Auxiliary binding tool for construction steel bars
By designing an auxiliary tying tool for construction steel bars that includes a disc, an air cylinder and a rod body, and using the air in the air cylinder to push the piston and rod body to extend, the problem of existing tool diameter and quantity adjustment limitations is solved, and flexible tying of different steel cages is achieved. And the expansion of the scope of application meets most construction needs and improves the flexibility and stability of use.
Patent Information
- Application Number
- CN202420526757.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-19
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-19
AI Technical Summary
Existing construction steel bar auxiliary tying tools have limitations in diameter and quantity adjustment during use, and cannot be applied to steel cages of different sizes and quantities, resulting in limited applicability.
A tool is designed that includes a disc, an air cylinder, a piston, a rod body and a positioning ring. The piston and rod body are pushed to extend by inflating the air cylinder. It combines multiple air holes and bolts to realize the binding of steel cages of different diameters and quantities, and rotates the threaded rod. and universal wheels for height adjustment and flexible movement.
It realizes the flexible binding of steel cages of different diameters and quantities, expands the scope of application of the tool, meets most construction needs, and improves the flexibility and stability of use.
Smart Images

Figure CN221920338U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel bar binding, in particular to an auxiliary binding tool for building steel bars. Background Art
[0002] The steel cage is a prefabricated steel component commonly used in construction projects, usually used for the reinforcement and support of concrete structures. It is made of steel bars woven in space according to design requirements to form a cage-like structure, and then concrete is poured on site to tightly combine the steel cage with the concrete, thereby enhancing the tensile properties and overall bearing capacity of the concrete. When tying the steel cage, auxiliary tying tools are usually required for positioning.
[0003] The Chinese patent with announcement number CN218438325U discloses an auxiliary steel bar binding tool for building construction. The binding tool, through the cooperation between the positioning ring, locking screw, splint, worm, working box, worm gear, rotating shaft, rotating plate, guide groove, guide rod, fixing rod, adjusting screw and supporting base plate and lifting bracket, can facilitate personnel to adjust the position of the steel bar according to the diameter of the steel bar cage binding, and at the same time, facilitate personnel to adjust the height of the steel bar binding according to the actual operation needs, which brings great convenience to personnel.
[0004] However, the number of fixing rods in the above patent is 8, which means that the above tool can only be used to tie a steel cage with no more than 8 steel bars. According to different needs of construction projects, the number of steel bars in the steel cage is not consistent, and some even have dozens of steel bars. Therefore, the above patent has certain scope limitations when used and is not widely applicable. Utility Model Content
[0005] The utility model aims to provide a construction steel bar auxiliary binding tool which has a wide application range and can be used for binding steel bar cages with different numbers of steel bars.
[0006] To achieve the above-mentioned purpose, the technical solution of the utility model is as follows.
[0007] A construction steel bar auxiliary binding tool comprises a disc, a plurality of first air holes are provided in a circular array inside the disc, a piston is provided inside the first air hole to seal, a rod body is connected to the upper surface of the piston, and the upper end of the rod body passes through the outside of the disc, and a positioning ring is installed at the end of the rod body. An air cylinder is installed on the outer surface of the disc, an inner cavity is provided inside the disc, and the air cylinder is connected to the inner cavity, and a one-way valve is provided between the air cylinder and the inner cavity, a plurality of second air holes are provided in a circular array on the inner wall of the inner cavity, and the ends of the second air holes are connected to the first air holes. A plurality of fixing blocks are installed on the outer surface of the disc, bolts are provided inside the fixing blocks, and a positioning hole is provided on the surface of the rod body, and the bolts are adapted to the positioning hole.
[0008] It can be seen that by using an air cylinder to inflate the inner cavity, the gas enters the first air hole through the second air hole, so that the piston can be pushed upward to push the rod body and the positioning ring to extend outward, so that it can be suitable for the binding of steel cages of different diameters. When it is necessary to bind steel cages with different numbers of steel bars, it is only necessary to screw the bolts into the positioning holes to fix the position of the rod body, so that when the inner cavity is inflated with air through the air cylinder, the rod body will not extend outward. Therefore, when it is necessary to bind steel cages with a certain number of steel bars, it is only necessary to fix the rod bodies other than the number, so that it can be adjusted according to the actual construction conditions, and has a wide range of applications.
[0009] Furthermore, the number of the first air holes, the second air holes and the fixing blocks is the same, and the number of the first air holes, the second air holes and the fixing blocks is not less than 20.
[0010] A steel cage with less than 20 steel bars can meet most construction needs.
[0011] Furthermore, a bracket is installed on the outer surface of the air cylinder, a base plate is arranged on the lower side of the bracket, a threaded rod is rotatably connected to the upper surface of the base plate, and the threaded rod passes through the interior of the bracket and is threadedly connected thereto, two limit rods are connected to the upper surface of the base plate, and the limit rods pass through the interior of the bracket, cross plates are installed on both sides of the lower surface of the bracket, and universal wheels are installed on both sides of the bottom of the cross plate.
