Hydropower station high-pressure shaft steel pipe overhaul channel and overhaul equipment
By setting up water diversion and pressure regulating shafts and maintenance guide holes above the high-pressure shafts of hydropower stations to form direct passages and equip them with maintenance equipment, the problem of lack of maintenance passages in high-pressure shafts is solved, efficient and safe maintenance operations are realized, and work efficiency is improved.
Patent Information
- Application Number
- CN202420175968.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Priority Date
- 2023-12-28
- Filing Date
- 2024-01-24
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-01-24
AI Technical Summary
The high-pressure shafts of hydropower stations lack access to inspections, making inspections difficult and unsafe. The layout of supporting equipment is uncoordinated, making it difficult to conduct effective inspections or maintenance.
A maintenance channel is designed that leads directly to the high-pressure shaft. A water diversion and pressure regulating shaft and a maintenance guide hole are set above the high-pressure shaft to form a maintenance channel. The maintenance channel is equipped with maintenance equipment, including cable brackets, hoisting equipment and a foldable cage platform. Allow maintenance personnel to safely and conveniently enter the high-pressure shaft for maintenance.
It improves the efficiency and safety of high-pressure shaft maintenance without affecting the normal operation and water level of the power station, provides a convenient maintenance plan, and ensures that maintenance personnel can directly access the interior of the high-pressure shaft for maintenance.
Smart Images

Figure CN221878173U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of maintenance engineering of hydropower stations, in particular to a maintenance channel and maintenance equipment for steel pipes in a high-pressure shaft of a hydropower station. Background Art
[0002] In the water supply system structure of a hydropower station, for a high-head power station, the water diversion system often adopts a vertical high-pressure shaft layout. At present, under normal circumstances, there is no maintenance passage for the high-pressure shaft of a hydropower station; or a maintenance manhole is directly set up upstream of the upper bend of the high-pressure shaft, equipped with a temporary winch, and the maintenance personnel tie a temporary lifting rope and enter the high-pressure shaft from the maintenance manhole. However, due to the difficulty of inspection, the lack of safety guarantee, and the uncoordinated layout of supporting equipment, it is difficult to inspect or repair after construction. If the high-pressure shaft is not equipped with a maintenance passage, it is impossible to reach the working surface for maintenance when it needs to be inspected or maintained. Therefore, the feasibility and convenience of the maintenance plan are particularly important. Utility Model Content
[0003] The first purpose of the utility model is to provide a maintenance passage directly connected to the high-pressure shaft for maintenance. To this end, the utility model adopts the following technical solutions:
[0004] The steel pipe inspection channel of the high-pressure shaft of the hydropower station, the water diversion and pressure regulating shaft is arranged above the high-pressure shaft, the end of the upper bend section at the upper part of the high-pressure shaft is connected to the upper flat hole, and a vertical hole is opened in the upper bend section to form an inspection channel directly connected to the high-pressure shaft in the well chamber of the water diversion and pressure regulating shaft, and a maintenance guide hole connected to the interior of the water diversion and pressure regulating shaft is opened at the top of the water diversion and pressure regulating shaft, and a removable cover plate is installed on the inspection guide hole.
[0005] Furthermore: the inspection channel is coaxially connected with the high-pressure shaft in the vertical direction.
[0006] Furthermore: the inspection guide hole is opened directly above the high-pressure shaft in the vertical direction.
[0007] Furthermore, a detachable flange cover is arranged at the top of the inspection passage, and the flange cover is located in the well chamber of the water diversion and pressure regulating well, and a vent hole is opened in the flange cover.
[0008] Furthermore, the height of the end of the inspection channel extending into the water diversion and pressure regulating well chamber is higher than the height of the bottom plate of the water diversion and pressure regulating well chamber.
[0009] Furthermore: a reinforcement plate is provided on the peripheral inner wall of the upper curved section which is connected with the inspection channel.
[0010] The second purpose of the utility model is to provide a maintenance equipment that is convenient for maintenance personnel to lift and lower to the wall of the high-pressure shaft through the maintenance passage for maintenance. To this end, the utility model adopts the following technical solutions:
[0011] The maintenance equipment for steel pipes in a high-pressure shaft of a hydropower station comprises a cable guide bracket arranged above the maintenance guide hole of a water diversion and pressure regulating shaft, a cable guide is installed on the cable guide bracket, and the end of the cable guide passes through the maintenance channel and is connected to the inner wall of the lower bend section downstream of the high-pressure shaft; a hoisting device is arranged outside the water diversion and pressure regulating shaft, and a hoisting cage cooperating with the cable guide is connected to the hook of the hoisting device, and the cable guide forms a lifting and lowering guide rail of the hoisting cage.
