Combined prefabricated concrete composite floor slab

By using a combined structure of skeletons and connecting components in the laminated floor slabs, the problem of unfixed gaps in the laminated floor slabs is solved, the effect of reducing gaps and improving concrete strength is achieved, concrete leakage is avoided, and the construction process is simplified.

CN221878498UActive Publication Date: 2024-10-22SHANDONG HONGYUAN PREFABRICATED CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420202984.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-29
Publication Date
2024-10-22
Estimated Expiration
2034-01-29

AI Technical Summary

Technical Problem

During the construction process of the laminated floor slabs, due to inaccurate crane adjustment, the gaps between the laminated floor slabs were not fixed, which could easily lead to concrete leakage.

Method used

A combined prefabricated concrete composite floor slab is designed, which adopts a combined structure of a skeleton and connecting components. Concrete is poured through the surface of the skeleton and connecting components are provided. The connecting components can pull the skeleton to align the two composite panels closely and reduce the gap. , and improve lifting and reinforcement through mounting brackets and reinforcing components.

Benefits of technology

It effectively avoids the problem of concrete leakage caused by excessive gaps in the laminated plates, improves the overall strength and stability of the construction, and simplifies the lifting and reinforcement processes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221878498U_ABST
    Figure CN221878498U_ABST
Patent Text Reader

Abstract

The utility model provides a combined prefabricated concrete composite floor slab, which relates to the technical field of composite floor slabs and comprises a framework, concrete is poured on the surface of the framework to form a concrete layer which covers the surface of the framework, the framework extends out of the concrete layer in the horizontal direction, and a connecting component is arranged between two composite floor slabs. The connecting assembly pulls the framework extending out of the concrete layer to enable the two composite floor slabs to be close to and aligned with each other, mounting frames are evenly and fixedly connected to the upper end of the framework, the mounting frames upwards extend out of the concrete layer, the connecting assembly comprises a connecting box, and the framework extends into the connecting box. The structure in the connecting assembly is used for dragging the frameworks of the two laminated slabs, so that the two laminated slabs are close to each other and are aligned, the gap between the two laminated slabs is reduced, and concrete leakage caused by later pouring due to the fact that the gap between the two laminated slabs is too large is avoided as much as possible.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of composite floor slabs, in particular to a combined prefabricated concrete composite floor slab. Background Art

[0002] Composite floor is an assembled integral floor made of prefabricated panels and cast-in-place reinforced concrete layers. Composite floor has good integrity and the upper and lower surfaces of the board are flat, which is convenient for later construction.

[0003] In the daily construction process, it is necessary to build the building frame first, and then lay the template on the top of the building frame, and then use the crane to lift the composite floor slabs to the top of the wooden board, and evenly lay multiple composite floor slabs on the surface of the wooden board to form the main structure of the top of the building, and then tie steel bars to the surface of the evenly laid composite floor slabs to form a steel structure skeleton, and finally pour concrete. The inventor found in his daily work that due to the crane's transportation of the composite floor slabs, the gaps between the composite floor slabs are not fixed (because the crane's hoisting rope is soft and it is difficult to accurately lower the composite floor slabs during the transportation process). This will result in large gaps between the composite floor slabs, and the later pouring of concrete will easily cause concrete to leak from the larger gaps. Utility Model Content

[0004] The utility model aims to solve the shortcomings in the prior art and proposes a combined prefabricated concrete composite floor slab.

[0005] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a combined precast concrete composite floor slab, including a frame, wherein concrete is poured on the surface of the frame to form a concrete layer covering the surface of the frame, and the frame extends horizontally out of the concrete layer. A connecting component is arranged between two composite floor slabs, and the connecting component pulls the frame extending out of the concrete layer to cause the two composite floor slabs to be close to each other and aligned.

[0006] The effects achieved by the above components are as follows: the skeleton is a frame structure formed by bundling together multiple steel bars arranged in longitude and latitude, and concrete is poured through the surface of the skeleton. After the concrete solidifies, a concrete layer covering the surface of the skeleton is formed. The skeleton and the concrete layer covering the surface of the skeleton constitute a precast concrete composite floor slab. The skeleton is in the middle of the concrete layer and can well support the concrete layer to ensure the overall strength and stability. During construction, the overall frame of the building is first built, and then the slab is laid on the top of the frame. The precast concrete composite floor slab is lifted by a crane and laid on the surface of the slab. A connecting component can be used to seal the gap between two adjacent precast concrete composite floor slabs. If there is a large gap between two adjacent precast concrete composite floor slabs, the structure inside the connecting component is used to pull the skeletons of the two composite plates, so that the two composite plates are aligned close to each other to reduce the gap between the two composite plates, and to avoid as much as possible the gap between the two composite plates being too large and causing concrete leakage during the later pouring.