[0012] The disc can be raised and lowered by rotating the threaded rod, and its height can be adjusted. If the device needs to be moved, the height of the disc can be lowered to the lowest point. At this time, the bracket drives the universal wheel to drop to the bottom side of the base plate, and the ground can be supported by the universal wheel, so that the device can be easily pushed to move, thereby improving the flexibility of use. When the device needs to be used, the disc can be raised to a certain height to separate the universal wheel from the ground. At this time, the base plate is supported by the ground again to obtain good stability.
[0013] Furthermore, two paving grooves are provided on the surface of the bottom plate, and the two paving grooves correspond to the two horizontal plates respectively.
[0014] When the cross plate descends, it just passes through the clearance groove, so that the universal wheel supports the ground. Therefore, by setting the clearance groove, the length of the cross plate can be reduced, so that the universal wheel can support the ground without extending the length of the cross plate to the outside of the bottom plate.
[0015] Furthermore, a handle is installed on the outer surface of the air cylinder, and an anti-slip pad is provided on the outer surface of the handle.
[0016] When using the air pump to inflate the inner cavity, the handle can be grasped by hand to keep the device stable.
[0017] Furthermore, an exhaust pipe is installed on the side of the disc facing away from the air cylinder, and a sealing plug is provided at the end of the exhaust pipe.
[0018] When the device is used, the sealing plug can be unscrewed to discharge the gas in the inner cavity and the first air hole, so that the rod body can be retracted into the first air hole. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is one of the three-dimensional structural schematic diagrams of the utility model;
[0020] Figure 2 This is the second schematic diagram of the three-dimensional structure of the utility model;
[0021] Figure 3 It is a schematic diagram of the cross-sectional structure of the disc in the utility model;
[0022] Figure 4 for Figure 1 A is an enlarged schematic diagram;
[0023] Figure 5 for Figure 3 A magnified schematic diagram of B.
[0024] In the figure: 100, disc; 101, first air hole; 102, piston; 103, rod body; 104, positioning ring; 105, air cylinder; 106, inner cavity; 107, second air hole; 108, fixing block; 109, bolt; 110, positioning hole; 200, bracket; 201, bottom plate; 202, threaded rod; 203, limit rod; 204, cross plate; 205, universal wheel; 300, make way groove; 400, handle; 500, exhaust pipe; 501, sealing plug. DETAILED DESCRIPTION
[0025] The utility model is described in detail below with reference to the accompanying drawings.
[0026] like Figure 1-5As shown, a construction steel bar auxiliary binding tool comprises a disc 100, wherein a plurality of first air holes 101 are provided in a circular array inside the disc 100, a piston 102 is provided inside the first air hole 101 in a sealed manner, a rod 103 is connected to the upper surface of the piston 102, and the upper end of the rod 103 penetrates the outer side of the disc 100, and a positioning ring 104 is installed at the end of the rod 103. An air cylinder 105 is installed on the outer surface of the disc 100, an inner cavity 106 is provided inside the disc 100, and the air cylinder 105 is connected to the inner cavity 106, and a one-way valve is provided between the air cylinder 105 and the inner cavity 106, and a plurality of second air holes 107 are provided in a circular array on the inner wall of the inner cavity 106, and the ends of the second air holes 107 are connected to the first air holes 101. A plurality of fixing blocks 108 are installed on the outer surface of the disk 100 , and bolts 109 are provided through the inside of the fixing blocks 108 . Positioning holes 110 are provided on the surface of the rod body 103 , and the bolts 109 are matched with the positioning holes 110 .
[0027] When in use, first set two devices opposite to each other, then fix the excess rod body 103 with bolts 109 according to the number of steel bars required for tying the steel cage, then use the air cylinder 105 to inflate the inner cavity 106, and the rod body enters the first air hole 101 through the second air hole 107. Through the setting of the piston 102, the part that is not fixed can be pushed up. When the rod body 103 extends to a suitable distance, the two ends of the steel bar are respectively inserted into the positioning rings 104 of the two devices, so as to position the steel bar and facilitate binding.
[0028] Specifically, the number of the first air hole 101, the second air hole 107 and the fixed block 108 is the same, and the number of the first air hole 101, the second air hole 107 and the fixed block 108 is not less than 20. The steel cage with less than 20 steel bars can meet most construction needs. It is worth noting that the higher the number, the wider the scope of application. If the specific number is 50, and 20 steel bars need to be tied during use, by fixing the excess rods 103, the number of rods 103 extending outward can be only 20, thereby avoiding the visual interference of the insertion of steel bars caused by too many rods 103, which is convenient for use.
