Lifting appliance for mounting prefabricated hollow slab
By designing the bottom connecting frame and adjusting seat, the problem of slow and laborious installation of existing spreaders when lifting heavy hollow slabs is solved, and the ability to conveniently lift hollow slabs and place hollow slabs of different sizes is realized.
Patent Information
- Application Number
- CN202420460312.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-11
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-03-11
AI Technical Summary
When the existing prefabricated hollow-core panel spreader lifts hollow-core panels weighing more than 40t, the wire rope is difficult to pull out, and the rope connection is troublesome in the absence of a top lifting ring, resulting in slow and laborious installation progress.
A bottom connection frame is designed, which includes a first beam, a second beam and a threaded connecting rod. The hollow plate is clamped by the threaded connecting rod and the locking nut, and the sliding is prevented by the adjusting seat and the limit bolt. The lifting rope and lifting lugs connection to achieve bottom lifting, simplifying the disassembly and assembly process.
This spreader can be lifted without the need for lifting rings on the upper side of the hollow plate. The adjustment seat and limit bolt prevent sliding, which solves the problem of slow and laborious installation and makes it more convenient to use.
Smart Images

Figure CN221853939U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction hangers, in particular to a hanger used for installing prefabricated hollow slabs. Background Art
[0002] The installation and construction of prefabricated hollow slabs need to be hoisted by a crane. The prior art discloses a prefabricated hollow slab hoist with a bulletin number of CN211521358U, which includes a shoulder pole beam, two upper hoisting ears are symmetrically welded on the top surface of the shoulder pole beam, and two lower hoisting ears are symmetrically connected to the bottom surface of the shoulder pole beam by bolts, each lower hoisting ear is connected to a hanging plate by a hanging ring, and a row of hooks are penetrated along the bottom edge of the hanging plate at the lower part of the hanging plate. When the utility model is used for hoisting the prefabricated hollow slab, the upper hoisting ear is connected to the crane hook by a hoisting rope, and the hoisting hook is manually hung in the hole of the prefabricated hollow slab. A maximum of 5 prefabricated hollow slabs can be hoisted at a time, with high hoisting efficiency, low labor intensity and good safety.
[0003] In the actual construction process, when the weight of the hollow slab exceeds 40t, the steel wire rope used is generally about 50mm. After installation, the wire rope head is difficult to pull out. In particular, some prefabricated hollow slabs are not designed with top lifting rings, and it is even more troublesome to connect the lifting rope to them. Based on this, the existing lifting equipment has the problems of slow and laborious installation, which brings inconvenience to use and needs further improvement. Utility Model Content
[0004] The utility model aims to provide a hanger for installing a prefabricated hollow slab to solve the problems raised in the above background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a hoist for installing prefabricated hollow slabs, comprising a lifting rope and a bottom connecting frame, the bottom connecting frame comprising a first crossbeam, a second crossbeam and two threaded connecting rods, both ends of the first crossbeam and the second crossbeam are provided with through holes, the threaded connecting rods can pass through the through holes, the first crossbeam is placed on the lower side of the hollow slab to be lifted, and the second crossbeam is placed on the upper side of the hollow slab to be lifted, the two threaded connecting rods respectively pass through the through holes at both ends of the first crossbeam and the second crossbeam, and locking nuts are threadedly installed on both ends of the threaded connecting rods, so that the first crossbeam and the second beam clamp the hollow slab to be lifted; a lifting ear is rotatably installed on the upper side of the second crossbeam, the lifting rope is connected to the lifting ear, and the lifting rope is used to lift the bottom of the hollow slab to be lifted through the bottom connecting frame. Compared with using a wire rope to bind the hollow slab to be lifted, the bottom connecting frame is more convenient to disassemble and assemble, and solves the problems of slow and laborious installation progress in the existing hoist.
[0006] In some embodiments, two adjustment seats are slidably mounted on the surface of the second crossbeam, and limiting bolts are threadedly mounted on the surfaces of the adjustment seats. The adjustment seats are fixedly connected to the second crossbeam via the limiting bolts.
