Visual transparent soil testing device for simulating impact holing construction
By using a visual transparent soil test device during impact drilling construction, the internal deformation of the soil can be observed in real time, which solves the problem of inaccurate traditional test data, achieves more intuitive and comprehensive three-dimensional test results, and improves the accuracy of the test. and reliability.
Patent Information
- Application Number
- CN202420819025.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2034-04-19
AI Technical Summary
Existing technology cannot directly observe the deformation inside the soil during the impact drilling construction process. The traditional model test data is not accurate enough and cannot provide continuous deformation information of the soil.
A visual transparent soil test device is designed to simulate impact drilling construction, including a test base, a visual model box, an impact drilling system and a three-dimensional observation system. The transparent soil simulates natural soil and uses industrial CCD cameras and lasers to observe the soil in real time. Internal deformation of the body, providing three-dimensional test results.
It achieves clear observation of the internal deformation of the soil, improves the accuracy and comprehensiveness of the test data, enhances the understanding of the soil deformation process and failure mechanism, and enhances the significance and reliability of the test.
Smart Images

Figure CN221883467U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of transparent soil model testing, in particular to a visualized transparent soil testing device for simulating impact hole-forming construction. Background Art
[0002] Bored piles are a kind of structural foundation widely used in infrastructure such as high-rise buildings, highways, bridges, etc. With the improvement of construction technology, various types of bored piles have emerged and play an important role in various projects. In particular, impact bored piles have the characteristics of strong adaptability and high construction efficiency, and are particularly suitable for construction in pebble layers, karst rock layers, and rock layers with developed fissures. However, during the construction process of impact drilling, vibrations will be generated, and mud needs to be injected into the hole for cooling and slag removal. These factors will affect the surrounding soil, thereby affecting the construction progress and construction safety. Therefore, model tests for impact drilling construction have gradually increased, but neither traditional model tests nor field tests can directly observe the deformation of the soil during the test. The deformation of the soil can only be collected by burying sensors, but the sensors cannot provide continuous deformation information of the soil, and the test data will also be affected by factors such as sensor stiffness and size and are not accurate enough.
[0003] With the continuous development of model tests, visualized transparent soil technology has provided new possibilities for solving this problem. In transparent soil model tests, transparent soil is used instead of natural soil. Due to its good transparency, the deformation inside the soil and the complete test process can be directly observed. In addition, visualized transparent soil technology uses movable lasers and cameras for data collection, which can present the test results in three-dimensional form and provide continuous deformation information inside the soil. Compared with traditional buried sensors, the test data provided by visualized transparent soil technology is also more accurate and reliable.
[0004] Therefore, it is necessary for us to develop a test device that simulates impact drilling construction with the help of visualized transparent soil technology to improve the accuracy of the test data and obtain continuous deformation information inside the soil through three-dimensional test results. Utility Model Content
[0005] In view of the defects in the prior art, the utility model provides a visualized transparent soil test device for simulating impact drilling construction, which is used to solve the problems that the prior art lacks a test device for simulating impact drilling construction with the help of visualized transparent soil technology, and the continuous deformation information inside the soil body is not obtained perfectly.
[0006] In order to achieve the above-mentioned purpose, the utility model provides a visualized transparent soil test device for simulating impact hole-forming construction, comprising:
[0007] Test base,
[0008] A visual model box, which is detachably mounted on the test base and is used to place transparent soil;
[0009] An impact hole forming system, which is fixedly mounted on the test base and located above the visual model box, and is used to perform impact hole forming construction on the transparent soil in the visual model box;
[0010] A three-dimensional observation system, which is slidably mounted on the test base and located on the side of the visualization model box, and is used to observe the internal deformation of the transparent soil in real time;
[0011] A manipulation and analysis platform is electrically connected to the impact hole forming system and the three-dimensional observation system.
[0012] With this setting, by using transparent soil to simulate natural soil for model tests, compared with traditional model tests, the transparent soil model test can clearly observe the deformation inside the soil and obtain more intuitive test results; at the same time, the transparent soil model test can also fully display the test process, enhance the ability to study the deformation process and failure mechanism of the soil, thereby enhancing the experimental significance of the model test.
[0013] Furthermore, the impact hole-forming system includes an impact device, a slurry extraction device and a slurry delivery device. The impact device, the slurry extraction device and the slurry delivery device are all fixedly installed on the test base, and the impact device is located above the visualization model box.
