Diagonal bracing jig frame for on-site tailor-welding of steel truss girder bridge deck slab

By designing the diagonal brace tire frame, using the alignment of the positioning holes and screw holes to determine the position accuracy and the rapid positioning of the hydraulic jack, the problem of welding accuracy and efficiency of the steel truss bridge deck was solved, and a high-precision and efficient bridge deck was achieved. Assemble.

CN221891254UActive Publication Date: 2024-10-25CHINA RAILWAY GUIZHOU HIGHWAY CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420127026.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-18
Publication Date
2024-10-25
Estimated Expiration
2034-01-18

AI Technical Summary

Technical Problem

In the process of tailor welding of steel truss bridge decks, due to multi-pass tailor welding of cross beams and longitudinal beams of bridge decks with larger spans, the simple alignment connection of the tire frame is difficult to meet the assembly accuracy, resulting in large tailor welding errors, which affects subsequent Tailor welding effect of components.

Method used

A diagonal support tire frame is designed, including support columns, vertical splicing positioning plates, horizontal splicing positioning plates and diagonal support channels. The position accuracy is judged by the alignment of positioning holes and screw holes, and hydraulic jacks and positioning pins are used Quick release device enables quick positioning and adjustment.

Benefits of technology

It improves the precision and efficiency of tailor welding, ensures the accurate cross slope and longitudinal slope of the bridge deck, reduces costs, and improves construction efficiency and quality through the positioning pin quick-release device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221891254U_ABST
    Figure CN221891254U_ABST
Patent Text Reader

Abstract

The utility model provides a diagonal bracing jig frame for on-site tailor-welding of a steel truss girder bridge deck slab, which relates to the technical field of auxiliary facilities for tailor-welding of steel bridge deck slabs and structurally comprises a support column, a vertical splicing positioning plate and a horizontal splicing positioning plate positioned below the vertical splicing positioning plate are arranged on the support column, and the horizontal splicing positioning plate is positioned below the vertical splicing positioning plate. The bottom of the horizontal splicing positioning plate is connected with inclined supporting channel steel which is connected with a supporting column; a connecting plate is arranged at the end, away from the supporting column, of the vertical splicing positioning plate, and a positioning hole is formed in the connecting plate. When the device is used for field tailor-welding of the steel truss girder bridge deck slab, the tailor-welding precision of the whole bridge deck slab is guaranteed by accurately controlling the precision of each tailor-welding point, the tailor-welding efficiency and the splicing precision are greatly improved, and the accuracy of a cross slope and a longitudinal slope of the bridge deck slab is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of auxiliary facilities for welding steel bridge panels, in particular to a diagonal brace frame for on-site welding of steel truss bridge panels. Background Art

[0002] For the traditional welding method of steel truss bridge deck, if there are not many components to be welded, the traditional method can be used to align the welding points on the tire frame. However, for bridge decks with larger spans, when there are multiple cross beams and longitudinal beams to be welded, it is difficult to meet the assembly accuracy by simply aligning and connecting on the tire frame. The slightest welding error will cause a large error impact on the welding of subsequent components. Therefore, in the construction of steel truss bridge decks with more welding points, it is necessary to propose a construction method for on-site welding of steel truss bridge decks, which is based on a new diagonal brace bracket. Utility Model Content

[0003] The utility model provides an inclined bracing frame for on-site welding of steel truss bridge panels, aiming to assist in completing on-site welding construction of steel truss bridge panels.

[0004] The utility model provides the following technical solutions to achieve the above objectives:

[0005] A diagonal brace frame for on-site welding of steel truss bridge panels includes a support column, on which a vertical splicing positioning plate and a horizontal splicing positioning plate located below the vertical splicing positioning plate are arranged, the bottom of the horizontal splicing positioning plate is connected to an oblique support channel steel, and the oblique support channel steel is connected to the support column; a connecting plate is arranged at one end of the vertical splicing positioning plate away from the support column, and a positioning hole is arranged on the connecting plate.

[0006] In the aforementioned diagonal brace frame for on-site welding of steel truss bridge decks, the vertical splicing positioning plate is provided with fixing screw holes; the connecting plate is provided with fixing holes and positioning holes, and the fixing holes and the fixing screw holes are correspondingly arranged and fixedly connected by bolts.

[0007] In the aforementioned diagonal brace frame used for on-site welding of steel truss bridge decks, four fixing screw holes are provided.

[0008] In the aforementioned diagonal bracing frame for on-site welding of steel truss bridge decks, positioning screw holes are provided on the horizontal splicing positioning plate.

