Access door structure

By filling the inner ring with a filler layer and setting a protrusion, combined with the design of a fiber material layer and a castable layer, the problems of high-temperature corrosion and dew point corrosion of the maintenance door are solved, achieving lightweight and easy opening and closing of the maintenance door, extending its service life and reducing costs.

CN221942279UActive Publication Date: 2024-11-01JIANGNAN BOILERS & PRESSURE VESSELS ZHANGJIAGANG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420219184.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-11-01
Estimated Expiration
2034-01-30

AI Technical Summary

Technical Problem

Existing inspection doors suffer from high-temperature corrosion of the lining ring and dew point corrosion in high-temperature flue gas environments, and are difficult to open and close, affecting their service life.

Method used

A filler layer is filled inside the liner ring and a protrusion is provided so that it extends into the equipment inlet to avoid direct contact with high-temperature flue gas. The weight is reduced by the filler layer composed of fiber material layer and castable layer, and the strength and stability are increased by combining steel mesh.

Benefits of technology

It improves the service life of the bushing, door frame and door cover, reduces flue gas leakage, facilitates the opening and closing of the maintenance door, extends the service life by several times, and reduces weight and cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221942279U_ABST
    Figure CN221942279U_ABST
Patent Text Reader

Abstract

The utility model relates to an access door structure, and relates to the technical field of access doors, the access door structure comprises a door frame and a door cover, the door cover comprises a door cover plate and a bushing ring, the door cover plate is rotatably connected with the door frame and blocks the door frame, the bushing ring is arranged on the side, close to the door frame, of the door cover plate, and the bushing ring is filled with a filler layer; the whole lining ring is located in the door frame, a protruding part is arranged on the side, away from the door cover plate, of the packing layer, and the protruding part is used for stretching into an inlet of equipment so as to prevent the lining ring from making direct contact with high-temperature flue gas. The lining ring can be prevented from being in direct contact with high-temperature flue gas mainly by adjusting the access door structure, filling the lining ring with the filler layer, arranging the protruding part on the lining ring and enabling the protruding part to extend into the inlet of the equipment, so that the service life of the lining ring can be prolonged, the high-temperature flue gas is difficult to enter a low-temperature area to form dew point corrosion, and the service life of the equipment is prolonged. Therefore, the service life of the door frame, the door cover plate and the bushing ring is prolonged, and smoke leakage can be reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of access door technology, and in particular to an access door structure. Background Art

[0002] The high-temperature flue gas generated by the incineration of hazardous waste contains a large amount of acidic gases, which are highly corrosive to the equipment and require regular entry into the equipment for maintenance. Therefore, multiple inspection doors are installed on the flue gas treatment device.

[0003] Existing inspection doors usually include a door frame and a door cover. The door frame is installed on the equipment. The door frame and the door cover are rotatably connected. The door cover mainly includes a cover plate and a lining ring. The lining ring is located in the door frame and extends into the equipment entrance. The lining ring is filled with corrosion-resistant castables, and the cover plate is sealed on the door frame. Existing inspection doors have the following problems: 1. The lining ring is subject to high-temperature corrosion: After the existing inspection door is closed, part of the lining ring will extend into the equipment and directly contact with the high-temperature flue gas. The acidic gas in the flue gas is highly corrosive to metals at high temperatures. The lining ring has been made of corrosion-resistant stainless steels such as 304, 316, and 310S, but none of them can solve this problem; 2. The door frame, lining ring and door cover are There is dew point corrosion: After the device has been running for a period of time (generally less than one year), dew point corrosion causes high-temperature flue gas to leak from the door frame and door cover. The untreated high-temperature flue gas contains a large amount of toxic and harmful components, which endangers the health of the operating personnel and pollutes the surrounding environment; 3. The inspection door is difficult to open and close: Since the inspection door lining ring is cast with corrosion-resistant castables, the inspection door cover weighs more than 200 kilograms. It is often stuck during maintenance and difficult to open. The sealing surface is difficult to reset when closing; the above problems will affect the service life of the inspection door, so it is urgent to develop an inspection door that can improve high-temperature corrosion and dew point corrosion problems and is easy to open and close. Utility Model Content

[0004] In order to develop an inspection door that can improve high-temperature corrosion and dew point corrosion problems and is easy to open and close, the present application provides an inspection door structure.

