Drainage device for constructional engineering
By installing filters and treatment tanks in the drainage device of the foundation pit of construction projects, the problems of blockage and equipment damage caused by gravel are solved, the drainage efficiency is improved and the water quality is environmentally friendly.
Patent Information
- Application Number
- CN202323452990.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-19
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2033-12-19
AI Technical Summary
Existing construction engineering foundation pit drainage devices are easily clogged by gravel impurities during pumping, affecting water absorption efficiency. The gravel may damage the pipes, causing damage to the equipment and affecting the use effect.
A drainage device including a foundation pit, drainage ditch, water collection well, pumping pipe, water pump and treatment tank is designed. A metal filter is installed at the water inlet end of the pumping pipe. The treatment tank is used for static and flocculation treatment to ensure that the water quality reaches the environmental level. safety standards.
The filter blocks large particles to prevent clogging and equipment damage, improves drainage efficiency, and makes the water quality meet environmental standards through the treatment pool to ensure safe discharge of the environment.
Smart Images

Figure CN221895811U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering, and in particular to a drainage device for construction engineering. Background Art
[0002] The foundation pit is an earth pit excavated at the foundation design position according to the base elevation and foundation plane dimensions. With the rapid development of modern construction industry, high-rise and super-high-rise buildings are increasing day by day. Due to the large upper load, high-rise and super-high-rise buildings mostly use compensatory foundations, and generally have multi-story basements to facilitate the stability of the building. However, this leads to a large foundation burial depth and deep foundation pit excavation. When excavating deep foundation pits in areas with high groundwater levels, the soil aquifer is cut off, and groundwater will continuously seep into the foundation pit, causing sand flow, slope instability or a decrease in the bearing capacity of the foundation. Therefore, a foundation pit drainage device for construction projects has appeared on the market.
[0003] The traditional construction engineering foundation pit drainage structure in the existing market still has some defects when in use. For example, due to the large number of impurities such as gravel in the foundation pit, blockage occurs during pumping, and some gravel will also knock against internal components, causing damage to the pipes and affecting the subsequent use effect, seriously affecting the water absorption efficiency of the pump pipe. Utility Model Content
[0004] The purpose of the utility model is to provide a drainage device for construction engineering to solve the problems raised in the above background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a drainage device for a construction project, which includes a foundation pit, a drainage ditch is arranged on one side or all around the bottom surface of the foundation pit, a water collection well is arranged at the four corners of the bottom surface of the foundation pit or every 20 to 30 meters, a first pumping pipe is arranged in the water collection well, the first pumping pipe extends upward along the slope of the foundation pit, the upper end of the first pumping pipe is fixedly connected to a pumping pump through a flange, the outlet of the pumping pump is connected to an outlet pipe, a treatment pool is excavated on one side of the foundation pit, the outlet of the outlet pipe is located above the treatment pool, a second pumping pipe is arranged in the treatment pool, the upper end of the second pumping pipe is fixedly connected to an external drainage pump through a flange, and the outlet of the external drainage pump is connected to an external drainage pipe.
[0006] Preferably, water inlet pipe filters are installed at the water inlet ends of the first water pumping pipe and the second water pumping pipe, and the main filtering element of the water inlet pipe filter is a metal filter mesh.
[0007] Preferably, the drainage ditch is always 0.4 to 0.5 m lower than the excavation surface of the foundation pit, and the water collection well is always 0.5 to 1 m lower than the drainage ditch.
[0008] Beneficial effects: Compared with the prior art, the beneficial effects of the utility model are: the setting of the water inlet pipe filter can block impurities such as larger particles of gravel, prevent blockage and protect drainage pipes, pumps and other facilities from damage, thereby ensuring drainage efficiency; the treatment pool allows the water pumped out of the foundation pit to stand and flocculate, so that it meets the standards for environmentally safe discharge and has good environmental performance. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] Figure 1 The utility model is a schematic diagram of the overall structure of a drainage device for a construction project.
