Powder storage bin and measuring bin shared dust removal structure
By installing a pulse bag dust removal system above the powder storage silo and using pneumatic valves and soft connectors to control gas emissions, the problem of material spraying caused by air pressure changes in the metering bin of the powder storage silo is solved, and the metering accuracy and It reduces energy consumption and achieves efficient powder metering, energy saving and emission reduction.
Patent Information
- Application Number
- CN202420620452.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-28
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-03-28
AI Technical Summary
Existing powder storage silos and metering silos spray material due to changes in air pressure during feeding. A pulse bag dust collector needs to be installed to exhaust the gas. However, the vibration of this device affects the measurement accuracy, resulting in unbalanced proportions and material loss. .
Design a shared dust removal structure for the powder storage silo and metering silo. By installing a pulse bag dust removal system above the storage silo, and using pneumatic valves and soft connectors to form a loop to control gas emissions and avoid vibrations that affect metering accuracy, it is possible to achieve The gas is repeatedly collected and recycled.
It improves the measurement accuracy, avoids the impact of dust removal equipment vibration on measurement accuracy, reduces maintenance costs and energy consumption, extends the service life of the equipment, ensures product quality and saves costs.
Smart Images

Figure CN221853554U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of lithium battery production equipment, and in particular to a powder storage bin and metering bin shared dust removal structure. Background Art
[0002] Powder silo is a storage device for storing powder materials. Powder materials are generally packed in bags. The existing powder feeding method is basically manual direct feeding, and the powder materials fall freely by gravity through the lower discharge port of the bag into the powder silo.
[0003] In the lithium battery manufacturing slurry mixing process, it is necessary to accurately measure the addition amount of various raw materials. The design adopts a dual-bin operation mode of a raw material bin and a metering bin. When feeding, the air pressure inside the existing powder storage bin and metering bin gradually decreases due to the volume of the bin. The gas volume is gradually compressed and will be higher than the external air pressure, resulting in material spraying; in order to avoid material spraying, the gas in the bin needs to be discharged to the outside. The usual solution is to install a pulse bag dust collector on the top to empty the gas in the bin, and use the pressure difference between the inside and outside of the bin to separate the gas and the material adsorbed on the filter bag. However, this device needs to be installed on the metering bin. Then, when the pulse timing works, the device will vibrate, which will affect the metering accuracy, cause unbalanced ratios during addition and waste of materials, thereby affecting the quality of the final battery product. Based on this, the utility model provides a powder storage bin and metering bin shared dust removal structure with a simple and ingenious structure, which can avoid the dust removal component on the metering bin affecting the metering accuracy. Utility Model Content
[0004] The utility model aims to solve the shortcomings of the prior art and provide a powder storage bin and metering bin common dust removal structure to solve the technical problem that the dust removal component installed on the metering bin will affect the metering accuracy.
[0005] The purpose of the utility model can be achieved through the following technical solutions:
[0006] A powder storage bin and metering bin shared dust removal structure, comprising:
[0007] A material storage bin body is connected to a feed pipe, and a first pneumatic valve is provided at the connection between the two, and the material storage bin body is connected to the feed end of the first spiral conveying assembly;
[0008] The metering bin body is connected to the discharge end of the first screw conveying assembly, and a third pneumatic valve is provided at the connection between the two. The discharge port of the metering bin body is connected to the feed end of the second screw conveying assembly;
[0009] A connecting pipe, whose feeding end is connected to the metering bin body, and a fourth pneumatic valve is provided at the connection between the two, the discharging end of the connecting pipe is connected to the storage bin body, and a second pneumatic valve is provided at the connection between the two, and two soft connectors are respectively provided at the connection between the metering bin body and the discharging end of the first spiral conveying assembly and the feeding end of the connecting pipe, and the two soft connectors are connected by the connecting pipe to form a loop; and
[0010] A pulse dust collector is arranged on the circuit, and a soft connector is arranged between the pulse dust collector and the metering bin body.
[0011] As a further solution of the utility model: the air inlet of the pulse dust collector is provided with an air inlet valve, and the exhaust port thereof is provided with an exhaust valve.
[0012] As a further solution of the utility model: two soft connectors are respectively provided at the connection between the metering bin body and the discharge end of the first spiral conveying assembly and the feed end of the connecting pipe.
[0013] As a further solution of the utility model: two agitators are respectively arranged in the storage bin body and the metering bin body.
