Synergistic melting treatment equipment for slag and fly ash produced by industrial hazardous waste

By adopting the combined structure of flip bracket, electric arc furnace and pumping mechanism in industrial hazardous waste treatment equipment, the collaborative optimization treatment of slag and fly ash is realized, the problems of incomplete melting and excessive material composition are solved, and the processing efficiency and Environmental safety.

CN221924512UActive Publication Date: 2024-10-29GRANDBLUE ENVIRONMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420479060.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-13
Publication Date
2024-10-29
Estimated Expiration
2034-03-13

AI Technical Summary

Technical Problem

In the existing technology, the slag and fly ash of industrial hazardous waste are often not processed in a coordinated and optimized manner during the molten vitrification treatment, resulting in incomplete melting or excessive material composition produced by the melting.

Method used

A collaborative melting treatment equipment for slag and fly ash produced from industrial hazardous waste is designed. It adopts a structure that combines a turning bracket, an electric arc furnace, a graphite electrode rod, a lifting mechanism and a material conveying mechanism. Through the turning mechanism and the moving water cooling tank, Cooperate with each other to achieve collaborative optimization of slag and fly ash, and control the air pressure of the electric arc furnace through the pressure pumping mechanism to reduce the generation of toxic gases.

Benefits of technology

It effectively reduces the situation of incomplete melting or excessive material composition, improves the melting treatment method, adapts to the fluctuation of blending ratio, and controls the exhaust of flue gas through a micro-negative pressure environment, which helps to reduce environmental hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221924512U_ABST
    Figure CN221924512U_ABST
Patent Text Reader

Abstract

The utility model discloses collaborative melting treatment equipment for slag and fly ash produced by industrial hazardous waste, which comprises a turnover bracket, an electric arc furnace is arranged on the turnover bracket through a turnover mechanism, a plurality of graphite electrode bars are arranged at the top of the electric arc furnace through a lifting mechanism, and the graphite electrode bars extend into the electric arc furnace; a pressure pumping mechanism is further arranged on the top of the electric arc furnace; the pressure pumping mechanism comprises an air inducing pipe cover, an induced draft fan pipe and an induced draft fan; a material conveying mechanism is further arranged on one side of the electric arc furnace and used for conveying materials into the electric arc furnace. And a movable water cooling tank is arranged below the pouring part of the electric arc furnace so as to collect melts. According to the method, the mixed materials of the fly ash, the slag and the quartz sand can be automatically conveyed into the electric arc furnace to be subjected to melting treatment, so that the situation that melting is not thorough or substance components generated by melting exceed the standard can be reduced, collaborative optimization step treatment can be carried out on the slag and the fly ash, the melting treatment method is improved by utilizing mutual characteristics, and the melting treatment efficiency is improved. And the method can adapt to blending proportion fluctuation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of industrial hazardous waste treatment machinery, and in particular to a device for the coordinated melting treatment of slag and fly ash produced by industrial hazardous waste. Background Art

[0002] At present, industrial hazardous waste is prohibited from direct discharge due to its special physical and chemical properties, which can cause great pollution and damage to the environment. Among many harmless treatments, high-temperature incineration using a rotary kiln is considered to be an efficient and safe method. However, this incineration method will produce slag and fly ash, both of which are also defined as hazardous waste (code HW18, incineration disposal residues). The common treatment method is to landfill it, which will occupy land and cause secondary pollution, so melt vitrification treatment has become a new technical direction.

[0003] GB / T410152021 "Technical Requirements for Products of Solid Waste Vitrification Treatment", which was implemented in July 2022, clarifies the composition of substances produced by hazardous waste after various types of melting, testing standards and other bases. It is a guiding technical document for melting and vitrifying hazardous waste. Under the guidance of this standard, it will promote the development and utilization of various melting disposal methods, making it one of the mainstream hazardous waste disposal technologies.