[0010] In the attached figure: 1- foundation pit, 2- drainage ditch, 3- water collection well, 4- first pumping pipe, 5- pumping pump, 6- outlet pipe, 7- treatment tank, 8- second pumping pipe, 9- external drainage pump, 10- external drainage pipe, 11- inlet pipe filter. DETAILED DESCRIPTION
[0011] In order to more clearly understand the above-mentioned purpose, features and advantages of the utility model, the utility model is further described below in conjunction with the accompanying drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0012] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.
[0013] Example
[0014] Please refer to the drawings of the specification. In the embodiment of the utility model, a drainage device for a construction project includes a foundation pit 1, a drainage ditch 2 is arranged on one side or around the bottom surface of the foundation pit 1, a water collection well 3 is arranged at the four corners of the bottom surface of the foundation pit 1 or every 20 to 30 meters, the drainage ditch 2 is always 0.4 to 0.5 meters lower than the excavation surface of the foundation pit 1, the water collection well 3 is always 0.5 to 1 meter lower than the drainage ditch 2, a first pumping pipe 4 is arranged in the water collection well 3, the first pumping pipe 4 extends upward along the slope of the foundation pit 1, and the upper end of the first pumping pipe 4 is connected by a method A pumping pump 5 is fixedly connected to the flange, and the outlet of the pumping pump 5 is connected to a water outlet pipe 6. A treatment pool 7 is excavated on one side of the foundation pit 1, and the outlet of the water outlet pipe 6 is located above the treatment pool 7. A second pumping pipe 8 is arranged in the treatment pool 7, and the upper end of the second pumping pipe 8 is fixedly connected to an external drainage pump 9 through a flange, and the outlet of the external drainage pump 9 is connected to an external drainage pipe 10. The water inlet ends of the first pumping pipe 4 and the second pumping pipe 8 are both installed with an inlet pipe filter 11, and the main filtering element of the inlet pipe filter 11 is a metal filter mesh. In order to improve the water quality after water treatment, some chemical reagents can be added to the treatment pool 7 according to the standard to precipitate harmful substances or convert them into harmless substances.
[0015] In the utility model, the setting of the water inlet pipe filter can block impurities such as large particles of gravel, prevent blockage and protect drainage pipes, pumps and other facilities from damage, thereby ensuring drainage efficiency; the treatment pool performs static and flocculation treatment on the water pumped out of the foundation pit to make it meet the environmental safety discharge standards and has good environmental protection performance; the present application has a simple structure, strong practicality, and simple operation, which is worthy of promotion.
[0016] The above specific embodiments further illustrate the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above are only specific embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
[0017] In the description of the present invention, it is necessary to understand that the terms indicating orientation or positional relationship are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0018] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0019] In the description of the present utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate the orientation or position relationship based on the orientation or position relationship shown in the accompanying drawings, or the orientation or position relationship in which the utility model product is usually placed when in use, which is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.
Claims
1. A drainage device for a construction project, comprising a foundation pit (1), characterized in that: A drainage ditch (2) is arranged on one side or around the bottom surface of the foundation pit (1); a water collection well (3) is arranged at the four corners of the bottom surface of the foundation pit (1) or every 20 to 30 meters; a first water pumping pipe (4) is arranged in the water collection well (3); the first water pumping pipe (4) extends upward along the slope of the foundation pit (1); the upper end of the first water pumping pipe (4) is fixedly connected to a water pump (5) through a flange; the outlet of the water pump (5) is connected to a water outlet pipe (6); a treatment pool (7) is excavated on one side of the foundation pit (1); the outlet of the water outlet pipe (6) is located above the treatment pool (7); a second water pumping pipe (8) is arranged in the treatment pool (7); the upper end of the second water pumping pipe (8) is fixedly connected to an external drainage pump (9) through a flange; the outlet of the external drainage pump (9) is connected to an external drainage pipe (10).
2. A construction engineering drainage device according to claim 1, characterized in that: The water inlet ends of the first water pumping pipe (4) and the second water pumping pipe (8) are both installed with a water inlet pipe filter (11), and the filter element of the water inlet pipe filter (11) is a metal filter mesh.
3. A construction engineering drainage device according to claim 1, characterized in that: The drainage ditch (2) is always 0.4 to 0.5 m lower than the excavation surface of the foundation pit (1), and the water collection well (3) is always 0.5 to 1 m lower than the drainage ditch (2).