[0014] As a further solution of the utility model: a discharge assembly is provided at the connection between the metering bin body and the feeding end of the second spiral conveying assembly.
[0015] As a further solution of the utility model: the unloading component is an equal amount batch type unloading structure.
[0016] Beneficial effects of the utility model:
[0017] (1) In the present invention, the storage bin body and the metering bin body are designed as two-layer platforms that are designed separately and not connected to each other. The two share a pulse bag dust removal system, and the system is installed above the storage bin body. The adsorbed powder is cleaned regularly by pulses and dust removal bags. When the metering bin body measures the weight of the powder, the operation mechanism controls the sequence of actions of each link without affecting the metering system. Therefore, the metering accuracy can reach an accuracy of one ten-thousandth. It can also avoid the problem of reduced metering accuracy due to the vibration of the dust removal equipment when the metering bin body is dusted. The addition of materials is accurate and controllable, ensuring product quality while saving costs.
[0018] (2) In the present invention, the pipes are connected by local soft connections to form an interconnected structure. When the internal air pressure is higher than the external air pressure, the gas can be discharged to the outside through the filter bag, and the powder is adsorbed on the filter bag to achieve repeated collection and recycling. This can prevent the vibration generated by the pulse dust collector during operation from affecting the weighing result in the metering bin body;
[0019] (3) In the present invention, only a single bag dust removal system is needed. Compared with the use of multiple bag dust removal systems, the maintenance cost can be reduced and the maintenance difficulty is reduced simultaneously, thereby improving the utilization efficiency and maintenance efficiency of the production line, extending the service life of the equipment, and reducing the burden on the enterprise;
[0020] (4) In the present invention, the usage of the bag dust removal system is reduced, and the usage of the compressor is greatly reduced, so the power consumption during actual production is greatly reduced, reducing energy consumption and achieving energy conservation and emission reduction. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The utility model is further described below in conjunction with the accompanying drawings.
[0022] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0023] Figure 2 This utility model Figure 1 Schematic diagram of the local enlarged structure at A.
[0024] In the figure: 1. Storage bin body; 2. Measuring bin body; 3. First screw conveying assembly; 4. Second screw conveying assembly; 5. Discharging assembly; 6. Feed pipe; 7. Pulse dust collector; 8. Connecting pipe; 9. Agitator; 10. Flexible connector; 11. First pneumatic valve; 12. Second pneumatic valve; 13. Third pneumatic valve; 14. Fourth pneumatic valve; 15. Inlet valve; 16. Exhaust valve. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] See also Figure 1-Figure 2 As shown, the utility model is a powder storage bin and metering bin shared dust removal structure, comprising:
[0027] The material storage bin body 1 is connected with a feed pipe 6, and a first pneumatic valve 11 is provided at the connection between the two. The material storage bin body 1 is connected with the feed end of the first spiral conveying assembly 3;
[0028] The metering bin body 2 is connected to the discharge end of the first screw conveying assembly 3, and a third pneumatic valve 13 is provided at the connection between the two. The discharge port of the metering bin body 2 is connected to the feed end of the second screw conveying assembly 4;
[0029] A connecting pipe 8, whose feeding end is connected to the metering bin body 2, and a fourth pneumatic valve 14 is provided at the connection between the two, the discharging end of the connecting pipe 8 is connected to the storage bin body 1, and a second pneumatic valve 12 is provided at the connection between the two, and two soft connectors 10 are respectively provided at the connection between the metering bin body 2 and the discharging end of the first spiral conveying assembly 3 and the feeding end of the connecting pipe 8, and the two soft connectors 10 are connected through the connecting pipe 8 to form a loop; and
[0030] The pulse dust collector 7 is arranged on the circuit, and a soft connector 10 is arranged between the pulse dust collector 7 and the metering bin body 2.
[0031] Among them, the pulse dust collector 7 can be installed on the storage bin body 1, or on the first spiral conveying assembly 3, or on the connecting pipe 8. Of course, it can also be selected to be set outside and connected to any one of the pulse dust collector 7, the first spiral conveying assembly 3 and the connecting pipe 8 through a pipeline, as long as it is not directly installed on the metering bin body 2, and a soft connector 10 is provided on the pipeline between the pulse dust collector 7 and the metering bin body 2 to reduce the impact of the pulse dust collector 7 on the metering bin body 2 when it is working to remove dust.