[0004] In the relevant technology, the melting disposal system is divided into three main parts: ① batching system; ② melting system and ③ flue gas treatment system. Among them, ① is introduced in CN113310056A. The batching system generally has pretreatment (crushing and magnetic attraction), weighing, mixing and granulation processes. Crushing is to control the particle size of the slag to prevent excessively large materials from entering the melting system; magnetic attraction is to remove metal blocks such as Fe. Due to the complexity of the various components in the raw materials, in order to lower the melting point, it is often necessary to proportion them so that their chemical composition is close to the theoretical lowest eutectic point. Therefore, after the chemical composition of the processed raw materials is known, additional flux needs to be added. Common ones are powders or particles such as quartz sand, alumina, and limestone, and the added ratio is controlled by weighing.

[0005] After the proportioning is completed, the materials need to be mixed to ensure that the components are evenly distributed. The last step is granulation. Because the particle size of fly ash is small, it will float with the hot flue gas generated in the furnace during the feeding process, causing the fly ash to be unable to fall into the heating area of ​​the furnace and fail to be melted. As the hot flue gas moves, the fly ash particles that are not melted and float away will enter the flue gas treatment system, increasing the burden of flue gas treatment and may even be deposited in the flue and block the flue. Through the granulation method, small particles are agglomerated into larger particles, making them less likely to be carried away by the hot flue gas (CN113798307B uses a small amount of cement for granulation).

[0006] ② Melting system. The melting system can use different heat sources and heating forms (CN113310056A and CN216159615U use plasma torches for heating; CN113701163A and CN113310056A use natural gas combustion for heating; CN115560336B uses an electric furnace). After the material is heated to the designed temperature, it is kept warm for a period of time to melt the material, and then poured out and quenched to form a reusable glass phase material.

[0007] Regarding the above-mentioned related technologies, the utility model applicant believes that: in the related technologies, two types of secondary hazardous wastes produced by high-temperature incineration of industrial hazardous wastes are slag and fly ash. The common melt vitrification treatment is aimed at one of them, or both can be melted, but the two are not processed in a coordinated optimized step, resulting in incomplete melting or excessive composition of the material produced by melting. Utility Model Content

[0008] The purpose of the present application is to provide a synergistic melting treatment device for slag and fly ash produced by industrial hazardous waste, so as to solve the problem that the common melting and vitrification treatment targets only one of them, or both can be melted, but no synergistic optimization steps are performed for both, resulting in incomplete melting or excessive composition of the material produced by the melting.

[0009] The present application provides a slag and fly ash collaborative melting treatment device produced by industrial hazardous waste, which adopts the following technical solution:

[0010] A device for coordinated melting treatment of slag and fly ash produced by industrial hazardous waste, comprising a flip bracket, on which an electric arc furnace is arranged via a flip mechanism, and a plurality of graphite electrode rods are arranged on the top of the electric arc furnace via a lifting mechanism, and the graphite electrode rods extend into the interior of the electric arc furnace; a suction and pressure mechanism is also arranged on the top of the electric arc furnace, and the suction and pressure mechanism comprises an induced draft duct cover connected to the top of the electric arc furnace, one end of the induced draft duct cover is connected to an induced draft fan pipe connected to an external induced draft fan; a material conveying mechanism is also arranged on one side of the electric arc furnace to convey materials to the interior of the electric arc furnace; a mobile water cooling trough is arranged below the tilting of the electric arc furnace to collect the molten material.

[0011] Furthermore, the material conveying mechanism includes a spiral conveying pipe arranged on one side of the electric arc furnace, the discharge end of the spiral conveying pipe is rotatably connected to a feeding pipe, a feeding hole connected to one end of the feeding pipe is opened on the top of the electric arc furnace, a mixing bin is arranged at the feeding end of the spiral conveying pipe, and a conveying motor is arranged at the end of the spiral conveying pipe away from the feeding pipe.

[0012] Furthermore, a coke bin is provided on one side of the spiral conveying pipe close to the mixing bin.