[0009] In the aforementioned diagonal brace frame used for on-site welding of steel truss bridge decks, four positioning screw holes are provided.

[0010] In the aforementioned diagonal brace frame for on-site welding of steel truss bridge decks, a positioning pin quick-release device is provided on the support column, and the positioning pin quick-release device includes a hydraulic jack connected to the support column, and the top seat of the hydraulic jack is connected to the positioning pin.

[0011] In the aforementioned diagonal brace frame for on-site welding of steel truss bridge decks, the top seat is connected to the positioning pins through a pin plate.

[0012] In the aforementioned diagonal bracing frame for on-site welding of steel truss bridge decks, the arrangement positions of the positioning pins correspond to the positioning holes.

[0013] Beneficial Effects

[0014] Compared with the prior art, the utility model has the following beneficial effects:

[0015] 1. The utility model is used for on-site welding of steel truss bridge decks. By accurately controlling the accuracy of each welding point, the welding accuracy of the entire bridge deck is ensured, which greatly improves the welding efficiency and assembly accuracy, and ensures that the transverse slope and longitudinal slope of the bridge deck are accurate;

[0016] 2. The utility model cleverly utilizes the bolt holes on the secondary cross beam and longitudinal beam of the bridge deck. Only bolt holes are added to the diagonal support bracket. The accuracy of the installation and welding positions of the secondary cross beam and longitudinal beam can be judged by whether the bolt holes can be smoothly aligned. The cost of the additional measures of this method is extremely low. In addition, temporary bolts can be passed through the positioning holes and positioning screw holes of the connecting plate to temporarily fix the components during welding to prevent displacement during welding.

[0017] 3. The utility model has strong practicability, improves the assembly quality of steel trusses, and speeds up the welding construction efficiency of components.

[0018] 4. The utility model also proposes a positioning pin quick-release device which can realize the rapid installation and removal of the pins horizontally, thereby improving the assembly and positioning efficiency; vertically, it can also be used to quickly adjust the height or inclination of the bridge deck. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below only relate to some embodiments of the utility model, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor.

[0020] Figure 1 It is a structural schematic diagram of the diagonal brace bracket of the utility model;

[0021] Figure 2 It is a structural schematic diagram of a horizontally spliced ​​positioning plate;

[0022] Figure 3 It is a schematic diagram of the welding unit structure of the panel and the U-rib;

[0023] Figure 4 Schematic diagram of the work during the beam welding;

[0024] Figure 5 yes Figure 4 Section 1-1 (longitudinal beam) is a schematic diagram of the work during welding;

[0025] Figure 6 This is a schematic diagram of the bridge deck top plate being installed to the "frame";

[0026] Figure 7 It is a schematic diagram of the hydraulic jack and its connection structure.

[0027] Figure markings: 1-diagonal support bracket, 2-vertical tire frame, 3-secondary cross beam one, 4-secondary cross beam two, 5-secondary cross beam three, 6-longitudinal beam, 7-secondary cross beam four, 8-secondary cross beam five, 9-connecting plate, 10-panel, 11-U rib, 12-vertical splicing positioning plate, 13-diagonal support channel steel, 14-horizontal splicing positioning plate, 15-support column, 16-hydraulic jack, 17-top seat, 18-positioning pin, 19-pin plate, 20-parts to be positioned. DETAILED DESCRIPTION

[0028] In order to enable those skilled in the art to better understand the solution of the present invention, the technical solution in the embodiment of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiment of the present invention.

[0029] It should be noted that in the present invention: the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices; the orientations or positional relationships indicated by the terms "upper", "lower", "left", "right", "front", "rear", "top", "bottom", "inside", "outside", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like are based on the orientations or positional relationships shown in the accompanying drawings. These terms are mainly for better describing the present invention and its embodiments, and are not used to limit the indicated devices, elements or components to have specific orientations, or to be constructed and operated in specific orientations; the terms "installed", "set", "provided with", "connected", "connected", "sleeved" and the like should be understood in a broad sense; for example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements or components. In addition, some terms may be used to express other meanings in addition to indicating a direction or position relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those skilled in the art, the specific meanings of these terms in this utility model can be understood according to specific circumstances.

[0030] Example 1. A diagonal brace frame for on-site welding of steel truss bridge decks, with a structure referenced to Figure 1 As shown, it includes a support column 15, on which a vertical splicing positioning plate 12 and a horizontal splicing positioning plate 14 located below the vertical splicing positioning plate 12 are arranged, the bottom of the horizontal splicing positioning plate 14 is connected to an oblique support channel steel 13, and the oblique support channel steel 13 is connected to the support column 15; a connecting plate 9 is arranged at one end of the vertical splicing positioning plate 12 away from the support column 15, and a positioning hole is arranged on the connecting plate 9.

