Blind ditch structure for draining and guiding seepage water in accumulation body

By arranging blind tubes side by side in the designed pits at the bottom of the accumulation body and reinforcing the structure of the components on the outside, the problem of insufficient seepage drainage capacity and easy deformation of blind tubes in the existing technology is solved, and more efficient seepage drainage and structural stability are achieved.

CN221895903UInactive Publication Date: 2024-10-25POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420500843.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-10-25
Estimated Expiration
Not applicable · inactive patent

Smart Images

  • Figure CN221895903U_ABST
    Figure CN221895903U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of soil and stone accumulation body water seepage, in particular to a blind ditch structure for draining and guiding water seepage in an accumulation body, which comprises a pit arranged at the bottom of the accumulation body, one or at least two blind pipes are arranged in the pit along the length direction, and the blind pipes are arranged in the pit along the length direction. The rest space in the pit is filled with filler, and the upper end face of the filler is flush with the ground. A reinforcing assembly is arranged on the outer side of the blind pipe and comprises a base arranged at the bottom of the blind pipe and fixing frames arranged on the upper portion of the blind pipe and connected with the base, and the multiple fixing frames are arranged at equal intervals. The base and the fixing frame are arranged on the upper portion and the bottom of the blind pipe respectively so as to surround the blind pipe, the blind pipe is protected, the blind pipe is effectively helped to resist most pressure, the situation that accumulation bodies are accumulated above a blind ditch, the blind pipe is pressed to deform and collapse, and the water seepage performance is affected is avoided, and material transportation is facilitated through the split design of the base and the fixing frame.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of water seepage in soil and stone accumulation bodies, and more specifically, particularly to a blind ditch structure for draining water seepage in an accumulation body. Background Art

[0002] With the rapid development of the economy and society, there are more and more earth and rock accumulations formed by various production and construction projects such as soil, material and slag. Conventional stone-filled blind ditches are set at the bottom of the accumulation to guide the seepage water of the accumulation into the downstream channel through the blind ditch. However, its water-passing capacity is greatly affected by the material, proportion and permeability of the stone filling, and the corresponding water-passing capacity is relatively small. Therefore, a new blind ditch structure is explored to improve the seepage drainage capacity and reduce the seepage in the accumulation to reduce the risk of the accumulation itself.

[0003] In the prior art, a plastic blind pipe is installed in the blind ditch, and a structure combining a stone-filled blind ditch and the plastic blind pipe is adopted to avoid the problem that the ordinary stone-filled blind ditch has low drainage efficiency due to factors such as the particle size of the stone-filled material, the permeability coefficient, and the easy clogging, and cannot quickly discharge the seepage water in the accumulation body, affecting the stability of the accumulation body. However, the structure of directly laying the plastic blind pipe in the blind ditch is prone to deformation and collapse of the plastic blind pipe, thereby affecting the water seepage performance. Utility Model Content

[0004] In order to overcome the above-mentioned shortcomings, the utility model aims to provide a blind ditch structure with a stable structure for draining water seepage in a pile body.

[0005] A blind ditch structure for draining water seepage from a pile, comprising a pit arranged at the bottom of the pile, wherein a blind pipe is arranged in the pit along the length direction, wherein one blind pipe is arranged or at least two blind pipes are arranged side by side, and the remaining space in the pit is filled with a filler, wherein the upper end surface of the filler is flush with the ground. A reinforcement assembly is arranged outside the blind pipe, wherein the reinforcement assembly comprises a base arranged at the bottom of the blind pipe and a fixing frame arranged at the upper part of the blind pipe and connected to the base, wherein a plurality of the fixing frames are arranged at equal intervals.

[0006] Furthermore, an arc-shaped groove matched with the blind tube is formed on the upper end surface of the base, and the lower part of the blind tube is embedded in the arc-shaped groove.

[0007] Furthermore, the fixing frame is in an arc-shaped structure and is spaced across the upper portion of the blind tube, and a connecting plate connected to the base is provided on the outer side of the bottom of the fixing frame.