[0013] Furthermore, the lifting mechanism includes a supporting frame arranged on a side wall of the electric arc furnace, the supporting frame is provided with a plurality of vertical slide rails, a sliding seat is slidably provided on the vertical slide rails, a lifting gripper cooperating with the graphite electrode rod is provided on one side of the sliding seat, and a driving assembly is provided between the supporting frame and the sliding seat to drive the sliding seat to move up and down.

[0014] Furthermore, the driving assembly includes a screw rod arranged on the supporting frame, a driving motor is arranged on the supporting frame, an output end of the driving motor is connected to the screw rod through a gear set, and a threaded block threadedly connected to the screw rod is arranged on one side of the sliding seat.

[0015] Furthermore, a plurality of pulleys are provided on both sides of the sliding seat, and the plurality of pulleys are in contact with the vertical sliding rails at the same time.

[0016] Furthermore, an exhaust hole matched with the induced draft duct cover is provided at the top of the electric arc furnace, and a movable part is also provided at the connection between the induced draft fan pipe and the induced draft duct cover.

[0017] Furthermore, the flipping mechanism includes flipping shafts symmetrically arranged on both outer sides of the electric arc furnace, the two flipping shafts are rotatably connected to both sides of the flipping bracket, flipping motors are symmetrically arranged on both sides of the flipping bracket, and the output end of the flipping motor is connected to one end of the flipping shaft.

[0018] Furthermore, a water supply pipe is provided on one side of the mobile water cooling tank, a water outlet end of the water supply pipe extends to the top of the mobile water cooling tank, and a water inlet end of the water supply pipe is connected to an external water supply device.

[0019] Furthermore, a casting pit which is slidably matched with the movable water cooling trough is provided on one side of the flip bracket.

[0020] Compared with the prior art, the beneficial effect of the present application lies in that: by setting a structure in which a flip bracket, an arc furnace, a graphite electrode rod, a lifting mechanism and a material conveying mechanism cooperate with each other, fly ash, slag and a mixture of quartz sand can be automatically conveyed to the arc furnace for melting treatment, thereby reducing the occurrence of incomplete melting or excessive material components produced by melting; then, through the cooperation of the flip mechanism and the mobile water cooling tank, the arc furnace is flipped, so that the molten material in the arc furnace is poured into the mobile water cooling tank for effective collection, and then the slag and fly ash can be processed in a coordinated and optimized step, and the melting treatment method can be improved by utilizing each other's characteristics, and can adapt to fluctuations in the blending ratio.

[0021] At the same time, by setting up the induced draft duct cover, induced draft fan pipe and induced draft fan to cooperate with each other, not only can the gas pressure of the electric arc furnace be controlled when the material is melted, so that the electric arc furnace is in a slightly negative pressure environment during the entire operation; but also a large amount of toxic and harmful gases generated when the slag and fly ash are melted can be absorbed and treated, thereby reducing the situation where the gas generated by the melting of hazardous waste is highly toxic and has great environmental damage. In addition, the appropriate negative pressure can extract the flue gas without drastically affecting the heating rate inside the electric arc furnace. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the structure of the equipment for coordinated melting treatment of slag and fly ash produced by industrial hazardous waste in an embodiment of the present application.

[0023] Figure 2 It is a structural schematic diagram of the material conveying mechanism and the lifting mechanism of the embodiment of the present application.

[0024] Figure 3 It is a structural schematic diagram of the pumping and pressing mechanism of an embodiment of the present application.

[0025] Explanation of the reference numerals in the accompanying drawings: 1. flip bracket; 2. electric arc furnace; 21. electrode rod hole; 22. feed hole; 23. exhaust hole; 3. graphite electrode rod; 4. mobile water cooling tank; 5. material conveying mechanism; 51. spiral conveying pipe; 52. feeding pipe; 53. mixing bin; 54. conveying motor; 55. coke bin; 6. lifting mechanism; 61. bearing frame; 62. vertical slide rail; 63. sliding seat; 64. lifting gripper; 65. screw rod; 66. driving motor; 67. threaded block; 68. pulley; 7. suction and pressure mechanism; 71. induced draft fan pipe; 72. induced draft pipe cover; 73. movable parts; 8. flip motor; 9. water supply pipe; 10. casting pit. DETAILED DESCRIPTION

[0026] The following is combined with Figure 1-3 This application is described in further detail.

