Dismantling and building integrated construction method for dismantling old rigid frame bridge in-situ newly-built suspension bridge

By utilizing the old bridge deck as a pilot cable crossing platform during the demolition of the old rigid frame bridge, and combining cable-mounted cranes and crawler cranes for cross-operation, the demolition of the old rigid frame bridge and the construction of a new suspension bridge were carried out simultaneously. This solved the problems of long construction period, high cost and poor safety, and achieved rapid, safe and economical bridge reconstruction.

CN118911023AActive Publication Date: 2024-11-08ROAD & BRIDGE INT CO LTD

Patent Information

Application Number
CN202411131994.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-11-08
Estimated Expiration
2044-08-19

AI Technical Summary

Technical Problem

Existing technologies for demolishing old rigid frame bridges result in long construction periods, disruption to navigation, high costs, and difficulty in ensuring safety.

Method used

The construction method of demolition and construction is adopted. The old bridge deck is used as a pilot cable crossing platform. Cable cranes and crawler cranes are used for cross-operation. The new suspension bridge is built while it is being demolished. The temporary support of the old bridge is used to set up sliding support as a transfer platform for the steel box girder segments of the new suspension bridge.

Benefits of technology

It shortened the construction period, reduced the impact on navigation, lowered construction costs, and improved construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911023A_ABST
    Figure CN118911023A_ABST
Patent Text Reader

Abstract

The invention relates to a dismantling and building integrated construction method for dismantling an old rigid frame bridge in-situ newly-built suspension bridge, which comprises the following steps of: firstly dismantling an old bridge, constructing an anchorage, a main tower and a side span of the newly-built suspension bridge, installing a suspension bridge main cable and a cable loading crane, dismantling a mid-span closure section, the side span and a mid-span main beam cantilever of the old bridge by using the cable loading crane, and hoisting a newly-built suspension bridge steel box beam. And meanwhile, a side span closure section, a side span cast-in-place section and a side pier of the old bridge are sequentially dismantled through a crawler crane. The bridge dismantling process and the bridge building process are in cross operation and synchronous construction, and the construction period can be shortened; an old bridge deck is used as a new suspension bridge pilot cable river-crossing traction platform, navigation is not affected, and cost is saved; the cable crane for newly building the suspension bridge is used for dismantling the old bridge, and the construction efficiency and safety are high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge construction, and relates to an integrated demolition and construction method for demolishing an old rigid frame bridge and building a new suspension bridge in situ. Background Art

[0002] A rigid frame bridge is a type of bridge that uses piers to support the main beam. Due to its low construction difficulty, convenient maintenance, and low cost, this type of bridge was mostly used in early cross-river bridges. However, after a certain number of years of use, some old cross-river rigid frame bridges have developed defects that can no longer meet the requirements of safe operation through maintenance. Some old bridges cannot meet the current navigation needs due to the mid-span and clear height under the bridge, and all need to be demolished and rebuilt. Suspension bridges have the advantages of large mid-span, strong bearing capacity, long service life, and convenient maintenance, and are the preferred type of bridge for bridge reconstruction.

[0003] At present, the conventional construction sequence for the demolition and reconstruction of old bridges is: demolish the old bridge - clear the site - build a new bridge, and the construction period is relatively long. For old concrete rigid frame bridges, bridge cranes or floating cranes are often used for demolition. The bridge crane demolition method is to demolish each section in reverse order according to the construction sequence when the bridge was built. Not only is the demolition speed slow, but the strength of the old bridge is not as strong as when the bridge was built. After the closing section is released, the T-structure cantilever section is at risk of overturning and breaking; the floating crane demolition method requires a stable upward lifting force to be applied to the T-structure cantilever section in advance to prevent the bridge section from falling out of control at the moment of cutting off. However, in rivers with turbulent water flow, it is difficult to control the stability of the floating crane, and the rental cost of the floating crane is high. In addition, the floating crane needs to occupy the waterway for a long time, which has a great impact on normal navigation. Summary of the invention

[0004] The purpose of the present invention is to provide an integrated demolition and construction method for demolishing an old rigid frame bridge and building a new suspension bridge in situ, in order to shorten the construction period, reduce the time occupied by the waterway, ensure construction safety and reduce construction costs.

