Compact LNG (Liquefied Natural Gas) filling equipment

By designing structures such as a locking tube, a locking outer tube, a lifting handle and a top pressure clamp in the LNG filling device, the existing problems in the prior art that the center is deflected and the filling pipe is easily stepped on when lifted are solved. for stable connection and convenient operation.

CN221881124UActive Publication Date: 2024-10-22TIANJIN ENERGY TECH OF GAS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420642525.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-10-22
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

When the existing LNG filling device is in use, the center of the existing LNG filling device is skewed when lifted due to the rear position of the handle, making it difficult to lift. Moreover, the liquid filling pipe is easily stepped on by the operator.

Method used

A compact LNG filling equipment is designed, which adopts structures such as a locking tube, a locking outer tube, a lifting handle, a lock assembly, a top pressure clamp and a limit groove. The locking tube is lifted up by the lifting handle and poured through the trapezoid. The angle top pressure clamp achieves a stable connection, ensuring that the top pressure clamp is always in a buckling state to avoid center deflection. The guide plate, limit clamp, control plate and spring design ensure that the locked outer tube is fixed at the current position to avoid stepping on it. .

Benefits of technology

It achieves a stable connection between the locking tube and the filling port, avoids center deflection and stepping problems, simplifies the operation process, and improves the convenience and safety of the equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221881124U_ABST
    Figure CN221881124U_ABST
Patent Text Reader

Abstract

The utility model discloses a compact type LNG filling device which comprises an LNG locking pipe, a locking outer pipe is installed on the outer surface of the LNG locking pipe in a sliding mode, a lifting handle is fixedly installed on the outer surface of the locking outer pipe, a guide groove is formed in the lifting handle, a lock catch assembly is installed in the guide groove in a sliding mode, the lower end of the lock catch assembly can be inserted into a limiting groove, and the limiting groove is formed in the outer surface of the LNG locking pipe. A pushing groove is formed in the outer surface of the LNG locking pipe, a jacking clamp is rotationally installed in the pushing groove, and the locking outer pipe jacks the outer surface of the jacking clamp. Through the design of the lock catch assembly, the locking outer pipe and the jacking clamp, due to the fact that the lifting handle is located in the middle, center deflection cannot occur in the process of lifting the locking outer pipe, a worker can more easily align the locking outer pipe with an LNG filling port, and the worker can keep away from stepping on a liquid adding pipe inserted in the middle of the LNG locking pipe when standing on the side face.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of liquefied natural gas filling, in particular to compact LNG filling equipment. Background Art

[0002] Liquefied natural gas, whose main component is methane, is recognized as the cleanest fossil energy on earth. It is colorless, odorless, non-toxic and non-corrosive. Its volume is about one-six hundred and twenty-fifth of the volume of the same amount of gaseous natural gas, and its mass is only about 45 percent of the same volume of water. Its manufacturing process is to first purify the natural gas produced by the gas field, and after a series of ultra-low temperature liquefaction, it is transported by liquefied natural gas ships. After combustion, liquefied natural gas causes very little air pollution and releases a lot of heat, so liquefied natural gas is a relatively advanced energy source.

[0003] For example, the patent with the national authorized patent announcement number CN214198147U discloses a liquefied natural gas filling device, including a locking inner tube, a locking outer tube, a pin inside the locking inner tube, a mounting hole on the outer wall of the locking inner tube, and a steel ball in the mounting hole, wherein the locking outer tube is sleeved on the outside of the locking inner tube; the characteristics are: the bottom of the locking inner tube is connected to a fixing plate through a plurality of connecting columns; a groove is provided in the center of the fixing plate, a liquid filling tube passes through the groove, and the upper part of the liquid filling tube is connected to the locking outer tube. The utility model of a liquefied natural gas filling device relies on turning the handle to move the locking outer tube forward, and uses the locking outer tube to squeeze the steel ball against the inner wall of the locking inner tube to achieve a stable connection between the locking inner tube and the liquid filling tube.