[0014] Furthermore, the impact equipment includes an impactor and an impact drill, columns are fixedly installed on both sides of the top of the test base, fixed ends are fixedly installed on the top of the two columns, a cross bar is fixedly connected between the two fixed ends, the impactor is fixedly installed in the middle of one side of the cross bar, the impact drill is slidably installed inside the impactor, the impact drill is made of transparent acrylic material, and the outer wall of the impact drill is provided with a reflection-suppressing coating.
[0015] Furthermore, the slurry delivery equipment includes a first transparent tube, a slurry delivery pump, a first flow control valve, a first connecting pipe, and a first water storage tank. The slurry delivery pump and the first water storage tank are both fixedly installed on the top of the test base. The slurry delivery pump and the first water storage tank are fixedly connected by a first connecting pipe. The slurry delivery pump is fixedly connected to the first transparent tube. The first transparent tube is fixedly installed with a first flow control valve. The first transparent tube is used to inject mixed slurry into the pile hole impacted in the transparent soil.
[0016] Furthermore, the grouting equipment includes a second transparent tube, a grouting pump, a second flow control valve, a second connecting pipe, and a second water storage tank. The grouting pump and the second water storage tank are both fixedly installed on the top of the test base. The grouting pump and the second water storage tank are fixedly connected by a second connecting pipe. The grouting pump is fixedly connected to the second transparent tube, and the second transparent tube is fixedly installed with a second flow control valve. The second transparent tube is used to suck the mixed slurry from the pile hole impacted by the transparent soil.
[0017] Furthermore, the impact drill comprises a drill rod and drill teeth. The drill rod is slidably installed inside the impactor, and a plurality of drill teeth are fixedly installed at the lower end of the drill rod at even intervals.
[0018] Furthermore, a first transparent tube groove and a second transparent tube groove are provided on the top of the visualization model box, and rubber rings are fixedly installed in the first transparent tube groove and the second transparent tube groove, and the first transparent tube and the second transparent tube are in contact with the corresponding rubber rings.
[0019] Furthermore, scale lines are evenly spaced on an inner wall of one side of the visualization model box.
[0020] Furthermore, the three-dimensional observation system includes a first telescopic straight rod, a second telescopic straight rod, an industrial CCD camera and a laser. A first track and a second track are fixedly installed on the test base. The first track and the second track are parallel and respectively face the adjacent two sides of the visualization model box. The first telescopic straight rod is slidably connected to the first track. A first ball joint is fixedly installed on the top of the first telescopic straight rod. The industrial CCD camera is movably connected to the first telescopic straight rod through the first ball joint. The second telescopic straight rod is slidably connected to the second track. A second ball joint is fixedly installed on the top of the second telescopic straight rod. The laser is movably connected to the second telescopic straight rod through the second ball joint.
[0021] Furthermore, the shooting direction of the industrial CCD camera and the laser direction of the laser are perpendicular to each other, and the moving speed and moving direction along the first track or the second track are the same.
[0022] The beneficial effects of this embodiment are as follows:
[0023] 1. By using transparent soil to simulate natural soil for model tests, compared with traditional model tests, transparent soil model tests can clearly observe the deformation inside the soil and obtain more intuitive test results; at the same time, transparent soil model tests can also fully display the test process, enhance the ability to study the deformation process and failure mechanism of the soil, thereby enhancing the experimental significance of the model test;
[0024] 2. The test data is collected by synchronously moving industrial CCD cameras and lasers, so that the test results can be displayed in three-dimensional form and the continuous deformation information inside the transparent soil body can be provided. At the same time, the accuracy of the test data is improved and the test data is more comprehensive;
[0025] 3. Use slurry extraction equipment and slurry delivery equipment to suck and inject the mixed slurry into the pile hole to simulate the actual impact drilling construction. The impact height of the impact drill is controlled by the impactor, so that the height of the impact drill from the bottom of the pile hole can be kept consistent each time the hole is punched. Therefore, the transparent soil model test is more in line with the impact drilling construction in actual projects, thereby improving the reliability of the transparent soil model test. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic diagram of the overall structure of the test device of an embodiment of the utility model from a first viewing angle;
[0027] Figure 2 The test device of the utility model embodiment Figure 1 A magnified view of the part A in the middle;
[0028] Figure 3 This is a schematic diagram of the overall structure of the test device according to an embodiment of the utility model from a second viewing angle.
