Large vertical pump hoisting and measuring lifting appliance
By designing a large vertical pump hoisting and measuring spreader, the lifting frame, measuring components and lifting rings are used to ensure the smooth lifting and measurement of the pump body. This solves the problems of tilt friction and support slippage during the hoisting process, simplifies rotor measurement, and improves maintenance efficiency.
Patent Information
- Application Number
- CN202420211046.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-29
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2034-01-29
AI Technical Summary
Large vertical pumps tend to tilt during the hoisting process, causing friction and collision. When placed horizontally, they require multiple adjustments and supports, which poses a risk of support slippage. Moreover, measurement and adjustment require the cooperation of the factory's driving force, which delays the maintenance schedule.
A large vertical pump hoisting measurement spreader is designed, including a lifting frame, a measuring component and a lifting ring. The connecting rod and rotating sleeve ensure that the pump body is upright when it is lifted vertically. The lifting ring is parallel to the pump body flange to ensure stable horizontal placement. The measuring component records the total movement and lift of the rotor without the need for factory driving cooperation.
It achieves smooth operation of the pump body during the hoisting process, avoids the risk of friction and support slippage, simplifies the rotor measurement and adjustment process, and improves maintenance efficiency.
Smart Images

Figure CN221894525U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of large-scale vertical pump hoisting, in particular to a large-scale vertical pump hoisting and measuring hoisting device. Background Art
[0002] The pump is controlled by the prime mover and drives the medium to move. It is an energy conversion device that converts the energy output by the prime mover into the pressure energy of the medium. When the large vertical pumps in nuclear power plants are being overhauled, the vertical pumps need to be hoisted in and out of the pump pit and flipped between the vertical and horizontal states.
[0003] When a large vertical pump is vertically hoisted, the pump body is tilted because the line connecting the hoisting points of the pump body does not pass through the rotor axis. Therefore, when hoisting in or out of the pump pit, it will rub and collide with the circumferential surface of the pump pit cylinder.
[0004] Large vertical pumps need to be placed horizontally during maintenance and transportation. At this time, the outlet flange of the pump body needs to be used as the support surface. However, there is a certain angle between the hanging point connection line of the vertical pump and the outlet flange, which requires multiple adjustments when placed horizontally: by landing multiple times and changing the position of the hanging point, the angle between the pump body outlet flange and the ground is gradually adjusted, and finally the condensate pump outlet flange is placed horizontally as the support surface. In addition, each time the vertical pump is landed, there will be a certain angle between the outlet flange surface of the vertical pump and the ground, resulting in the risk of support slippage. After the support slips, it will cause impact on the crane and there is a risk of injury to maintenance personnel. At the same time, the workload of the plant crane is large. The measurement and adjustment of the total amount of rotor leakage and lifting during the disassembly process require the cooperation of the plant crane. The coordination and waiting of the crane will delay the maintenance period of the vertical pump.
[0005] Therefore, there is an urgent need for large vertical pump hoisting and measuring slings to solve the above problems. Utility Model Content
[0006] The purpose of the utility model is to provide a large vertical pump hoisting measurement hoist to ensure that the large vertical pump is in a vertical state during vertical hoisting to avoid friction and collision with the pump barrel; to ensure that the pump body can be placed stably during horizontal hoisting without multiple ground supports and adjustments, thereby avoiding the risk of injury caused by support slippage; at the same time, the total leakage and lifting amount of the rotor can be measured without the cooperation of the factory crane.
[0007] In order to solve the above problems existing in the prior art, the utility model adopts the following technical solutions:
[0008] Large vertical pump hoisting and measuring sling, including:
[0009] A lifting frame, the bottom of which is connected to the pump body;
[0010] A measuring assembly, the measuring assembly comprising a connecting rod, a rotating sleeve and a measuring gauge, the measuring gauge being mounted on the rotor, the connecting rod being slidably arranged through the lifting frame and being connected to the rotor, the central axis of the connecting rod being coincident with the central axis of the lifting frame, the rotating sleeve being sleeved on the connecting rod, the rotating sleeve being able to drive the connecting rod and the rotor to rise and fall in a vertical direction, and the measuring gauge being used to measure the total amount of leakage and the amount of lifting of the rotor;
[0011] A lifting ring is arranged on the top of the lifting frame, there are two lifting rings, the two lifting rings are respectively located on both sides of the connecting rod, and the center line of the lifting holes of the two lifting rings is parallel to the flange surface of the pump body outlet.
[0012] Preferably, a center line connecting the lifting holes of the two lifting rings passes through the central axis of the lifting frame.
[0013] Preferably, the lifting frame includes a connecting plate, a ring plate and a plurality of rib plates, the connecting plate is located above the ring plate, the rib plate is connected between the connecting plate and the ring plate, and the plurality of rib plates are spaced apart along the circumferential direction of the ring plate.
