Fabricated large-span composite steel frame concrete laminated slab

By using multiple sets of triangular components, oblique support frames and load-bearing arcs in large-span combined steel frames, combined with the combination of truss layer and steel mesh, the traditional stacked plates are solved when using large-spans. The deformation and excessive load bearing problems improve the stability and safety of the structure.

CN221941725UActive Publication Date: 2024-11-01TIANSHUIHENG INNOVATION BUILDING MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323442221.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-18
Publication Date
2024-11-01
Estimated Expiration
2033-12-18

AI Technical Summary

Technical Problem

Traditional steel frame concrete stacked plates are prone to deformation and cracks caused by excessive load bearing when used on a large span, which poses safety hazards.

Method used

The prefabricated large-span combined steel frame concrete stacking plate is used to form an internal steel frame through multiple groups of triangular components, oblique support frames and load-bearing arcs distributed internally to increase structural support and load-bearing reinforcement, and through distributed truss layers and precast concrete The plate and steel mesh combine to form a stable inner member, which combines the lifting and reinforcement mechanism to reduce safety hazards.

Benefits of technology

It improves the strength and stability of the internal structure of the laminated plate, reduces safety risks during the assembly process, and provides convenient assembly and useability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221941725U_ABST
    Figure CN221941725U_ABST
Patent Text Reader

Abstract

The utility model discloses an assembly type large-span combined steel frame concrete laminated slab which comprises a laminated main body, combined bearing mechanisms and hoisting reinforcing mechanisms, the combined bearing mechanisms are distributed in the laminated main body, and the hoisting reinforcing mechanisms are connected to the two ends of the laminated main body. The combined bearing mechanism comprises a prefabricated steel bar layer, triangular components, bevel angle supporting frames, bearing arcs, supporting heads and supporting ribs, and the triangular components are welded to the two sides of the top face of the prefabricated steel bar layer. According to the fabricated large-span composite steel frame concrete laminated slab, supporting and load-bearing reinforcement of the whole structure are formed through an inner structure steel frame composed of multiple sets of triangular components distributed in the whole laminated slab, the bevel angle supporting frames and the load-bearing arcs; through combination of the bevel angle supporting frames and the bearing arcs, central bearing is supported and reinforced through pulling force on the two sides and the supporting ribs in the bearing process, so that the internal structural strength and stability of the whole laminated slab are improved, and potential safety hazards in the assembling and using process are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of combined steel frame concrete composite slabs, in particular to an assembled large-span combined steel frame concrete composite slab. Background Art

[0002] Concrete composite slab is a new type of assembled formwork that does not require dismantling. It is composed of a high-strength calcium silicate board with a pre-embedded galvanized steel grid in the middle, a pre-embedded keel on the back and welded to a steel truss. Grooves are provided on the inside of the formwork to enhance adhesion. When the concrete is poured, the connecting parts of the composite slab are integrated with the steel bars and concrete, achieving a more bonded and firmer effect. The frosted surface on the outside of the formwork is smooth and beautiful, and no mortar is required. Concrete composite slabs can be prefabricated in the factory and then transported to the construction site for installation, reducing on-site construction time and improving construction efficiency.

[0003] Traditional steel frame concrete composite slabs are mostly composed of precast concrete slabs, steel frames and steel meshes. When the composite slabs are hoisted in blocks in the floor building, the composite floor slab structure needs to be erected on the beam as a whole. If the surface area span of the composite slab is too large, it will cause the middle part of the slab to bear too much load. The internal structure of the composite slab is prone to deformation or cracks due to excessive load during the assembly process, which poses a safety hazard. Therefore, we propose an assembled large-span composite steel frame concrete composite slab. Utility Model Content

[0004] The utility model aims to provide an assembled large-span composite steel frame concrete composite slab to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: an assembled large-span composite steel frame concrete composite slab, comprising a composite body, a combined load-bearing mechanism and a lifting and reinforcement mechanism, wherein the composite load-bearing mechanism is distributed inside the composite body, and the two ends of the composite body are connected with the lifting and reinforcement mechanism, the combined load-bearing mechanism comprises a prefabricated steel bar layer, a triangular member, an angled support frame, a load-bearing arc, a support head and support ribs, and triangular members are welded on both sides of the top surface of the prefabricated steel bar layer, an angled support frame is welded on one side outer wall of the triangular member, and load-bearing arcs are welded on both sides of the top surface of the angled support frame, a support head is arranged at the bottom center of the angled support frame, and support ribs are welded at the bottom end of the support head.