[0005] The present application provides an access door structure that adopts the following technical solution:

[0006] A maintenance door structure comprises a door frame and a door cover, wherein the door cover comprises a door cover plate and a lining ring, wherein the door cover plate is rotatably connected to the door frame and seals the door frame, wherein the lining ring is arranged on a side of the door cover plate close to the door frame, wherein a packing layer is filled in the lining ring, wherein the lining ring is entirely located in the door frame, and a protrusion is provided on a side of the packing layer away from the door cover plate, wherein the protrusion is used to extend into an inlet of a device to prevent the lining ring from directly contacting with high-temperature flue gas.

[0007] By adopting the above-mentioned technical scheme, the present application mainly adjusts the structure of the inspection door. By filling a packing layer in the liner ring and extending the protrusions thereon into the entrance of the equipment, the liner ring can be prevented from directly contacting with the high-temperature flue gas, thereby improving the service life of the liner ring and making it difficult for the high-temperature flue gas to enter the low-temperature zone to form dew point corrosion, thereby improving the service life of the door frame, door cover and liner ring, and reducing flue gas leakage. The present application optimizes the structure of the inspection door, improves the problems of high-temperature corrosion and dew point corrosion of the inspection door structure, and increases the service life of the inspection door by several times.

[0008] In a specific embodiment, the diameter of the backing ring is larger than the width of the inlet of the device, and a gap of 5-15 mm is left between the protrusion and the inlet of the device.

[0009] By adopting the above-mentioned technical solution and design method, a "dead zone" can be formed between the door frame, the lining ring and the entrance of the equipment, so that the protrusion can prevent the lining ring from directly contacting the high-temperature flue gas, making it difficult for the high-temperature flue gas to enter the low-temperature zone to form dew point corrosion, thereby improving the service life of the door frame, door cover plate and lining ring, and reducing flue gas leakage.

[0010] In a specific possible implementation manner, the filler layer includes a fiber material layer and a casting material layer, the casting material layer is located between the protrusion and the fiber material layer, the casting material layer and the protrusion are made of the same material and constitute a casting layer.

[0011] By adopting the above technical solution, the filler layer is composed of a fiber material layer and a castable layer. Compared with the prior art, a part of the castable is eliminated, which can achieve the effect of reducing the weight of the filler layer, thereby reducing the weight of the entire inspection door structure and making it easier for workers to open and close the inspection door structure.

[0012] In a specific possible implementation manner, the fiber material layer is an aluminum silicate fiber layer or a ceramic fiber felt layer, and the casting layer is a corundum casting material layer; the ratio of the fiber material layer to the casting layer is in the range of 2:3-1:1.

[0013] By adopting the above technical solution, utilizing the above material design and a design in which the ratio of the fiber material layer to the casting layer is between 2:3 and 1:1, the combination of the fiber material layer and the casting layer under this design parameter can reduce the weight of the inspection door while ensuring the strength, durability and stability of the inspection door, and this design can also improve the sound insulation and heat insulation performance of the inspection door.

[0014] In a specific possible implementation manner, it further comprises a gripping nail connected to the door cover plate, wherein the gripping nail is arranged on a side of the door cover plate close to the door frame, and the gripping nail passes through the fiber material layer and is inserted into the casting layer.

[0015] By adopting the above technical solution, the grabbing nails are used to pass through the fiber material layer and insert into the cast material layer. The grabbing nails can effectively connect the fiber material layer and the cast material layer together to form a whole, thereby improving the overall bearing capacity of the inspection door structure, reducing the risk of the filler layer falling off or being damaged, and increasing the overall stability of the inspection door structure.

[0016] In a specific possible implementation manner, it further includes a steel plate mesh, which is arranged between the fiber material layer and the casting material layer, and the steel plate mesh is connected to both the grabbing nails and the lining ring.

[0017] By adopting the above technical solution, by setting a steel plate mesh between the fiber material layer and the casting material layer, the steel plate mesh can effectively increase the overall strength of the inspection door structure, further reduce the risk of falling off or damage of the filler layer, and further increase the overall stability of the inspection door structure.

[0018] In a specific embodiment, a sealing box is further included, and the sealing box is used for the door frame to be installed on different devices.

