By designing semi-finished photovoltaic panel array installation equipment, and using the combination of main car and hanger trolley to directly lift and install semi-finished photovoltaic panel array, the problem of low installation efficiency of existing photovoltaic panels is solved and the installation efficiency is significantly improved.
Patent Information
- Application Number
- CN202323133728.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-20
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2033-11-20
AI Technical Summary
The installation process of existing photovoltaic panels is inefficient, mainly due to manual assembly and large size of photovoltaic brackets, resulting in huge on-site installation workload and long construction period.
A semi-finished photovoltaic panel array installation equipment is designed, including the main car, a hanger car and a scatter. Through the sliding connection between the main car's walking mechanism and the hanger car, the semi-finished photovoltaic panel array can be directly lifted and installed, simplifying the installation process.
It greatly improves the efficiency of photovoltaic panel installation, reduces the complexity of manual single-piece installation and on-site measurement time, and shortens the construction period.
Smart Images

Figure CN221939939U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of photovoltaic panel installation, and in particular to a photovoltaic panel array semi-finished product installation device. Background Art
[0002] The installation process of existing photovoltaic panels is mainly done by manual assembly. The photovoltaic brackets are large in size and each photovoltaic panel is heavy, resulting in a huge workload for manual on-site installation. In addition, the dimensions need to be repeatedly measured on site, resulting in a long construction period and low installation efficiency. Utility Model Content
[0003] The embodiment of the present application provides a photovoltaic panel array semi-finished product installation device, which can improve the installation efficiency of photovoltaic panels.
[0004] An embodiment of the present application provides a photovoltaic panel array semi-finished product installation device, including: a main vehicle, including a vertical support assembly, a transverse support assembly and a traveling mechanism assembly, the transverse support assembly is carried on one side of the vertical support assembly along the vertical direction, the traveling mechanism assembly is arranged on the other side of the vertical support assembly along the vertical direction, the transverse support assembly includes a first unit and a second unit distributed side by side along a first direction, the first unit and the vertical support assembly are enclosed together to form a first space, and the second unit and the vertical support assembly are enclosed together to form a second space; a hanger trolley, slidably connected to the transverse support assembly of the main vehicle, for connecting a hanger; wherein the first direction intersects with the vertical direction, the first space can provide an installation working space for the photovoltaic panel array semi-finished product hoisted on the hanger, and the second space can provide a hoisting working space for the photovoltaic panel array semi-finished product to be hoisted on the hanger.
[0005] In some embodiments of the present application, the vertical support assembly includes a plurality of brackets, and the plurality of brackets are distributed at intervals along the circumference of a first unit of the lateral support assembly, and the second unit extends the vertical support assembly along the first direction and is suspended above the second space; or, the plurality of brackets are distributed along the circumference of the lateral support assembly.
[0006] In some embodiments of the present application, the vertical support assembly also includes a first reinforcing beam and a second reinforcing beam, the first reinforcing beam is arranged between adjacent brackets spaced apart along the first direction, and the second reinforcing beam is arranged between adjacent brackets spaced apart along the second direction; the first direction and the second direction intersect each other vertically.
[0007] In some embodiments of the present application, the lateral support assembly includes two or more beams spaced apart in the second direction, each beam extending along the first direction and spanning the first unit and the second unit; the lateral support assembly also includes two or more connecting beams spaced apart in the first direction, each connecting beam connected between adjacent beams; adjacent brackets spaced apart along the first direction are connected to the beams via a first reinforcing beam.
[0008] In some embodiments of the present application, a slide rail is provided on the side of each beam facing away from the walking mechanism assembly, the two opposite ends of the hanger trolley along the second direction are connected to two adjacent beams, and each end is provided with a slider that can be coupled to the slide rail so that the hanger trolley can be slidably connected to the lateral support assembly.
