Waterproof structure of highway engineering roadbed
By designing water-isolating structures in highway projects, including water inlets, drainage pipes, slope protection pipes and water barriers, the problem of insufficient drainage of the roadbed under heavy rainfall has been solved, effectively preventing water damage and extending the service life of the roadbed. Effect.
Patent Information
- Application Number
- CN202420292554.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-18
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2034-02-18
AI Technical Summary
The roadbed in existing highway projects is difficult to effectively drain under heavy rainfall, leading to the risk of water damage and slope protection collapse. The existing road drainage facilities are insufficient in long-term use.
A water-proof structure for highway engineering subgrade is designed, including a rammed earth layer, a sand and gravel layer, a base layer, a geotechnical waterproof material layer and a pavement layer. The pavement layer is provided with water inlets connected to drainage pipes, and the drainage pipes are connected to slope protection pipes. Connected, the water in the slope protection pipe flows into the drainage ditch and prevents external water erosion through the water barrier. The surface of the base layer is laid with waterproof membrane to prevent the penetration of accumulated water.
It effectively reduces the hazard of water damage to the roadbed, prevents accumulated water from penetrating into the roadbed, extends the service life of the road, and ensures that the roadbed is always dry and solid.
Smart Images

Figure CN221855174U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of highway engineering, in particular to a water-isolating structure for a highway engineering roadbed. Background Art
[0002] With the progress of society and the rapid development of economy, the construction of my country's transportation industry has achieved remarkable results. However, due to various reasons, the highways that have been put into operation have all suffered from diseases to varying degrees. Among them, the diseases caused by water damage to the roadbed are particularly serious. The roadbed, as the foundation of the road surface, on the one hand bears the diffusion stress of the traffic load and the gravity of the pavement structure layer, and on the other hand is affected by various natural factors, among which water is one of the most important factors. Therefore, it is extremely important to do a good job of roadbed drainage to ensure that the roadbed is always in a dry, solid and stable state.
[0003] At present, road surface drainage mainly uses pavement drainage facilities, including side ditches and drainage channels, etc., whose main function is to guide the flow of rainwater during heavy rain, so that most of the rainwater is discharged from the roadbed in the form of runoff. However, for heavy rainfall, some rainwater cannot be discharged from the roadbed and will infiltrate into the roadbed. During long-term use, structures such as roadbed slope protection are in danger of collapse, so they need to be improved. Utility Model Content
[0004] The purpose of the utility model is to provide a water-proof structure for a roadbed of a highway engineering project, so as to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a waterproof structure for a highway engineering roadbed, including a roadbed, the roadbed including a rammed earth layer, a gravel layer, a base layer, a geotechnical waterproof material layer, and a pavement layer, the rammed earth layer is fixedly connected to the sand and gravel layer at the upper end, the sand and gravel layer is provided with a base layer at the upper end, the base layer is provided with a geotechnical waterproof material layer at the upper end, the geotechnical waterproof material layer is fixedly connected to the pavement layer at the upper end, the pavement layer is provided with a plurality of water inlet holes at the upper end, the water inlet holes are connected with drainage pipes, and the drainage pipes are fixedly connected to the pavement layer.
[0006] Preferably, both ends of the roadbed are fixedly connected with roadbed slope protection, the inner wall of the roadbed slope protection is fixedly connected with a slope protection pipe, and one end of the drainage pipe away from the pavement layer is fixedly connected to the slope protection pipe.
[0007] Preferably, one end of the roadbed slope protection is fixedly connected to a drainage ditch, the end of the roadbed slope protection close to the drainage ditch is provided with a plurality of water outlets, and the end of the drainage ditch away from the roadbed slope protection is fixedly connected to a water-blocking board.
[0008] Preferably, a waterproof coiled material is fixedly connected to the surface of the base layer.
[0009] Preferably, the two ends of the pavement layer centered on the central axis are arranged to be inclined downward.