[0029] Specifically, a bracket 200 is installed on the outer surface of the air cylinder 105, a bottom plate 201 is arranged on the lower side of the bracket 200, a threaded rod 202 is rotatably connected to the upper surface of the bottom plate 201, and the threaded rod 202 passes through the inside of the bracket 200 and is threadedly connected thereto, two limit rods 203 are connected to the upper surface of the bottom plate 201, and the limit rods 203 pass through the inside of the bracket 200, and a cross plate 204 is installed on both sides of the lower surface of the bracket 200, and universal wheels 205 are installed on both sides of the bottom of the cross plate 204, which can be driven by rotating the threaded rod 202. The disc 100 can be raised and lowered, and its height can be adjusted. If the device needs to be moved, the height of the disc 100 can be lowered to the lowest point. At this time, the bracket 200 drives the universal wheel 205 to descend to the bottom side of the bottom plate 201, and the universal wheel 205 can be used to support the ground, so that the device can be easily pushed to move, thereby improving the flexibility of use. When the device needs to be used, the disc 100 can be raised to a certain height to separate the universal wheel 205 from the ground. At this time, the bottom plate 201 is re-supported by the ground to obtain good stability.
[0030] Specifically, two clearance grooves 300 are provided on the surface of the bottom plate 201, and the two clearance grooves 300 correspond to the two cross plates 204 respectively. When the cross plate 204 descends, it just passes through the clearance grooves 300, so that the universal wheel 205 supports the ground. Therefore, by setting the clearance grooves 300, the length of the cross plate 204 can be reduced, so that the length of the cross plate 204 does not need to extend to the outside of the bottom plate 201 to enable the universal wheel 205 to support the ground.
[0031] Specifically, a handle 400 is installed on the outer surface of the air cylinder 105, and an anti-slip pad is provided on the outer surface of the handle 400. When the air cylinder 105 is used to inflate the inner cavity 106, the handle 400 can be grasped by hand to keep the device stable.
[0032] Specifically, an exhaust pipe 500 is installed on the side of the disc 100 facing away from the air cylinder 105, and a sealing plug 501 is provided at the end of the exhaust pipe 500. When the device is used, the sealing plug 501 can be unscrewed to discharge the gas in the inner cavity 106 and the first air hole 101, so that the rod body 103 can be retracted into the first air hole 101.
[0033] The above is a detailed description of the utility model in combination with specific embodiments, and it cannot be determined that the specific implementation methods of the utility model are limited to these descriptions. For ordinary technicians in the technical field to which the utility model belongs, making several equivalent substitutions or obvious modifications without departing from the concept of the utility model, and having the same performance or use, should be regarded as belonging to the patent protection scope of the utility model determined by the submitted claims.
Claims
1. A construction steel bar auxiliary binding tool, comprising a disc (100), characterized in that: The disk (100) is provided with a plurality of first air holes (101) in a circular array inside, a piston (102) is provided inside the first air hole (101) in a sealed manner, a rod (103) is connected to the upper surface of the piston (102), and the upper end of the rod (103) passes through the outer side of the disk (100), and a positioning ring (104) is installed at the end of the rod (103); An air cylinder (105) is installed on the outer surface of the disk (100), an inner cavity (106) is opened inside the disk (100), and the air cylinder (105) is connected to the inner cavity (106), and a one-way valve is arranged between the air cylinder (105) and the inner cavity (106), and a plurality of second air holes (107) are opened in a circumferential array on the inner wall of the inner cavity (106), and the ends of the second air holes (107) are connected to the first air holes (101); A plurality of fixing blocks (108) are installed on the outer surface of the disk (100), bolts (109) are provided inside the fixing blocks (108), and positioning holes (110) are provided on the surface of the rod body (103), and the bolts (109) are matched with the positioning holes (110).
2. A construction steel bar auxiliary binding tool according to claim 1, characterized in that: The number of the first air holes (101), the second air holes (107) and the fixing blocks (108) is the same, and the number of the first air holes (101), the second air holes (107) and the fixing blocks (108) is not less than 20.
3. A construction steel bar auxiliary binding tool according to claim 2, characterized in that: A bracket (200) is installed on the outer surface of the air cylinder (105), a bottom plate (201) is arranged on the lower side of the bracket (200), a threaded rod (202) is rotatably connected to the upper surface of the bottom plate (201), and the threaded rod (202) passes through the interior of the bracket (200) and is threadedly connected thereto, two limit rods (203) are connected to the upper surface of the bottom plate (201), and the limit rods (203) pass through the interior of the bracket (200), transverse plates (204) are installed on both sides of the lower surface of the bracket (200), and universal wheels (205) are installed on both sides of the bottom of the transverse plate (204).
4. The auxiliary binding tool for building steel bars according to claim 3, characterized in that: Two clearance grooves (300) are provided on the surface of the bottom plate (201), and the two clearance grooves (300) correspond to the two transverse plates (204) respectively.
5. The auxiliary binding tool for building steel bars according to claim 4, characterized in that: A handle (400) is installed on the outer surface of the air cylinder (105), and an anti-slip pad is provided on the outer surface of the handle (400).
6. The construction steel bar auxiliary binding tool according to claim 1, characterized in that: An exhaust pipe (500) is installed on the side of the disc (100) facing away from the gas cylinder (105), and a sealing plug (501) is provided at the end of the exhaust pipe (500).