[0027] The present application embodiment discloses a slag and fly ash collaborative melting treatment device produced by industrial hazardous waste, referring to Figure 1 and Figure 2 In this embodiment, the device includes a flip bracket 1, a flip mechanism, an arc furnace 2, a graphite electrode rod 3, a mobile water cooling tank 4, a material conveying mechanism 5, a lifting mechanism 6, and a pumping mechanism 7. Among them, there are two flip brackets 1, and the arc furnace 2 is rotatably installed between the two flip brackets 1 through the flip mechanism. The two flip brackets 1 can effectively carry the arc furnace 2, so that the arc furnace 2 is stably installed on the ground of the industrial hazardous waste plant; and the arc furnace 2 can be dumped and unloaded under the action of the flip mechanism.

[0028] Three graphite electrode rods 3 are provided, and the three graphite electrode rods 3 are simultaneously movably installed on the top of the electric arc furnace 2 through the lifting mechanism 6, and the lifting mechanism 6 is installed on the outer wall of the electric arc furnace 2; and three electrode rod holes 21 are opened on the top surface of the electric arc furnace 2, and the three electrode rod holes 21 are respectively matched with the three graphite electrode rods 3. When the lifting mechanism 6 is started, the lifting mechanism 6 drives the graphite electrode rods 3 to be inserted and pulled out of the interior of the electric arc furnace 2 along the electrode rod holes 21.

[0029] At the same time, the furnace transformer on the arc furnace 2 energizes the graphite electrode rods 3, so that the arcs generated by the graphite electrode rods 3 transfer extremely high temperatures to the materials inside the arc furnace 2 to melt the materials. Specifically, when the arc furnace 2 is used for melting, the melting temperature is controlled at around 1300°C.

[0030] The pressure extraction mechanism 7 is arranged on the top of the electric arc furnace 2. When the material is melted, the pressure extraction mechanism 7 can control the gas pressure of the electric arc furnace 2, so that the electric arc furnace 2 is in a slightly negative pressure environment during the whole operation, thereby reducing the gas toxicity and environmental damage caused by the melting of hazardous waste. In addition, the appropriate negative pressure can extract the flue gas without drastically affecting the heating rate inside the electric arc furnace 2.

[0031] The material conveying mechanism 5 is arranged on one side of the electric arc furnace 2. When the electric arc furnace 2 needs melting treatment, the material conveying mechanism 5 can automatically convey the material to the inside of the electric arc furnace 2. Specifically, the conveyed material is fly ash, slag and quartz sand uniformly mixed with each other, and the proportion of fly ash, slag and quartz sand coordinated with each other is 68 parts of slag, 7 parts of fly ash and 25 parts of quartz sand; among them, quartz sand, as a flux, can play an effective fluxing effect.

[0032] The mobile water cooling trough 4 is arranged below the pouring part of the electric arc furnace 2. The mobile water cooling trough 4 can move, and cold water is stored in the mobile water cooling trough 4. After the melting process is completed, the furnace of the electric arc furnace 2 is controlled to rotate a certain angle by utilizing the flipping mechanism, so that the molten material in the electric arc furnace 2 is poured out along the pouring port and flows into the interior of the mobile water cooling trough 4, so that the molten material is uniformly collected and cooled.

[0033] Preferably, a casting pit 10 is opened on the ground on one side of the flip bracket 1, and the casting pit 10 is slidably matched with the movable water cooling trough 4, so that the movable water cooling trough 4 can slide in the casting pit 10, so that more space can be reserved for the dumping of the electric arc furnace 2, and the safety of the operators can also be ensured.