[0009] In some embodiments of the present application, the walking mechanism assembly includes a plurality of walking mechanisms correspondingly connected to each bracket, and each walking mechanism includes a connecting frame and a plurality of linked traveling wheels.
[0010] In some embodiments of the present application, the hanger trolley includes two or more hangers arranged in a vertical stack, one of the two or more hangers is connected to a lateral support assembly and is movably arranged along a first direction, and at least another one of the two or more hangers can be movably connected to one in multiple directions.
[0011] In some embodiments of the present application, the two or more hangers include a first hanger and a second hanger, the first hanger is connected to the lateral support assembly, the second hanger is connected to the first hanger and is movably arranged in multiple directions relative to the first hanger, and the hanger is connected to the second hanger; the hanger includes multiple connecting parts and lifting parts, the lifting parts are connected to the second hanger through multiple connecting parts, and the connecting parts are telescopic parts with adjustable length.
[0012] In some embodiments of the present application, a plurality of connecting members are distributed in an array along a first direction and a second direction and are spaced apart from each other to be connected to different positions of a hanging member, and each connecting member can be independently controlled along a vertical length to adjust the spatial orientation posture and orientation angle of the hanging member.
[0013] In some embodiments of the present application, each connecting member is slidably or rollingly disposed on the second hanger.
[0014] In some embodiments of the present application, the connecting member includes a winding mechanism and a connecting rope. The winding mechanism is arranged on the second hanger, at least part of the connecting rope is wound around the winding mechanism, the winding mechanism is connected to the hanging member through the connecting rope, and the winding mechanism is configured to achieve variable length of the connecting member by winding the connecting rope.
[0015] The photovoltaic panel array semi-finished product installation equipment provided in the embodiment of the present application can directly lift the photovoltaic panel array semi-finished product formed by splicing multiple photovoltaic panels to the installation position and installation height for direct installation operations, thereby solving the problem of low installation efficiency caused by manual installation of single photovoltaic panels and improving the efficiency of photovoltaic panel installation operations. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Other features, objects and advantages of the present application will become more apparent by reading the following detailed description of non-limiting embodiments with reference to the accompanying drawings, in which the same or similar reference numerals represent the same or similar features.
[0017] Figure 1 It is a structural schematic diagram of a photovoltaic panel array semi-finished product installation device provided in an embodiment of the present application;
[0018] Figure 2 It is a schematic diagram of the structure of the connecting member and the hanging member provided in the embodiment of the present application;
[0019] Figure 3 yes Figure 1 A partial enlarged view of area A.
[0020] Explanation of the reference numerals: 100, main vehicle; 110, vertical support assembly; 111, bracket; 113, first reinforcing beam; 112, second reinforcing beam; 120, walking mechanism assembly; 121, connecting frame; 122, walking wheel; 130, lateral support assembly; 131, first unit; 132, second unit; 133, crossbeam; 134, connecting beam; 135, slide rail; 200, hanger trolley; 210, first hanger; 220, second hanger; 300, hanger; 310, connector; 311, winding mechanism; 312, connecting rope; 320, lifting member; 400, photovoltaic panel array semi-finished product. DETAILED DESCRIPTION
[0021] The features and exemplary embodiments of various aspects of the present application will be described in detail below. In the detailed description below, many specific details are proposed to provide a comprehensive understanding of the present application. However, it is obvious to those skilled in the art that the present application can be implemented without the need for some of these specific details. The following description of the embodiments is only to provide a better understanding of the present application by illustrating examples of the present application. In the accompanying drawings and the following description, at least some of the known structures and technologies are not shown to avoid unnecessary ambiguity in the present application; and, for clarity, the size of some structures may be exaggerated. In addition, the features, structures or characteristics described below may be combined in one or more embodiments in any suitable manner.