[0012] Furthermore: a folding plate is arranged at the bottom of the cage, and when the folding plate is unfolded, a maintenance work platform close to the wall of the high-pressure shaft is formed.
[0013] Compared with the prior art, the utility model has the following beneficial effects:
[0014] The utility model pre-builds an inspection passage between the water diversion pressure regulating shaft and the high-pressure shaft at the same position, so that when the high-pressure shaft is inspected and repaired in the later stage, the inspection personnel can be hoisted from top to bottom directly to the inside of the high-pressure shaft, and the inspection passage of the high-pressure shaft can not affect the normal operation of the power station, and will not affect the water level of the power station during load shedding and load increase; and when the high-pressure shaft is inspected and maintained, the work efficiency can be improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a longitudinal section layout diagram of the utility model;
[0016] Figure 2 For this utility model Figure 1 AA section view in;
[0017] Figure 3 It is a schematic diagram of the maintenance passage of the utility model;
[0018] Figure 4 A schematic diagram of removing the manhole cover during maintenance of the utility model;
[0019] Figure 5 It is a schematic diagram of the crane lifting the cage into the water diversion and pressure regulating well during the maintenance of the utility model;
[0020] Figure 6 It is a schematic diagram of dismantling the flange cover at the bottom of the water diversion and pressure regulating shaft during maintenance of the utility model;
[0021] Figure 7 It is a schematic diagram of installing the cable guide bracket during maintenance of the utility model;
[0022] Figure 8It is a schematic diagram of fixing the guide cable during maintenance of the utility model;
[0023] Fig. 9 It is a schematic diagram of the crane hoisting the cage into the well and stopping during the maintenance of the utility model;
[0024] Fig.10 It is a schematic diagram of unfolding the folding platform of the cage and performing maintenance during maintenance of the utility model;
[0025] Fig.11 It is an unfolded plan view of the folding platform of the cage of the utility model;
[0026] Fig.12 It is a plan view of the folding platform of the cage of the utility model after being folded.
[0027] The markings in the attached drawings are: 1-water diversion and pressure regulating shaft, 101-bottom plate, 102-inspection guide hole, 2-upper flat tunnel, 3-upper curved section, 4-high-pressure vertical shaft, 5-lower curved section, 6-high-pressure lower flat tunnel, 7-underground powerhouse, 8-impedance hole, 9-inspection passage, 91-flange cover, 911-vent hole, 92-cover plate; 93-reinforcement plate;
[0028] 20-maintenance equipment, 21-hoisting equipment, 22-hoisting cage, 221-folding plate, 23-cable guide bracket, 24-cable guide. DETAILED DESCRIPTION
[0029] The present invention is further described below in conjunction with the accompanying drawings and embodiments, but they are not intended to limit the present invention.
[0030] like Figure 1 As shown, the water delivery system in the hydropower station includes a high-pressure shaft 4 arranged between the upper horizontal tunnel 2 and the high-pressure lower horizontal tunnel 6. By considering that the hydraulic conditions are smooth when the water flow in the water delivery system changes from horizontal to vertical, an upper curved section 3 is arranged at the end of the horizontal section of the upper horizontal tunnel 2 and the beginning of the vertical section of the high-pressure shaft 4 to minimize the head loss. The high-pressure shaft 4 is also provided with a lower curved section 5 between its lower part and the high-pressure lower horizontal tunnel 6, and the end of the high-pressure lower horizontal tunnel 6 is connected to the underground powerhouse 7. At the same time, the water diversion and pressure regulating shaft 1 is located above the high-pressure shaft 4, and the bottom of the well chamber of the water diversion and pressure regulating shaft 1 is provided with an impedance hole 8 connected to the upper horizontal tunnel 2.