[0008] Furthermore, clamping blocks are arranged on both sides of the upper end surface of the base, and clamping holes matched with the clamping blocks are opened on the connecting plate. When the fixing frame is installed above the base, the clamping blocks are clamped into the clamping holes.

[0009] Furthermore, the fixing frame includes two inner and outer fixing plates which are cocentrically arranged, the fixing plates are in an arc-shaped structure, and a plurality of reinforcing plates are arranged in a circular array between the two fixing plates, and the reinforcing plates penetrate through the plurality of fixing frames.

[0010] Furthermore, a connecting groove is opened on one side where the two layers of the fixing plates are close to each other, and the position of the connecting groove corresponds to the reinforcing plate. Connecting strips adapted to the connecting groove are fixed on both sides of the reinforcing plate, and the connecting strips are partially inserted into the connecting groove.

[0011] Furthermore, the bottoms of the two layers of the fixing plates are flush, and the connecting plate is fixedly connected to the two layers of the fixing plates.

[0012] Furthermore, a geotextile is laid on the upper end surface of the filler and the ground, and a gravel cushion layer is laid on the geotextile.

[0013] Furthermore, the filling material includes a large stone layer laid at the bottom of the pit and a pebble layer laid above the large stone layer, and the upper surface of the pebble layer is flush with the ground.

[0014] Furthermore, the blind pipe and reinforcement assembly are arranged in the large stone layer.

[0015] Compared with the prior art, the beneficial effects of the utility model are:

[0016] The blind ditch structure for draining water seepage in the accumulation body in the utility model has a blind pipe arranged in the pit, and a reinforcement component arranged outside the blind pipe, the reinforcement component including a base and a fixing frame, the base and the fixing frame are respectively arranged on the upper part and the bottom part of the blind pipe so as to surround the blind pipe, protect the blind pipe, effectively help the blind pipe resist most of the pressure, thereby preventing the accumulation body from accumulating above the blind ditch, causing the blind pipe to be deformed and collapsed under pressure, and affecting the water seepage performance. In addition, the design of the base and the fixing frame being separated facilitates material transportation and installation.

[0017] An arc-shaped groove is provided on the upper end surface of the base, and the lower part of the blind pipe can be embedded in the arc-shaped groove to prevent the blind pipe from rolling during installation and later filling of the pit. The fixed frame and the blind pipe are arranged at intervals so as not to cover the water-permeable holes on the blind pipe, thereby protecting the blind pipe without affecting the water seepage function of the blind pipe. The reinforcement plate is arranged in the fixed frame. On the one hand, it can effectively enhance the strength of the reinforcement component. On the other hand, the radial arrangement allows the reinforcement plate to diffuse outward from the side away from the blind pipe, guiding the seepage, so that the seepage in a larger range can enter the blind pipe along the reinforcement plate. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0019] Figure 1 It is a schematic diagram of the overall structure of a blind ditch structure for draining water seepage in a pile body in an embodiment of the utility model.

[0020] Figure 2 It is a structural schematic diagram of a blind pipe and a reinforcement assembly in an embodiment of the utility model.

[0021] Figure 3 It is a schematic diagram of the connection structure between the fixed frame and the base in the embodiment of the utility model.

[0022] Figure 4 It is a structural schematic diagram of the reinforcement plate in the embodiment of the utility model.

[0023] Figure 5 yes Figure 2 Enlarged view of point A in the middle.

[0024] In the figure: 1, pit; 2, blind pipe; 3, base; 4, fixing frame; 401, connecting plate; 402, clamping hole; 403, fixing plate; 404, connecting groove; 5, arc-shaped groove; 6, clamping block; 7, reinforcement plate; 8, connecting strip; 9, geotextile; 10, gravel cushion layer; 11, large stone layer; 12, pebble layer. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0026] like Figure 1 , Figure 2 As shown, the blind ditch structure for draining water seepage from the accumulation body in this embodiment includes a pit 1 arranged at the bottom of the accumulation body. A blind pipe 2 is arranged in the pit 1 along the length direction, and one blind pipe 2 is arranged or at least two blind pipes 2 are arranged side by side. Specifically, in this embodiment, two blind pipes 2 are arranged side by side. The remaining space in the pit 1 is filled with a filler, and the upper end surface of the filler is flush with the ground. A reinforcement component is arranged on the outside of the blind pipe 2, and the reinforcement component includes a base 3 arranged at the bottom of the blind pipe 2 and a fixed frame 4 arranged on the upper part of the blind pipe 2 and connected to the base 3, and a plurality of fixed frames 4 are arranged at equal intervals.