[0029] Among them, test base 1;
[0030] Visual model box 2, first transparent tube groove 21;
[0031] Impact device 31, column 311, fixed end 312, cross bar 313, impactor 314, impact drill 315, drill rod 3151, drill teeth 3152;
[0032] Slurry delivery equipment 32, slurry delivery pump 321, first water storage tank 322, first transparent tube 323, first connecting tube 324;
[0033] Slurry extraction equipment 33, slurry extraction pump 331, second water storage tank 332, second transparent tube 333, second connecting tube 334;
[0034] Three-dimensional observation system 4, first track 411, industrial CCD camera 412, first telescopic straight rod 413, second track 421, laser 422, second telescopic straight rod 423;
[0035] Control analysis station 5. DETAILED DESCRIPTION
[0036] The specific embodiments of the present invention will be described in detail below. It should be noted that the embodiments described here are only for illustration and are not intended to limit the present invention. In the following description, a large number of specific details are set forth in order to provide a thorough understanding of the present invention. However, it is obvious to those of ordinary skill in the art that these specific details do not have to be adopted to implement the present invention. In other examples, in order to avoid confusing the present invention, known circuits, software or methods are not specifically described.
[0037] Throughout the specification, references to "one embodiment", "an embodiment", "an example" or "an example" mean that a particular feature, structure or characteristic described in conjunction with the embodiment or example is included in at least one embodiment of the present invention. Therefore, the phrases "in one embodiment", "in an embodiment", "an example" or "an example" appearing in various places throughout the specification do not necessarily refer to the same embodiment or example. In addition, particular features, structures or characteristics may be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. In addition, it should be understood by those of ordinary skill in the art that the illustrations provided herein are for illustrative purposes and that the illustrations are not necessarily drawn to scale.
[0038] See also Figure 1 The utility model provides an embodiment of a visualized transparent soil test device for simulating impact hole construction, comprising a test base 1, a visualized model box 2, an impact hole system and a three-dimensional observation system 4. The visualized model box 2, the impact hole system and the three-dimensional observation system 4 are all installed on the test base 1. The impact hole system is located above the visualized model box 2 and is used to simulate the impact hole construction. The three-dimensional observation system 4 is located on the side of the visualized model box 2 and is used to observe in real time the continuous deformation inside the soil body during impact hole construction.
[0039] See also Figure 1 In this embodiment, a control and analysis platform 5 is fixedly installed on one side of the test base 1. The control and analysis platform 5 is electrically connected to the impact hole forming system and the three-dimensional observation system 4 to achieve the effect of controlling the normal operation of the entire device, ensuring that the impact hole forming system and the three-dimensional observation system 4 cooperate accurately, thereby making the test more stable and repeatable; at the same time, it can also effectively save manpower and material resources, reduce test costs, and improve test efficiency. In this embodiment, the control and analysis platform 5 is a prior art, so it will not be described in detail here.
[0040] See also Figure 1In this embodiment, the impact drilling system includes an impact device 31, a grouting device 33 and a grouting device 32. The impact device 31, the grouting device 33 and the grouting device 32 are all fixedly installed on the test base 1. The impact device 31 is located above the visualization model box 2. The grouting device 33 and the grouting device 32 are used to suck and inject mixed slurry into the pile hole to simulate the actual impact drilling construction. The impact device 31 is used to keep the height from the bottom of the pile hole consistent each time the hole is punched. Therefore, the transparent soil model test is more in line with the impact drilling construction in actual engineering, thereby improving the reliability of the transparent soil model test.
[0041] See also Figure 3 In this embodiment, the impact device 31 includes an impactor 314 and an impact drill 315. The top sides of the test base 1 are fixedly installed with columns 311 by bolts. The tops of the two columns 311 are fixedly installed with fixed ends 312 by bolts. A crossbar 313 is fixedly connected between the two fixed ends 312. The impactor 314 is fixedly installed in the middle of one side of the crossbar 313 by bolts. The impact drill 315 is slidably installed inside the impactor 314. When in use, the impactor 314 is turned on, so that the impact drill 315 starts to lift and lower, that is, the transparent soil in the visualization model box 2 is impacted and holed; at the same time, the impact height of the impact drill 315 is controlled by the impactor 314, so that the height of the impact drill 315 from the bottom of the pile hole can be kept consistent each time a hole is punched, so as to improve the reliability of the transparent soil model test. In this embodiment, the various components are installed by bolts, which can not only ensure the stability of the test components, but also make the installation and disassembly process of the test components more efficient, and improve the ease of use and convenience of operation of the test components.
