefits of technology

It improves the connection stability of double-layer gypsum boards, reduces the risk of cracking, and enhances the adaptability and stability of the structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221823196U_ABST
    Figure CN221823196U_ABST
Patent Text Reader

Abstract

The utility model discloses a double-layer plasterboard suspended ceiling, and belongs to the technical field of plasterboard suspended ceilings, the double-layer plasterboard suspended ceiling comprises suspenders connected to a building wall body, external threads are formed in the exteriors of the suspenders, and connecting components used for connection, main keels used for bearing and double-layer plasterboards used for tiling are arranged on the exteriors of the suspenders; a hanging piece is installed outside the main keel in a sliding mode, an auxiliary keel is installed outside the hanging piece in a sliding mode, and the double-layer gypsum board is fixedly connected to the auxiliary keel to complete hoisting. According to the double-layer plasterboard suspended ceiling, the mounting screws and the limiting plates on the auxiliary keels used for connecting the double-layer plasterboards are attached to the double-layer plasterboards, so that the double-layer plasterboards can be borne by the limiting plates dispersing the stress area, and the possibility that the double-layer plasterboards are disengaged from original screws is reduced; and a movable groove is formed to provide a screw movable space, so that the position of the limiting plate relative to the double-layer gypsum board is conveniently adjusted, and the adaptability of the structure is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of gypsum board ceilings, in particular to double-layer gypsum board ceilings. Background Art

[0002] Double-layer gypsum board ceiling is a common interior decoration material. Double-layer gypsum board ceiling refers to the use of two layers of gypsum boards laid with staggered joints. Compared with single-layer gypsum boards, double-layer gypsum board ceilings are more stable, have better tensile and crack resistance, and have a lower chance of cracking.

[0003] Since the double-layer gypsum board ceiling is composed of two layers of gypsum boards, the weight of the double-layer gypsum board ceiling is relatively large. Currently, the double-layer gypsum boards are fixed to the supporting keel parts by self-tapping screws. Due to the large weight of the double-layer gypsum boards, the depth of the self-tapping screw caps sinking into the double-layer gypsum boards is difficult to control. The self-tapping screw caps entering too deep or protruding from the surface are likely to cause the connection stability of the gypsum boards to decrease. In this regard, a double-layer gypsum board ceiling is proposed to solve the above-mentioned problems. Utility Model Content

[0004] In view of the deficiencies in the prior art, the present application provides a double-layer gypsum board ceiling, which has the advantages of having a stable structure and improving the connection stability of the double-layer gypsum board.

[0005] In summary, the present application provides the following technical solutions: a double-layer gypsum board ceiling, comprising a suspension rod connected to a building wall, the exterior of each of the suspension rods being provided with an external thread, and the exterior of each of the suspension rods being provided with a connecting member for connection;

[0006] Main keels for load bearing and double-layer gypsum board for tiling;

[0007] A hanger is slidably installed outside the main keel, a secondary keel is slidably installed outside the hanger, and the double-layer gypsum board is fixedly connected to the secondary keel to complete the hoisting;

[0008] The secondary keel is provided with a movable component, and a limit plate is installed through the movable component, and the limit plate is attached to the double-layer gypsum board.

[0009] By adopting the above technical solution, the double-layer gypsum board can be supported by the limiting plate with dispersed force area, thereby reducing the possibility of the double-layer gypsum board being separated from the original screws.

[0010] Furthermore, the connecting member includes an expansion bolt fixedly mounted on one end of the hanger rod, and the expansion bolt extends through the building wall.

[0011] By adopting the above technical solution, the suspension rod can be suspended on the indoor top wall of the building.

[0012] Furthermore, the connecting component also includes a hanging piece threadedly mounted on the other end of the hanging rod, the hanging piece is U-shaped and connected to the outside of the main keel, and the top end of the hanging piece is bent and threadedly connected to the hanging rod.

[0013] By adopting the above technical solution, the hanging piece can carry the main keel to fine-tune the height position relative to the hanging rod.

[0014] Furthermore, bolts are threadedly installed between two side edges of the U-shape of the hanging piece.

[0015] By adopting the above technical solution, it is possible to facilitate clamping the main keel through the hanging piece.

[0016] Furthermore, a movable groove is provided on the surface of the secondary keel.

[0017] By adopting the above technical solution, the movable component can be adjusted to adapt to the double-layer gypsum board.

[0018] Furthermore, the movable component includes a guide plate fixedly mounted on the inner wall of the secondary keel, and the number of the guide plates is two, and the two guide plates are located on both sides of the movable groove.

[0019] By adopting the above technical solution, a guide space can be formed for the movement of the connecting nut.

[0020] Furthermore, a nut is slidably installed between the two guide plates, the nut is fitted to the guide plate, a screw is threadedly installed on the nut, and the screw is rotatably connected to the limit plate.

[0021] By adopting the above technical solution, the limiting plate can be adjusted to be close to the secondary keel.

[0022] The double-layer gypsum board ceiling is provided with screws installed on a secondary keel for connecting the double-layer gypsum board and a limit plate to fit the double-layer gypsum board, so that the double-layer gypsum board can be supported by the limit plate with a dispersed force-bearing area, thereby reducing the possibility of the double-layer gypsum board being detached from the original screws. At the same time, a nut is provided to move in the secondary keel, and a movable groove is provided to provide a movable space for the screw, so as to facilitate the adjustment of the position of the limit plate relative to the double-layer gypsum board and improve the adaptability of the structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a schematic diagram of the overall structure of this application;

[0024] Figure 2 It is a bottom view of the secondary keel of this application;

[0025] Figure 3 It is a top view of the secondary keel of this application.

