Temporary water stopping device for drilling
By designing a temporary water stop device including an oil pump, expansion casing and oil pipe, the problem of water inflow after drilling in tunnel engineering is solved, and a fast and reliable water stop effect is achieved. It is suitable for one-time monitoring needs and reduces operational complexity. and cost.
Patent Information
- Application Number
- CN202323451284.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-18
- Publication Date
- 2024-10-25
- Estimated Expiration
- 2033-12-18
AI Technical Summary
In tunnel projects, the phenomenon of water inflow after drilling often affects monitoring construction and instrument safety. The existing water stop methods are complex and costly, and are not suitable as a one-time pre-monitoring treatment solution.
A temporary water stop device including an oil pump, expansion casing and oil pipe is designed. It is fed into the borehole through a stainless steel rod, and uses a rubber expansion layer and a fixed ring to achieve water stop. It is simple to operate, does not require special machinery, and has strong applicability.
It achieves fast and reliable borehole water-stopping, is suitable for one-time monitoring work, the equipment is reusable, the operation is flexible, and the time cost is low.
Smart Images

Figure CN221896564U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of tunnel engineering monitoring, and more specifically to a simple temporary water stopping device for water gushing boreholes before tunnel monitoring. Background Art
[0002] Tunnel engineering monitoring is an important task to ensure construction safety and quality. When conducting monitoring projects such as surrounding rock temperature and ground stress testing, it is necessary to drill holes in advance to provide monitoring operation space inside the surrounding rock. Mountain tunnels are prone to water gushing after drilling, which affects monitoring construction and monitoring results, and even causes damage to monitoring instruments.
[0003] At present, there are mature solutions for drilling water stopping. However, most of them require the preparation of special materials, grouting equipment, drilling rigs, etc. The existing solutions are relatively complicated to operate, with high economic costs in terms of time and cost, and are not suitable for pre-drilling treatment solutions as one-time monitoring. There is a lack of solutions with simple materials, easy-to-obtain instruments, and stronger operability. Utility Model Content
[0004] The utility model aims to overcome the problems existing in the above-mentioned background technology and provides a temporary water-stopping device for drilling holes.
[0005] The utility model is achieved in this way:
[0006] The utility model provides a temporary water stopping device for drilling, which comprises an oil pump, an expansion sleeve inserted into the drilling hole, and an oil pipe connecting the oil pump and the expansion sleeve. The expansion sleeve is sleeved with a fixing ring, and the expansion sleeve is sent into the drilling hole by a stainless steel rod.
[0007] Preferably, the oil pump is a manual oil pump with an oil pressure gauge. The oil pressure gauge stops water after the water-stopping effect is observed, and the pressure is replenished in time during the monitoring process.
[0008] Preferably, the fixing ring is made of plastic, and the main body of the fixing ring is a cable tie, which can adapt to the diameter of the expansion sleeve and quickly fix the fixing ring on the expansion sleeve. The fixing ring has three fixing ring claws, the opening diameter of the fixing ring claws is larger than the diameter of the drill hole, and the opening direction of the fixing ring claws is the direction of the drill hole opening. When in use, the main body of the fixing ring is fixed to the front section of the expansion sleeve and fixed. Due to the effect of the fixing ring, the drill hole can be at any elevation angle. The fixing ring is a disposable product.
[0009] Preferably, threads are left at both ends of the stainless steel rod, and the stainless steel rod can be extended according to the placement depth of the expansion sleeve. The stainless steel rod is used to send the expansion sleeve into the borehole.
[0010] Preferably, the oil pipe is a high-pressure oil pipe, and the oil pipe is threadedly connected to the expansion casing and the oil pump. After the expansion casing is depressurized, the oil pipe can be used to pull out the expansion casing, and the fixing ring claw is destroyed at this time.
[0011] Preferably, the expansion sleeve is a hollow structure, and the outer surface is a rubber expansion layer. When the hydraulic oil is pressed into the oil pump, the expansion layer will open and fit tightly against the inner wall of the borehole.
[0012] Preferably, one end of the rubber expansion sleeve is connected to the oil pipe and the other end is spherical. The diameter of the expansion sleeve should be significantly smaller than the diameter of the borehole, and the length of the expansion sleeve should be within 20 cm to facilitate its delivery into the borehole.
[0013] Preferably, the expansion sleeve can control the deformation of the rubber expansion layer by increasing or decreasing oil pressure, and the position of the expansion sleeve in the drilling hole can be changed by depressurizing the expansion sleeve and moving it and then increasing pressure.
[0014] Preferably, the depth of the borehole should be greater than the depth required for monitoring, and the insertion depth of the expansion sleeve should be greater than the depth required for monitoring. The insertion position of the expansion sleeve can be determined by observing the water-stopping effect after pressure testing.
[0015] The utility model has the following beneficial results:
[0016] The utility model provides a temporary water-stopping device for drilling holes, which is simple to operate, reliable in effect, does not require the cooperation of special machinery, and has strong applicability. The device can be reused, is flexible in use and adjustment, can achieve a water-stopping effect in a relatively short time, and can cooperate with rapid one-time monitoring work. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a device diagram of the utility model;
[0018] Figure 2 The expansion casing of the utility model;
[0019] Figure 3 It is the fixing ring of the utility model; DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is described in detail in conjunction with the accompanying drawings and specific embodiments. This embodiment is implemented based on the technical solution of the utility model, and a detailed implementation method and specific operation process are given, but the protection scope of the utility model is not limited to the following embodiments.
[0021] like Figure 1The utility model provides a temporary water-stopping device for drilling. The device comprises an oil pump 1, an oil pressure gauge 2, an oil pipe 3 and an expansion sleeve 4. The oil pump 1, the oil pressure gauge 2, the oil pipe 3 and the expansion sleeve 4 are connected by threads. The expansion sleeve 4 is a hollow structure with a rubber expansion layer 5 on the surface. When in use, a fixing ring 6 is fixed on the expansion sleeve 4. The expansion sleeve 4 is placed in a borehole 8 using a stainless steel rod 7. The fixing ring 6 comprises a fixing ring body 9 and a fixing ring claw 10.
[0022] In this example, temporary water stopping has the following steps:
[0023] (1) Obtaining borehole 8 according to monitoring requirements;
[0024] (2) The oil pump 1, the oil meter 2, the oil pipe 3 and the expansion casing 4 are connected in sequence, and the fixing ring 6 is fixed on the expansion casing 4;
[0025] (3) Use the stainless steel rod 7 to push the expansion casing 4 into the borehole 8, use the oil pump 1 to increase the pressure until the water stops, record the oil gauge 2 reading, and start monitoring. During the monitoring process, pay attention to the oil gauge 2 reading. Replenish the pressure at any time.
[0026] (4) After the monitoring work is completed, the oil pump 1 is depressurized and the expansion casing 4 is pulled out using the oil pipe 3.
[0027] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.
Claims
1. A temporary water stopping device for drilling, characterized in that: The device comprises an oil pump (1), an oil pressure gauge (2), an oil pipe (3) and an expansion sleeve (4); the expansion sleeve (4) is a hollow structure with a rubber expansion layer (5) on its surface; a fixing ring (6) is fixed on the expansion sleeve (4) when in use; the expansion sleeve (4) is fixed with the fixing ring (6); the fixing ring (6) is made of plastic; the fixing ring (6) comprises a fixing ring body (9) and a fixing ring claw (10); the fixing ring body (9) is a cable tie adapted to the expansion sleeve (4); the fixing ring claw (10) opens in the direction of the borehole (8) orifice.