[0004] However, when the liquefied natural gas filling device is in use, the handle is located backward, which causes the center to deviate during the process of lifting the locking tube, making it difficult to lift it, and the filling tube inserted in the middle is easily stepped on by the staff when operating the device. Utility Model Content

[0005] The purpose of the utility model is to provide a compact LNG filling equipment to solve the problems raised in the above-mentioned background technology that when in use, the handle is located backward, which causes the center to be skewed during the process of lifting the locking tube, making it difficult to lift it, and the filling tube inserted in the middle is also easily stepped on by the staff when operating this device.

[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0007] The compact LNG filling equipment comprises: an LNG locking tube, a locking outer tube is slidably mounted on the outer surface of the LNG locking tube, a lifting handle is fixedly mounted on the outer surface of the locking outer tube, a guide groove is provided in the lifting handle, a locking assembly is slidably mounted in the guide groove, the lower end of the locking assembly can be inserted into a limiting groove, the limiting groove is provided on the outer surface of the LNG locking tube, an advancement groove is provided on the outer surface of the LNG locking tube, a pressing clamp is rotatably mounted in the advancement groove, and the locking outer tube presses against the outer surface of the pressing clamp.

[0008] Preferably, the tail end of the pressing clamp is convex, and the inner extension of the locking outer tube is provided with a trapezoidal chamfer. When the trapezoidal chamfer of the locking outer tube presses on the convex tail end of the pressing clamp, the pressing clamp can be pressed and lifted from the advancement groove;

[0009] When the trapezoidal chamfer of the locking outer tube slides forward and presses on the middle section of the pressing clamp, the pressing clamp can be pressed into the advancement groove, and the pressing portion of the pressing clamp can be pushed into the LNG locking tube.

[0010] Preferably, a limiting column is fixedly mounted on one end of the locking outer tube, the limiting column is slidably mounted in a limiting plate, and the limiting plate is fixedly mounted on the outer surface of the tail portion of the LNG locking tube.

[0011] Preferably, the locking assembly includes a guide plate, which is slidably installed in the guide groove, and a limiting clamp is fixedly installed on the lower surface of the guide plate. The limiting clamp can be received in the receiving groove by the upward sliding of the guide plate. The receiving groove is opened in the inner ring of the locking outer tube and is connected with the guide groove. The limiting clamp can be inserted into the limiting groove by the downward sliding of the guide plate.

[0012] Preferably, a control plate is fixedly mounted on one end of the guide plate, and the control plate extends from the sliding opening into the handle. The sliding opening is opened at one end of the handle and is communicated with the guide groove.

[0013] Preferably, guide rail grooves are provided on both sides of the guide plate, the guide rail grooves are slidably mounted on the outer surface of the guide rail blocks, and the guide rail blocks are fixedly mounted on both sides of the guide grooves.

[0014] Preferably, a slide column is fixedly installed in the guide rail groove, and the slide column slides through the guide rail block at the same time. A spring is mounted on the outer surface of the slide column, and the upper end of the spring contacts the lower end of the guide rail block, and the lower end of the spring contacts the lower end of the guide rail groove.

[0015] Compared with the prior art, the beneficial effects of the utility model are:

[0016] 1. Through the design of LNG locking tube, locking outer tube, lifting handle, locking buckle assembly, top pressing clamp and limit groove, when connecting the LNG locking tube to the LNG filling port, the filling tube is first connected to the LNG locking tube, and then the staff can stand on the side and lift the LNG locking tube and the locking outer tube by the lifting handle, and then dock the LNG locking tube with the LNG filling port, and push the lifting handle forward by external force to drive the locking outer tube to slide forward on the surface of the LNG locking tube, and the locking outer tube sliding forward will be pressed on the surface of the top pressing clamp through the trapezoidal chamfer of the inner ring, so that the top pressing clamp can be pressed into the advancement groove, and the barb at the front end of the top pressing clamp will be pressed into the LNG locking tube, so that the top pressing clamp can be embedded in the annular embedded groove on the outer surface of the LNG filling port through the barb, so as to achieve a stable connection between the LNG locking tube and the LNG filling port, and lock it at the same time The limit column of the locking outer tube will slide to the top position of the limit plate, and the receiving groove on the inner ring surface of the locking outer tube will be flush with the limiting groove opened on the surface of the LNG locking tube, so that the locking buckle assembly in the receiving groove will spring into the limiting groove through elastic force, so that the locking outer tube can be fixed in the current position, and the top pressing clamp can be ensured to be in a buckled state at all times. When disassembling, it is only necessary to press the locking buckle assembly to lift it from the limiting groove and pull the locking outer tube back, and the trapezoidal chamfer of the locking outer tube will press on the raised inclined surface at the tail end of the top pressing clamp, so that the top pressing clamp can be pressed and tilted from the advancement groove to achieve the unlocking operation, and because the position of the lifting handle is in the middle position, there will be no center deviation in the process of lifting the locking outer tube and the LNG locking tube, which can be easily aligned with the LNG filling port for the staff, and standing on the side will also avoid the filling pipe inserted in the middle of the LNG locking tube.

[0017] 2. Through the design of the guide plate, the limit clamp, the control plate and the spring, when the receiving groove on the inner ring surface of the locking outer tube is flush with the limit groove on the surface of the LNG locking tube, the limit clamp in the receiving groove will be pushed by the elastic force applied by the spring in the guide plate to drive the limit clamp to be inserted into the limit groove, thereby fixing the locking outer tube in the current position and ensuring that the top pressure clamp is always in the buckling state;

[0018] When disassembling, the staff only needs to hold the outer surface of the handle and press the lower surface of the control board with their fingers, so that the guide plate can be lifted up through the control board and slide upward in the guide groove, and at the same time, the limit clamp will be lifted up from the limit groove and slid into the storage groove, so that the locking limit of the locking outer tube can be unlocked. Then the staff can pull back the locking outer tube, and the trapezoidal chamfer of the locking outer tube will press on the rear end of the pressing clamp to form a raised inclined block, so that the pressing clamp can be pressed and lifted up from the advancement groove to achieve the disconnection operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1It is a schematic diagram of the top pressure clamp tilting structure of the utility model;

[0020] Figure 2 This is a schematic diagram of the top pressing clamp and the top pressing structure of the utility model;

[0021] Figure 3 It is a cross-sectional view of the overall structure of the utility model;

[0022] Figure 4 This is a schematic diagram of the locking outer tube and locking inner ring structure of the utility model;

[0023] Figure 5 It is a schematic diagram of the limit groove and the advancement groove structure of the utility model;

[0024] Figure 6 This is a schematic diagram of the guide groove structure of the utility model;

[0025] Figure 7 This is a schematic diagram of the storage tank structure of the utility model;

[0026] Figure 8 It is a schematic diagram of the structure of the lock assembly of the utility model.

[0027] In the figure: 1. LNG locking tube; 101. Limit plate; 102. Limit groove; 103. Advance groove; 2. Locking outer tube; 201. Lifting handle; 202. Guide block; 203. Limit column; 204. Guide groove; 205. Storage groove; 206. Sliding opening; 3. Locking assembly; 301. Guide plate; 302. Limit clamp; 303. Guide groove; 304. Sliding column; 305. Spring; 306. Control panel; 4. Top pressure clamp. DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0029] See also Figure 1-Figure 8 , the utility model provides the following technical solutions:

[0030] like Figure 1-Figure 6As shown, the compact LNG filling equipment includes: an LNG locking tube 1, a locking outer tube 2 is slidably installed on the outer surface of the LNG locking tube 1, a lifting handle 201 is fixedly installed on the outer surface of the locking outer tube 2, a guide groove 204 is opened in the lifting handle 201, a locking component 3 is slidably installed in the guide groove 204, the lower end of the locking component 3 can be inserted into the limiting groove 102, the limiting groove 102 is opened on the outer surface of the LNG locking tube 1, an advancing groove 103 is opened on the outer surface of the LNG locking tube 1, a pressing clamp 4 is rotatably installed in the advancing groove 103, and the locking outer tube 2 presses on the outer surface of the pressing clamp 4.