[0022] In the description of the present application, it should be noted that, unless otherwise specified, "multiple" means more than two; the terms "upper", "lower", "left", "right", "inner", "outer", etc., indicating directions or positional relationships, are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as limiting the present application. In addition, the terms "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0023] The directional words appearing in the following description are all directions shown in the figures, and do not limit the specific structure of the embodiments of the present application. In the description of the present application, it should also be noted that, unless otherwise clearly specified and limited, the terms "installation" and "connection" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to the specific circumstances.
[0024] In order to better understand this application, Figures 1 to 3 The photovoltaic panel array semi-finished product installation equipment of the embodiment of the present application is described in detail.
[0025] like Figures 1 to 3 As shown, the first aspect of the present application proposes a photovoltaic panel array semi-finished product installation device, which includes: a main vehicle 100 and a hanger trolley 200, the main vehicle 100 includes a vertical support assembly 110, a walking mechanism assembly 120 and a transverse support assembly 130, the transverse support assembly 130 is carried on one side of the vertical support assembly 110, the walking mechanism assembly 120 is arranged on the other side of the vertical support assembly 110, the transverse support assembly 130 includes a first unit 131 and a second unit 132 distributed side by side along a first direction, the first unit 131 and the vertical support assembly 110 are enclosed together to form a first space, and the second unit 132 and the vertical support assembly 110 are enclosed together to form a second space. The hanger trolley 200 is slidably connected to the transverse support assembly 130 of the main vehicle 100, and is used to connect the sling 300. The first direction intersects with the vertical direction, and the first space can provide an installation work space for the semi-finished photovoltaic panel array that has been hoisted on the hoist 300, and the second space can provide a hoisting work space for the semi-finished photovoltaic panel array waiting to be hoisted to the hoist 300.
[0026] In the embodiment provided in the present application, the main vehicle 100 is moved to a preset position through the walking mechanism assembly 120, and the main vehicle 100 is ridden at the interval of the installation support piles through the first space, and a plurality of photovoltaic panel array semi-finished products 400 to be installed are transported through the second space, and then the photovoltaic panel array semi-finished products 400 are lifted from the carrying equipment by the hanger trolley 200 and the hoisting device 300 carried by the lateral support assembly 130 to complete the lifting operation in the second space, and the lifted photovoltaic panel array semi-finished products 400 are moved to the top of the position to be installed in the first space by the hanger trolley 200 for installation, so that the installation equipment and the transportation equipment can operate separately and achieve the purpose of continuous operation, thereby greatly improving the operation efficiency.
[0027] Optionally, the photovoltaic panel array semi-finished product 400 includes multiple photovoltaic panels. By using photovoltaic panel array semi-finished product installation equipment to lift the photovoltaic panel array semi-finished product 400, the photovoltaic panel array semi-finished product 400 is lifted from the lifting work space to the installation work space, and the photovoltaic panel array semi-finished product 400 is suspended in the air and can be directly installed, which solves the problem of low installation efficiency caused by manual single-piece photovoltaic panel installation and improves the efficiency of photovoltaic panel installation.
[0028] like Figure 1 As shown, in some optional embodiments, the vertical support assembly 110 includes a plurality of brackets 111, and the plurality of brackets 111 are spaced apart around a first unit 131 of the lateral support assembly 130, and a second unit 132 extends out of the vertical support assembly 110 along a first direction and is suspended above the second space.
[0029] In these optional embodiments, multiple brackets 111 are spaced apart around the first unit 131 of the lateral support assembly 130, and the multiple brackets 111 are used to support the lateral support assembly 130, while the second unit 132 extends out of the vertical support assembly 110 along the first direction and is suspended above the second space, that is, the second unit 132 is not within the contour range formed by the projection of the vertical support assembly 110, and the second unit 132 is suspended above the second space. The second space is not provided with the vertical support assembly 110, which can ensure that the second space has moving space for the carrying equipment.
[0030] It is understood that as another example, multiple brackets 111 are distributed along the circumference of the lateral support assembly 130. The orthographic projections of the first unit 131 and the second unit 132 fall within the contour range formed by the orthographic projections of the multiple brackets 111, and the lateral support assembly 130 is supported as a whole by the multiple brackets 111.