[0019] By adopting the above technical solution and utilizing the setting of a sealing box, the sealing box is usually prefabricated and can be customized according to the size and shape of the equipment, thereby simplifying the installation work, improving the installation efficiency of the inspection door structure, and being able to meet the installation and use of different equipment. The sealing box has a sealing function, and the sealing box can effectively isolate the gap between the inspection door structure and the equipment, preventing dust, moisture and other debris from entering the interior of the equipment, thereby protecting the safety and stability of the equipment.

[0020] In a specific possible implementation manner, a rotating arm is rotatably provided on the door frame, and the rotating arm is connected to the door cover plate via a connecting piece.

[0021] By adopting the above technical solution, during installation, the door cover plate is installed on the rotating arm through the connecting piece, so as to realize the installation of the door frame and the door cover, and the rotating connection between the door cover and the door frame is realized through the rotating arm.

[0022] In a specific possible implementation manner, the connecting member includes a hook and a lifting ring connected to the door cover plate, and the lifting ring is connected to the rotating arm through the hook.

[0023] By adopting the above technical solution, during installation, the rotating arm is connected to the lifting ring through the lifting hook, so as to realize the connection between the door cover plate and the rotating arm, and then realize the rotation connection between the door frame and the door cover.

[0024] In a specific possible implementation manner, a sealing gasket is further included, wherein the sealing gasket is arranged between the door frame and the door cover plate, and the sealing gasket is arranged along the circumference of the door frame.

[0025] By adopting the above technical solution, a sealing gasket is arranged between the door frame and the door cover, and the sealing gasket can prevent leakage of high-temperature smoke, reduce safety hazards, and improve the reliability and stability of the inspection door structure.

[0026] In a specific possible implementation manner, a handle is further provided on a side of the door cover plate away from the door frame.

[0027] By adopting the above technical solution and utilizing the setting of the handle, it is possible to facilitate the staff to open and close the inspection door structure, provide a control point, support and balance the door body, and increase the safety of the opening and closing operations.

[0028] In summary, the present application includes at least one of the following beneficial technical effects:

[0029] 1. The present application optimizes the structure of the inspection door, improves the problems of high temperature corrosion and dew point corrosion of the inspection door structure, and increases the service life of the inspection door by several times. The inspection door structure is mainly adjusted by filling a packing layer in the liner ring and extending the protrusions provided thereon into the inlet of the equipment, so that the liner ring can be prevented from directly contacting with the high temperature flue gas, thereby increasing the service life of the liner ring, and making it difficult for the high temperature flue gas to enter the low temperature area to form dew point corrosion, thereby increasing the service life of the door frame, the door cover plate and the liner ring, and reducing flue gas leakage;

[0030] 2. The present application adopts a design method in which the protrusion extends into the equipment entrance and leaves a gap of 5-15mm between the protrusion and the equipment entrance, so that a "dead zone" can be formed between the door frame, the lining ring and the equipment entrance. The protrusion can prevent the lining ring from directly contacting the high-temperature flue gas, ensure the sealing effect of the inspection door structure and form a maze structure, so that it is difficult for the high-temperature flue gas to enter the low-temperature area to form dew point corrosion;

[0031] 3. In the present application, the filler layer is composed of a fiber material layer and a castable layer. Compared with the prior art, a part of the castable is eliminated, which can achieve the effect of reducing the weight of the filler layer, thereby reducing the weight of the entire inspection door structure and making it convenient for the staff to open and close the inspection door structure; and the combination of the fiber material layer and the castable layer can reduce the weight of the inspection door while ensuring the strength, durability and stability of the inspection door, and this design can also improve the sound insulation and heat insulation performance of the inspection door. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 It is a structural schematic diagram of the maintenance door structure of an embodiment of the present application.

[0033] Figure 2 It is a cross-sectional view used to show the packing layer.

[0034] Explanation of the reference numerals: 1. door frame; 11. swivel arm; 2. door cover; 21. door cover plate; 211. handle; 22. lining ring; 3. filler layer; 31. fiber material layer; 32. casting layer; 321. casting material layer; 322. protrusion; 4. grab nail; 5. steel plate mesh; 6. sealing box; 7. connector; 71. hook; 72. lifting ring; 8. sealing gasket; 9. equipment. DETAILED DESCRIPTION

[0035] The following is combined with Figure 1-2 This application is described in further detail.