[0007] Specifically, the adjusting seat includes a sliding sleeve, a load-bearing plate is fixedly installed on the upper surface of the sliding sleeve, a limiting side plate is fixedly installed on the upper surface of the load-bearing plate, a limiting bolt is threadedly installed on the surface of the sliding sleeve, and the surface of the second beam is pressed by the end of the limiting bolt, a triangular plate is welded and fixedly installed on the outer side of the limiting side plate, and the bottom of the triangular plate is welded and fixed to the upper surface of the second beam. The adjusting seat can limit the hollow plate to be lifted to prevent sliding during the lifting process.
[0008] In some embodiments, a first square timber is placed on the upper surface of the load-bearing plate, the bottom of the hollow plate to be hung is placed on the upper surface of the first square timber, a second square timber is placed on the upper side of the hollow plate to be hung, and the first crossbeam presses the upper surface of the second square timber. The first square timber and the second square timber can effectively prevent the first crossbeam and the second crossbeam from colliding and damaging the hollow plate to be hung.
[0009] In some embodiments, the first square wood is fixedly connected to the upper surface of the load-bearing plate by screws, a side wooden board is provided on the inner side of the limiting side plate, and an adjusting bolt is threadedly installed on the surface of the limiting side plate. The end of the adjusting bolt is pressed against the side wooden board, so that the surface of the side wooden board is tightly against the side of the hollow plate to be hung, thereby further strengthening the constraint on the hollow plate to be hung.
[0010] In some embodiments, a plurality of limiting holes are provided on both sides of the second cross beam, and the ends of the limiting bolts can be inserted into the limiting holes to constrain the sliding of the adjustment seat and adjust the distance between the two adjustment seats to facilitate the placement of hollow slabs of different sizes to be suspended.
[0011] In some embodiments, both ends of the threaded connecting rod are sleeved with pads, and the pads are arranged between the locking nut and the first beam or the second beam to strengthen the connection between the threaded connecting rod and the first beam and the second beam.
[0012] Beneficial Effects
[0013] The utility model provides a hanger for installing a prefabricated hollow slab, which has the following beneficial effects:
[0014] 1. The hoist is provided with a bottom connection frame to carry out bottom lifting of the hollow slab to be lifted, and there is no need to provide a lifting ring on the upper side of the hollow slab to be lifted. Moreover, the bottom connection frame connects the first crossbeam and the second crossbeam through two threaded connecting rods. The threaded connecting rods can be removed by removing the locking nuts on the threaded connecting rods, so that the bottom connection frame is separated from the hollow slab to be lifted, thereby solving the problems of slow and laborious installation of the existing hoist.
[0015] 2. The hoist can effectively avoid the first beam and the second beam from being damaged by collision with the hollow slab to be hoisted by arranging the first square wood and the second square wood in the bottom connecting frame, and two adjustment seats are arranged on the second beam, which can limit the hollow slab to be hoisted and prevent sliding during the hoisting process. The distance between the two adjustment seats can be adjusted to facilitate the placement of hollow slabs of different sizes to be hoisted, making it more convenient to use. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 This is a schematic diagram of the front view structure of the utility model;
[0017] Figure 2 It is a schematic diagram of the side section structure of the bottom connection frame;
[0018] Figure 3 for Figure 2 Enlarged structural diagram at A in the middle.
[0019] In the figure: 1 lifting rope, 2 first crossbeam, 3 second crossbeam, 4 threaded connecting rod, 5 hollow plate to be lifted, 6 locking nut, 7 lifting ear, 8 adjusting seat, 9 limiting bolt, 10 sliding sleeve, 11 load-bearing plate, 12 limiting side plate, 13 first square wood, 14 triangle plate, 15 screw, 16 side wood board, 17 adjusting bolt, 18 limiting hole, 19 cushion block, 20 second square wood. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] See also Figure 1-3 The utility model provides a technical solution: a hanger for installing a prefabricated hollow slab, comprising a hanging rope 1 and a bottom connecting frame, the bottom connecting frame comprising a first crossbeam 2, a second crossbeam 3 and two threaded connecting rods 4, the first crossbeam 2 and the second crossbeam 3 are made of steel, the threaded connecting rod 4 is made of fine-rolled threaded steel, and the threaded teeth are processed at both ends of the fine-rolled threaded steel.