[0014] Preferably, the large vertical pump hoisting and measuring sling further comprises a connecting piece, the ring plate is provided with a mounting hole, the connecting piece is passed through the mounting hole and connected to the pump body.
[0015] Preferably, the lifting frame also includes a support ring, which is arranged between the connecting plate and the ring plate, and the outer ring of the support ring is connected to the plurality of rib plates, and the top of the support ring is connected to the connecting plate.
[0016] Preferably, the lifting frame also includes a lifting plate, which is arranged between the connecting plate and the ring plate, and the lifting plate is provided with a through hole, and the through hole is used to connect a hook of a lifting machine.
[0017] Preferably, the measuring assembly further comprises a support seat, wherein the support seat is mounted on the lifting frame, the support seat is provided with a connecting hole, and the connecting rod is slidably passed through the connecting hole and connected to the rotor.
[0018] Preferably, the measuring component also includes a limit member, the connecting rod is provided with a limit slot, the support seat is also provided with a fixing hole, the fixing hole is connected to the connecting hole, the limit member is passed through the fixing hole and abuts against the two side walls of the limit slot.
[0019] Preferably, the outer circumferential wall of the connecting rod is provided with an external thread, the inner circumferential wall of the rotating sleeve is provided with an internal thread, and the connecting rod is threadedly connected to the rotating sleeve.
[0020] Preferably, the lifting ring is detachably connected to the lifting frame.
[0021] The beneficial effects of the utility model are:
[0022] The utility model provides a large vertical pump hoisting and measuring sling, the bottom of the hoisting frame is connected to the pump body, the measuring assembly includes a connecting rod, a rotating sleeve and a measuring meter, the measuring meter is installed on the rotor, the connecting rod is slidably inserted into the hoisting frame and connected to the rotor, the central axis of the connecting rod coincides with the central axis of the hoisting frame, the rotating sleeve is sleeved on the connecting rod, and the rotating sleeve can drive the connecting rod and the rotor to rise and fall in the vertical direction. A lifting ring is arranged at the top of the hoisting frame, and there are two lifting rings. The connecting line of the two lifting rings passes through the rotor axis to ensure that the pump body remains upright when it is vertically hoisted, and avoids friction and collision with the outer cylinder of the pump body when it is hoisted into or out of the pump pit; the two lifting rings are respectively located on both sides of the connecting rod, and the center connecting line of the lifting holes of the two lifting rings is parallel to the flange surface of the pump body outlet, to ensure that the pump body can be placed stably during horizontal hoisting, without the need for multiple ground support and adjustments, and avoiding the risk of injury caused by support slippage. Pass the connecting rod through the lifting frame and connect it to the rotor of the pump body. Use a measuring meter to record the reading. Turn the rotating sleeve on the connecting rod to make the connecting rod and the rotor rise simultaneously in the vertical direction. When the reading of the measuring meter no longer changes, record the reading. The difference between the two recorded readings is the total leakage of the rotor. Observe the reading of the measuring meter while rotating the rotating sleeve. When the lifting range requirements of the rotor are met, fix the rotor and obtain the lifting amount of the rotor. The total leakage and lifting amount of the rotor can be measured and obtained without the cooperation of the factory crane. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a structural schematic diagram of a large vertical pump hoisting and measuring sling in an embodiment of the utility model;
[0024] Figure 2 for Figure 1 A partial enlarged view of the middle A;
[0025] Figure 3 It is a side view of a large vertical pump hoisting and measuring sling in an embodiment of the utility model;
[0026] Figure 4 It is a cross-sectional view of the support seat in the embodiment of the utility model;
[0027] Figure 5 It is a structural schematic diagram of the connecting rod in the embodiment of the utility model.