[0006] Furthermore, the prefabricated steel bar layer is connected to the triangular member and the angled support frame by welding, and the angled support frame is fixed to the middle end of the support bar in an inverted triangle shape.

[0007] Furthermore, the support head is connected to the angled support frame and the support ribs by welding, and the load-bearing arc is fixed by welding at symmetrical points on both sides of the top surface of the angled support frame.

[0008] Furthermore, the composite body includes a bottom plate layer, a truss layer, a precast concrete slab, a steel mesh and a cast-in-place concrete layer, and the truss layer is distributed on the top surface of the bottom plate layer, the precast concrete slab is distributed around the truss layer, and the steel mesh is welded to the top of the truss layer, and the cast-in-place concrete layer is distributed around the steel mesh.

[0009] Furthermore, the bottom plate layer is integrated with the truss layer and the precast concrete slab, and the combined load-bearing structure is evenly distributed along the inside of the truss layer.

[0010] Furthermore, the hoisting reinforcement mechanism includes a hoisting frame, connecting bars, beam reinforcements and a reinforcement member, and one end of the hoisting frame is connected to the connecting bars, one end of the connecting bars is connected to the beam reinforcements, and the inner side of the connecting bars is connected to the reinforcement member.

[0011] Furthermore, the reinforcing member is connected to the hanging frame and the connecting ribs by welding, and the hanging frame is integrated with the connecting ribs and the beam reinforcement.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] The assembled large-span composite steel frame concrete composite slab forms a support and load-bearing reinforcement for the overall structure through an internal steel frame composed of multiple sets of triangular components, oblique support frames and load-bearing arcs distributed in the overall composite slab. The oblique support frames and load-bearing arcs are combined to support and reinforce the central load-bearing force on both sides during the load-bearing process and the support ribs, thereby increasing the internal structural strength and stability of the overall composite slab and reducing safety hazards during assembly and use.

[0014] The internal components of the integral composite slab are formed by combining multiple groups of distributed truss layers with precast concrete slabs and steel meshes. The precast concrete slabs formed by the combination of the truss layers and the bottom slab layers cooperate with the steel meshes to maintain the stability of the overall composite slab structure.

[0015] The beam reinforcements connected on both sides provide convenience for the assembly and use of the overall composite plate, and each set of beam reinforcements is welded and fixed by reinforcing components to improve the stability of the structural angle between the beam reinforcements and the hanging frame, thereby playing a reinforcing role. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a schematic diagram of the cutaway three-dimensional structure of the superimposed main body of the utility model;

[0017] Figure 2 This is a schematic diagram of the three-dimensional structure of the combined load-bearing mechanism of the utility model;

[0018] Figure 3 This is a schematic diagram of the main structure of the combined load-bearing mechanism of the utility model;

[0019] Figure 4 It is a three-dimensional structural schematic diagram of the lifting reinforcement mechanism of the utility model.

[0020] In the figure: 1. Composite body; 101. Bottom plate layer; 102. Truss layer; 103. Precast concrete slab; 104. Steel mesh; 105. Cast-in-place concrete layer; 2. Combined load-bearing structure; 201. Precast steel layer; 202. Triangular member; 203. Angle support frame; 204. Load-bearing arc; 205. Support head; 206. Support ribs; 3. Hoisting and reinforcement mechanism; 301. Hoisting frame; 302. Connecting ribs; 303. Beam reinforcement; 304. Reinforcement member. DETAILED DESCRIPTION