[0005] The technical solution of the present invention is as follows:

[0006] A method for integrated demolition and construction of a new suspension bridge in situ by demolishing an old rigid frame bridge, wherein the river-spanning portion of the old rigid frame bridge is designed with a side span and a middle span, and approach bridges are designed on both sides, and the river-spanning portion of the new suspension bridge is designed as a middle span, and both sides are designed as side spans, characterized in that it comprises the following steps;

[0007] (1) Remove the approach bridge of the old bridge; build construction trestle bridges from both banks to the river, with the trestle bridges on each bank being built along the bridge direction to the outside of the cast-in-place section of the side span of the old bridge; build temporary supports under the cast-in-place section of the side span of the old bridge, and the temporary supports are used to temporarily support the cast-in-place section of the side span of the old bridge when the joint section of the side span of the old bridge is removed;

[0008] (2) Construct the anchorage, main tower and side span of the new suspension bridge at the location of the old bridge approach, and install the main cables of the suspension bridge; install two cable-mounted cranes on the two main cables of the new suspension bridge;

[0009] (3) Use a cable-mounted crane to dismantle the closure section of the middle span of the old bridge and lower it to a transport ship for transportation; at the same time, a crawler crane drives from the shore to the trestle and uses the crawler crane to dismantle the closure section of the side span and the cast-in-place section of the side span of the old bridge in sequence;

[0010] (4) Using a cable-mounted crane to symmetrically dismantle the side spans and the cantilever of the middle span of the old bridge, and using a crawler crane to dismantle the side piers of the old bridge; after the side piers of the old bridge are dismantled, the temporary support is used as a foundation to erect a sliding support, and the sliding support serves as a transportation platform for the steel box girder segments of the suspension bridge near the main tower area;

[0011] (5) Install suspension bridge slings on the main cables of the newly built suspension bridge;

[0012] The beam transport ship transports the steel box beam segment near the main tower area of ​​the suspension bridge to the bottom of the bridge, and the cable crane lifts the steel box beam on the ship and moves it toward the main tower. When it is a certain distance away from the main tower, the cable crane cannot lift the steel box beam and walk on the main cable in this area because the main cable has a large inclination angle near the tower area. The steel box beam is swung to the sliding bracket by the swinging method.

[0013] Slide the steel box girder on the sliding bracket to below the installation position, run the cable-mounted crane unloaded to above the steel box girder installation position, lift the steel box girder on the sliding bracket to the installation height and connect it with the sling; install the steel box girders of the two bridge tower areas symmetrically;

[0014] While installing the steel box girder in the tower area, the floating crane was used to remove the 0# block, piers and underwater caps in the middle span of the old bridge;

[0015] (6) After the steel box girder segments in the bridge tower area are installed, the sliding brackets are removed, and the steel box girders are then installed symmetrically from the middle of the span to both sides using a cable-mounted crane until the steel box girders in the middle span of the suspension bridge are closed, completing the demolition of the old rigid frame bridge and the construction of the new suspension bridge.

[0016] Furthermore, in step (2) of the above-mentioned integrated construction method for demolishing an old rigid frame bridge and building a new suspension bridge in its place, during the installation of the main cable of the suspension bridge, the side span and the middle span of the old bridge are used as a platform for the guide cable to cross the river, and a trolley is used on the old bridge to pull the guide cable from one bank to the other bank.

[0017] Furthermore, in step (3) of the above-mentioned integrated construction method for demolishing an old rigid frame bridge and building a new suspension bridge in its place, before demolishing the middle span and side span closure sections of the old bridge, temporary cables are first connected between the main beam of the old bridge and the main cables of the suspension bridge to prevent the cantilever section of the main beam of the old bridge from being too long and causing it to overturn or break after the closure section of the old bridge is removed.

[0018] The present invention has the following advantages:

[0019] 1. The process of dismantling and building the bridge is cross-operation, with dismantling and building at the same time. Some processes can be carried out simultaneously, breaking the conventional construction mode of dismantling first and then building, which is conducive to shortening the construction period and reducing the impact on navigation under the bridge;

[0020] 2. The deck of the old bridge is used as the traction platform for the guide cable to cross the river for the main cable of the new suspension bridge. Compared with the conventional suspension bridge construction, the guide cable needs to be towed across the river by ships or drones, which does not affect navigation and saves costs;

[0021] 3. Using the cable-mounted crane used in the construction of the new suspension bridge to dismantle the old bridge further reduces costs and increases the safety of bridge dismantling;

[0022] 4. Use the dismantled brackets of the cast-in-place section of the side span of the old bridge as the foundation to build a sliding bracket as the swing and sliding platform for the steel box girder segments in the tower area of ​​the new suspension bridge, saving the amount of steel used in the temporary structure of the bridge;

