Preparation tank for gel paste production
By designing a preparation tank for gel paste production with linkage mechanism and pressurization pump, the mixing and cleaning problems in gel processing are solved, and the production efficiency and discharge efficiency are improved.
Patent Information
- Application Number
- CN202420432451.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-06
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2034-03-06
AI Technical Summary
During the processing process, the gel is difficult to mix evenly due to its high viscosity and is easy to adhere to the inner wall of the preparation tank, resulting in an increase in production costs. It is necessary to stir and clean the inner wall of the preparation tank at the same time.
A preparation tank for gel paste production is designed, equipped with a detachable top cover, a rotating mixing rod, a linkage mechanism, a scraper and a pressurization pump. The linkage mechanism drives the mixing rod and scraper to rotate simultaneously for cleaning, and use the linkage mechanism to add Pressure pump improves gel discharge efficiency.
It realizes efficient mixing of gels and cleaning of the inner wall of the preparation tank, reducing production costs and improving gel discharge efficiency.
Smart Images

Figure CN221933803U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of gel paste production, in particular to a preparation tank for gel paste production. Background Art
[0002] At present, the colloidal particles or polymers in the sol or solution are interconnected under certain conditions to form a spatial network structure. The gaps in the structure are filled with liquid (or gas in dry gel, which is also called aerogel) as a dispersion medium. Such a special dispersion system is called gel. There is no fluidity and often contains a large amount of liquid inside. For example, the water content of blood gel and agar can reach more than 99%. It can be divided into elastic gel and brittle gel. After the elastic gel loses the dispersion medium, the volume is significantly reduced, and when the dispersion medium is reabsorbed, the volume expands again, such as gelatin, etc. When the brittle gel loses or reabsorbs the dispersion medium, the shape and volume do not change, such as silica gel, etc. The process of forming a gel from a solution or sol is called gelation.
[0003] Among them, under appropriate conditions, the viscosity of a polymer solution or sol of a certain concentration gradually increases and finally loses fluidity, and the entire system becomes an elastic semisolid with a uniform appearance and a certain shape. This elastic semisolid is called a gel.
[0004] However, due to the high viscosity of the gel, it is difficult to mix the gel during processing and it is very easy to adhere to the inner wall of the preparation tank. The gel needs to be stirred and the inner wall of the preparation tank needs to be cleaned simultaneously, which requires multiple sets of motors to operate synchronously, greatly increasing the production cost. Therefore, a new technical solution needs to be designed to solve the problem, which can clean the inner wall of the preparation tank while stirring the gel. Utility Model Content
[0005] The utility model aims to provide a preparation tank for gel paste production, which solves the problems raised in the background technology.
[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a preparation tank for gel paste production, comprising a preparation tank, a top cover is detachably mounted on the top of the preparation tank, stirring rods are rotatably mounted on both sides of the top cover, a rotating rod is rotatably mounted in the middle of the top cover, and a linkage mechanism is mounted on the top cover;
[0007] The linkage mechanism includes a gear ring fixedly installed on the outer side of the top of the two groups of rotating rods, a large gear fixedly installed on the top of the stirring rod, a transmission gear shaft fixedly installed on the outer side of the bottom of the two groups of rotating rods, and a toothed belt connected to the two groups of transmission gear shafts, and the large gear is meshed with the two groups of gear rings.
[0008] As an optional solution to the technical solution of the present application, protective covers are fixedly installed on the top and bottom of the cover, and a servo motor is fixedly installed on one side of the protective cover at the top. The drive output end of the servo motor is connected to the transmission shaft, and the other end of the transmission shaft is fixedly connected to the top of the rotating rod on one side, which can drive the rotating rod on the displaced side to rotate.
[0009] As an optional solution of the technical solution of the present application, stirring paddles are fixedly installed at the bottom of the two groups of rotating rods to mix the gel inside the preparation tank.
[0010] As an optional solution of the technical solution of the present application, connecting frames are fixedly installed on both sides of the stirring rod, and scrapers are fixedly installed on the other sides of the two groups of connecting frames. The outer walls of the two groups of scrapers are in contact with the inner wall of the preparation tank, so that the gel on the inner wall of the preparation tank can be cleaned.
[0011] As an optional solution of the technical solution of the present application, a pressure pump is fixedly installed on the side wall of the preparation tank, and the air inlet end of the pressure pump is connected to the preparation tank and installed to pressurize the interior of the preparation tank.
[0012] As an optional solution of the technical solution of the present application, a discharge pipe is installed at the bottom of the preparation tank, and a valve is installed on the discharge pipe to control the discharge of the discharge pipe.