[0036] Please refer to Figure 1 and Figure 2 The embodiment of the present application discloses an inspection door structure. In this embodiment, the inspection door structure is installed on a hazardous waste incineration device 9; the inspection door structure includes a door frame 1 and a door cover 2. In this embodiment, the door frame 1 may be, but is not limited to, an annular frame with an inner diameter of 560 mm. The door frame 1 includes, but is not limited to, a Q235-B steel plate with a thickness of 6 mm;

[0037] The inspection door structure also includes a sealing box 6, and the sealing box 6 is used for the door frame 1 to be installed on different equipment 9. In this embodiment, the sealing box 6 and the door frame 1 are welded into a whole, and the sealing box 6 and the equipment 9 are connected by welding. The sealing box 6 includes but is not limited to being made of a 6mm thick Q235-B steel plate. The sealing box 6 is usually prefabricated and can be customized according to the size and shape of the equipment 9, which can avoid a lot of cutting and processing work on site, thereby simplifying the installation process, improving the installation efficiency of the inspection door structure, and being able to meet the installation and use of different equipment 9. The sealing box 6 has a sealing function, and the sealing box 6 can effectively isolate the gap between the inspection door structure and the equipment 9, preventing dust, moisture and other debris from entering the interior of the equipment 9, thereby protecting the safety and stability of the equipment 9;

[0038] The door cover 2 includes a door cover plate 21 and a lining ring 22. The door cover plate 21 includes but is not limited to being made of a 14 mm thick Q235-B steel plate. A handle 211 is also provided on the side of the door cover plate 21 away from the door frame 1. The setting of the handle 211 can facilitate the staff to open and close the inspection door structure, provide a control point, support and balance the door body, and increase the safety of the opening and closing operation;

[0039] The door cover plate 21 is rotatably connected to the door frame 1 and blocks the door frame 1. A rotating arm 11 is rotatably provided on the door frame 1. In the present embodiment, the rotating arm 11 includes but is not limited to being made of Q235-B round steel with a diameter of 36 mm. The rotating arm 11 is connected to the door cover plate 21 through a connecting member 7; the connecting member 7 includes a hook 71 and a lifting ring 72 connected to the door cover plate 21, and the lifting ring 72 is connected and fixed to the rotating arm 11 through the hook 71; during installation, the rotating arm 11 is connected to the lifting ring 72 through the hook 71 to realize the connection between the door cover plate 21 and the rotating arm 11, thereby realizing the installation of the door frame 1 and the door cover 2, and realizing the rotatable connection between the door cover 2 and the door frame 1 through the rotating arm 11;

[0040] The inspection door structure also includes a sealing gasket 8, which is arranged between the door frame 1 and the door cover plate 21, and the sealing gasket 8 is arranged along the circumference of the door frame 1; the sealing gasket 8 can prevent high-temperature smoke from leaking from the gap between the door cover plate 21 and the door frame 1, reduce safety hazards, and improve the reliability and stability of the inspection door structure;

[0041] The lining ring 22 is arranged on a side of the door cover plate 21 close to the door frame 1. In this embodiment, the lining ring 22 is welded and fixed to the door cover plate 21. The lining ring 22 includes but is not limited to being made of a 5mm thick Q235-B steel plate. The inner diameter of the lining ring 22 may be but is not limited to 520mm. A gap of 15-25mm is left between the lining ring 22 and the door frame 1. In this embodiment, a gap of 20mm is left between the lining ring 22 and the door frame 1.

[0042] The lining ring 22 is filled with a packing layer 3, and the lining ring 22 is entirely located in the door frame 1. In this embodiment, a protrusion 322 is provided on the side of the packing layer 3 away from the door cover plate 21, and the protrusion 322 is used to extend into the inlet of the device 9 to prevent the lining ring 22 from directly contacting with the high-temperature flue gas;

[0043] The diameter of the lining ring 22 is larger than the width of the entrance of the device 9, and a gap of 5-15 mm is left between the protrusion 322 and the entrance of the device 9. In the present embodiment, a gap of 10 mm is left between the protrusion 322 and the entrance of the device 9. The aforementioned design method can form a "dead zone" between the door frame 1, the lining ring 22 and the entrance of the device 9. The protrusion 322 can prevent the lining ring 22 from directly contacting the high-temperature flue gas, ensure the sealing effect of the inspection door structure and form a labyrinth structure, so that the high-temperature flue gas is difficult to enter the low-temperature zone to form dew point corrosion, thereby improving the service life of the door frame 1, the door cover 21 and the lining ring 22, and reducing flue gas leakage.