[0010] Compared with the prior art, the utility model has the following beneficial effects: the multiple water inlet holes arranged on the pavement layer can allow the accumulated water on the pavement to enter the interior of the slope protection pipe after passing through the drainage pipe, and the accumulated water in the slope protection pipe flows into the drainage ditch through the multiple water outlets at one end of the roadbed slope protection. Since the pavement layer has a certain inclination angle toward both ends of the roadbed slope protection, the accumulated water on the pavement layer can flow downstream to both ends, and the roadbed slope protection is inclined, so that the accumulated water on the roadbed will flow into the drainage ditch. The water-blocking plate can prevent water outside the roadbed from entering the roadbed and causing erosion to the roadbed. It effectively reduces the harm of water damage. When the amount of water on the pavement layer is large, the drainage system is not enough to drain the water quickly. The waterproof membrane laid on the surface of the base layer can prevent the accumulated water from seeping from the pavement layer from penetrating the base layer. The accumulated water in the pavement layer is guided and discharged through multiple sets of water inlet holes and drainage pipes. It can effectively avoid the situation when the amount of water on the pavement layer is large, causing part of the accumulated water to penetrate into the interior of the roadbed through infiltration, causing erosion of the roadbed and leading to the collapse of the roadbed. The geotextile waterproof material layer can effectively reduce the erosion of groundwater on the roadbed and extend the service life of the highway. BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Figure 1 It is a schematic diagram of the structure of the utility model;
[0012] Figure 2 It is a cross-sectional structural schematic diagram of the utility model;
[0013] Figure 3 It is a structural schematic diagram of the pavement layer of the utility model;
[0014] Figure 4 It is a structural schematic diagram of the rammed earth layer of the utility model.
[0015] In the figure: 1. Roadbed; 2. Rammed earth layer; 3. Sand and gravel layer; 4. Base layer; 5. Geotextile waterproof material layer; 6. Pavement layer; 7. Water inlet hole; 8. Drainage pipe; 9. Roadbed slope protection; 10. Slope protection pipe; 11. Drainage ditch; 12. Water outlet; 13. Waterproof board; 14. Waterproof membrane. DETAILED DESCRIPTION
[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] See also Figure 1-4The utility model provides a technical solution: a waterproof structure of a highway engineering roadbed, including a roadbed 1, the roadbed 1 includes a rammed earth layer 2, a gravel layer 3, a base layer 4, a geotechnical waterproof material layer 5, and a pavement layer 6. The upper end of the rammed earth layer 2 is fixedly connected to the gravel layer 3, the upper end of the gravel layer 3 is provided with a base layer 4, the upper end of the base layer 4 is provided with a geotechnical waterproof material layer 5, the upper end of the geotechnical waterproof material layer 5 is fixedly connected to the pavement layer 6, the upper end of the pavement layer 6 is provided with a plurality of water inlet holes 7, the water inlet holes 7 are connected through with drainage pipes 8, and the drainage pipes 8 are fixedly connected to the pavement layer 6.
[0018] Furthermore, roadbed slope protection 9 is fixedly connected to both ends of the roadbed 1, and a slope protection pipe 10 is fixedly connected to the inner wall of the roadbed slope protection 9. The end of the drainage pipe 8 away from the pavement layer 6 is fixedly connected to the slope protection pipe 10. The multiple groups of water inlet holes 7 on the roadbed 1 can allow the accumulated water on the road surface to enter the slope protection pipe 10 through the drainage pipe 8, and the roadbed slope protection 9 is arranged at an angle, so that the accumulated water on the roadbed 1 will flow into the drainage ditch 11.
[0019] Furthermore, one end of the roadbed slope protection 9 is fixedly connected to a drainage ditch 11, and a plurality of water outlets 12 are provided at the end of the roadbed slope protection 9 close to the drainage ditch 11. The end of the drainage ditch 11 away from the roadbed slope protection 9 is fixedly connected to a baffle 13. The accumulated water in the slope protection pipe 10 flows into the drainage ditch 11 through the multiple groups of water outlets 12 at one end of the roadbed slope protection 9. The baffle 13 can prevent water outside the range of the roadbed 1 from entering the roadbed 1 and causing erosion to the roadbed 1, thereby effectively reducing the harm of water damage.