[0032] In one case of the present embodiment, the pulse dust collector 7 is provided with an air inlet and an exhaust port; the electrical components such as the first spiral conveying assembly 3, the second spiral conveying assembly 4, the pulse dust collector 7, the first pneumatic valve 11, the second pneumatic valve 12, the third pneumatic valve 13 and the fourth pneumatic valve 14 are all connected to an external controller. The above-mentioned electrical components and the external controller are all prior arts, and the present application does not improve them. Therefore, there is no need to disclose their specific mechanical structure and circuit structure, and it does not affect the integrity of the present application. The soft connector 10 is a hose. Of course, other structures that can achieve soft connection can also be selected. This embodiment does not make specific limitations here.
[0033] In actual application of this embodiment, the storage bin body 1 and the metering bin body 2 are designed as two-layer platforms that are independently designed and not connected to each other, and the two share a pulse bag dust removal system, that is, a pulse dust collector 7. The pulse dust collector 7 is installed above the storage bin body 1, and the adsorbed powder is cleaned regularly by pulses and dust bags; a DN40 air hole is respectively provided in the storage bin body 1 and the metering bin body 2, and the two air holes are respectively connected to the feeding end and the discharging end of the connecting pipe 8; when the metering bin body 2 measures the weight of the powder, the operation mechanism is used to control the order of the actions of each link. It does not affect the metering system, so the metering accuracy can reach an accuracy of one ten-thousandth. It can also avoid the problem of reduced metering accuracy due to the vibration of the dust removal equipment when the metering bin body 2 is dusted. The added materials are precisely controllable, ensuring product quality while saving costs. The pipelines are connected by setting local soft connections to form an interconnected structure. When the internal air pressure is higher than the external air pressure, the gas can be discharged to the outside through the filter bag, and the powder is adsorbed on the filter bag to achieve repeated collection and recycling. In this way, the vibration generated by the pulse dust collector 7 when it is working can be avoided. The impact on the weighing result in the metering bin body 2.
[0034] When the storage bin body 1 is being fed, the first pneumatic valve 11 and the exhaust port of the pulse dust collector 7 are opened, and the second pneumatic valve 12, the third pneumatic valve 13, the fourth pneumatic valve 14 and the air inlet of the pulse dust collector 7 are closed. At this time, the pulse dust collector 7 is not working, and its exhaust port is opened to connect the inside and outside for exhaust;
[0035] When the storage bin body 1 is full of material, the air inlet of the pulse dust collector 7 is opened, and the first pneumatic valve 11, the second pneumatic valve 12, the third pneumatic valve 13, the fourth pneumatic valve 14 and the exhaust port of the pulse dust collector 7 are closed. At this time, the pulse dust collector 7 works to clean the bag adsorbing the material;
[0036] When the metering bin body 2 is charged, the second pneumatic valve 12, the third pneumatic valve 13, the fourth pneumatic valve 14 and the exhaust port of the pulse dust collector 7 are opened, and the first pneumatic valve 11 and the air inlet of the pulse dust collector 7 are closed. At this time, the pulse dust collector 7 does not work, and its exhaust port is opened to connect the inside and outside to exhaust;
[0037] When the metering bin body 2 is weighed, the second pneumatic valve 12, the fourth pneumatic valve 14 and the exhaust port of the pulse dust collector 7 are opened, and the first pneumatic valve 11, the third pneumatic valve 13 and the air inlet of the pulse dust collector 7 are closed. At this time, the pulse dust collector 7 does not work, and its exhaust port can be opened to connect the inside and outside to exhaust, and the weight of the material is measured;
[0038] When the metering bin body 2 is not weighed, the air inlet of the pulse dust collector 7 is opened, and the first pneumatic valve 11, the second pneumatic valve 12, the third pneumatic valve 13, the fourth pneumatic valve 14 and the exhaust port of the pulse dust collector 7 are closed. At this time, the pulse dust collector 7 works to clean the bag adsorbed materials.
[0039] like Figure 2 As shown, as a preferred embodiment of the utility model, the air inlet of the pulse dust collector 7 is provided with an air inlet valve 15, and the exhaust port thereof is provided with an exhaust valve 16.
[0040] like Figure 1 As shown, as a preferred embodiment of the present utility model, two agitators 9 are respectively arranged in the storage bin body 1 and the metering bin body 2 .