[0023] 5. The present invention is not limited to the integrated demolition and reconstruction of old rigid frame bridges, but is also applicable to the demolition and reconstruction of old continuous beam bridges, steel truss bridges, simply supported beam bridges and top-supported arch bridges and suspension bridges. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a construction flow chart of the present invention;

[0025] Figure 2 It is a side view structural diagram of an old rigid frame bridge to be demolished;

[0026] Figure 3 It is a schematic diagram of the state of dismantling the approach bridge of the old bridge and erecting the construction trestle and temporary support;

[0027] Figure 4 It is a schematic diagram of the status of the side span, main tower, main cable and cable-mounted crane of the newly built suspension bridge after construction;

[0028] Figure 5 It is a schematic diagram of the state of the cable-mounted crane dismantling the middle span closure section of the old bridge, and the crawler crane dismantling the side span closure section and cast-in-place section of the old bridge;

[0029] Figure 6 This is a schematic diagram of the state where the cable-mounted crane is dismantling the side span and the cantilever of the middle span of the old bridge, while the crawler crane is dismantling the side span and piers and setting up the sliding support;

[0030] Figure 7 It is a schematic diagram of the state in which the cable-mounted crane lifts and installs the steel box girder near the main tower area of ​​the suspension bridge;

[0031] Figure 8 Schematic diagram of the cable-mounted crane hoisting a mid-span steel box girder segment;

[0032] Fig. 9 This is a schematic diagram of the state of a newly built suspension bridge when it is closed. DETAILED DESCRIPTION

[0033] Figure 1 The construction method of the present invention is specifically described below through a specific embodiment.

[0034] Figure 2 The figure shows a side view structure of an old rigid-frame bridge across a river, the river-spanning portion of which is designed with a middle span 101 and a side span 102, and approach bridges 103 are designed on both sides. It is now necessary to demolish the old rigid-frame bridge and build a new suspension bridge on the original site. The river-spanning portion of the new suspension bridge is designed as a middle span, and both sides are designed as side spans. If the old bridge is demolished first and then a new bridge is built according to the conventional method, not only will the construction period be long, the navigation under the bridge will be affected for a long time, and the safety of the bridge demolition construction will not be easy to guarantee. Therefore, the integrated demolition and construction construction method of the present invention is proposed, which specifically includes the following steps;

[0035] (1) Figure 3 As shown, the approach bridge of the old bridge is first dismantled, and at the same time, construction trestle bridges 1 are respectively built from both banks to the river, and the trestle bridges on each bank are respectively built along the bridge direction to the outside of the cast-in-place section of the side span 102 of the old bridge; a temporary support 2 is built under the cast-in-place section of the side span of the old bridge, and the temporary support 2 is used to temporarily support the cast-in-place section of the side span of the old bridge when the joint section of the side span of the old bridge is dismantled, so as to prevent the cantilever of the cast-in-place section of the side span of the old bridge from becoming unstable and overturning.

[0036] (2) Figure 4 As shown, after the approach bridge of the old bridge is dismantled, the anchorage 3, main tower 4 and side span 5 of the new suspension bridge are constructed at the location of the approach bridge of the old bridge, and the main cable 6 of the suspension bridge is installed; two cable-mounted cranes 7 are respectively installed on the two main cables 6 of the new suspension bridge.

[0037] Usually, during the installation of the main cable of a suspension bridge, due to the heavy weight of the main cable, a pilot cable needs to be set up between the two banks first, and the catwalk and main cable are pulled up using the pilot cable, and the main cable is shaped, and locking clamps and slings are installed on the catwalk. When setting up the pilot cable, one end of the pilot cable is first connected to a winch on one bank, and the other end is sent over the top of the tower to the other bank, where it passes over the top of the tower and is connected to the winch on the other bank. This process is usually called crossing the river with the pilot cable.

[0038] Crossing the river with the pilot cable is an important process in the installation of the main cable. Currently, the pilot cable crossing the river is usually towed by a tugboat, or towed by a drone, helicopter, or launched by a rocket. Towing by a tugboat requires a temporary blockade of the waterway, which will affect navigation, while other methods are more expensive.

[0039] During the installation and construction of the main cable of the suspension bridge of the present invention, the side span 102 and the middle span 101 of the old bridge are not dismantled first, and the old bridge deck can be used as a platform for the guide cable to cross the river. A trolley is used on the old bridge to pull the guide cable across the river, which can avoid affecting navigation and save costs.