[0034] At the same time, since a large amount of water will evaporate during the rapid cooling process of pouring out the molten material, a water supply pipe 9 is provided on one side of the mobile water cooling tank 4. The water outlet end of the water supply pipe 9 extends to the top of the mobile water cooling tank 4, and the water inlet end of the water supply pipe 9 is connected to an external water supply device. The water supply device can effectively supply water to the water supply pipe 9, so that the water supply pipe 9 can continuously cool down and supply water into the mobile water cooling tank 4.

[0035] Therefore, by setting up a structure in which the flip bracket 1, the electric arc furnace 2, the graphite electrode rod 3, the lifting mechanism 6 and the material conveying mechanism 5 cooperate with each other, the fly ash, slag and quartz sand mixture can be automatically conveyed to the electric arc furnace 2 for melting treatment, thereby reducing the occurrence of incomplete melting or excessive material components produced by melting.

[0036] Then, the arc furnace 2 is flipped through the cooperation of the flipping mechanism and the mobile water-cooling tank 4, so that the molten material in the arc furnace 2 is poured into the mobile water-cooling tank 4 for effective collection, thereby being able to perform coordinated optimization steps for both slag and fly ash, utilizing each other's characteristics, improving the melting treatment method, and adapting to fluctuations in the blending ratio.

[0037] The structures of the material conveying mechanism 5, the lifting mechanism 6, the pumping and pressing mechanism 7 and the turning mechanism are described in detail below:

[0038] Specifically, refer to Figure 1 and Figure 2 In this embodiment, the material conveying mechanism 5 includes a spiral conveying pipe 51, a feeding pipe 52, a mixing bin 53 and a conveying motor 54. The spiral conveying pipe 51 is installed on one side of the electric arc furnace 2 through a support frame; one end of the feeding pipe 52 is rotatably connected to the discharge end of the spiral conveying pipe 51, and a feeding hole 22 is opened on the top of the electric arc furnace 2. One end of the feeding pipe 52 away from the spiral conveying pipe 51 cooperates with the feeding hole 22, so that one end of the feeding pipe 52 extends into the electric arc furnace 2 along the feeding hole 22, thereby feeding the inside of the electric arc furnace 2.

[0039] The mixing bin 53 is installed at the feeding end of the spiral conveying pipe 51. The mixing bin 53 and the spiral conveying pipe 51 are interconnected, and the mixing bin 53 itself is equipped with a mixer to evenly mix the fly ash, slag and quartz sand; the conveying motor 54 is installed at one end of the spiral conveying pipe 51 away from the feeding pipe 52, and the output end of the conveying motor 54 is interconnected with one end of the spiral rod in the spiral conveying pipe 51.

[0040] When the arc furnace 2 needs to be loaded with materials for melting, the conveying motor 54 is started, and the output end of the conveying motor 54 drives the screw rod in the spiral conveying pipe 51 to rotate, and the mixed material in the mixing bin 53 is fed into the spiral conveying pipe 51, and the screw rod in the spiral conveying pipe 51 further mixes the mixed material and transports it to the feeding pipe 52, and the outlet end of the feeding pipe 52 is connected to the feeding hole 22 to transport the mixed material to the interior of the arc furnace 2, thereby completing the conveying process of the mixed material.

[0041] Preferably, in this embodiment, a coke bin 55 is installed on one side of the spiral conveying pipe 51 near the mixing bin 53, the coke bin 55 is connected to the spiral conveying pipe 51, and coke is stored in the coke bin 55. The function of the coke is to be added to the interior of the electric arc furnace 2 each time the electric arc furnace 2 is started, so as to help heat up and generate a molten pool. After the electric arc furnace 2 completes the feeding of the mixed material, the coke is transported into the interior of the electric arc furnace 2 through the spiral conveying pipe 51, and the operator manually lays the coke through the feed hole 22, and closes the feed hole 22 after completion to start the melting process.