[0027] In this embodiment, a plurality of bases 3 are arranged in one-to-one correspondence with the fixing frame 4. In some other embodiments, one base 3 is arranged corresponding to one blind tube 2, and the length of the base 3 is the same as the length of the blind tube 2. Figure 3As shown, the upper end surface of the base 3 is provided with an arc-shaped groove 5 adapted to the blind tube 2, and the lower part of the blind tube 2 is embedded in the arc-shaped groove 5, thereby limiting the blind tube 2 and preventing the blind tube 2 from rolling during installation and subsequent filling of the pit 1.

[0028] In this embodiment, the fixed frame 4 is an arc-shaped structure and is arranged at intervals across the upper part of the blind pipe 2, so as not to cover the water-permeable holes on the blind pipe 2, and protect the blind pipe 2 without affecting the water seepage function of the blind pipe 2. A connecting plate 401 connected to the base 3 is provided on the outer side of the bottom of the fixed frame 4. A clamping block 6 is fixed on the upper end surface of the base 3 and located on both sides of the arc-shaped groove 5. A clamping hole 402 adapted to the clamping block 6 is provided on the connecting plate 401. When the fixed frame 4 is installed above the base 3, the clamping block 6 is clamped into the clamping hole 402, thereby determining the installation position of the fixed frame 4, limiting the horizontal movement of the fixed frame 4, and convenient installation.

[0029] Preferably, in this embodiment, the base 3 can be made of hard plastic, and the base 3 and the block 6 are integrally provided.

[0030] In this embodiment, if Figure 4 , Figure 5 As shown, the fixing frame 4 includes two layers of fixing plates 403, which are in an arc-shaped structure and are arranged concentrically inside and outside, the diameter of the outer fixing plate 403 is larger than the diameter of the inner fixing plate 403, and the protrusions of the two fixing plates 403 are arranged upward, the bottoms of the two fixing plates 403 are flush, and the connecting plate 401 extends to the inner fixing plate 403 and is fixedly connected to the two fixing plates 403. There are multiple reinforcing plates 7 in an annular array between the two fixing plates 403, the length of the reinforcing plates 7 is the same as the length of the blind pipe 2, and the reinforcing plates 7 pass through multiple fixing frames 4.

[0031] In this embodiment, a connection groove 404 is provided on one side where the two layers of fixing plates 403 are close to each other, and the position of the connection groove 404 corresponds to the reinforcing plate 7. Connecting strips 8 adapted to the connection groove 404 are fixed on both sides of the reinforcing plate 7, and the connecting strips 8 are partially inserted into the connection groove 404. By arranging the reinforcing plate 7 in the fixing frame 4, on the one hand, the strength of the reinforcing assembly can be effectively enhanced, and on the other hand, the radial arrangement allows the reinforcing plate 7 to diffuse outward from the side away from the blind pipe 2, and guides the seepage, so that the seepage in a larger range can enter the blind pipe 2 along the reinforcing plate 7.

[0032] Preferably, in this embodiment, the fixing frame 4 can be made of hard plastic or steel, and the fixing plate 403 is integrally provided with the connecting plate 401. The reinforcing plate 7 can be made of hard plastic or steel, and the reinforcing plate 7 is integrally provided with the connecting strip 8. The blind tube 2 is a plastic blind tube 2.

[0033] In this embodiment, the filler includes a large stone layer 11 laid at the bottom of the pit 1 and a pebble layer 12 laid above the large stone layer 11, the upper surface of the pebble layer 12 is flush with the ground, and the blind pipe 2 and the reinforcement assembly are arranged in the large stone layer 11. A geotextile 9 is laid on the upper end surface of the filler and the ground, and a gravel cushion layer 10 is laid on the geotextile 9.