[0031] In some optional embodiments, the vertical support assembly 110 further includes a first reinforcing beam 113 and a second reinforcing beam 112. The first reinforcing beam 113 is arranged between adjacent brackets 111 spaced apart along the first direction, and the second reinforcing beam 112 is arranged between adjacent brackets 111 spaced apart along the second direction. The first direction and the second direction intersect each other vertically.
[0032] The first reinforcing beam 113 and the second reinforcing beam 112 are conducive to enhancing the structural strength of the vertical support assembly 110. Optionally, the first reinforcing beam 112 can connect the bracket 111 and the transverse support assembly 130, and the second reinforcing beam 113 can connect the bracket 111 and the transverse support assembly 130. The first reinforcing beam 112, the bracket 11 and the transverse support assembly 130 form a triangular structure, and the second reinforcing beam 113, the bracket 111 and the transverse support assembly 130 form a triangular structure, which is conducive to enhancing the structural strength of the vertical support assembly 110.
[0033] The first direction and the second direction intersect, the first direction and the second direction both intersect with the vertical direction, and the first direction and the second direction may be horizontal directions.
[0034] Optionally, the first direction and the second direction are perpendicular to each other, the first direction and the second direction are horizontal directions, and the first direction, the second direction and the vertical direction are perpendicular to each other.
[0035] like Figure 1 As shown, in some optional embodiments, the lateral support assembly 130 includes two or more beams 133 spaced apart in the second direction, and each beam 133 extends along the first direction and spans the first unit 131 and the second unit 132;
[0036] The lateral support assembly 130 further includes two or more connecting beams 134 spaced apart in the first direction, each connecting beam 134 being connected between adjacent cross beams 133. Adjacent brackets 111 spaced apart in the first direction are connected to the cross beams 133 via the first reinforcing beams 113.
[0037] In these optional embodiments, the lateral support assembly 130 includes more than two beams 133 spaced apart in the second direction, each beam 133 extends along the first direction, the beams 133 are distributed across the first unit 131 and the second unit 132, each connecting beam 134 is connected between adjacent beams 133, the beams 133 and the connecting beams 134 together constitute a frame structure to enhance the structural strength of the lateral support assembly 130, the first reinforcing beams of adjacent brackets 111 spaced apart along the first direction are connected to the beams 133, that is, the adjacent brackets 111 spaced apart along the first direction and the first reinforcing beams and the beams 133 together constitute a frame structure to enhance the structural strength of the equipment.
[0038] In some optional embodiments, a slide rail 135 is provided on the side of each cross beam 133 facing away from the walking mechanism assembly 120, and the two opposite ends of the hanger trolley 200 along the second direction are connected to two adjacent cross beams 133, and each end is provided with a slider that can be coupled with the slide rail 135, so that the hanger trolley 200 is slidably connected to the lateral support assembly 130.
[0039] In these optional embodiments, a slide rail 135 is provided on one side of each cross beam 133 facing away from the walking mechanism assembly 120, and the slide rail 135 extends along the extension direction of the cross beam 133, that is, the slide rail 135 extends along the first direction. Two opposite ends of the hanger trolley 200 along the second direction are connected to two adjacent cross beams 133, and each end is provided with a slider that can be coupled to the slide rail 135. The hanger trolley 200 slides in the slide rail 135 through the slider, so that the hanger trolley 200 is slidably connected to the transverse support assembly 130. The hanger trolley 200 can move along the extension direction of the slide rail 135, that is, move from the first unit 131 to the second unit 132 along the first direction, or move from the second unit 132 to the first unit 131. The hanger trolley 200 hoists the semi-finished photovoltaic panel array 40 from the first space to the second space through the hoist 300, or the hanger trolley 200 hoists the semi-finished photovoltaic panel array 40 from the second space to the first space through the hoist 300. Thus, the semi-finished photovoltaic panel array 40 is hoisted from the hoisting operation space to the installation operation space.