[0013] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0014] 1. The technical solution of the present application uses a linkage mechanism. When the two sets of rotating rods rotate synchronously, the gear rings on the top of the two sets of rotating rods will be driven to rotate. The large gear meshing with the two sets of gear rings will also rotate slowly with the rotation of the gear rings, driving the scraper at the bottom to clean the gel on the inner wall of the preparation tank, ensuring that the linkage mechanism can synchronously drive the stirring paddle and the scraper to rotate, and efficiently complete the processing of the gel.
[0015] 2. The technical solution of the present application is to fix a pressure pump on the side wall of the preparation tank, and the air inlet end of the pressure pump is connected to the preparation tank. When the preparation tank completes the processing of the gel, the pressure pump can be driven to pressurize the inside of the preparation tank, and the gel inside the preparation tank is pressurized to facilitate the discharge of the gel from the discharge pipe, thereby improving the gel discharge efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:
[0017] Figure 1 This is a schematic diagram of the overall structure of a preparation tank for gel paste production according to the utility model;
[0018] Figure 2The utility model is a schematic diagram of the linkage mechanism structure of a preparation tank for gel paste production.
[0019] In the figure: 1. preparation tank; 11. top cover; 12. stirring rod; 13. rotating rod; 2. gear ring; 21. large gear; 22. transmission gear shaft; 23. toothed belt; 24. protective cover; 25. servo motor; 3. stirring paddle; 31. connecting frame; 32. scraper; 33. discharge pipe; 34. pressure pump. DETAILED DESCRIPTION
[0020] See also Figure 1-2 The utility model provides a technical solution: a preparation tank 1 for gel paste production, comprising a preparation tank 1, a top cover 11 is detachably installed on the top of the preparation tank 1, stirring rods 12 are rotatably installed on both sides of the top cover 11, a rotating rod 13 is rotatably installed in the middle of the top cover 11, and a linkage mechanism is installed on the top cover 11;
[0021] The linkage mechanism includes a gear ring 2 fixedly installed on the outer side of the top of the two sets of rotating rods 13, a large gear 21 fixedly installed on the top of the stirring rod 12, a transmission gear shaft 22 fixedly installed on the outer side of the bottom of the two sets of rotating rods 13, and a toothed belt 23 connected to the two sets of transmission gear shafts 22, and the large gear 21 is meshed with the two sets of gear rings 2.
[0022] In this technical solution, by driving the servo motor 25 on the top of the top cover 11, the rotating rod 13 on one side can be driven to rotate, and the toothed belt 23 connected to the outer side of the two sets of transmission gear shafts 22 can synchronously drive the stirring paddle 3 at the bottom of the two sets of rotating rods 13 to rotate, so as to efficiently mix the gel inside the preparation tank 1. At the same time, through the linkage mechanism, when the two sets of rotating rods 13 rotate synchronously, the gear ring 2 on the top of the two sets of rotating rods 13 will be driven to rotate, and the large gear 21 meshing with the two sets of gear rings 2 will also rotate slowly with the rotation of the gear ring 2, driving the scraper 32 at the bottom to clean the gel on the inner wall of the preparation tank 1, ensuring that the linkage mechanism can synchronously drive the stirring paddle 3 and the scraper 32 to rotate, and efficiently complete the processing of the gel.
[0023] In some technical solutions, a pressure pump 34 is fixedly installed on the side wall of the preparation tank 1, and the air inlet end of the pressure pump 34 is connected to the preparation tank 1 to pressurize the inside of the preparation tank 1. A discharge pipe 33 is installed at the bottom of the preparation tank 1 to control the discharge of the discharge pipe 33.
[0024] In this technical solution, after the preparation tank 1 completes the processing of the gel, the pressure pump 34 can be driven to pressurize the inside of the preparation tank 1, thereby pressurizing the gel inside the preparation tank 1 to facilitate the discharge of the gel from the discharge pipe 33, thereby improving the gel discharge efficiency.
[0025] In some technical solutions, stirring paddles 3 are fixedly installed at the bottom of the two groups of rotating rods 13, which can mix the gel inside the preparation tank 1. Connecting frames 31 are fixedly installed on both sides of the stirring rods 12, and scrapers 32 are fixedly installed on the other sides of the two groups of connecting frames 31. The outer walls of the two groups of scrapers 32 are in contact with the inner wall of the preparation tank 1, so that the gel on the inner wall of the preparation tank 1 can be cleaned.