[0031] The tail end of the pressing clip 4 is convex, and a trapezoidal chamfer is provided at the inner extension of the locking outer tube 2. When the trapezoidal chamfer of the locking outer tube 2 is pressed on the convex tail end of the pressing clip 4, the pressing clip 4 can be pressed and lifted from the advancing groove 103;

[0032] When the trapezoidal chamfer of the locking outer tube 2 slides forward and presses on the middle section of the pressing clamp 4 , the pressing clamp 4 can be pressed into the advancement groove 103 , and the pressing portion of the pressing clamp 4 can be pushed into the LNG locking tube 1 .

[0033] A limiting column 203 is fixedly installed at one end of the locking outer tube 2 . The limiting column 203 is slidably installed in the limiting plate 101 . The limiting plate 101 is fixedly installed on the outer surface of the tail of the LNG locking tube 1 .

[0034] Through the design of the LNG locking tube 1, the locking outer tube 2, the lifting handle 201, the locking assembly 3, the top pressure clamp 4 and the limiting groove 102, when the LNG locking tube 1 is connected to the LNG filling port, the filling pipe is first connected to the LNG locking tube 1, and then the staff can stand on the side and lift the LNG locking tube 1 and the locking outer tube 2 through the lifting handle 201, and then dock the LNG locking tube 1 with the LNG filling port, and push the lifting handle 201 forward by external force to drive the locking outer tube 2 to The surface of the LNG locking tube 1 slides forward, and the locking outer tube 2 that slides forward will press on the surface of the pressing clamp 4 through the trapezoidal chamfer of the inner ring, so that the pressing clamp 4 can be pressed into the advancement groove 103, and the barb at the front end of the pressing clamp 4 can be pressed into the LNG locking tube 1, so that the pressing clamp 4 can be embedded in the annular embedded groove on the outer surface of the LNG filling port through the barb, thereby achieving a stable connection between the LNG locking tube 1 and the LNG filling port, and at the same time locking the outer tube 2. The limiting post 203 will slide to the top position of the limiting plate 101, and the receiving groove 205 on the inner ring surface of the locking outer tube 2 will be flush with the limiting groove 102 opened on the surface of the LNG locking tube 1, so that the locking component 3 in the receiving groove 205 will be elastically rebounded into the limiting groove 102, so that the locking outer tube 2 can be fixed in the current position, and the top pressing clamp 4 can be ensured to be always in the buckled state. When disassembling, it is only necessary to press the locking component 3 to lift it from the limiting groove 102 and pull it back The locking outer tube 2 is locked, and the trapezoidal chamfer of the locking outer tube 2 will press on the rear end of the pressing clamp 4 to form a raised inclined block, so that the pressing clamp 4 can be pressed and tilted from the advancement groove 103 to achieve the unlocking operation, and because the position of the lifting handle 201 is in the middle position, there will be no center deviation in the process of lifting the locking outer tube 2 and the LNG locking tube 1, which can be easily aligned with the LNG filling port for the staff, and standing at the side position will also avoid the liquid filling tube inserted in the middle of the LNG locking tube 1.

[0035] like Figure 7-Figure 8 As shown, the locking assembly 3 includes a guide plate 301, which is slidably installed in the guide groove 204. A limiting clamp 302 is fixedly installed on the lower surface of the guide plate 301. The limiting clamp 302 can be received in the receiving groove 205 by the upward sliding of the guide plate 301. The receiving groove 205 is provided in the inner ring of the locking outer tube 2 and is connected to the guide groove 204. The limiting clamp 302 can be inserted into the limiting groove 102 by the downward sliding of the guide plate 301.

[0036] A control plate 306 is fixedly mounted on one end of the guide plate 301 . The control plate 306 extends from the sliding opening 206 into the handle 201 . The sliding opening 206 is provided at one end of the handle 201 and communicates with the guide slot 204 .