[0040] like Figure 1 As shown, in some optional embodiments, the walking mechanism assembly 120 includes a plurality of walking mechanisms correspondingly connected to each of the brackets 111 , and each of the walking mechanisms includes a connecting frame 121 and a plurality of linked traveling wheels 122 .
[0041] In these optional embodiments, the walking mechanism includes a connecting frame 121 and a plurality of linked traveling wheels 122, the traveling wheels 122 being connected to the bracket 111 via the connecting frame 121, the traveling wheels 122 being universal wheels, and the semi-finished photovoltaic panel array installation equipment can be moved in various horizontal directions via the universal wheels, so that the semi-finished photovoltaic panel array installation equipment can be moved more smoothly to the installation position of the photovoltaic panel array 40.
[0042] like Figure 1 As shown, in some optional embodiments, the hanger trolley 200 includes more than two hangers arranged in the vertical stack, one of the more than two hangers is connected to the lateral support assembly 130, and is movably arranged along the first direction, and at least another one of the more than two hangers can be movably connected to the one along multiple directions.
[0043] In these optional embodiments, more than two hangers are stacked vertically and connected to each other, and one of the more than two hangers is connected to the lateral support assembly 130, and is movably arranged along the first direction, and can drive the other to move along the first direction during the movement along the first direction. At least one of the more than two hangers can be movably connected to one in multiple directions, that is, the other can move in multiple directions relative to one. The movement of one of the more than two hangers along the first direction can be a long-distance movement, such as moving from a first space to a second space. And the movement of one of the more than two hangers along multiple directions can be a short-distance movement, and the position of the photovoltaic panel array semi-finished product 400 can be fine-tuned for installation.
[0044] like Figure 1 and Figure 2 As shown, as an example, the two or more hangers include a first hanger 210 and a second hanger 220, the first hanger 210 is connected to the lateral support assembly 130, the second hanger 220 is connected to the first hanger 210 and is movably arranged relative to the first hanger 210 in multiple directions in the horizontal plane, and the hanger 300 is connected to the second hanger 220. The hanger 300 includes a plurality of connecting members 310 and a hanging member 320, the hanging member 320 is connected to the second hanger 220 through a plurality of connecting members 310, and the connecting member 310 is a telescopic member with adjustable length.
[0045] In these optional embodiments, the second hanger 220 is connected to the first hanger 210, and the second hanger 220 can be movably arranged in multiple directions in the horizontal plane relative to the first hanger 210, that is, the hanger 300 can move in multiple directions driven by the second hanger 220. The hanger 300 includes a plurality of connecting members 310 and a hanging member 320, and the hanging member 320 is connected to the second hanger 220 through a plurality of connecting members 310, and the connecting member 310 is a telescopic member with adjustable length, and the photovoltaic panel array semi-finished product 400 is connected to the hanging member 320, and the height of the hanging member 320 can be adjusted by adjusting the length of the connecting member 310, so as to adjust the lifting height of the photovoltaic panel array semi-finished product 400.
[0046] The first hanger 210 is connected to the lateral support assembly 130 and can move on the lateral support assembly 130 along the first direction. This process drives the second hanger 220 to move along the first direction, thereby driving the hanger 300 to move along the first direction through the second hanger 220. In other words, the hanger 300 can drive the photovoltaic panel array 400 to move along the first direction.
[0047] The second hanger 220 moves the hanger 300 in the first direction for a long distance through the first hanger 210, and the second hanger 220 is connected to the first hanger 210 and moves in multiple directions relative to the first hanger 210 for a short distance, so as to achieve fine adjustment in various directions in the horizontal plane. In addition, the distance that the second hanger 220 is connected to the first hanger 210 and moves in multiple directions relative to the first hanger 210 is more accurate, which is conducive to moving the semi-finished photovoltaic panel array 400 to the installation area.