[0040] (3) Figure 5 As shown, after the main cable 6 and the cable-mounted crane 7 are installed, the cable-mounted crane 7 is used to dismantle the closure section of the middle span of the old bridge and lower it to the transport ship for transportation; at the same time, the crawler crane 8 travels from the shore to the pier, and the crawler crane 8 is used to dismantle the closure section of the side span and the cast-in-place section of the side span of the old bridge in turn.

[0041] After the middle span and side span closure sections of the old bridge are removed, cantilevers will be formed at both ends of the main beam. Since the stress-bearing performance of the concrete structure of the old bridge is lower than when the bridge was built, its cantilever is at risk of breaking or overturning. In order to avoid the above problems, the present invention can connect temporary cables 9 between the main beams of the side span 102 and the middle span 101 of the old bridge and the main cable 6 of the suspension bridge before removing the middle span and side span closure sections of the old bridge, so as to prevent the cantilever section of the main beam of the old bridge from being too long and overturning or breaking after the closure section of the old bridge is removed.

[0042] (4) Figure 6 As shown, after the main side span joint section of the old bridge is removed, the side span 102 and the cantilever of the middle span 101 of the old bridge are symmetrically removed by using a cable-mounted crane 7, and the removal is carried out in reverse order according to the pouring sequence of the concrete beam segments during the construction of the old bridge.

[0043] The lifting capacity of the cable-mounted crane is designed to meet the weight of the steel box girder segment of the suspension bridge. The weight of a steel box girder segment is generally 2-3 times the weight of a concrete beam segment. Therefore, when dismantling the cantilever of an old bridge, the cable-mounted crane can dismantle 2-3 concrete segments at a time, which is more efficient than the existing bridge crane's section-by-section dismantling.

[0044] While dismantling the cantilever of the middle span main beam on the side of the old bridge, the crawler crane 8 is used to dismantle the side piers of the old bridge; after the side piers of the old bridge are dismantled, the temporary support 2 is used as a foundation to set up a sliding support 10, on which a sliding track or a sliding plate is arranged. The sliding support is used as a transfer platform for the steel box girder segments of the suspension bridge close to the main tower area when the steel box girder of the subsequent suspension bridge is installed.

[0045] (5) Figure 7 As shown, the suspension bridge sling 11 is installed on the main cable of the newly built suspension bridge;

[0046] The beam transport ship transports the steel box girder segment 12 of the suspension bridge near the main tower area to under the bridge, and the cable-mounted crane 7 lifts the steel box girder on the ship and moves it toward the main tower. When it is a certain distance away from the main tower, the cable crane cannot lift the steel box girder and walk on the main cable in this area due to the large inclination angle of the main cable near the tower area. Therefore, the swinging method is used to swing the steel box girder segment 12 onto the sliding bracket 10 first; the steel box girder is slid to below the installation position on the sliding bracket, and the cable-mounted crane 7 runs unloaded to above the steel box girder installation position, lifts the steel box girder on the sliding bracket to the installation height and connects it with the sling; during the specific construction, the steel box girders in the two bridge tower areas should be installed symmetrically.

[0047] The swinging method is a common method for installing steel box girders of suspension bridges. Usually, during the swinging construction, it is necessary to set a sliding bracket under the steel box girder in the tower area. When the cable-mounted crane lifts the steel box girder to a certain distance from the main tower, the steel box girder is connected by a cable or an extended sling 13, and then the cable-mounted crane releases the steel box girder. The steel box girder is lifted by the extended sling 13 and pulled onto the sliding bracket. After the steel box girder is slid to the bottom of the installation position on the sliding bracket, the cable crane moves unloaded to the top of the steel box girder to lift and install the steel box girder. The present invention uses the temporary bracket of the cast-in-place section of the side span of the old bridge to set up the sliding bracket, which improves the reuse rate of the temporary bracket and can save a certain amount of cost.

[0048] While installing the steel box girder in the tower area, the 0# block, piers and underwater abutments of the middle span of the old bridge were removed using floating crane 14.

[0049] (6) Figure 8 As shown, after the steel box girder segment of the bridge tower area is installed, the sliding bracket is removed, and then the cable-mounted crane 7 is used to symmetrically install the steel box girder segment 12 from the middle of the span to both sides, while the floating crane 14 continues to remove the remaining 0# blocks, piers and underwater caps of the old bridge;

[0050] like Fig. 9 As shown, the cable-mounted crane 7 hoists the joint section 12 of the steel box girder of the suspension bridge, completing the demolition of the old rigid frame bridge and the construction of the new suspension bridge.