[0037] The guide plate 301 has guide rail grooves 303 on both sides. The guide rail grooves 303 are slidably mounted on the outer surface of the guide rail block 202 . The guide rail block 202 is fixedly mounted on both sides of the guide groove 204 .

[0038] A slide column 304 is fixedly installed in the guide rail groove 303, and the slide column 304 slides through the guide rail block 202 at the same time. A spring 305 is mounted on the outer surface of the slide column 304, and the upper end of the spring 305 contacts the lower end of the guide rail block 202, and the lower end of the spring 305 contacts the lower end of the guide rail groove 303.

[0039] Through the design of the guide plate 301, the limiting clamp 302, the control plate 306 and the spring 305, when the receiving groove 205 on the inner ring surface of the locking outer tube 2 is flush with the limiting groove 102 opened on the surface of the LNG locking tube 1, the limiting clamp 302 in the receiving groove 205 will push the guide plate 301 through the elastic force applied by the spring 305 in the guide plate 301 to drive the limiting clamp 302 to be inserted into the limiting groove 102, thereby the locking outer tube 2 can be fixed in the current position, and the top pressing clamp 4 can be ensured to be always in a buckling state;

[0040] When disassembling, the staff only needs to hold the outer surface of the handle 201 and press the lower surface of the control board 306 with their fingers, so that the guide plate 301 can be lifted up through the control board 306 and slide upward in the guide groove 204, and at the same time, the limit clamp 302 will be lifted up from the limit groove 102 and slid into the storage groove 205, so that the locking limit of the locking outer tube 2 can be unlocked, and then the staff can pull back the locking outer tube 2, and the trapezoidal chamfer of the locking outer tube 2 will press on the rear end of the pressing clamp 4 to form a raised inclined block, so that the pressing clamp 4 can be pressed and lifted up from the advancement groove 103 to achieve the disconnection operation.

[0041] The working steps of this scheme are summarized and sorted out according to the above technical scheme: when connecting the LNG locking tube 1 to the LNG filling port, first insert the filling tube from the rear end of the LNG locking tube 1 and connect it with the LNG locking tube. Then the staff can stand on the side and lift the LNG locking tube 1 and the locking outer tube 2 through the lifting handle 201, and then dock the LNG locking tube 1 with the LNG filling port. The ejector pin in the LNG locking tube 1 will push through the LNG filling port and push the lifting handle 201 forward through external force to drive the locking outer tube 2 to slide forward on the surface of the LNG locking tube 1. The locking outer tube 2 that slides forward will be pressed on the surface of the pressing clamp 4 through the trapezoidal chamfer of the inner ring, so that the pressing clamp 4 can be pressed into the advancement groove 103, and the front of the pressing clamp 4 The barb at the end will be pressed into the LNG locking tube 1, so that the top pressure clamp 4 can be embedded in the annular embedded groove on the outer surface of the LNG filling port through the barb, so as to achieve a stable connection between the LNG locking tube 1 and the LNG filling port, and at the same time, the limiting column 203 of the locking outer tube 2 will slide to the top position of the limiting plate 101, and the receiving groove 205 on the inner ring surface of the locking outer tube 2 will be flush with the limiting groove 102 opened on the surface of the LNG locking tube 1, so that the limiting clamp 302 in the receiving groove 205 will be pushed by the elastic force applied by the spring 305 in the guide plate 301 to drive the limiting clamp 302 to be inserted into the limiting groove 102, so that the locking outer tube 2 can be fixed at the current position, and it can be ensured that the top pressure clamp 4 is always in a buckled state;

[0042] When disassembling, the staff only needs to hold the outer surface of the handle 201 and press the lower surface of the control board 306 with their fingers, so that the guide plate 301 can be lifted up through the control board 306 and slide upward in the guide groove 204, and at the same time, the limit clamp 302 will be lifted up from the limit groove 102 and slid into the storage groove 205, so that the locking limit of the locking outer tube 2 can be unlocked, and then the staff can pull back the locking outer tube 2, and the trapezoidal chamfer of the locking outer tube 2 will press on the rear end of the pressing clamp 4 to form a raised inclined block, so that the pressing clamp 4 can be pressed and lifted up from the advancement groove 103 to achieve the disconnection operation.