[0031] The vertical splicing positioning plate 12 is provided with fixing screw holes; the connecting plate 9 is provided with fixing holes and positioning holes, the fixing holes and the fixing screw holes are arranged correspondingly and fixedly connected by bolts; four fixing screw holes are arranged.

[0032] The horizontal splicing positioning plate 14 is provided with positioning screw holes; four positioning screw holes are provided.

[0033] This diagonal brace bracket is used in the construction of on-site welding of steel truss bridge panels. The steel truss bridge panels are composed of U ribs, longitudinal beams, secondary beams, panels, etc. The height, screw holes, positions of components such as the vertical splicing positioning plate 12 and the horizontal splicing positioning plate 14 of this diagonal brace bracket correspond to the dimensions of the secondary beams and other components of the bridge panel to be processed. The tire frame is made of 28# I-beams, which provides good support for the assembly of the upper bridge panel. It should be noted that: currently the secondary beams all have bolt holes. This diagonal brace bracket can directly use these bolt holes to correspond to the positioning holes on the connecting plate 9 and the positioning screw holes on the horizontal splicing positioning plate 14 for temporary fixing and positioning through temporary bolts, which greatly saves costs; if there is an exception such as no bolt holes in actual circumstances, it is only necessary to open holes on the secondary beams for positioning to meet the use conditions of this diagonal brace bracket.

[0034] This diagonal brace bracket specifically positions and fixes the secondary beam from two directions through the vertical splicing positioning plate 12 and the horizontal splicing positioning plate 14, ensuring the accurate position of the secondary beam during welding; the vertical splicing positioning plate 12 is further positioned with the secondary beam through the connecting plate 9, and the connecting plate 9 can be used in multiple specifications, so that the appropriate connecting plate 9 can be selected for use according to the positioning requirements of the secondary beam. The vertical splicing positioning plate 12 improves the positioning adaptability through the connecting plate 9; the diagonal support channel steel 13 improves the bearing capacity of the horizontal splicing positioning plate 14.

[0035] Through the above technology, the diagonal brace bracket can be used for supporting and positioning the on-site welding of steel truss bridge decks, and can position the bridge deck in four directions: front, back, left and right, to ensure the accuracy of the longitudinal and transverse slopes of the bridge deck.

[0036] The above-mentioned diagonal brace bracket is implemented to form a new construction method for on-site welding of steel truss bridge decks. Figure 4 The bridge deck shown is relatively large, with a horizontal length of 28 meters. The bridge deck is composed of U-ribs, longitudinal beams, secondary beams, and panels. The steps for installing the bridge deck are as follows:

[0037] ① Such as Figure 3 As shown in the figure, the U-ribs, panels and other components are transported to the assembly site and welded on the ground to form small units of the bridge deck top plate, such as Figure 3 As shown;

[0038] ② Place the secondary cross beam 1 3, secondary cross beam 2 4, secondary cross beam 3 5, and longitudinal beam 6 on the diagonal support bracket 1 and the vertical tire frame 2 in sequence, use the diagonal support bracket to position, and the vertical tire frame 2 to support. After accurate positioning, prepare for welding to form a "skeleton", such as Figure 4-5 As shown;

[0039] ③ Install the multiple bridge deck top plate small units assembled in step ① on the skeleton in step ② to form a complete bridge deck, such as Figure 6 As shown;

[0040] ④The bridge deck is hoisted into place.

[0041] Since there are 24 welding points on the above bridge deck, the installation is difficult. In order to ensure the installation accuracy of the entire bridge deck, the transverse slope and the longitudinal slope are accurate, the installation accuracy requirements for each welding point are extremely high. Once a large error occurs in a welding point, it will affect the overall bridge deck line shape and the installation of subsequent welding points. To ensure the installation accuracy, the diagonal brace bracket is temporarily positioned and installed using positioning holes and positioning screw holes in step ② to ensure the accuracy of the installation position of the secondary crossbeam and the longitudinal beam, thereby ensuring the accuracy of the welding of the entire bridge deck. The way to ensure the installation accuracy of the diagonal brace bracket is to take the splicing of secondary crossbeam 1 3 and secondary crossbeam 2 4 as an example. First, the diagonal brace bracket is set according to the standard position, and then the vertical splicing positioning plate 12 is matched with a A connecting plate 9 is used, and the connecting plate 9 is provided with 4 fixing holes and 4 positioning holes, which are respectively connected with the vertical splicing positioning plate 12 and the secondary beam 3; after the vertical position is set accurately, the horizontal position is determined, and the horizontal bolt holes at the bottom of the secondary beam 3 are aligned with the positioning screw holes on the horizontal splicing positioning plate 14, and then temporary bolts are used to connect to determine the horizontal position of the secondary beam 3 during welding; the secondary beam is fixed by temporary bolt connection, and can also be fixed firmly with rivets in combination with conventional technology, so as to fix the vertical and horizontal positions of the secondary beam 3 to ensure accuracy during welding; the position of the secondary beam 4 is fixed by the same method to ensure the accurate position of the two components to be welded.