[0041] In one case of this embodiment, the agitator 9 includes a stirring rod and a motor driving the agitator 9 to rotate, and the stirring rods of the two agitators 9 are respectively placed in the storage bin body 1 and the metering bin body 2.
[0042] like Figure 1 As shown, as a preferred embodiment of the present utility model, a discharge assembly 5 is provided at the connection between the metering bin body 2 and the feeding end of the second spiral conveying assembly 4 .
[0043] In one case of this embodiment, the unloading assembly 5 is an equal amount batch unloading structure.
[0044] Among them, the equal-amount batch unloading structure is a star-shaped unloader. Of course, other structures that can achieve equal-amount batch unloading can also be selected, which will not be elaborated here. After the powder in the metering bin body 2 is discharged into the second screw conveying component 4, it is input into the mixing kettle through the second screw conveying component 4 for the next step of processing.
[0045] Working principle of the utility model: the above embodiment of the utility model provides a powder storage bin and metering bin shared dust removal structure, which designs the storage bin body 1 and the metering bin body 2 as two-layer platforms that are independently designed and not connected to each other, and the two share a pulse bag dust removal system, and the system is installed above the storage bin body 1, and the adsorbed powder is cleaned regularly by pulses and dust bags. When the metering bin body 2 measures the weight of the powder, the operation mechanism controls the sequence of actions of each link without affecting the metering system, so the metering accuracy can reach an accuracy of one ten-thousandth, and it can also avoid the problem of reduced metering accuracy due to the vibration of the dust removal equipment when the metering bin body 2 is dusted. The added materials are accurately controllable, ensuring product quality while saving costs; the pipelines are connected by setting local soft connections to form an interconnected structure. When the internal air pressure is higher than the external air pressure, the gas can be discharged outward through the filter bag, and the powder adsorbed on the filter bag is repeatedly collected and recycled, so that the vibration generated by the pulse dust collector 7 when working can be avoided. The impact on the weighing result in the metering bin body 2.
[0046] The above is a detailed description of an embodiment of the utility model, but the content is only a preferred embodiment of the utility model and cannot be considered to limit the scope of implementation of the utility model. All equivalent changes and improvements made within the scope of application of the utility model should still fall within the scope of the patent coverage of the utility model.
Claims
1. A powder storage bin and metering bin shared dust removal structure, characterized in that: include: A material storage bin body (1) is connected to a material feed pipe (6), and a first pneumatic valve (11) is provided at the connection between the two. The material storage bin body (1) is connected to the material feed end of the first screw conveying assembly (3); A metering bin body (2) connected to the discharge end of the first screw conveying assembly (3), and a third pneumatic valve (13) is provided at the connection between the two, and the discharge port of the metering bin body (2) is connected to the feed end of the second screw conveying assembly (4); A connecting pipe (8), the feeding end of which is connected to the metering bin body (2), and a fourth pneumatic valve (14) is provided at the connection between the two; the discharging end of the connecting pipe (8) is connected to the storage bin body (1), and a second pneumatic valve (12) is provided at the connection between the two; two flexible connectors (10) are provided at the connection between the metering bin body (2) and the discharging end of the first spiral conveying assembly (3) and the feeding end of the connecting pipe (8), respectively; the two flexible connectors (10) are connected via the connecting pipe (8) to form a loop; and A pulse dust collector (7) is arranged on the loop, and a flexible connection piece (10) is arranged between the pulse dust collector (7) and the metering bin body (2).
2. A powder storage bin and metering bin shared dust removal structure according to claim 1, characterized in that: The air inlet of the pulse dust collector (7) is provided with an air inlet valve (15), and the air outlet is provided with an air outlet valve (16).
3. The powder storage bin and metering bin shared dust removal structure according to claim 1 is characterized in that: Two agitators (9) are respectively arranged in the material storage bin body (1) and the metering bin body (2).
4. The powder storage bin and metering bin shared dust removal structure according to claim 1, characterized in that: A discharge assembly (5) is provided at the connection between the metering bin body (2) and the feeding end of the second screw conveying assembly (4).
5. A powder storage bin and metering bin shared dust removal structure according to claim 4, characterized in that: The unloading assembly (5) is an equal amount batch unloading structure.
Citation Information
Cited By
Bulk material in-out bin equipment and control system thereof
CN119822082A