[0034] The working principle of the blind ditch structure for draining water seepage from the accumulation body in this embodiment is:

[0035] A blind pipe 2 is arranged in the pit 1, and a reinforcement component is arranged outside the blind pipe 2. The reinforcement component includes a base 3 and a fixing frame 4. The base 3 and the fixing frame 4 are respectively arranged on the upper part and the bottom part of the blind pipe 2 so as to surround the blind pipe 2, protect the blind pipe 2, and effectively help the blind pipe 2 resist most of the pressure, thereby preventing the accumulation body from accumulating above the blind ditch, causing the blind pipe 2 to deform and collapse under pressure, affecting the water permeability. In addition, the design of the base 3 and the fixing frame 4 being separated facilitates material transportation and installation.

[0036] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A blind ditch structure for draining water seepage from a pile, characterized in that: It comprises a pit (1) arranged at the bottom of the stack, wherein a blind pipe (2) is arranged in the pit (1) along the length direction, wherein one blind pipe (2) is arranged or at least two blind pipes (2) are arranged side by side, and the remaining space in the pit (1) is filled with a filler, wherein the upper end surface of the filler is flush with the ground; A reinforcement component is arranged on the outside of the blind tube (2), and the reinforcement component comprises a base (3) arranged at the bottom of the blind tube (2) and a fixing frame (4) arranged at the top of the blind tube (2) and connected to the base (3), wherein a plurality of the fixing frames (4) are arranged at equal intervals.

2. The blind ditch structure for draining water seepage from a pile according to claim 1 is characterized in that: The upper end surface of the base (3) is provided with an arc-shaped groove (5) adapted to the blind tube (2), and the lower part of the blind tube (2) is embedded in the arc-shaped groove (5).

3. The blind ditch structure for draining water seepage from a pile according to claim 2, characterized in that: The fixing frame (4) is of an arc-shaped structure and is arranged at intervals across the upper part of the blind tube (2). A connecting plate (401) connected to the base (3) is arranged on the outer side of the bottom of the fixing frame (4).

4. The blind ditch structure for draining water seepage in a pile according to claim 3 is characterized in that: Blocks (6) are arranged on both sides of the upper end surface of the base (3); a clamping hole (402) adapted to the block (6) is provided on the connecting plate (401); when the fixing frame (4) is installed above the base (3), the block (6) is clamped into the clamping hole (402).

5. The blind ditch structure for draining water seepage in a pile according to claim 4, characterized in that: The fixing frame (4) comprises two inner and outer layers of fixing plates (403) which are arranged concentrically, the fixing plates (403) being in an arc-shaped structure, and a plurality of reinforcing plates (7) are arranged in a circular array between the two layers of the fixing plates (403), the reinforcing plates (7) passing through the plurality of fixing frames (4).

6. The blind ditch structure for draining water seepage in a pile according to claim 5, characterized in that: A connecting groove (404) is provided on one side of the two layers of the fixing plates (403) close to each other, the position of the connecting groove (404) corresponds to the reinforcing plate (7), and connecting strips (8) adapted to the connecting groove (404) are fixed on both sides of the reinforcing plate (7), and the connecting strips (8) are partially inserted into the connecting groove (404).

7. The blind ditch structure for draining water seepage in a pile according to claim 6, characterized in that: The bottoms of the two layers of the fixing plates (403) are flush with each other, and the connecting plate (401) is fixedly connected to the two layers of the fixing plates (403).

8. The blind ditch structure for draining water seepage from a pile according to any one of claims 1 to 7, characterized in that: A geotextile (9) is laid on the upper end surface of the filler and the ground, and a gravel cushion layer (10) is laid on the geotextile (9).

9. The blind ditch structure for draining water seepage from a pile according to any one of claims 1 to 7, characterized in that: The filling material comprises a large stone layer (11) laid at the bottom of the pit (1) and a pebble layer (12) laid above the large stone layer (11), and the upper surface of the pebble layer (12) is flush with the ground.

10. The blind ditch structure for draining water seepage in a pile according to claim 9, characterized in that: The blind pipe (2) and the reinforcement assembly are arranged in the large stone layer (11).