[0007] Preferably, a mounting frame is evenly and fixedly connected to the upper end of the frame, and the mounting frame extends upward out of the concrete layer.

[0008] The effect achieved by the above components is that since the mounting frame is directly connected to the frame and the mounting frame extends upward out of the concrete layer, the mounting frame can be directly hooked on the surface of the mounting frame for lifting during lifting.

[0009] Preferably, the connection assembly comprises a connection box, and the skeleton extends into the connection box.

[0010] The effect achieved by the above components is: when there is a gap between the two superimposed plates, the connection box is sleeved on the frame between the two superimposed plates, and the larger gap between the two superimposed plates is shielded and protected by the connection box.

[0011] Preferably, a pull rod is slidably connected inside the connection box, a connecting rod is fixedly connected to a portion of the pull rod surface relative to the skeleton extending into the connection box, and a clamping seat is fixedly connected to a free end of the connecting rod.

[0012] The effect achieved by the above components is: if the gap between the two overlapping plates is relatively large, the skeleton can be extended into the connection box and between the card seat for welding, and then the connecting rod is pulled, and the card seat is pulled by the connecting rod, so that the card seat pulls the skeleton inside the connection box along the sliding direction of the connecting rod, so that the two overlapping plate skeletons are continuously pulled into the connection box, thereby forcing the two overlapping plates to approach each other to reduce the gap between the two overlapping plates.

[0013] Preferably, the pull rod extending out of the connection box has a threaded sleeve with a nut on its surface.

[0014] The effect achieved by the above components is: by loosening the nut at one end of the pull rod and then tightening the nut at the other side, the nut and the connecting rod thread cooperate to thread-drive the connecting rod to slide outside the connection box.

[0015] Preferably, a reinforcing assembly for supporting the concrete layer below is provided at one end of the skeleton away from the mounting frame, and the reinforcing assembly includes a connecting arm fixedly connected to the skeleton, and a bolt is threadedly inserted into the bottom end of the connecting arm, wherein the bolt squeezes the pressure plate to the bottom of the concrete layer.

[0016] The effect achieved by the above components is: steel bars can be arranged between the pressure plate and the concrete layer, and then the bolts are tightened to ensure that the pressure plate presses the steel bars to the bottom of the concrete layer, and then the bottom steel bars are used to further reinforce the concrete layer.

[0017] Preferably, a reinforcement frame is sleeved on the surface of the connecting arm, wherein the reinforcement frame is pressed upward by bolts to press against the bottom of the concrete layer for reinforcement.

[0018] Compared with the prior art, the advantages and positive effects of the utility model are:

[0019] In the utility model, if there is a large gap between two adjacent precast concrete composite floor slabs, the structure inside the connecting component is used to pull the skeletons of the two composite plates, so that the two composite plates are aligned close to each other to narrow the gap between the two composite plates, and to avoid as much as possible the gap between the two composite plates being too large and causing concrete leakage during the later pouring. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 The utility model provides a schematic structural diagram of the assembled state of one side of a combined prefabricated concrete composite floor slab;

[0021] Figure 2 A schematic diagram of the internal part of a combined prefabricated concrete composite floor slab is proposed for the utility model;

[0022] Figure 3 A schematic diagram of the back structure of a combined prefabricated concrete composite floor slab is provided for the utility model;

[0023] Figure 4 The utility model proposes a combined prefabricated concrete composite floor Figure 1 A partial cross-sectional view of

[0024] Figure 5 The utility model proposes a combined prefabricated concrete composite floor Figure 4 Enlarged view of point A.