[0043] In summary: since the position of the lifting handle is in the middle position, there will be no center deviation in the process of lifting and locking the outer tube, which makes it easier for the staff to align it with the LNG filling port, and standing at the side will also avoid stepping on the liquid filling tube inserted in the middle of the locking inner tube.

[0044] Parts not involved in the present invention are the same as the prior art or can be implemented by the prior art. Although the embodiments of the present invention have been shown and described, it is understood by those skilled in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the attached claims and their equivalents.

Claims

1. Compact LNG bunkering equipment, It is characterized in that include: An LNG locking tube (1), wherein a locking outer tube (2) is slidably mounted on the outer surface of the LNG locking tube (1), a lifting handle (201) is fixedly mounted on the outer surface of the locking outer tube (2), a guide groove (204) is provided in the lifting handle (201), a locking assembly (3) is slidably mounted in the guide groove (204), a lower end of the locking assembly (3) can be inserted into a limiting groove (102), the limiting groove (102) is provided on the outer surface of the LNG locking tube (1), an advancing groove (103) is provided on the outer surface of the LNG locking tube (1), a pressing clamp (4) is rotatably mounted in the advancing groove (103), and the locking outer tube (2) is pressed against the outer surface of the pressing clamp (4).

2. The compact LNG refueling equipment according to claim 1, Features: The rear end of the pressing clamp (4) is convex, and the inner extension of the locking outer tube (2) is provided with a trapezoidal chamfer. When the trapezoidal chamfer of the locking outer tube (2) presses against the convex rear end of the pressing clamp (4), the pressing clamp (4) can be pressed and lifted from the advancement groove (103); When the trapezoidal chamfer of the locking outer tube (2) slides forward and presses against the middle section of the pressing clamp (4), the pressing clamp (4) can be pressed into the advancement groove (103), and the pressing portion of the pressing clamp (4) can be pushed into the LNG locking tube (1).

3. The compact LNG refueling equipment according to claim 1, Features: A limiting column (203) is fixedly mounted on one end of the locking outer tube (2); the limiting column (203) is slidably mounted in a limiting plate (101); and the limiting plate (101) is fixedly mounted on the outer surface of the rear end of the LNG locking tube (1).

4. The compact LNG filling equipment according to claim 1, Features: The locking assembly (3) comprises a guide plate (301), wherein the guide plate (301) is slidably mounted in the guide groove (204), and a limit clamp (302) is fixedly mounted on the lower surface of the guide plate (301), and the limit clamp (302) can be received in a receiving groove (205) by the guide plate (301) sliding upwards, and the receiving groove (205) is provided in the inner ring of the locking outer tube (2) and is connected to the guide groove (204), and the limit clamp (302) can be inserted into the limit groove (102) by the guide plate (301) sliding downwards.

5. The compact LNG refueling equipment according to claim 4, Features: A control plate (306) is fixedly mounted on one end of the guide plate (301), and the control plate (306) extends from the sliding opening (206) into the handle (201). The sliding opening (206) is opened at one end of the handle (201) and is connected to the guide groove (204).

6. The compact LNG refueling equipment according to claim 4, Features: The guide plate (301) has guide rail grooves (303) on both sides. The guide rail grooves (303) are slidably mounted on the outer surface of the guide rail block (202). The guide rail block (202) is fixedly mounted on both sides of the guide groove (204).

7. The compact LNG refueling equipment according to claim 6, Features: A slide column (304) is fixedly installed in the guide rail groove (303), and the slide column (304) slides through the guide rail block (202) at the same time. A spring (305) is sleeved on the outer surface of the slide column (304), and the upper end of the spring (305) contacts the lower end of the guide rail block (202), and the lower end of the spring (305) contacts the lower end of the guide rail groove (303).