[0022] Both ends of the first crossbeam 2 and the second crossbeam 3 are provided with through holes, and both ends of the threaded connecting rod 4 can pass through the through holes. The first crossbeam 2 is placed on the lower side of the hollow slab 5 to be suspended, and the second crossbeam 3 is placed on the upper side of the hollow slab 5 to be suspended. The two threaded connecting rods 4 pass through the through holes at both ends of the first crossbeam 2 and the second crossbeam 3 respectively, and locking nuts 6 are threadedly installed on both ends of the threaded connecting rods 4, so that the first crossbeam 2 and the second crossbeam 3 clamp the hollow slab 5 to be suspended. Both ends of the threaded connecting rod 4 are sleeved with pads 19, and the pads 19 are arranged between the locking nuts 6 and the first crossbeam 2 or the second crossbeam 3.
[0023] A lifting lug 7 is rotatably mounted on the upper side of the second cross beam 3 , a lifting rope 1 is connected to the lifting lug 7 , a lifting hook of the crane is connected to the lifting rope 1 , and the lifting rope 1 lifts the hollow slab 5 to be lifted from the bottom through a bottom connecting frame.
[0024] Among them, two adjustment seats 8 are slidably installed on the surface of the second crossbeam 3, and limiting bolts 9 are threadedly installed on the surface of the adjustment seats 8. A number of limiting holes 18 are opened on both sides of the second crossbeam 3. The ends of the limiting bolts 9 can be inserted into the limiting holes 18 to restrict the sliding of the adjustment seats 8. The adjustment seats 8 are fixedly connected to the second crossbeam 3 through the limiting bolts 9.
[0025] The adjustment seat 8 includes a sliding sleeve 10, a load-bearing plate 11 is fixedly installed on the upper surface of the sliding sleeve 10, a limiting side plate 12 is fixedly installed on the upper surface of the load-bearing plate 11, a triangular plate 14 is welded and fixedly installed on the outer side of the limiting side plate 12, and the bottom of the triangular plate 14 is welded and fixed to the upper surface of the second beam 3.
[0026] The limiting bolt 9 is threadedly installed on the surface of the sliding sleeve 10, and the surface of the second cross beam 3 is pressed by the end of the limiting bolt 9. A first square timber 13 is placed on the upper surface of the load-bearing plate 11, and the bottom of the hollow slab 5 to be suspended is placed on the upper surface of the first square timber 13. A second square timber 20 is placed on the upper side of the hollow slab 5 to be suspended, and the first cross beam 2 presses the upper surface of the second square timber 20.
[0027] The first square wood 13 is fixedly connected to the upper surface of the load-bearing plate 11 by screws 15. A side wooden board 16 is arranged on the inner side of the limiting side plate 12. An adjusting bolt 17 is threadedly installed on the surface of the limiting side plate 12. The end of the adjusting bolt 17 presses against the side wooden board 16 so that the surface of the side wooden board 16 is in close contact with the side of the hollow slab 5 to be suspended.
[0028] By arranging the first square wood 13 and the second square wood 20 in the bottom connecting frame, the first crossbeam 2 and the second crossbeam 3 are prevented from directly contacting the hollow slab 5 to be suspended, and bump damage can be effectively avoided. In addition, two adjustment seats 8 are arranged on the second crossbeam 3, and the adjustment seats 8 can limit the hollow slab 5 to be suspended to prevent the sliding of the hollow slab 5 to be suspended during the lifting process. The distance between the two adjustment seats 8 can be adjusted to facilitate the placement of hollow slabs 5 of different sizes to be suspended, which is more convenient to use.