[0026] In this technical solution, the gel inside the preparation tank 1 can be mixed by the stirring paddles 3 on both sides of the preparation tank 1, and the gel on the inner wall of the preparation tank 1 can be cleaned by the scraper 32 to prevent the gel from adhering to the inner wall of the preparation tank 1 for a long time.
[0027] In some technical solutions, protective covers 24 are fixedly installed on the top and bottom of the cover, and a servo motor 25 is fixedly installed on one side of the top protective cover 24. The drive output end of the servo motor 25 is connected to the transmission shaft, and the other end of the transmission shaft is fixedly connected to the top of the rotating rod 13 on one side, which can drive the rotating rod 13 on one side to rotate.
[0028] In this technical solution, the protective covers 24 installed on both sides of the cover can protect the linkage mechanism, and the servo motor 25 can drive the rotating rod 13 on one side to rotate.
[0029] When a preparation tank 1 for producing a gel paste is used, it should be noted that the utility model is a preparation tank 1 for producing a gel paste, and each component is a universal standard part or a component known to technical personnel in this field, and its structure and principle can be known to technical personnel through technical manuals or through conventional experimental methods.
[0030] When in use, the servo motor 25 on the top of the top cover 11 is driven to drive the rotating rod 13 on one side to rotate, and the toothed belt 23 connected to the outer side of the two sets of transmission gear shafts 22 can synchronously drive the stirring paddle 3 at the bottom of the two sets of rotating rods 13 to rotate, so as to efficiently mix the gel inside the preparation tank 1. At the same time, through the linkage mechanism, when the two sets of rotating rods 13 rotate synchronously, the gear ring 2 on the top of the two sets of rotating rods 13 will be driven to rotate, and the large gear 21 meshing with the two sets of gear rings 2 will also rotate slowly with the rotation of the gear ring 2. The scraper 32 at the bottom is driven to clean the gel on the inner wall of the preparation tank 1, ensuring that the linkage mechanism can synchronously drive the stirring paddle 3 and the scraper 32 to rotate, and efficiently complete the processing of the gel. At the same time, a pressure pump 34 is fixedly installed on the side wall of the preparation tank 1, and the air inlet end of the pressure pump 34 is connected and installed with the preparation tank 1. When the preparation tank 1 completes the processing of the gel, the pressure pump 34 can be driven to pressurize the inside of the preparation tank 1, and the gel inside the preparation tank 1 is pressurized, which is convenient for the gel to be discharged from the discharge pipe 33, thereby improving the gel discharge efficiency.
Claims
1. A preparation tank for gel paste production, comprising a preparation tank (1), characterized in that: The top of the preparation tank (1) is detachably mounted with a top cover (11), stirring rods (12) are rotatably mounted on both sides of the top cover (11), a rotating rod (13) is rotatably mounted in the middle of the top cover (11), and a linkage mechanism is mounted on the top cover (11); The linkage mechanism comprises a toothed ring (2) fixedly mounted on the outer sides of the tops of the two groups of rotating rods (13), a large gear (21) fixedly mounted on the tops of the stirring rods (12), a transmission gear shaft (22) fixedly mounted on the outer sides of the bottoms of the two groups of rotating rods (13), and a toothed belt (23) connected to the two groups of transmission gear shafts (22), wherein the large gear (21) is meshed with the two groups of toothed rings (2).
2. A preparation tank (1) for gel paste production according to claim 1, characterized in that: A protective cover (24) is fixedly installed on the top and bottom of the top cover, and a servo motor (25) is fixedly installed on one side of the protective cover (24) at the top. The drive output end of the servo motor (25) is connected to the transmission shaft in a transmission connection, and the other end of the transmission shaft is fixedly connected to the top of the rotating rod (13) at one side.
3. A preparation tank (1) for gel paste production according to claim 1, characterized in that: A stirring paddle (3) is fixedly mounted on the bottom of the two groups of rotating rods (13).
4. A preparation tank (1) for producing a gel paste according to claim 1, characterized in that: Connecting frames (31) are fixedly mounted on both sides of the stirring rod (12), and scrapers (32) are fixedly mounted on the other sides of two groups of the connecting frames (31), and the outer walls of the two groups of the scrapers (32) are in contact with the inner wall of the preparation tank (1).
5. A preparation tank (1) for producing a gel paste according to claim 1, characterized in that: A pressure pump (34) is fixedly mounted on the side wall of the preparation tank (1), and an air inlet end of the pressure pump (34) is connected to the preparation tank (1).
6. A preparation tank (1) for gel paste production according to claim 1, characterized in that: The bottom of the preparation tank (1) is connected to a discharge pipe (33), and a valve is installed on the discharge pipe (33).