[0025] Legend:

[0026] 1. Concrete layer; 2. Frame; 3. Mounting frame;

[0027] 4. Connecting assembly; 41. Connecting box; 42. Card holder; 43. Connecting rod; 44. Pull rod; 45. Nut;

[0028] 5. Reinforcement assembly; 51. Connecting arm; 52. Pressure plate; 53. Bolt; 54. Reinforcement frame. DETAILED DESCRIPTION

[0029] Embodiment 1, as Figure 1-5As shown, a combined precast concrete composite floor slab comprises a frame 2, wherein concrete is poured on the surface of the frame 2 to form a concrete layer 1 covering the surface of the frame 2, the frame 2 extends out of the concrete layer 1 in a horizontal direction, a connecting component 4 is arranged between two composite floor slabs, the connecting component 4 pulls the frame 2 extending out of the concrete layer 1 to align the two composite floor slabs close to each other, the frame 2 is a frame structure formed by bundling together a plurality of steel bars arranged in longitude and latitude, concrete is poured on the surface of the frame 2, and after the concrete solidifies, a concrete layer 1 covering the surface of the frame 2 is formed, the frame 2 and the concrete layer 1 covering the surface of the frame 2 constitute a precast concrete composite floor slab, and the frame 2 is located in the middle of the concrete layer 1 and can well support the concrete layer 1 to ensure the overall strength and stability. During construction, the overall frame of the building is first built, and then the panels are laid on the top of the frame. The precast concrete composite floor slabs are lifted by a crane and laid on the surface of the panels. The gaps between two adjacent precast concrete composite floor slabs can be sealed with a connecting component 4. If the gap between two adjacent precast concrete composite floor slabs is large, the structure inside the connecting component 4 is used to pull the skeletons 2 of the two composite boards, so that the two composite boards are aligned close to each other to narrow the gap between the two composite boards, and to avoid as much as possible that the gap between the two composite boards is too large and concrete leakage is caused by later pouring. The upper end of the skeleton 2 is evenly fixedly connected with a mounting frame 3, and the mounting frame 3 extends upward from the concrete layer 1. Since the mounting frame 3 is directly connected to the skeleton 2 and the mounting frame 3 extends upward The concrete layer 1 can be directly hooked on the surface of the mounting frame 3 for lifting during lifting. The connecting assembly 4 includes a connecting box 41, and the frame 2 is inserted into the connecting box 41. When there is a gap between the two composite plates, the connecting box 41 is put on the frame 2 between the two composite plates. The larger gap between the two composite plates is shielded and protected by the connecting box 41. The inner sliding connection of the connecting box 41 is connected with a pull rod 44. The surface of the pull rod 44 is fixedly connected with a connecting rod 43 relative to the part where the frame 2 is inserted into the connecting box 41. The free end of the connecting rod 43 is fixedly connected with a holder 42. If the gap between the two composite plates is relatively large, the frame 2 can be inserted into the connecting box 41 and welded between the holder 42. Then, the connecting rod 43 can be pulled through the connecting rod 43. The pulling seat 42 causes the seat 42 to pull the frame 2 along the sliding direction of the connecting rod 43 inside the connecting box 41, so that the two composite plate frames 2 are continuously pulled into the connecting box 41, thereby causing the two composite plates to approach each other to reduce the gap between the two composite plates. The pull rod 44 extends out of the connecting box 41 and is threaded with a nut 45 on the surface. By loosening the nut 45 at one end of the pull rod 44 and then tightening the nut 45 on the other side, the nut 45 and the connecting rod 43 are threadedly matched to thread the connecting rod 43 to slide toward the outside of the connecting box 41. The end of the frame 2 away from the mounting frame 3 is provided with a reinforcing component 5 that supports the bottom of the concrete layer 1. The reinforcing component 5 includes a connecting arm 51 fixedly connected to the frame 2, and a bolt 53 is threadedly inserted at the bottom end of the connecting arm 51.The bolts 53 squeeze the pressure plate 52 at the bottom of the concrete layer 1. Steel bars can be arranged between the pressure plate 52 and the concrete layer 1, and then the bolts 53 are tightened to ensure that the pressure plate 52 squeezes the steel bars at the bottom of the concrete layer 1, and then the bottom steel bars are used to further reinforce the concrete layer 1. The surface of the connecting arm 51 is covered with a reinforcement frame 54, and the reinforcement frame 54 is squeezed upward by the bolts 53 to press against the bottom of the concrete layer 1 for reinforcement.