[0044] During installation, first weld and fix the lining ring 22 and the door cover plate 21, then fill the lining ring 22 with a packing layer 3, and set a protrusion 322 on the side of the packing layer 3 away from the door cover plate 21 to complete the production of the door cover 2; select a sealing box 6 that is consistent with the size and shape of the equipment 9, weld the door frame 1 and the sealing box 6 into a whole, and then weld the sealing box 6 to the equipment 9 to complete the installation of the door frame 1 and the equipment 9; then rotatably connect the door cover 2 to the door frame 1, specifically, connect the rotating arm 11 on the door frame 1 to the hanging ring 72 on the door cover plate 21 through the hook 71, realize the connection between the door cover plate 21 and the rotating arm 11, thereby realizing the installation of the door frame 1 and the door cover 2, and realize the rotatable connection between the door cover 2 and the door frame 1 through the rotating arm 11, complete the connection and fixation of the door cover 2 and the door frame 1, and complete the installation of the inspection door structure on the equipment 9;

[0045] The present application optimizes the structure of the inspection door, improves the problems of high-temperature corrosion and dew-point corrosion of the inspection door structure, and increases the service life of the inspection door by several times; mainly by adjusting the inspection door structure, since the width of the entrance of the equipment 9 is smaller than the diameter of the liner ring 22 and a 10 mm gap is left between the protrusion 322 and the entrance of the equipment 9, a local maze structure is formed by changing the casting pattern of the filler layer 3 and the protrusion 322 in the liner ring 22, so that a "dead zone" is formed between the door frame 1, the liner ring 22 and the entrance of the equipment 9. This can avoid direct contact between the liner ring 22 and the high-temperature flue gas, thereby increasing the service life of the liner ring 22, and making it difficult for the high-temperature flue gas to enter the low-temperature zone to form dew-point corrosion, thereby increasing the service life of the door frame 1, the door cover plate 21 and the liner ring 22, and reducing flue gas leakage.

[0046] The filler layer 3 includes a fiber material layer 31 and a casting material layer 321 . The casting material layer 321 is located between the protrusion 322 and the fiber material layer 31 . The casting material layer 321 and the protrusion 322 are made of the same material and constitute a casting layer 32 .

[0047] The fiber material layer 31 is an aluminum silicate fiber layer or a ceramic fiber felt layer. In the present embodiment, the fiber material layer 31 is a ceramic fiber felt layer. The ceramic fiber felt layer has excellent high temperature resistance and heat insulation performance, provides heat insulation effect for the inspection door structure, protects the inspection door lining ring 22 from high temperature, and is suitable for high temperature equipment 9; the casting layer 32 is a corundum casting layer, and the corundum casting layer is made of a corundum casting with a content of ≥98%. The corundum casting layer enables the casting layer 32 to provide a wear-resistant, fire-resistant, corrosion-resistant and high temperature-resistant protective layer for the lining ring 22, can withstand impact and erosion in a high temperature environment, and is suitable for high temperature equipment 9;

[0048] The ratio of the fiber material layer 31 to the casting layer 32 is between 2:3 and 1:1, and the thickness of the fiber material layer 31 is 100-150 mm. In this embodiment, the thickness of the fiber material layer 31 is 150 mm, and the thickness of the casting layer 32 is 150 mm.

[0049] The packing layer 3 is composed of a fiber material layer 31 and a casting material layer 321. Compared with the prior art, a part of the casting material is eliminated and replaced by the fiber material layer 31, which can achieve the effect of reducing the weight of the packing layer 3, thereby reducing the weight of the entire inspection door structure, and can reduce the weight of the door cover 2 of the inspection door structure to less than 100 kilograms. In practice, it can be easier for the staff to open and close the inspection door structure; and through the selection and design of the material and thickness of the fiber material layer 31 and the casting layer 32, the combination of the fiber material layer 31 and the casting layer 32 under this design can achieve the goal of reducing the weight of the inspection door while ensuring the strength, durability and stability of the inspection door. This design can also improve the sound insulation and heat insulation performance of the inspection door, protect the inspection door lining ring 22 from high temperature, and increase the service life of the overall inspection door structure.