[0042] Embodiment 2. A diagonal brace for on-site welding of steel truss bridge decks. The structure of this embodiment is similar to that of embodiment 1, except that: a positioning pin quick release device is provided on the support column 15 of this embodiment. The positioning pin quick release device includes a hydraulic jack 16 connected to the support column 15. The top seat 17 of the hydraulic jack 16 is connected to the positioning pin 18. The structure is as follows: Figure 7 shown.

[0043] The top seat 17 is connected to the positioning pins 18 through the pin plate 19. The positioning pins 18 on the pin plate 19 match the holes of the beam to be positioned. The arrangement position of the positioning pins 18 also corresponds to the positioning hole setting.

[0044] A positioning pin quick-release device is provided on the diagonal support bracket, which can realize quick assembly and disassembly of the positioning pin 18 by hydraulically controlling the hydraulic jack 16, thereby improving the assembly and positioning efficiency.

[0045] Example 3. A diagonal brace for on-site welding of steel truss bridge decks. The structure of this example is similar to that of Example 2, except that Figure 7Structure, the positioning pin quick-release device of this embodiment is vertically arranged on the support column 15, and the positioning pin 18 is pressed upward against the bottom of the bridge deck. When the linear height of the bridge deck is not correct, the hydraulic jack 16 is hydraulically controlled to push out or retract the positioning pin 18 so that the linear height of the bridge deck meets the requirements.

[0046] Obviously, the above is only a part of the embodiments of the utility model, not all of the embodiments. The above embodiments are not used to limit the utility model. For those skilled in the art, the utility model can have various changes and variations. Any combination, modification, equivalent replacement, improvement and all other embodiments that can be made by ordinary technicians in the field within the spirit and principle of the utility model should be within the protection scope of the utility model.

Claims

1. A diagonal brace for on-site welding of steel truss bridge decks, characterized by: The invention comprises a support column (15), wherein a vertical splicing positioning plate (12) and a horizontal splicing positioning plate (14) located below the vertical splicing positioning plate (12) are arranged on the support column (15), the bottom of the horizontal splicing positioning plate (14) is connected to an oblique support channel steel (13), and the oblique support channel steel (13) is connected to the support column (15); a connecting plate (9) is arranged at one end of the vertical splicing positioning plate (12) away from the support column (15), and a positioning hole is arranged on the connecting plate (9).

2. The diagonal brace frame for on-site welding of steel truss bridge decks according to claim 1 is characterized in that: The vertical splicing positioning plate (12) is provided with a fixing screw hole; the connecting plate (9) is provided with a fixing hole and a positioning hole, and the fixing hole and the fixing screw hole are arranged correspondingly and fixedly connected by bolts.

3. The diagonal brace for on-site welding of steel truss bridge decks according to claim 2 is characterized in that: Four fixing screw holes are provided.

4. The diagonal brace for on-site welding of steel truss bridge decks according to claim 1 is characterized in that: The horizontal splicing positioning plate (14) is provided with positioning screw holes.

5. The diagonal brace frame for on-site welding of steel truss bridge decks according to claim 4 is characterized in that: Four positioning screw holes are provided.

6. The diagonal brace for on-site welding of steel truss bridge decks according to claim 1 is characterized in that: The support column (15) is provided with a positioning pin quick-release device, which comprises a hydraulic jack (16) connected to the support column (15), and a top seat (17) of the hydraulic jack (16) is connected to the positioning pin (18).

7. The diagonal brace for on-site welding of steel truss bridge decks according to claim 6 is characterized in that: The top seat (17) is connected to the positioning pin (18) via a pin plate (19).

8. The diagonal brace for on-site welding of steel truss bridge decks according to claim 7 is characterized in that: The arrangement position of the positioning pin (18) corresponds to the setting of the positioning hole.