[0042] At the same time, refer to Figure 1 and Figure 2 In this embodiment, the lifting mechanism 6 includes a carrier 61, a vertical slide rail 62, a sliding seat 63, a lifting gripper 64 and a driving assembly. The carrier 61 is mounted on an outer wall of the electric arc furnace 2; three vertical slide rails 62 are provided, and the three vertical slide rails 62 are respectively installed on the top of the carrier 61; three sliding seats 63 are provided, and the three sliding seats 63 are respectively slidably installed on the three vertical slide rails 62; three lifting grippers 64 are provided, and the three lifting grippers 64 are respectively installed on the side of the three sliding seats 63 facing the electric arc furnace 2, and the three lifting grippers 64 cooperate with the three graphite electrode rods 3 respectively to fasten and limit the graphite electrode rods 3.

[0043] There are three drive assemblies, which are respectively arranged between the carrier 61 and the sliding seat 63 to drive the sliding seat 63 to move up and down. Specifically, in this embodiment, the drive assembly includes a screw 65, a drive motor 66 and a threaded block 67. The screw 65 is vertically installed on the top of the carrier 61; the drive motor 66 is installed on the top of the carrier 61, and the output end of the drive motor 66 is connected to the screw 65 through a gear set to drive the screw 65 to rotate; the threaded block 67 is installed on the side of the sliding seat 63 away from the lifting gripper 64, and the threaded block 67 is threadedly connected to the screw 65.

[0044] When the drive motor 66 is started, the output end of the drive motor 66 drives the gear set to be linked, and under the linkage of the gear set, the screw rod 65 is driven to rotate, so that the threaded block 67 drives the sliding seat 63 to move up and down, and the sliding seat 63 drives the graphite electrode rod 3 on the lifting gripper 64 to move up and down, thereby realizing the lifting and insertion of the graphite electrode rod 3 along the electrode rod hole 21 in the electric arc furnace 2, and then facilitating the graphite electrode rod 3 to be extended into the electric arc furnace 2 or extended out of the electric arc furnace 2.

[0045] Preferably, in this embodiment, a plurality of pulleys 68 are installed on both sides of the sliding seats 63, and the pulleys 68 are in contact with the vertical slide rails 62. The arrangement of the pulleys 68 can reduce the friction between the sliding seat 63 and the vertical slide rails 62, so that the sliding seat 63 can slide more smoothly.

[0046] In addition, refer to Figure 2 and Figure 3 In this embodiment, the extraction and pressure mechanism 7 includes an induced draft fan, an induced draft fan pipe 71 and an induced draft pipe cover 72. The induced draft fan is installed on one side of the electric arc furnace 2; one end of the induced draft fan pipe 71 is connected to the exhaust end of the induced draft fan; the induced draft pipe cover 72 is installed on the end of the induced draft fan pipe 71 away from the induced draft fan, and an exhaust hole 23 is also opened on the top of the electric arc furnace 2. The exhaust hole 23 and the induced draft pipe cover 72 are connected and matched with each other, so that the induced draft pipe cover 72 covers the exhaust hole 23 and its surroundings.

[0047] When the induced draft fan is started, suction is generated at the induced draft duct cover 72, so that the air pressure in the arc furnace 2 can be controlled along the exhaust holes 23, so that the arc furnace 2 is in a slightly negative pressure environment during the entire operation. At the same time, a large amount of toxic and harmful gases will be generated when the slag and fly ash are melted. The induced draft duct cover 72 absorbs and processes these large amounts of toxic and harmful gases, thereby reducing the occurrence of highly toxic gases generated by the melting of hazardous wastes and the occurrence of severe environmental hazards.

[0048] Specifically, the negative pressure value in the furnace of the electric arc furnace 2 should be maintained at -26Pa. During the whole process, the induced draft fan is required to control the air pressure in the furnace to keep it at a slightly negative pressure. When the negative pressure value is too large, a large amount of light fly ash particles will be drawn away, causing the formula component deviation; at the same time, the heat will be taken away, causing the temperature of the high-temperature section in the furnace to rise slowly, and even unable to reach the designed melting temperature.