[0042] See also Figure 2-3 In this embodiment, the impact drill 315 includes a drill rod 3151 and a drill tooth 3152. The drill rod 3151 is slidably installed inside the impactor 314. A plurality of drill teeth 3152 are evenly fixedly installed on the lower end of the drill rod 3151. Four drill teeth 3152 can be selected. The drill rod 3151 and the drill teeth 3152 are both made of transparent acrylic material. The outer wall of the drill rod 3151 and the outer wall of the drill tooth 3152 are both provided with an anti-reflection coating. The anti-reflection coating is used to suppress the reflection of light. Because the drill rod 3151 and the drill tooth 3152 are both made of transparent material, light can better penetrate the drill rod 3151 and the drill tooth 3152.
[0043] See also Figure 3In this embodiment, the slurry delivery equipment 32 includes a first transparent tube 323, a slurry delivery pump 321, a first flow control valve, a first connecting tube 324, and a first water storage tank 322. The slurry delivery pump 321 and the first water storage tank 322 are both fixedly installed on the top of the test base 1 by bolts and are located in front of the visualization model box 2. The slurry delivery pump 321 and the first water storage tank 322 are fixedly connected by a first connecting tube 324. The slurry delivery pump 321 is fixedly connected to the first transparent tube 323, and the first transparent tube 323 is fixedly installed with a first flow control valve. The first flow control valve is located at the connection between the first transparent tube 323 and the slurry pump 321. When the impact drill 315 impacts a pile hole in the transparent soil, the outlet end of the first transparent tube 323 is arranged in the pile hole and is located between two adjacent drill teeth 3152. The first transparent tube 323 has a certain support. When it is placed in the pile hole, it is not easy to shake and will not affect the normal operation of the impact drill 315. The first transparent tube 323 is used to inject pore solution into the pile hole to ensure that there is solution in the pile hole and there is not too much solution outside the pile hole.
[0044] See also Figure 3 In this embodiment, the slurry pumping device 33 includes a second transparent tube 333, a slurry pump 331, a second flow control valve, a second connecting tube 334, and a second water storage tank 332. The slurry pump 331 and the second water storage tank 332 are both fixedly installed on the top of the test base 1 by bolts and are located on the right side of the visualization model box 2. The slurry pump 331 and the second water storage tank 332 are fixedly connected by a second connecting tube 334. The slurry pump 331 is fixedly connected to the second transparent tube 333. A second flow control valve is fixedly installed and located at the connection between the second transparent tube 333 and the slurry pump 331. When the impact drill 315 impacts a pile hole in the transparent soil, the suction end of the second transparent tube 333 is arranged in the pile hole and located between two adjacent drill teeth 3152. The second transparent tube 333 has a certain degree of support and is not easy to shake when placed in the pile hole, which will not affect the normal operation of the impact drill 315. The second transparent tube 333 is used to suck the pore solution from the pile hole.
[0045] See also Figure 1 In this embodiment, scale lines are evenly spaced on the inner wall of one side of the visualization model box 2 to determine the thickness of the transparent soil and the depth of each impact of the impact drill when impacting the hole. In this embodiment, the visualization model box 2 is made of transparent acrylic material, which is convenient for clearly observing the continuous deformation of the transparent soil in the visualization model box 2.
[0046] See also Figure 2In this embodiment, a first transparent tube groove 21 and a second transparent tube groove are provided on the top of the visualization model box 2, and rubber rings are fixedly installed in the first transparent tube groove 21 and the second transparent tube groove. The first transparent tube 323 and the second transparent tube 333 are in contact with the corresponding rubber rings, which can first fix the approximate positions of the first transparent tube 323 and the second transparent tube 333 to prevent the first transparent tube 323 and the second transparent tube 333 from shaking at will, and the rubber rings can be used to protect the first transparent tube 323 and the second transparent tube 333.