[0031] like Figure 1-12As shown, the steel pipe inspection channel of the high-pressure shaft of the hydropower station, the water diversion and pressure regulating shaft 1 is arranged above the high-pressure shaft 4, and a vertical hole of suitable diameter is opened between the water diversion and pressure regulating shaft 1 and the upper bend section 3 at the top of the high-pressure shaft 4, and a steel pipe is arranged on the inner wall of the vertical hole, and both ends of the steel pipe are bidirectionally connected with the well chamber of the water diversion and pressure regulating shaft 1 and the high-pressure shaft 4 to form an inspection channel 9 directly connected to the high-pressure shaft 4 in the well chamber of the water diversion and pressure regulating shaft 1, and the diameter of the steel pipe of the inspection channel 9 needs to meet the requirements for the passage of the maintenance cage 22 in the later stage, and the diameter of the steel pipe of the inspection channel 9 is also smaller than the inner diameter of the high-pressure shaft 4; the top of the water diversion and pressure regulating shaft 1 is opened with an inspection guide hole 102 connected with the interior thereof, and a removable cover plate 92 is installed on the inspection guide hole 102.
[0032] Specifically, the inspection channel 9 is arranged at a position of the upper curved section 3 facing the center point of the high-voltage shaft 4 , so that the inspection channel 9 is coaxially connected with the high-voltage shaft 4 in the vertical direction.
[0033] The inspection guide hole 102 is opened directly above the high-pressure shaft 4 in the vertical direction, and the center line of the inspection channel 9 also coincides with the center of the top cover plate 92 of the water diversion and pressure regulating shaft 1.
[0034] Specifically, a removable flange cover 91 is provided at the top of the inspection channel 9, and the flange cover 91 is located in the well chamber of the water diversion and pressure regulating well 1, and a vent hole 911 is provided in the flange cover 91. In this embodiment, the diameter of the vent hole 911 is about 5 cm to ensure the exhaust of the inspection channel 9 during the initial water storage, otherwise it will be difficult to exhaust the gas and it will be brought into the unit during operation.
[0035] Among them, the height of the insertion end of the steel pipe of the inspection channel 9 extending into the water diversion and pressure regulating well 1 is higher than the height of the bottom plate 101 in the water diversion and pressure regulating well 1, and the elevation of the flange cover 91 is preferably 20 cm higher than the elevation of the bottom plate 101, so that maintenance personnel can disassemble and assemble the flange cover 91.
[0036] Specifically, a reinforcing plate 93 is provided on the peripheral inner wall of the upper curved section 3 which is connected to the maintenance passage 9, so as to strengthen the connection strength between the maintenance passage 9 and the upper curved section 3 and ensure safety.
[0037] This embodiment also provides a high-pressure shaft steel pipe maintenance equipment for a hydropower station. The maintenance equipment can hoist maintenance personnel through the maintenance passage 9 to reach the working surface in the high-pressure shaft 4, thereby improving maintenance efficiency.
[0038] Specifically, the maintenance equipment 20 includes a cable guide bracket 23 arranged above the maintenance guide hole 102 of the water diversion and pressure regulating shaft 1, a cable guide 24 is installed on the cable guide bracket 23, and the end of the cable guide 24 passes through the maintenance channel 9 and is connected to the inner wall of the lower curved section 5 at the lower part of the high-pressure shaft 4; a hoisting device 21 is arranged outside the water diversion and pressure regulating shaft 1, and a hoisting cage 22 cooperating with the cable guide 24 is connected to the hook of the hoisting device 21, and the cable guide 24 forms a lifting and lowering guide rail of the hoisting cage 22. In this embodiment, the hoisting device 21 can be a crane.
[0039] Among them, a folding plate 221 is set on the bottom side wall of the cage 22. The cage 22 adopts a retractable umbrella shape, so that the folding plate 221 forms a maintenance work platform close to the wall of the high-pressure shaft 4 after being unfolded. At the same time, the folding plate 221 is attached to the side wall of the cage 22 before it is unfolded, so that the cage 22 can move unhindered during the movement process.