[0049] When the negative pressure value is too small, the flue gas will leak out from the gaps such as the feed hole 22 and the electrode rod hole 21 of the electric arc furnace 2, causing air pollution; at the same time, there is not enough air at the beginning of heating, resulting in incomplete oxidation exothermic reaction and a decrease in the heating rate. Therefore, a suitable negative pressure can remove the flue gas without drastically affecting the heating rate.

[0050] In addition, refer to Figure 2 and Figure 3 In this embodiment, the flip mechanism includes a flip shaft and a flip motor 8. There are two flip shafts, one end of which is symmetrically mounted on the two outer side walls of the electric arc furnace 2, and the other ends of which are rotatably connected to the two sides of the flip bracket 1, so that the electric arc furnace 2 can be tilted and flipped on the flip bracket 1 through the flip shaft. There are two flip motors 8, which are symmetrically mounted on the two sides of the flip bracket 1, and the output end of the flip motor 8 is connected to the end of the flip shaft away from the electric arc furnace 2.

[0051] When the two turning motors 8 are started, the output ends of the two turning motors 8 simultaneously drive the two turning shafts to rotate, so that the electric arc furnace 2 can automatically dump and unload the melt to pour it into the interior of the mobile water cooling tank 4.

[0052] Preferably, in this embodiment, a movable part 73 is also installed at the connection between the induced draft fan pipe 71 and the induced draft duct cover 72. The induced draft duct cover 72 can continuously draw air into the induced draft fan pipe 71 through the movable part 73, so that the movable part 73 cooperates with the flipping mechanism to achieve the effect of synchronously tilting the induced draft duct cover 72 and the arc furnace 2.

[0053] The implementation principle of the slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste in an embodiment of the present application is as follows: when the electric arc furnace 2 needs to be loaded and melted, the drive motor 66 is started first, and the output end of the drive motor 66 drives the gear set to be linked, and under the linkage of the gear set, the screw rod 65 is driven to rotate, so that the threaded block 67 drives the sliding seat 63 to lift and slide, and the sliding seat 63 drives the graphite electrode rod 3 on the lifting gripper 64 to be inserted and pulled out into the electric arc furnace 2 along the electrode rod hole 21.

[0054] At the same time, the conveying motor 54 is started, and the output end of the conveying motor 54 drives the screw rod in the spiral conveying pipe 51 to rotate, and the mixed material in the mixing bin 53 is discharged into the spiral conveying pipe 51, and the screw rod in the spiral conveying pipe 51 further mixes the mixed material and transports it to the feeding pipe 52, and the outlet end of the feeding pipe 52 is connected to the feeding hole 22 to transport the mixed material to the interior of the electric arc furnace 2; when the electric arc furnace 2 completes the feeding of the mixed material, the coke in the coke bin 55 is transported into the interior of the electric arc furnace 2 through the spiral conveying pipe 51, and the operator manually levels the coke through the feeding hole 22, and closes the feeding hole 22 after completion.

[0055] Then the electric arc furnace 2 is started, and the electric furnace transformer on the electric arc furnace 2 energizes the graphite electrode rods 3, so that the graphite electrode rods 3 will transfer the extremely high temperature to the material inside the electric arc furnace 2 to melt the material. After reaching the melting temperature point, the melt is kept warm for 60 minutes. At the same time, the induced draft fan needs to be started during the melting process to generate suction at the induced draft pipe cover 72, so that the air pressure in the electric arc furnace 2 can be controlled along the exhaust hole 23, so that the negative pressure value in the furnace of the electric arc furnace 2 should be maintained at a slightly negative pressure state of -26Pa.