[0021] The utility model provides Figure 1-4The assembled large-span composite steel frame concrete composite slab shown in the figure comprises a composite body 1, a composite load-bearing mechanism 2 and a hoisting reinforcement mechanism 3, wherein the composite load-bearing mechanism 2 is distributed inside the composite body 1, and the two ends of the composite body 1 are connected with the hoisting reinforcement mechanism 3, the composite load-bearing mechanism 2 comprises a prefabricated steel layer 201, a triangular member 202, an angled support frame 203, a load-bearing arc 204, a support head 205 and a support rib 206, and the triangular member 202 is welded on both sides of the top surface of the prefabricated steel layer 201, the outer wall of one side of the triangular member 202 is welded with an angled support frame 203, and the top surface of the angled support frame 203 is welded on both sides. A load-bearing arc 204 is connected, a support head 205 is arranged at the bottom center of the angled support frame 203, and a support rib 206 is welded to the bottom end of the support head 205, the prefabricated steel bar layer 201 is welded to the triangular member 202 and the angled support frame 203, and the angled support frame 203 is fixed to the middle end of the support rib 206 in an inverted triangle shape, the support head 205 is welded to the angled support frame 203 and the support rib 206, and the load-bearing arc 204 is welded and fixed at symmetrical points on both sides of the top surface of the angled support frame 203. When this concrete composite slab is used for floor assembly, the hoisting frames 301 at both ends assist in completing the composite slab. After loading, when the middle part of the composite board is overloaded due to the large overall span, multiple sets of triangular components 202 are distributed internally for internal support and reinforcement. The distributed triangular components 202 are welded and fixed to the prefabricated steel bar layer 201 inside the bottom plate layer 101 to form an overall arranged support. When the middle part of the overall composite board is loaded downward, the angled support frame 203 connected between each set of triangular components 202 forms a support point through the support head 205 and the support rib 206 at the middle end. When the middle end of the composite board is loaded, the two sets of triangular components 202 maintain the stability of the structure through the angled support frame 203. At the same time, the pulling force on both sides of the angled support frame 203 is borne and dispersed through the connected load-bearing arc 204, thereby minimizing the instability of the force under the middle load-bearing state. This structure forms an internal structural steel frame composed of multiple groups of triangular components 202 distributed in the overall composite plate and the angled support frame 203 and the load-bearing arc 204 to support and reinforce the overall structure. The angled support frame 203 and the load-bearing arc 204 are combined to support and reinforce the central load-bearing with the pulling force on both sides during the load-bearing process and the support ribs 206, thereby increasing the internal structural strength and stability of the overall composite plate and reducing safety hazards during assembly and use.

[0022] In order to maintain the stability of the concrete composite slab during the pouring process, the truss layer 102 structure is prefabricated and reinforced by using prefabricated concrete slabs 103. Figure 1As shown, the composite body 1 includes a bottom plate layer 101, a truss layer 102, a precast concrete slab 103, a steel mesh 104 and a cast-in-place concrete layer 105, and the top surface of the bottom plate layer 101 is distributed with the truss layer 102, and the precast concrete slab 103 is distributed around the truss layer 102, and the top of the truss layer 102 is welded with a steel mesh 104, and the cast-in-place concrete layer 105 is distributed around the steel mesh 104. The bottom plate layer 101 is integrated with the truss layer 102 and the precast concrete slab 103, and the combined load-bearing mechanism 2 is equidistantly distributed inside the truss layer 102. Before the composite plate is put into assembly and use, the precast concrete slabs in the composite plate need to be assembled. The steel bar layer 201 is combined with multiple groups of triangular components 202 to form a truss layer 102, which is matched with concrete pouring in advance to form a precast concrete slab 103. After the assembly is completed, the steel mesh 104 is mounted and welded on the surface of the triangular component 202, and finally poured to form a cast-in-place concrete layer 105, completing the subsequent assembly construction of the entire composite slab. This structure is formed by combining multiple groups of distributed truss layers 102 with precast concrete slabs 103 and steel mesh 104 to form the internal components of the overall composite slab. The precast concrete slab 103 formed by the combination of the truss layer 102 and the bottom plate layer 101 cooperates with the steel mesh 104 to maintain the stability of the overall composite slab structure.

[0023] Finally, in order to maintain the stability of the entire composite board during the assembly process, a hanging frame 301 is distributed on both sides. Figure 4 As shown, the hoisting reinforcement mechanism 3 includes a hoisting frame 301, a connecting rib 302, a beam rib 303 and a reinforcement member 304, and one end of the hoisting frame 301 is connected to the connecting rib 302, one end of the connecting rib 302 is connected to the beam rib 303, and the inner side of the connecting rib 302 is connected to the reinforcement member 304, the reinforcement member 304 is welded to the hoisting frame 301 and the connecting rib 302, and the hoisting frame 301 is integrated with the connecting rib 302 and the beam rib 303. The hoisting frames 301 are connected and fixed to the internal prefabricated steel bar layer 201, and the hoisting operation is carried out through the hoisting frames 301 on both sides, and the beam reinforcement 303 fixedly welded at the end of the hoisting frames 301 are used to stably mount it on the beam body. This structure provides convenience for the assembly and use of the overall composite plate through the beam reinforcement 303 distributed and connected on both sides, and each group of beam reinforcement 303 is welded and fixed by the reinforcement component 304, which improves the stability of the structural angle between the beam reinforcement 303 and the hoisting frame 301 and plays a reinforcement role.