[0026] Description of reference numerals:

[0027] 1. Hanging rod; 2. Expansion bolt; 3. Hanging parts; 4. Main keel; 5. Hanging parts; 6. Secondary keel; 7. Double-layer gypsum board; 8. Movable groove; 9. Guide plate; 10. Nut; 11. Screw; 12. Limit plate. DETAILED DESCRIPTION

[0028] See also Figure 1 The double-layer gypsum board ceiling in this embodiment includes a hanger 1 connected to the building wall, a main keel 4 for bearing and a double-layer gypsum board 7 for paving. The outside of the hanger 1 is provided with an external thread, and a connecting member for connection is provided on the outside of the hanger 1. The hanger 1 and the main keel 4 are relatively connected through the connecting member.

[0029] It should be noted that the connecting member includes an expansion bolt 2 fixedly mounted on one end of the hanger 1, and the expansion bolt 2 extends through the building wall, so that the hanger 1 can be suspended on the indoor ceiling of the building.

[0030] The connecting component also includes a hanger 3 threadedly installed on the other end of the hanger 1. The hanger 3 is U-shaped and connected to the outside of the main keel 4, and the top of the hanger 3 is bent and threadedly connected to the hanger 1, so that the hanger 3 can carry the main keel 4 to fine-tune the height position relative to the hanger 1.

[0031] It is understandable that bolts may be threadedly installed between the two sides of the U-shape of the hanger 3 to clamp the main keel 4 .

[0032] See also Figure 1 In this embodiment, a hanger 5 is slidably installed on the outside of the main keel 4, and a secondary keel 6 is slidably installed on the outside of the hanger 5. The double-layer gypsum board 7 is fixedly connected to the secondary keel 6 to complete the hoisting.

[0033] See also Figure 2-3 In this embodiment, a movable component is provided on the secondary keel 6, and a limit plate 12 is installed through the movable component. The limit plate 12 is attached to the double-layer gypsum board 7 to stabilize the fastening connection between the double-layer gypsum board 7 and the secondary keel 6.

[0034] A movable groove 8 is provided on the surface of the secondary keel 6 in this embodiment, and the movable component includes a guide plate 9 fixedly installed on the inner wall of the secondary keel 6. There are two guide plates 9, and the two guide plates 9 are located on both sides of the movable groove 8. A nut 10 is slidably installed between the two guide plates 9. The nut 10 is fitted to the guide plate 9 so that the nut 10 can avoid rotating relative to the secondary keel 6.

[0035] It should be noted that a screw 11 is threadedly mounted on the nut 10 , and the screw 11 is rotatably connected to the limiting plate 12 , so that the screw 11 can be engaged with the nut 10 by rotating the thread to enable the limiting plate 12 to clamp the double-layer gypsum board 7 .

[0036] The working principle of the above embodiment is:

[0037] The installation of the hanger 1 is completed by extending the expansion bolt 2 into the building wall, and the main keel 4 can be installed on the building wall by threading the hanger 3 on the hanger 1. After the secondary keel 6 is slidably connected to the hanger 5, the hanger 5 is slid on the main keel 4, so that the secondary keel 6 can be installed on the building wall. At the same time, the screw 11 sliding on the secondary keel 6 is passed through the joint connecting the double-layer gypsum board 7, so that the limit plate 12 connected by the rotation of the end of the screw 11 can fit the double-layer gypsum board 7, and the screw 11 is rotated so that the limit plate 12 squeezes the double-layer gypsum board 7 and the secondary keel 6 to complete the fixation, thereby stabilizing the double-layer gypsum board 7.

Claims

1. A double-layer gypsum board ceiling, comprising a suspension rod (1) connected to a building wall, wherein the outside of the suspension rod (1) is provided with an external thread, and the outside of the suspension rod (1) is provided with a connecting member for connection; The main keel (4) for bearing and the double-layer gypsum board (7) for tiling, Features: A hanging piece (5) is slidably mounted on the outside of the main keel (4), a secondary keel (6) is slidably mounted on the outside of the hanging piece (5), and the double-layer gypsum board (7) is fixedly connected to the secondary keel (6) to complete the hoisting; A movable component is provided on the secondary keel (6), and a limit plate (12) is installed via the movable component, wherein the limit plate (12) is attached to the double-layer gypsum board (7).

2. The double-layer gypsum board ceiling according to claim 1 is characterized in that: The connecting member comprises an expansion bolt (2) fixedly mounted on one end of the suspension rod (1), and the expansion bolt (2) extends through the building wall.

3. The double-layer gypsum board ceiling according to claim 1 is characterized in that: The connecting member further comprises a hanging piece (3) threadedly mounted on the other end of the hanging rod (1); the hanging piece (3) is connected to the outside of the main keel (4) in a U-shape, and the top end of the hanging piece (3) is threadedly connected to the hanging rod (1) in a bent shape.

4. The double-layer gypsum board ceiling according to claim 3 is characterized in that: Bolts are threadedly mounted between the two side edges of the U-shape of the hanging member (3).

5. The double-layer gypsum board ceiling according to claim 1, characterized in that: A movable groove (8) is provided on the surface of the secondary keel (6).

6. The double-layer gypsum board ceiling according to claim 5, characterized in that: The movable component comprises a guide plate (9) fixedly mounted on the inner wall of the secondary keel (6), the number of the guide plates (9) being two, and the two guide plates (9) being located on both sides of the movable groove (8).

7. The double-layer gypsum board ceiling according to claim 6, characterized in that: A nut (10) is slidably mounted between the two guide plates (9), the nut (10) being fitted to the guide plate (9), a screw (11) being threadedly mounted on the nut (10), and the screw (11) being rotatably connected to the limiting plate (12).