[0048] like Figure 1 and Figure 2 As shown, in some optional embodiments, a plurality of connecting members 310 are distributed in an array along the first direction and the second direction at intervals from each other to be connected to different positions of the hanging member 320, and each of the connecting members 310 can be independently controlled along the vertical length to adjust the spatial orientation posture and orientation angle of the hanging member 320.
[0049] In these optional embodiments, a plurality of connectors 310 are connected to different positions of the hanging member 320. The hanging member 320 may be a rectangular structure, and the plurality of connectors 310 are respectively connected to the four corners of the rectangle. Each connector 310 can be independently controlled along the vertical length to adjust the spatial orientation and orientation angle of the hanging member 320. For example, the vertical length of the connector 310 on one side of the hanging member 320 with a rectangular structure is adjusted to be smaller than the vertical length of the other side. At this time, the hanging member 320 is in an inclined state, and the semi-finished photovoltaic panel array 400 connected to the hanging member 320 is in an inclined state, which is conducive to realizing a flexible installation angle of the semi-finished photovoltaic panel array 400.
[0050] like Figure 1 and Figure 2 As shown, in some optional embodiments, each connecting member 310 is slidably or rollingly disposed on the second hanger 220 .
[0051] In these optional embodiments, the connecting member 310 is slidably or rollingly disposed on the second hanger 220, the connecting member 310 can move in various directions relative to the second hanger 220, and each connecting member 310 can move independently of each other. Since each connecting member 310 is connected to a different position of the hanging member 320, the movement of each connecting member 310 can realize the movement or rotation of the hanging member 320. When each connecting member 310 moves in the same direction, the hanging member 320 moves in this direction. When the moving directions of the connecting members 310 on one side of the hanging member 320 are opposite to those on the other side, the hanging member 320 realizes rotation.
[0052] like Figures 1 to 3As shown, in some optional embodiments, the connecting member 310 includes a winding mechanism 311 and a connecting rope 312, the winding mechanism 311 is arranged on the second hanger 220, at least part of the connecting rope 312 is wound around the winding mechanism 311, the winding mechanism 311 is connected to the hanging member 320 through the connecting rope 312, and the winding mechanism 311 is configured to realize the variable length of the connecting member 310 by winding the connecting rope 312.
[0053] In these optional embodiments, at least part of the connecting rope 312 is wound around the winding mechanism 311, and another part of the connecting rope 312 is not wound around the winding mechanism 311. By controlling the length of the connecting rope 312 wound around the winding mechanism 311, the length of the part not wound around the winding mechanism 311 can be adjusted, so that the length of the connecting member 310 is adjustable. The winding mechanism 311 is disposed on the second hanger 220, and the winding mechanism 311 is connected to the hanging member 320 through the connecting rope 312. When the winding mechanism 311 adjusts the length of the wound part of the connecting rope 312, the hanging member 320 is moved closer to or farther from the second hanger 220.
[0054] Although the present application has been described with reference to preferred embodiments, various modifications may be made thereto and parts thereof may be replaced with equivalents without departing from the scope of the present application. In particular, the various technical features mentioned in the various embodiments may be combined in any manner as long as there are no structural conflicts. The present application is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
Claims
1. A photovoltaic panel array semi-finished product installation device, characterized in that: include: The main vehicle comprises a vertical support assembly, a transverse support assembly and a running mechanism assembly, wherein the transverse support assembly is carried on one side of the vertical support assembly in the vertical direction, and the running mechanism assembly is arranged on the other side of the vertical support assembly in the vertical direction, and the transverse support assembly comprises a first unit and a second unit arranged side by side in a first direction, wherein the first unit and the vertical support assembly are enclosed to form a first space, and the second unit and the vertical support assembly are enclosed to form a second space; A hanger trolley, slidably connected to the transverse support assembly of the main vehicle, and used for connecting a hanger; Among them, the first direction intersects with the vertical direction, the first space can provide an installation working space for the semi-finished photovoltaic panel array hoisted on the hoist, and the second space can provide a hoisting working space for the semi-finished photovoltaic panel array to be hoisted on the hoist.