[0024] In summary, when the assembled large-span composite steel frame concrete composite slab is used, before the composite slab is put into assembly and use, the prefabricated steel bar layer 201 in the composite slab needs to be combined with multiple sets of triangular components 202 to form a truss layer 102, and the concrete is poured in advance to form a prefabricated concrete slab 103, which is hoisted by the hoisting frames 301 on both sides, and the beam reinforcement 303 fixed and welded at the end of the hoisting frame 301 is used to stably mount it on the beam body to complete the assembly. After the hoisting frames 301 at both ends assist the composite slab to be mounted, when the composite slab has a large overall area span and the middle part bears too much load, the composite slab is internally supported and reinforced by the combined structure of multiple sets of triangular components 202 distributed internally, and the distributed triangular components 202 and the bottom plate layer 101 are connected. The internal prefabricated steel bar layer 201 is welded and fixed to form an overall arranged support. When the middle part of the overall composite plate is loaded downward, the angled support frame 203 connected between each group of triangular components 202 forms a support point through the support head 205 and the support rib 206 at the middle end. When the middle end of the composite plate is loaded, the two groups of triangular components 202 maintain structural stability through the angled support frame 203. At the same time, the pulling force on both sides of the angled support frame 203 is borne and dispersed through the connected load-bearing arc 204, thereby minimizing the instability of the force under the middle load-bearing state. The steel mesh 104 is then mounted and welded on the surface of the triangular component 202, and finally poured to form a cast-in-place concrete layer 105, completing the subsequent assembly construction of the entire composite plate.

Claims

1. An assembled large-span composite steel frame concrete composite slab, comprising a composite body (1), a composite load-bearing mechanism (2) and a hoisting reinforcement mechanism (3), characterized in that: A combined load-bearing mechanism (2) is distributed inside the composite body (1), and both ends of the composite body (1) are connected to hoisting reinforcement mechanisms (3), the combined load-bearing mechanism (2) comprising a prefabricated steel bar layer (201), a triangular member (202), an angled support frame (203), a load-bearing arc (204), a support head (205) and support ribs (206), and the triangular member (202) is welded to both sides of the top surface of the prefabricated steel bar layer (201), an angled support frame (203) is welded to one side outer wall of the triangular member (202), and load-bearing arcs (204) are welded to both sides of the top surface of the angled support frame (203), a support head (205) is arranged at the center of the bottom end of the angled support frame (203), and a support rib (206) is welded to the bottom end of the support head (205).

2. The assembled large-span composite steel frame concrete composite slab according to claim 1 is characterized by: The prefabricated steel bar layer (201) is connected to the triangular member (202) and the oblique angle support frame (203) by welding, and the oblique angle support frame (203) is fixed to the middle end of the support bar (206) in an inverted triangle shape.

3. The assembled large-span composite steel frame concrete composite slab according to claim 1 is characterized by: The support head (205) is connected to the angled support frame (203) and the support rib (206) by welding, and the load-bearing arc (204) is fixed by welding at symmetrical points along both sides of the top surface of the angled support frame (203).

4. The assembled large-span composite steel frame concrete composite slab according to claim 1 is characterized by: The composite body (1) comprises a bottom plate layer (101), a truss layer (102), a precast concrete slab (103), a steel mesh (104) and a cast-in-place concrete layer (105), wherein the truss layer (102) is distributed on the top surface of the bottom plate layer (101), the precast concrete slab (103) is distributed around the truss layer (102), the steel mesh (104) is welded to the top of the truss layer (102), and the cast-in-place concrete layer (105) is distributed around the steel mesh (104).

5. The assembled large-span composite steel frame concrete composite slab according to claim 4 is characterized in that: The bottom plate layer (101) is integrated with the truss layer (102) and the precast concrete slab (103), and the combined load-bearing structure (2) is evenly distributed inside the truss layer (102).

6. The assembled large-span composite steel frame concrete composite slab according to claim 1 is characterized by: The hoisting reinforcement mechanism (3) comprises a hoisting frame (301), connecting bars (302), beam bridging bars (303) and a reinforcement member (304), wherein one end of the hoisting frame (301) is connected to the connecting bars (302), one end of the connecting bars (302) is connected to the beam bridging bars (303), and the inner side of the connecting bars (302) is connected to the reinforcement member (304).

7. The assembled large-span composite steel frame concrete composite slab according to claim 6 is characterized by: The reinforcing member (304) is welded to the hanging frame (301) and the connecting rib (302), and the hanging frame (301) is integrated with the connecting rib (302) and the beam bridging rib (303).