Claims

1. A method for integrated demolition and construction of a new suspension bridge in situ by demolishing an old rigid frame bridge. The river-spanning portion of the old rigid frame bridge is designed with side spans and middle spans, and approach bridges are designed on both sides. The river-spanning portion of the new suspension bridge is designed with a middle span, and both sides are designed with side spans. It is characterized in that The steps include: (1) Remove the approach bridge of the old bridge; build construction trestle bridges from both banks to the river, with the trestle bridges on each bank being built along the bridge direction to the outside of the cast-in-place section of the side span of the old bridge; build temporary supports under the cast-in-place section of the side span of the old bridge, and the temporary supports are used to temporarily support the cast-in-place section of the side span of the old bridge when the joint section of the side span of the old bridge is removed; (2) Construct the anchorage, main tower and side span of the new suspension bridge at the location of the old bridge approach, and install the main cables of the suspension bridge; install two cable-mounted cranes on the two main cables of the new suspension bridge; (3) Use a cable-mounted crane to dismantle the closure section of the middle span of the old bridge and lower it to a transport ship for transportation; at the same time, a crawler crane drives from the shore to the trestle and uses the crawler crane to dismantle the closure section of the side span and the cast-in-place section of the side span of the old bridge in sequence; (4) Using a cable-mounted crane to symmetrically dismantle the side spans and the cantilever of the middle span of the old bridge, and using a crawler crane to dismantle the side piers of the old bridge; after the side piers of the old bridge are dismantled, the temporary support is used as a foundation to erect a sliding support, and the sliding support serves as a transportation platform for the steel box girder segments of the suspension bridge near the main tower area; (5) Install suspension bridge slings on the main cables of the newly built suspension bridge; The beam transport ship transports the steel box beam segment near the main tower area of ​​the suspension bridge to the bottom of the bridge, and the cable crane lifts the steel box beam on the ship and moves it toward the main tower. When it is a certain distance away from the main tower, the cable crane cannot lift the steel box beam and walk on the main cable in this area because the main cable has a large inclination angle near the tower area. The steel box beam is swung to the sliding bracket by the swinging method. Slide the steel box girder on the sliding bracket to below the installation position, run the cable-mounted crane unloaded to above the steel box girder installation position, lift the steel box girder on the sliding bracket to the installation height and connect it with the sling; install the steel box girders of the two bridge tower areas symmetrically; While installing the steel box girder in the tower area, the floating crane was used to remove the 0# block, piers and underwater caps in the middle span of the old bridge; (6) After the steel box girder segments in the bridge tower area are installed, the sliding brackets are removed, and the steel box girders are then installed symmetrically from the middle of the span to both sides using a cable-mounted crane until the steel box girders in the middle span of the suspension bridge are closed, completing the demolition of the old rigid frame bridge and the construction of the new suspension bridge.

2. The integrated construction method for demolishing an old rigid frame bridge and building a new suspension bridge in situ according to claim 1, Features: In step (2), during the installation of the main cable of the suspension bridge, the side span and middle span deck of the old bridge are used as a platform for the guide cable to cross the river, and a trolley is used on the old bridge to pull the guide cable from one bank to the other bank.

3. The integrated construction method for demolishing an old rigid frame bridge and building a new suspension bridge in situ according to claim 1, Features: In the step (3), before removing the middle span and side span closure sections of the old bridge, temporary cables are first connected between the main beam of the old bridge and the main cables of the suspension bridge to prevent the main beam of the old bridge from overturning or breaking due to the excessive cantilever section after the closure section of the old bridge is removed.

Citation Information

Patent Citations

  • A method for removing an upper structure of an overwater thin-cable system cable-stayed bridge

    CN109695206A

  • Construction method for replacing bridge girder

    JP2009052305A

  • Removal method of existent bridge and renewal method of existent bridge

    JP2014066007A

  • Method for mounting self-anchored suspension bridge

    WO2018133045A1

Cited By

  • A cantilever construction method for long-span bridges based on Internet of Things monitoring

    CN119195016B

  • Construction method of old bridge in-situ newly-built arch bridge

    CN121428924A

  • Dismounting and building construction method for reconstructing rigid bridge into steel truss girder bridge

    CN121675337A