[0028] Reference numerals:
[0029] 1. Lifting frame; 11. Connecting plate; 12. Ring plate; 13. Rib plate; 14. Support ring; 15. Lifting plate;
[0030] 2. Measuring assembly; 21. Connecting rod; 211. Limiting groove; 22. Rotating sleeve; 23. Support seat; 231. Connecting hole; 232. Fixing hole; 24. Limiting piece;
[0031] 3. Rings;
[0032] 4. Connectors. DETAILED DESCRIPTION
[0033] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0034] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0035] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0036] In the description of this embodiment, the terms "upper", "lower", "left", "right" and other directions or positional relationships are based on the directions or positional relationships shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0037] like Figure 1-Figure 5As shown, in this embodiment, the large vertical pump hoisting and measuring sling includes a hoisting frame 1, a measuring assembly 2 and a lifting ring 3. Among them, the bottom of the hoisting frame 1 is connected to the pump body, the measuring assembly 2 includes a connecting rod 21, a rotating sleeve 22 and a measuring meter, the measuring meter is installed on the rotor, the connecting rod 21 is slidably inserted into the hoisting frame 1 and connected to the rotor, the central axis of the connecting rod 21 coincides with the central axis of the hoisting frame 1, the rotating sleeve 22 is sleeved on the connecting rod 21, the rotating sleeve 22 can drive the connecting rod 21 and the rotor to rise and fall in the vertical direction, and the measuring meter is used to measure the total amount of leakage and lifting of the rotor. The lifting ring 3 is arranged at the top of the hoisting frame 1, and there are two lifting rings 3, the two lifting rings 3 are respectively located on both sides of the connecting rod 21, and the center line of the lifting holes of the two lifting rings 3 passes through the axis of the hoisting frame 1 and is parallel to the flange surface of the pump body outlet. Specifically, the bottom of the lifting frame 1 is connected to the flange of the pump body, and two lifting rings 3 for lifting are arranged on the top of the lifting frame 1. The center line of the lifting holes of the two lifting rings 3 is parallel to the flange surface of the main body outlet, ensuring that the pump body can be placed stably during horizontal lifting, without the need for multiple ground support and adjustments, and avoiding the risk of injury caused by support slippage. The measuring meter is a dial indicator, which is installed on the shaft head of the rotor and records the readings. The connecting rod 21 is located at the center of the lifting frame 1, that is, the central axis of the connecting rod 21 coincides with the central axis of the lifting frame 1. The connecting rod 21 is passed through the lifting frame 1 and connected to the rotor of the pump body. The reading is recorded with a measuring meter. The rotating sleeve 22 on the connecting rod 21 is rotated to make the connecting rod 21 and the rotor rise simultaneously in the vertical direction. The reading is recorded when the reading of the measuring meter no longer changes. The difference between the maximum and minimum readings recorded twice by the measuring meter is the total leakage of the rotor. The reading of the measuring meter is observed while rotating the rotating sleeve 22. The rotor falls to the bottom and the rotating sleeve is rotated to lift the rotor. When the lifting range requirements of the rotor are met, the rotor is fixed and the lifting amount of the rotor is obtained. The total leakage and lifting amount of the rotor can be measured and obtained without the cooperation of the factory crane.
[0038] Further, continue to refer to Figure 1-Figure 5 The center line of the lifting holes of the two lifting rings 3 passes through the central axis of the lifting frame 1, which can ensure that the pump body is always in a vertical state when it is vertically lifted, and avoid the pump body from tilting and aggravating the shaking during the lifting process, which may cause collision and friction with the cylinder when entering and exiting.
[0039] Further, continue to refer to Figure 1-Figure 5The lifting frame 1 includes a support ring 14, a connecting plate 11, a ring plate 12, and a plurality of ribs 13. The connecting plate 11 is located above the ring plate 12. The ribs 13 are connected between the connecting plate 11 and the ring plate 12. The plurality of ribs 13 are arranged at intervals along the circumferential direction of the ring plate 12. The support ring 14 is arranged between the connecting plate 11 and the ring plate 12, and the outer ring of the support ring 14 is connected to the plurality of ribs 13. The top of the support ring 14 is connected to the connecting plate 11. Specifically, the two ends of the ribs 13 are fixedly connected to the connecting plate 11 and the ring plate 12, respectively, and the ribs 13 are arranged at an angle relative to the horizontal plane, which has the effect of enhancing the structural stability of the lifting frame 1 as a whole. The support ring 14 is fixedly connected to the fence structure formed by the plurality of ribs 13, and plays the role of fixing and supporting the plurality of ribs 13.
[0040] Further, continue to refer to Figure 1-Figure 5 The large vertical pump hoisting measuring sling also includes a connecting piece 4, a ring plate 12 is provided with a mounting hole, and the connecting piece 4 is passed through the mounting hole and connected to the pump body. The connecting piece 4 is a bolt, and the ring plate 12 is fixedly connected to the flange of the pump body through a plurality of connecting pieces 4.
[0041] Further, continue to refer to Figure 1-Figure 5 The lifting frame 1 also includes a lifting plate 15, which is arranged between the connecting plate 11 and the ring plate 12. The lifting plate 15 is provided with a through hole, which is used to connect the hook of the lifting machine to facilitate the disassembly and assembly of the lifting frame when the pump body is in a horizontal state.
[0042] Further, continue to refer to Figure 1-Figure 5 The measuring assembly 2 further includes a support seat 23, which is mounted on the lifting frame 1. The support seat 23 is provided with a connecting hole 231. The connecting rod 21 is slidably penetrated through the connecting hole 231 and connected to the rotor. Specifically, the measuring assembly 2 further includes a stopper 24, which is a pin. The connecting rod 21 is provided with a limit slot 211. The support seat 23 is further provided with a fixing hole 232, which is connected to the connecting hole 231. The stopper 24 is penetrated through the fixing hole 232 and abuts against the two side walls of the limit slot 211 to prevent the rotor from rotating together with the connecting rod 21 during the rising process, thereby playing a limiting role.