[0047] See also Figure 3 In this embodiment, the three-dimensional observation system 4 includes a first telescopic straight rod 413, a second telescopic straight rod 423, an industrial CCD camera 412 and a laser 422. A first track 411 and a second track 421 are fixedly installed on the test base 1 by bolts. The first track 411 and the second track 421 are parallel and respectively face the adjacent two sides of the visualization model box 2. The first track 411 is located on the left side of the visualization model box 2 and is perpendicular to the opposite side of the visualization model box 2. The second track 421 is located at the rear of the visualization model box 2 and is parallel to the opposite side of the visualization model box 2. The first telescopic straight rod 413 is slidably connected to the first track 411. The top of the first telescopic straight rod 413 is fixedly installed with a first ball joint. The industrial CCD camera 412 and the laser 422 are fixedly installed with a first ball joint. The D camera 412 is movably connected to the first telescopic straight rod 413 through a first ball joint, the second telescopic straight rod 423 is slidably connected to the second track 421, the top of the second telescopic straight rod is fixedly installed with a second ball joint, and the laser 422 is movably connected to the second telescopic straight rod 423 through the second ball joint. Before use, the height and angle position of the industrial CCD camera 412 and the laser 422 are adjusted through the first ball joint and the second ball joint so that the shooting direction and the laser direction are kept horizontal. When in use, the industrial CCD camera 412 and the laser 422 are moved along the first track 411 and the second track 421 at the same moving speed and moving direction, so as to observe the continuous deformation inside the transparent soil during impact drilling in real time.
[0048] See also Figure 3 In this embodiment, the bottom of the first telescopic straight rod 413 and the bottom of the second telescopic straight rod 423 are fixedly connected with a slider, and the bottom of the two sliders are provided with a track groove matching the first track 411 or the second track 421, which is used for sliding connection with the first track 411 or the second track 421, thereby achieving the effect of sliding connection between the first telescopic straight rod 413 and the first track 411, and the second telescopic straight rod 423 and the second track 421, so that the industrial CCD camera 412 and the laser 422 can move synchronously relative to the visualization model box 2.
[0049] See also Figure 3In this embodiment, the shooting direction of the industrial CCD camera 412 and the laser direction of the laser 422 are perpendicular to each other, and the moving speed and moving direction along the first track 411 or the second track 421 are the same, so as to collect test data, realize the display of test results in three-dimensional form, and provide continuous deformation information inside the transparent soil body. At the same time, the accuracy of the test data is improved, and the test data is more comprehensive.
[0050] The specific usage method of this embodiment is as follows:
[0051] When in use, first install and debug the test base 1, visualization model box 2, impact drilling system, three-dimensional observation system 4, and control and analysis platform 5; then prepare the transparent soil required for the test in the visualization model box 2; when the transparent soil is prepared and the thickness reaches the test requirements, fix the visualization model box 2 in the area of the impact drilling system.
[0052] Secondly, after completing the above operations, adjust the height of the impact drill 315 through the impactor 314, and add pore solution into the first water tank 322; then adjust the height and angle position of the industrial CCD camera 412 and the laser 422, and turn on the industrial CCD camera 412 and the laser 422; then input the test setting value through the control analysis platform 5 to control the movement speed and movement direction of the first telescopic straight rod 413 and the second telescopic straight rod 423.
[0053] Then, when the operation and analysis platform 5 controls the first telescopic straight rod 413 and the second telescopic straight rod 423 to move at the same moving speed and moving direction, the first flow control valve, the second flow control valve and the impactor 314 are opened, the slurry delivery pump 321 and the slurry extraction pump 331 operate at the same flow rate, and the impact drill 315 performs impact drilling construction at the same height from the bottom of the pile hole.
[0054] Finally, the industrial CCD camera 412 continuously shoots and sends the collected information to the control and analysis station 5, which analyzes and processes the collected information; after the visual transparent soil test simulating the impact drilling construction is completed, the test data is recorded, the visual model box 2 is removed, and the transparent soil is removed.
[0055] In summary, the utility model uses transparent soil to simulate natural soil for model testing. Compared with traditional model tests, the transparent soil model test can clearly observe the deformation inside the soil body and obtain more intuitive test results; and the test data is collected by synchronously moving industrial CCD camera 412 and laser 422, so as to display the test results in three-dimensional form and provide continuous deformation information inside the transparent soil body. At the same time, the accuracy of the test data is improved and the test data is more comprehensive. Therefore, the utility model effectively overcomes various shortcomings in the prior art.
[0056] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model, and they should all be included in the scope of the claims and specification of the utility model.