[0050] The inspection door structure also includes a grabbing nail 4 connected to the door cover plate 21. The grabbing nail 4 is arranged on the side of the door cover plate 21 close to the door frame 1. In the present embodiment, the grabbing nail 4 is welded to the door cover plate 21. The grabbing nail 4 passes through the fiber material layer 31 and is inserted into the casting layer 32. In the present embodiment, the grabbing nail 4 is made of Q235-B round steel with a diameter of 6 mm. By setting the grabbing nail 4 to pass through the fiber material layer 31 and be inserted into the casting layer 321, the grabbing nail 4 can effectively connect the fiber material layer 31 and the casting layer 321 together to form a whole, which can improve the overall bearing capacity of the inspection door structure, reduce the risk of falling off or damage of the packing layer 3, and increase the overall stability of the inspection door structure.

[0051] The inspection door structure also includes a steel plate mesh 5. In the present embodiment, the steel plate mesh 5 is laid between the fiber material layer 31 and the cast material layer 321. In the present embodiment, the steel plate mesh 5 is made of Q235-B steel. The steel plate mesh 5 is connected to the gripping nails 4 and the lining ring 22. In the present embodiment, the steel plate mesh 5 is spot welded to the gripping nails 4 and the lining ring 22. The steel plate mesh 5 can effectively increase the overall strength of the inspection door structure, further reduce the risk of falling off or damage of the filler layer 3, and further increase the overall stability of the inspection door structure.

[0052] In the actual production process, during installation, the lining ring 22 is first welded and fixed to the door cover plate 21, and then the filling layer 3 is filled in the lining ring 22. Specifically, the grabbing nails 4 are first welded to the door cover plate 21, and then the fiber material layer 31 is laid in the lining ring 22. After laying, a layer of steel plate mesh 5 is laid on the fiber material layer 31, and the steel plate mesh 5 is spot welded to the grabbing nails 4 and the lining ring 22, and then the casting material is poured to form a casting layer 32, that is, a casting material layer 321 and a protrusion 322 are formed, and the production of the door cover 2 is completed.

[0053] In the use of the equipment 9 of the present application in an actual hazardous waste incineration project, the flue gas generated by the incineration of this equipment 9 contains 3-6% HF corrosive gas, and the flue gas temperature is between 550℃-1100℃. The new structure of the inspection door structure has been operating under this working condition for 3 years, and the inspection door structure has no high-temperature corrosion or dew point corrosion, and can be easily opened and closed during maintenance; in the actual production and use process of the present application, the cost is reduced by 30% without significantly increasing the production process, and the problems of high-temperature corrosion, dew point corrosion and difficulty in opening of the inspection door can be successfully solved, and the service life of the inspection door is extended by 4-5 times.

[0054] The implementation principle of the maintenance door structure of the embodiment of the present application is as follows: the present application optimizes the maintenance door structure, improves the high temperature corrosion and dew point corrosion problems of the maintenance door structure, and increases the service life of the maintenance door by several times; during installation, the lining ring 22 is first welded and fixed to the door cover plate 21, and then the filling layer 3 is filled in the lining ring 22. Specifically, the grab nails 4 are first welded to the door cover plate 21, and then the fiber material layer 31 is laid in the lining ring 22. After laying, a layer of steel plate mesh 5 is laid on the fiber material layer 31, and the steel plate mesh 5 is spot welded to the grab nails 4 and the lining ring 22, and then the casting material is cast to form the casting layer 32, that is, the casting material layer 321 and the protrusion 322 are formed, and the door cover 2 is completed.