[0043] Further, continue to refer to Figure 1-Figure 5 The outer circumferential wall of the connecting rod 21 is provided with an external thread, the inner circumferential wall of the rotating sleeve 22 is provided with an internal thread, the connecting rod 21 is threadedly connected to the rotating sleeve 22, the lifting ring 3 is detachably connected to the lifting frame 1, and a fixing plate is installed on the lifting frame 1, and the fixing plate is threadedly matched with the threaded end of the lifting ring 3, so that the lifting ring 3 can be detachably connected and replaced conveniently.
[0044] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the scope of protection of the present invention. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention.
Claims
1. Large vertical pump hoisting measuring sling, It is characterized in that include: A lifting frame (1), the bottom of the lifting frame (1) being connected to the pump body; A measuring assembly (2), the measuring assembly (2) comprising a connecting rod (21), a rotating sleeve (22) and a measuring gauge, the measuring gauge being mounted on the rotor, the connecting rod (21) being slidably disposed on the lifting frame (1) and being connected to the rotor, the central axis of the connecting rod (21) being coincident with the central axis of the lifting frame (1), the rotating sleeve (22) being sleeved on the connecting rod (21), the rotating sleeve (22) being capable of driving the connecting rod (21) and the rotor to rise and fall in a vertical direction, the measuring gauge being used to measure the total amount of leakage and the amount of lift of the rotor; A lifting ring (3), wherein the lifting ring (3) is arranged at the top of the lifting frame (1), and there are two lifting rings (3). The two lifting rings (3) are respectively located on both sides of the connecting rod (21), and the center line of the lifting holes of the two lifting rings (3) is parallel to the flange surface of the pump body outlet.
2. The large vertical pump hoisting and measuring sling according to claim 1, It is characterized in that The center line connecting the lifting holes of the two lifting rings (3) passes through the central axis of the lifting frame (1).
3. The large vertical pump hoisting and measuring sling according to claim 1, It is characterized in that The lifting frame (1) comprises a connecting plate (11), a ring plate (12) and a plurality of rib plates (13); the connecting plate (11) is located above the ring plate (12); the rib plate (13) is connected between the connecting plate (11) and the ring plate (12); and the plurality of rib plates (13) are arranged at intervals along the circumferential direction of the ring plate (12).
4. The large vertical pump hoisting and measuring sling according to claim 3, It is characterized in that The vertical pump hoisting and measuring hanger also includes a connecting piece (4), the ring plate (12) is provided with a mounting hole, and the connecting piece (4) is passed through the mounting hole and connected to the pump body.
5. The large vertical pump hoisting and measuring sling according to claim 3, It is characterized in that The lifting frame (1) also includes a support ring (14), which is arranged between the connecting plate (11) and the ring plate (12), and the outer ring of the support ring (14) is connected to the plurality of rib plates (13), and the top of the support ring (14) is connected to the connecting plate (11).
6. The large vertical pump hoisting and measuring sling according to claim 3, It is characterized in that The lifting frame (1) also includes a lifting plate (15), wherein the lifting plate (15) is arranged between the connecting plate (11) and the ring plate (12), and the lifting plate (15) is provided with a through hole, wherein the through hole is used to connect a hook of a lifting machine.
7. The large vertical pump hoisting and measuring sling according to claim 1, It is characterized in that The measuring assembly (2) further comprises a support seat (23), wherein the support seat (23) is mounted on the lifting frame (1), and the support seat (23) is provided with a connecting hole (231), and the connecting rod (21) is slidably inserted into the connecting hole (231) and connected to the rotor.
8. The large vertical pump hoisting and measuring sling according to claim 7, It is characterized in that The measuring assembly (2) further comprises a limiting member (24), the connecting rod (21) is provided with a limiting groove (211), the supporting seat (23) is further provided with a fixing hole (232), the fixing hole (232) is connected to the connecting hole (231), and the limiting member (24) is passed through the fixing hole (232) and abuts against two side walls of the limiting groove (211).
9. The large vertical pump hoisting and measuring sling according to claim 1, It is characterized in that The outer peripheral wall of the connecting rod (21) is provided with an external thread, the inner peripheral wall of the rotating sleeve (22) is provided with an internal thread, and the connecting rod (21) is threadedly connected to the rotating sleeve (22).
10. The large vertical pump hoisting and measuring sling according to claim 1, It is characterized in that The lifting ring (3) is detachably connected to the lifting frame (1).