[0056] Finally, when the molten material is kept warm, the two flip motors 8 are started, and the output ends of the two flip motors 8 simultaneously drive the two flip shafts to rotate, so that the electric arc furnace 2 can automatically dump and unload the material, so as to pour the molten material into the interior of the mobile water cooling tank 4, so as to collect the molten material, thereby completing the melting process of the electric arc furnace 2.

[0057] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste, characterized by: The invention comprises a flip support (1), an electric arc furnace (2) is arranged on the flip support (1) via a flip mechanism, a plurality of graphite electrode rods (3) are arranged on the top of the electric arc furnace (2) via a lifting mechanism (6), and the graphite electrode rods (3) extend into the interior of the electric arc furnace (2); a suction and pressure mechanism (7) is also arranged on the top of the electric arc furnace (2), and the suction and pressure mechanism (7) comprises an induced draft pipe cover (72) connected to the top of the electric arc furnace (2), and one end of the induced draft pipe cover (72) is connected to an induced draft fan pipe (71) connected to an external induced draft fan; a material conveying mechanism (5) is also arranged on one side of the electric arc furnace (2) to convey materials to the interior of the electric arc furnace (2); a movable water cooling tank (4) is arranged below the tilting part of the electric arc furnace (2) to collect molten material.

2. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 1 is characterized by: The material conveying mechanism (5) comprises a spiral conveying pipe (51) arranged on one side of the electric arc furnace (2); the discharge end of the spiral conveying pipe (51) is rotatably connected to a feeding pipe (52); a feeding hole (22) connected to one end of the feeding pipe (52) is provided on the top of the electric arc furnace (2); a mixing bin (53) is provided at the feeding end of the spiral conveying pipe (51); and a conveying motor (54) is provided at one end of the spiral conveying pipe (51) away from the feeding pipe (52).

3. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 2 is characterized by: A coke bin (55) is also provided on one side of the spiral conveying pipe (51) close to the mixing bin (53).

4. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 1 is characterized by: The lifting mechanism (6) comprises a support frame (61) arranged on a side wall of the electric arc furnace (2), a plurality of vertical slide rails (62) are arranged on the support frame (61), a sliding seat (63) is slidably arranged on the vertical slide rail (62), a lifting gripper (64) matched with the graphite electrode rod (3) is arranged on one side of the sliding seat (63), and a driving component is arranged between the support frame (61) and the sliding seat (63) to drive the sliding seat (63) to move up and down.

5. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 4, characterized in that: The driving assembly comprises a screw rod (65) arranged on the supporting frame (61), a driving motor (66) is arranged on the supporting frame (61), an output end of the driving motor (66) is connected to the screw rod (65) via a gear set, and a threaded block (67) threadedly connected to the screw rod (65) is arranged on one side of the sliding seat (63).

6. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 5, characterized in that: A plurality of pulleys (68) are also provided on both sides of the sliding seat (63), and the plurality of pulleys (68) are in contact with the vertical sliding rail (62) at the same time.

7. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 1, characterized in that: The top of the electric arc furnace (2) is provided with an exhaust hole (23) matched with the induced draft pipe cover (72), and a movable part (73) is also provided at the connection between the induced draft fan pipe (71) and the induced draft pipe cover (72).

8. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 1, characterized in that: The flip mechanism comprises flip shafts symmetrically arranged on two outer sides of the electric arc furnace (2), the two flip shafts are rotatably connected to the two sides of the flip bracket (1), and flip motors (8) are symmetrically arranged on the two sides of the flip bracket (1), and the output end of the flip motor (8) is connected to one end of the flip shaft.

9. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 1, characterized in that: A water supply pipe (9) is provided on one side of the mobile water cooling tank (4), the water outlet end of the water supply pipe (9) extends to the top of the mobile water cooling tank (4), and the water inlet end of the water supply pipe (9) is connected to an external water supply device.

10. The slag and fly ash collaborative melting treatment equipment produced by industrial hazardous waste according to claim 9, characterized in that: A casting pit (10) which is slidably matched with the movable water cooling trough (4) is also provided on one side of the flip bracket (1).