[0055] Select a sealing box 6 that is consistent with the size and shape of the equipment 9, weld the door frame 1 and the sealing box 6 into a whole, and then weld the sealing box 6 to the equipment 9 to complete the installation of the door frame 1 and the equipment 9; then rotatably connect the door cover 2 to the door frame 1, specifically, connect the rotating arm 11 on the door frame 1 with the lifting ring 72 on the door cover plate 21 through the hook 71, realize the connection between the door cover plate 21 and the rotating arm 11, thereby realizing the installation of the door frame 1 and the door cover 2, and realize the rotatable connection between the door cover 2 and the door frame 1 through the rotating arm 11, complete the connection and fixation of the door cover 2 and the door frame 1, and complete the installation of the inspection door structure on the equipment 9;

[0056] The present application mainly adjusts the structure of the inspection door. Since the width of the entrance of the equipment 9 is smaller than the diameter of the liner ring 22 and a gap of 10 mm is left between the protrusion 322 and the entrance of the equipment 9, a local maze structure is formed by changing the casting pattern of the filler layer 3 and the protrusion 322 in the liner ring 22. A "dead zone" is formed between the door frame 1, the liner ring 22 and the entrance of the equipment 9. This can prevent the liner ring 22 from directly contacting the high-temperature flue gas, thereby increasing the service life of the liner ring 22 and making it difficult for the high-temperature flue gas to enter the low-temperature zone to form dew point corrosion, thereby increasing the service life of the door frame 1, the door cover plate 21 and the liner ring 22 and reducing flue gas leakage.

[0057] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. An access door structure, characterized in that: The invention comprises a door frame (1) and a door cover (2), wherein the door cover (2) comprises a door cover plate (21) and a lining ring (22), wherein the door cover plate (21) is rotatably connected to the door frame (1) and seals the door frame (1), wherein the lining ring (22) is arranged on a side of the door cover plate (21) close to the door frame (1), wherein a packing layer (3) is filled in the lining ring (22), wherein the lining ring (22) is entirely located in the door frame (1), and a protrusion (322) is provided on a side of the packing layer (3) away from the door cover plate (21), wherein the protrusion (322) is used to extend into the entrance of the device (9) to prevent the lining ring (22) from directly contacting with high-temperature flue gas.

2. The inspection door structure according to claim 1, characterized in that: The diameter of the liner ring (22) is greater than the width of the inlet of the device (9), and a gap of 5-15 mm is left between the protrusion (322) and the inlet of the device (9).

3. The inspection door structure according to claim 1, characterized in that: The filler layer (3) comprises a fiber material layer (31) and a casting material layer (321); the casting material layer (321) is located between the protrusion (322) and the fiber material layer (31); the casting material layer (321) and the protrusion (322) are made of the same material and constitute a casting layer (32).

4. The inspection door structure according to claim 3, characterized in that: The fiber material layer (31) is an aluminum silicate fiber layer or a ceramic fiber felt layer, and the casting layer (32) is a corundum casting material layer; the ratio of the fiber material layer (31) to the casting layer (32) is in the range of 2:3-1:

1.

5. The inspection door structure according to claim 4, characterized in that: It also comprises a grabbing nail (4) connected to the door cover plate (21), wherein the grabbing nail (4) is arranged on a side of the door cover plate (21) close to the door frame (1), and the grabbing nail (4) passes through the fiber material layer (31) and is inserted into the casting layer (32).

6. The inspection door structure according to claim 5, characterized in that: It also comprises a steel plate mesh (5), wherein the steel plate mesh (5) is arranged between the fiber material layer (31) and the casting material layer (321), and the steel plate mesh (5) is connected to the grabbing nails (4) and the lining ring (22).

7. The inspection door structure according to claim 1, characterized in that: It also comprises a sealing box (6), wherein the sealing box (6) is used for the door frame (1) to be installed on different devices (9).

8. The inspection door structure according to claim 1, characterized in that: A rotating arm (11) is rotatably provided on the door frame (1), and the rotating arm (11) is connected to the door cover plate (21) via a connecting piece (7).

9. The inspection door structure according to claim 8, characterized in that: The connecting member (7) comprises a hook (71) and a lifting ring (72) connected to the door cover plate (21); the lifting ring (72) and the rotating arm (11) are connected via the hook (71).

10. The inspection door structure according to claim 1, characterized in that: It also comprises a sealing gasket (8), wherein the sealing gasket (8) is arranged between the door frame (1) and the door cover plate (21), and the sealing gasket (8) is arranged along the circumference of the door frame (1).