[0030] Working principle: the frame 2 is a frame structure formed by bundling together multiple steel bars arranged in longitude and latitude. Concrete is poured on the surface of the frame 2. After the concrete solidifies, a concrete layer 1 covering the surface of the frame 2 is formed. The frame 2 and the concrete layer 1 covering the surface of the frame 2 constitute a precast concrete composite floor. The frame 2 is located in the middle of the concrete layer 1 and can well support the concrete layer 1 to ensure the overall strength and stability. During construction, the overall frame of the building is first built, and then the plate is laid on the top of the frame. The precast concrete composite floor is then lifted by a crane and laid on the surface of the plate. The gap between two adjacent precast concrete composite floors can be sealed by a connecting component 4. If the gap between two adjacent precast concrete composite floors is large, the structure inside the connecting component 4 is used to pull the frame 2 of the two composite plates, so that the two composite plates are aligned close to each other to narrow the gap between the two composite plates, and to avoid as much as possible the gap between the two composite plates. Leakage of concrete caused by later pouring due to excessive gap. Since the mounting frame 3 is directly connected to the frame 2 and the mounting frame 3 extends upward from the concrete layer 1, it can be lifted during lifting. The connecting box 41 is directly hooked on the surface of the mounting frame 3 for lifting. When there is a gap between the two superimposed plates, the connecting box 41 is put on the frame 2 between the two superimposed plates. The larger gap between the two superimposed plates is shielded and protected by the connecting box 41. If the gap between the two superimposed plates is relatively large, the frame 2 can be inserted into the connecting box 41 and welded between the card seat 42. Then, by pulling the connecting rod 43, the card seat 42 is pulled by the connecting rod 43 to cause the card seat 42 to pull the frame 2 in the connecting box 41 along the sliding direction of the connecting rod 43, so that the two The composite plate skeleton 2 is continuously pulled into the connection box 41, thereby pushing the two composite plates closer to each other to reduce the gap between the two composite plates. By loosening the nut 45 at one end of the pull rod 44 and then tightening the nut 45 on the other side, the nut 45 and the connecting rod 43 are threadedly matched to drive the connecting rod 43 to slide to the outside of the connection box 41. Reinforcement can be arranged between the pressure plate 52 and the concrete layer 1, and then the bolts 53 are tightened to ensure that the pressure plate 52 presses the reinforcement to the bottom of the concrete layer 1, and then the bottom reinforcement is used to further reinforce the concrete layer 1.

[0031] The above is only a preferred embodiment of the utility model, and does not limit the utility model in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the utility model without departing from the technical solution of the utility model still belongs to the protection scope of the technical solution of the utility model. In the description of the utility model, it should be noted that unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the utility model can be understood by specific circumstances.

Claims

1. A combined prefabricated concrete composite floor slab, comprising a frame (2), characterized in that: Concrete is poured on the surface of the skeleton (2) to form a concrete layer (1) covering the surface of the skeleton (2); the skeleton (2) extends out of the concrete layer (1) in a horizontal direction; a connecting component (4) is arranged between the two composite floor slabs; the connecting component (4) pulls the skeleton (2) extending out of the concrete layer (1) to cause the two composite floor slabs to be close to each other and aligned; the connecting component (4) includes a connecting box (41), and the skeleton (2) extends into the connecting box (41); a pull rod (44) is slidably connected to the inside of the connecting box (41); a connecting rod (43) is fixedly connected to the surface of the pull rod (44) relative to the part of the skeleton (2) extending into the connecting box (41); the free end of the connecting rod (43) is fixedly connected to a holder (42); a nut (45) is threadedly sleeved on the surface of the pull rod (44) extending out of the connecting box (41).

2. The combined precast concrete composite floor slab according to claim 1, characterized in that: The upper end of the frame (2) is evenly and fixedly connected with a mounting frame (3), and the mounting frame (3) protrudes upward from the concrete layer (1).

3. The combined precast concrete composite floor slab according to claim 2, characterized in that: A reinforcing assembly (5) for supporting the bottom of the concrete layer (1) is arranged at one end of the frame (2) away from the mounting frame (3), and the reinforcing assembly (5) comprises a connecting arm (51) fixedly connected to the frame (2), and a bolt (53) is threadedly inserted at the bottom end of the connecting arm (51), wherein the bolt (53) presses the pressure plate (52) against the bottom of the concrete layer (1).

4. The combined precast concrete composite floor slab according to claim 3 is characterized in that: The surface of the connecting arm (51) is covered with a reinforcement frame (54), wherein the reinforcement frame (54) is pressed upwards by bolts (53) to abut against the bottom of the concrete layer (1).