[0020] Furthermore, a waterproof coiled material 14 is fixedly connected to the surface of the base layer 4 . The waterproof coiled material 14 is laid on the surface of the base layer 4 to prevent the accumulated water seeping from the pavement layer 6 from penetrating the base layer 4 .
[0021] Furthermore, the two ends of the pavement layer 6 are inclined downward with the central axis as the center. Since the pavement layer 6 has a certain inclination angle toward the two ends of the roadbed slope protection 9, it is convenient for the accumulated water on the road surface to flow down to the two ends.
[0022] Specifically, when the utility model is used, the roadbed 1 is paved with a rammed earth layer 2, a gravel layer 3, a base layer 4, a geotechnical waterproof material layer 5, and a pavement layer 6 in sequence from bottom to top. The pavement layer 6 is provided with multiple groups of water inlet holes 7 that can allow the accumulated water on the road surface to enter the interior of the slope protection pipe 10 through the drainage pipe 8. The accumulated water in the slope protection pipe 10 flows into the drainage ditch 11 through multiple groups of water outlets 12 at one end of the roadbed slope protection 9. Since the pavement layer 6 has a certain inclination angle toward both ends of the roadbed slope protection 9, the accumulated water on the pavement layer 6 can flow downstream to both ends, and the roadbed slope protection 9 is inclined, so that the accumulated water on the roadbed 1 will flow into the drainage ditch 11. The waterproof plate 13 can prevent water outside the range of the roadbed 1 from entering the roadbed 1 and causing erosion to the roadbed 1, thereby effectively reducing the harm of water damage. When the amount of water accumulated on the pavement layer 6 is large, the drainage system is not sufficient to drain the water quickly. The waterproof membrane 14 laid on the surface of the base layer 4 can prevent the accumulated water that seeps down from the pavement layer 6 from penetrating the base layer 4.
[0023] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A water-proof structure for a roadbed of a highway engineering project, comprising a roadbed (1), characterized in that: The roadbed (1) comprises a rammed earth layer (2), a gravel layer (3), a base layer (4), a geotechnical waterproof material layer (5), and a pavement layer (6); the upper end of the rammed earth layer (2) is fixedly connected to the gravel layer (3); the upper end of the gravel layer (3) is provided with a base layer (4); the upper end of the base layer (4) is provided with a geotechnical waterproof material layer (5); the upper end of the geotechnical waterproof material layer (5) is fixedly connected to the pavement layer (6); the upper end of the pavement layer (6) is provided with a plurality of water inlet holes (7); the water inlet holes (7) are connected through drainage pipes (8); and the drainage pipes (8) are fixedly connected to the pavement layer (6).
2. The water-proof structure for a highway engineering roadbed according to claim 1, characterized in that: The two ends of the roadbed (1) are fixedly connected to roadbed slope protection (9), the inner wall of the roadbed slope protection (9) is fixedly connected to a slope protection pipe (10), and one end of the drainage pipe (8) away from the pavement layer (6) is fixedly connected to the slope protection pipe (10).
3. The water-proof structure for a highway engineering roadbed according to claim 2, characterized in that: One end of the roadbed slope protection (9) is fixedly connected to a drainage ditch (11); one end of the roadbed slope protection (9) close to the drainage ditch (11) is provided with a plurality of water outlets (12); and one end of the drainage ditch (11) away from the roadbed slope protection (9) is fixedly connected to a water blocking board (13).
4. The water-proof structure for a highway engineering roadbed according to claim 1, characterized in that: A waterproof coiled material (14) is fixedly connected to the surface of the base layer (4).
5. The water-proof structure for roadbed of a highway engineering project according to claim 1, characterized in that: The two ends of the pavement layer (6) are arranged to be inclined downward with the central axis as the center.