Claims
1. A visual transparent soil test device for simulating impact hole construction, characterized in that: include: Test base, A visual model box, which is detachably mounted on the test base and is used to place transparent soil; An impact hole forming system, which is fixedly mounted on the test base and located above the visual model box, and is used to perform impact hole forming construction on the transparent soil in the visual model box; A three-dimensional observation system, which is slidably mounted on the test base and located on the side of the visualization model box, and is used to observe the internal deformation of the transparent soil in real time; A manipulation and analysis platform is electrically connected to the impact hole forming system and the three-dimensional observation system.
2. The visualized transparent soil test device for simulating impact hole-forming construction according to claim 1 is characterized in that: The impact hole-forming system comprises an impact device, a slurry extraction device and a slurry delivery device. The impact device, the slurry extraction device and the slurry delivery device are all fixedly installed on the test base, and the impact device is located above the visualization model box.
3. The visualized transparent soil test device for simulating impact hole-forming construction according to claim 2 is characterized in that: The impact equipment includes an impactor and an impact drill. Vertical columns are fixedly installed on both sides of the top of the test base. Fixed ends are fixedly installed on the tops of the two vertical columns. A cross bar is fixedly connected between the two fixed ends. The impactor is fixedly installed in the middle of one side of the cross bar. The impact drill is slidably installed inside the impactor. The impact drill is made of transparent acrylic material, and the outer wall of the impact drill is provided with a reflection-suppressing coating.
4. The visualized transparent soil testing device for simulating impact hole-forming construction according to claim 2 is characterized in that: The slurry delivery equipment includes a first transparent tube, a slurry delivery pump, a first flow control valve, a first connecting pipe, and a first water storage tank. The slurry delivery pump and the first water storage tank are both fixedly installed on the top of the test base. The slurry delivery pump and the first water storage tank are fixedly connected by a first connecting pipe. The slurry delivery pump is fixedly connected to the first transparent tube, and the first transparent tube is fixedly installed with a first flow control valve. The first transparent tube is used to inject mixed slurry into the pile hole impacted in the transparent soil.
5. The visualized transparent soil testing device for simulating impact hole-forming construction according to claim 4 is characterized in that: The grouting equipment includes a second transparent tube, a grouting pump, a second flow control valve, a second connecting pipe, and a second water storage tank. The grouting pump and the second water storage tank are both fixedly installed on the top of the test base. The grouting pump and the second water storage tank are fixedly connected by a second connecting pipe. The grouting pump is fixedly connected to the second transparent tube, and the second transparent tube is fixedly installed with a second flow control valve. The second transparent tube is used to extract mixed slurry from the pile hole impacted by transparent soil.
6. The visualized transparent soil testing device for simulating impact hole-forming construction according to claim 3 is characterized in that: The impact drill comprises a drill rod and drill teeth. The drill rod is slidably installed inside the impactor, and a plurality of drill teeth are fixedly installed at the lower end of the drill rod at even intervals.
7. The visualized transparent soil testing device for simulating impact hole-forming construction according to claim 5 is characterized in that: A first transparent tube groove and a second transparent tube groove are provided on the top of the visualization model box. Rubber rings are fixedly installed in the first transparent tube groove and the second transparent tube groove. The first transparent tube and the second transparent tube are in contact with the corresponding rubber rings.
8. The visualized transparent soil testing device for simulating impact hole-forming construction according to claim 1 is characterized by: Scale lines are evenly spaced on an inner wall of one side of the visualization model box.
9. The visualized transparent soil testing device for simulating impact hole-forming construction according to claim 1 is characterized in that: The three-dimensional observation system includes a first telescopic straight rod, a second telescopic straight rod, an industrial CCD camera and a laser. A first track and a second track are fixedly installed on the test base. The first track and the second track are parallel and respectively face the adjacent two sides of the visualization model box. The first telescopic straight rod is slidably connected to the first track. A first ball joint is fixedly installed on the top of the first telescopic straight rod. The industrial CCD camera is movably connected to the first telescopic straight rod through the first ball joint. The second telescopic straight rod is slidably connected to the second track. A second ball joint is fixedly installed on the top of the second telescopic straight rod. The laser is movably connected to the second telescopic straight rod through the second ball joint.
10. The visualized transparent soil test device for simulating impact hole-forming construction according to claim 9 is characterized in that: The shooting direction of the industrial CCD camera and the laser direction of the laser are perpendicular to each other, and the moving speed and moving direction along the first track or the second track are the same.