2. The photovoltaic panel array semi-finished product installation device according to claim 1, characterized in that: The vertical support assembly includes a plurality of brackets, and the plurality of brackets are spaced apart along the circumference of a first unit of the lateral support assembly, and the second unit extends out of the vertical support assembly along the first direction and is suspended above the second space; or, the plurality of brackets are distributed along the circumference of the lateral support assembly.
3. The photovoltaic panel array semi-finished product installation device according to claim 2, characterized in that: The vertical support assembly also includes a first reinforcing beam and a second reinforcing beam. The first reinforcing beam is arranged between adjacent brackets spaced apart along the first direction, and the second reinforcing beam is arranged between adjacent brackets spaced apart along the second direction. The first direction and the second direction intersect the vertical direction in pairs.
4. The photovoltaic panel array semi-finished product installation device according to claim 3, characterized in that: The lateral support assembly includes two or more cross beams spaced apart in the second direction, each of the cross beams extending along the first direction and spanning the first unit and the second unit; The lateral support assembly further includes two or more connecting beams spaced apart in the first direction, each connecting beam being connected between adjacent beams; Adjacent brackets spaced apart and distributed along the first direction are connected to the cross beam via a first reinforcing beam.
5. The photovoltaic panel array semi-finished product installation device according to claim 4, characterized in that: A slide rail is provided on the side of each cross beam facing away from the walking mechanism assembly, and the two opposite ends of the hanger trolley along the second direction are connected to two adjacent cross beams, and each end is provided with a slider that can be coupled with the slide rail so that the hanger trolley is slidably connected to the lateral support assembly.
6. The photovoltaic panel array semi-finished product installation device according to claim 2, characterized in that: The walking mechanism assembly includes a plurality of walking mechanisms correspondingly connected to each of the brackets, and each of the walking mechanisms includes a connecting frame and a plurality of linked traveling wheels.
7. The photovoltaic panel array semi-finished product installation device according to claim 1, characterized in that: The hanger trolley includes two or more hangers stacked along the vertical direction, one of the two or more hangers is connected to the lateral support assembly and is movably arranged along the first direction, and at least another one of the two or more hangers can be movably connected to the one along multiple directions.
8. The photovoltaic panel array semi-finished product installation device according to claim 7, characterized in that: The two or more hangers include a first hanger and a second hanger, the first hanger is connected to the lateral support assembly, the second hanger is connected to the first hanger and is movably arranged in multiple directions relative to the first hanger, and the sling is connected to the second hanger; The sling comprises a plurality of connecting members and a slinging member, the slinging member is connected to the second hanger via the plurality of connecting members, and the connecting member is a telescopic member with adjustable length.
9. The photovoltaic panel array semi-finished product installation device according to claim 8, characterized in that: The multiple connecting members are distributed in an array along the first direction and the second direction at intervals to be connected to different positions of the hanging member, and each of the connecting members can be independently controlled along the vertical length to adjust the spatial orientation posture and orientation angle of the hanging member.
10. The photovoltaic panel array semi-finished product installation device according to claim 9, characterized in that: Each of the connecting members is slidably or rollably arranged on the second hanger.
11. The photovoltaic panel array semi-finished product installation device according to claim 9, characterized in that: The connecting member includes a winding mechanism and a connecting rope, the winding mechanism is arranged on the second hanger, at least part of the connecting rope is wound around the winding mechanism, the winding mechanism is connected to the hanging member through the connecting rope, and the winding mechanism is configured to achieve variable length of the connecting member by winding the connecting rope.
Citation Information
Cited By
Photovoltaic panel array semi-finished product installation device
WO2025108251A1