[0040] See also Figure 1-12 When the maintenance equipment 20 is used to pass through the maintenance channel 4 to perform maintenance on the high-pressure shaft 7, the specific maintenance steps are as follows:
[0041] S1: First, open the maintenance cover 92 at the top of the water diversion and pressure regulating shaft 1, and use the lifting equipment 21 to lift the maintenance cage 22 to the bottom of the water diversion and pressure regulating shaft 1, with two maintenance personnel on board in the cage 22;
[0042] S2: The maintenance personnel remove the bolts on the flange cover 91 using a torque wrench and remove the flange cover 91 using a temporary lifting device;
[0043] S3: Install the cable guide bracket 23 on the top of the water diversion and pressure regulating shaft 1, and fix the upper and lower ends of the cable guide 24 on the cable guide bracket 23 and the inner wall of the lower curved section 5 respectively, so that the cable guide 24 can be used as a guide rail for the hoist cage 22 and as a locking safety cable when the hoist cable is disconnected;
[0044] S4: Use the hoisting equipment 21 to lift the cage 22 with guide cables 24 on both sides to the bottom, pass through the vertical section of the maintenance passage 9, and reach the maintenance work area in the high-voltage shaft 4;
[0045] S5: unfold the folding plate 221 on the cage 22, and the folding plate 221 serves as a maintenance platform extending from the cage 22, and extends all the way to the side wall of the high-voltage shaft 4. The maintenance personnel can approach the side wall of the high-voltage shaft 4 under the protection of the safety rope to perform maintenance work on the high-voltage shaft 4;
[0046] S6: After the maintenance work is completed, the folding plate 221 is folded up, the cage 22 is lifted to the bottom plate 101 of the water diversion and pressure regulating shaft 1, the flange cover 91 is covered and the bolts are locked, and then the cage 22 is lifted out of the water diversion and pressure regulating shaft 1 to complete the maintenance.
[0047] The above embodiment is only a preferred technical solution of the present invention. Those skilled in the art should understand that the technical solutions or parameters in the embodiments can be modified or replaced without departing from the principle and essence of the present invention, and all should be included in the protection scope of the present invention.
Claims
1. The high-pressure shaft steel pipe maintenance channel of the hydropower station is characterized by: A water diversion and pressure regulating well (1) is arranged above a high-pressure vertical well (4); the end of an upper curved section (3) at the upper part of the high-pressure vertical well (4) is connected to an upper flat hole (2); a vertical hole is provided in the upper curved section (3) to form an inspection passage (9) in the well chamber of the water diversion and pressure regulating well (1) directly connected to the high-pressure vertical well (4); a top end of the water diversion and pressure regulating well (1) is provided with an inspection guide hole (102) connected to the interior thereof; a removable cover plate (92) is installed on the inspection guide hole (102).
2. The high-pressure shaft steel pipe maintenance channel of a hydropower station according to claim 1 is characterized by: The inspection channel (9) is coaxially connected to the high-pressure shaft (4) in the vertical direction.
3. The high-pressure shaft steel pipe maintenance channel of a hydropower station according to claim 1 or 2, characterized in that: The inspection guide hole (102) is opened directly above the high-pressure shaft (4) in the vertical direction.
4. The high-pressure shaft steel pipe maintenance channel of a hydropower station according to claim 1 is characterized by: The inspection channel (9) is provided with a detachable flange cover (91) at its top, and the flange cover (91) is located in the well chamber of the water diversion and pressure regulating well (1), and a vent hole (911) is opened in the flange cover (91).
5. The high-pressure shaft steel pipe maintenance channel of a hydropower station according to claim 4 is characterized by: The height of the end of the inspection channel (9) extending into the well chamber of the water diversion and pressure regulating well (1) is higher than the height of the bottom plate (101) inside the well chamber of the water diversion and pressure regulating well (1).
6. The high-pressure shaft steel pipe maintenance channel of a hydropower station according to claim 1 is characterized by: The upper curved section (3) is provided with a reinforcing plate (93) on the peripheral inner wall thereof which is connected with the inspection channel (9).
7. Hydropower station high-pressure shaft steel pipe maintenance equipment, characterized by: Arranged on the steel pipe inspection channel of the high-pressure shaft of the hydropower station as described in any one of claims 1-6, the inspection equipment (20) includes a cable guide bracket (23) arranged above the inspection guide hole (102) of the water diversion and pressure regulating shaft (1), a cable guide (24) is installed on the cable guide bracket (23), and the end of the cable guide (24) passes through the inspection channel (9) and is connected to the inner wall of the lower bend section (5) at the lower part of the high-pressure shaft (4); a hoisting device (21) is arranged outside the water diversion and pressure regulating shaft (1), and a hoisting cage (22) cooperating with the cable guide (24) is connected to the hook of the hoisting device (21), and the cable guide (24) forms a lifting and lowering guide rail of the cage (22).
8. The hydropower station high-pressure shaft steel pipe maintenance equipment according to claim 7 is characterized by: A folding plate (221) is provided at the bottom of the cage (22), and when the folding plate (221) is unfolded, a maintenance operation platform close to the wall of the high-pressure shaft (4) is formed.