[0029] The lifting device can lift the hollow slab 5 to be lifted by arranging a bottom connecting frame, and there is no need to provide a lifting ring on the upper side of the hollow slab 5 to be lifted. In addition, the bottom connecting frame connects the first crossbeam 2 and the second crossbeam 3 through two threaded connecting rods 4. The locking nuts 6 on the threaded connecting rods 4 can be removed to remove the threaded connecting rods 4, so that the bottom connecting frame and the hollow slab 5 to be lifted can be separated, thereby solving the problems of slow and laborious installation of the existing lifting device.
[0030] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A sling for installing a prefabricated hollow slab, comprising a sling rope (1) and a bottom connecting frame, characterized in that: The bottom connecting frame comprises a first crossbeam (2), a second crossbeam (3) and two threaded connecting rods (4); both ends of the first crossbeam (2) and the second crossbeam (3) are provided with through holes, and the threaded connecting rods (4) can pass through the through holes; the first crossbeam (2) is placed on the lower side of the hollow slab (5) to be suspended, and the second crossbeam (3) is placed on the upper side of the hollow slab (5) to be suspended; the two threaded connecting rods (4) respectively pass through the through holes at both ends of the first crossbeam (2) and the second crossbeam (3), and locking nuts (6) are threadedly installed at both ends of the threaded connecting rods (4), so that the first crossbeam (2) and the second crossbeam (3) clamp the hollow slab (5) to be suspended; A lifting lug (7) is rotatably mounted on the upper side of the second cross beam (3), a lifting rope (1) is connected to the lifting lug (7), and the lifting rope (1) lifts the hollow slab (5) to be lifted from the bottom via a bottom-lifting connecting frame.
2. A hanger for installing a prefabricated hollow slab according to claim 1, characterized in that: Two adjustment seats (8) are slidably mounted on the surface of the second cross beam (3), and limiting bolts (9) are threadedly mounted on the surfaces of the adjustment seats (8). The adjustment seats (8) are fixedly connected to the second cross beam (3) via the limiting bolts (9).
3. A hanger for installing a prefabricated hollow slab according to claim 2, characterized in that: The adjustment seat (8) comprises a sliding sleeve (10), a bearing plate (11) is fixedly mounted on the upper surface of the sliding sleeve (10), a limiting side plate (12) is fixedly mounted on the upper surface of the bearing plate (11), a limiting bolt (9) is threadedly mounted on the surface of the sliding sleeve (10), and the surface of the second cross beam (3) is pressed by the end of the limiting bolt (9).
4. A hanger for installing a prefabricated hollow slab according to claim 3, characterized in that: A first square timber (13) is placed on the upper surface of the load-bearing plate (11), the bottom of the hollow slab (5) to be suspended is placed on the upper surface of the first square timber (13), a second square timber (20) is placed on the upper side of the hollow slab (5) to be suspended, and the first crossbeam (2) presses the upper surface of the second square timber (20).
5. A hanger for installing a prefabricated hollow slab according to claim 4, characterized in that: A triangular plate (14) is welded and fixedly installed on the outer side of the limiting side plate (12), and the bottom of the triangular plate (14) is welded and fixedly installed to the upper surface of the second cross beam (3).
6. A hanger for installing a prefabricated hollow slab according to claim 5, characterized in that: The first square wood (13) is fixedly connected to the upper surface of the load-bearing plate (11) by means of screws (15); a side wooden board (16) is arranged on the inner side of the limiting side plate (12); an adjusting bolt (17) is threadedly installed on the surface of the limiting side plate (12); the end of the adjusting bolt (17) is pressed against the side wooden board (16) so that the surface of the side wooden board (16) is pressed against the side surface of the hollow slab (5) to be suspended.
7. A hanger for installing a prefabricated hollow slab according to claim 6, characterized in that: A plurality of limiting holes (18) are provided on both sides of the second cross beam (3), and the ends of the limiting bolts (9) can be inserted into the limiting holes (18) to restrict the sliding of the adjustment seat (8).
8. A hanger for installing a prefabricated hollow slab according to any one of claims 1 to 7, characterized in that: Both ends of the threaded connecting rod (4) are sleeved with cushion blocks (19), and the cushion blocks (19) are arranged between the locking nut (6) and the first crossbeam (2) or the second crossbeam (3).