Tunnel pipe jacking device

By using multiple excavation structures and adjustable excavation modules in the tunnel pipe top device, the problem of excavation of hard rock in the composite formation is solved, and pipeline installation is simplified through additional pipe section structures, which improves construction efficiency and efficiency .

CN221942441UActive Publication Date: 2024-11-01CHINA RAILWAY ENGINEERING EQUIPMENT GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420040727.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-08
Publication Date
2024-11-01
Estimated Expiration
2034-01-08

AI Technical Summary

Technical Problem

The existing rectangular tunnel pipe header cannot effectively cut the rock mass when the composite formation is excavated, resulting in construction suspension. During the replacement of the pipe section, power supply lines, signal lines and other pipelines need to be removed and reinstalled, which seriously affects the construction efficiency.

Method used

A tunnel top pipe device was designed, adopting multiple excavation structures and adjustable excavation modules, and the cutting wheel was arranged layered to cover the excavation edges to avoid blind spots. An additional pipe section structure was set up at the bottom of the shield shell to facilitate the installation of signal cables, reducing the Construction downtime.

Benefits of technology

It realizes efficient excavation of hard rock in composite formations, avoids excessive overexcavation, improves construction efficiency, and simplifies the pipe section replacement process and reduces construction downtime.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221942441U_ABST
    Figure CN221942441U_ABST
Patent Text Reader

Abstract

The utility model provides a tunnel pipe jacking device which comprises a shield shell, a plurality of pipe joint mechanisms and a plurality of pipe joint mechanisms. The cutterhead mechanism is connected to the front end of the shield shell, and the cutterhead mechanism is provided with a first tunneling structure provided with a plurality of tunneling cutterheads arranged in the width direction of the tunnel; the second tunneling structure is arranged below the first tunneling structure in the height direction of the tunnel, and the second tunneling structure is provided with at least two tunneling parts arranged on the two sides of the tunnel in the width direction of the tunnel and an adjustable tunneling module located between the at least two tunneling parts; and the tunneling section of the adjustable tunneling module can cover the tunneling edge of the tunneling piece adjacent to the adjustable tunneling module. Through the cutterhead mechanism, the hard rock cutting capacity of the pipe jacking machine is guaranteed while excessive overexcavation is avoided in the technical field of tunneling.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel excavation, in particular to a tunnel jacking device. Background Art

[0002] The description in this section merely provides background information related to the disclosure of the present utility model and does not constitute prior art.

[0003] In the field of tunnel excavation technology, rectangular pipe jacking machines are generally used for the construction of some rectangular tunnels. Existing rectangular pipe jacking machines are generally divided into two categories, one is a full-section excavation cutterhead arrangement scheme, and the other is a non-full-section excavation cutterhead arrangement scheme. Among them, the full-section excavation cutterhead mainly includes eccentric multi-axis swing cutterheads, drum cutterheads, planetary wheel cutterheads, etc. This type of cutterhead can theoretically achieve complete excavation of the rectangular end face without generating construction blind spots, but it is also restricted by its structure. This type of cutterhead cannot be used for composite strata and rock strata and cannot effectively cut rock mass; however, when a non-full-section excavation cutterhead arrangement scheme is adopted, a processing blind spot will naturally be generated. When excavating in soil strata, a blade can be arranged in the blind spot for jacking and cutting operations, but when encountering a composite stratum with soft top and hard bottom, the bottom blind spot may be a rock stratum, and the blade cannot effectively cut the rock mass, and the entire equipment cannot be further jacked, resulting in construction suspension.

[0004] In the prior art, in order to solve the rock mass problems encountered in the construction of rectangular tunnels, some adopt a design of a pipe jacking machine without blind spots. That is, on the basis of the non-full-section excavation cutter head arrangement plan, each cutter head is over-excavated outward to avoid the occurrence of blind spots within the rectangular range. However, this method has a large over-excavation amount and cannot control land subsidence. At the same time, it requires non-standard special-shaped pipe segments and the construction speed is slow.

[0005] At the same time, in the prior art, most rectangular pipe jacking sections are industrial products configured as a set. As a result, during the construction process of the pipe jacking machine, as the pipe jacking machine is pushed forward, the new pipe section needs to be lowered and installed. After the new pipe section is installed, the power supply line, signal line, grouting pipe and other pipelines of the pipe jacking machine need to be removed, and then the new pipe section needs to be installed. Then, the power supply line, signal line, grouting pipe and other pipelines of the pipe jacking machine need to be reinstalled before the machine can be started for excavation again. This type of operation also seriously restricts the construction efficiency of the pipe jacking machine.

[0006] It should be noted that the above introduction to the technical background is only for the convenience of providing a clear and complete description of the technical solutions of the utility model and for the convenience of understanding by those skilled in the art. It cannot be considered that the above technical solutions are well known to those skilled in the art simply because these solutions are described in the background technology section of the utility model. Utility Model Content

[0007] The utility model aims to provide a tunnel jacking device, which solves the problem of avoiding excessive over-excavation and ensuring the ability of the jacking machine to cut hard rock in the technical field of tunnel excavation.

[0008] The above-mentioned implementation purpose of the utility model is mainly achieved by the following technical solutions:

[0009] The utility model provides a tunnel pipe jacking device, comprising:

[0010] A shield shell, a rear end of which is connected to a plurality of pipe joint mechanisms;

[0011] A cutter disc mechanism is connected to the front end of the shield shell, and the cutter disc mechanism has:

[0012] A first excavation structure having a plurality of excavation cutterheads arranged along the width direction of the tunnel;

[0013] A second excavation structure is arranged below the first excavation structure along the height direction of the tunnel. The second excavation structure has at least two excavation pieces arranged on both sides of the tunnel along the width direction of the tunnel, and an adjustable excavation module located between the at least two excavation pieces. The excavation section of the adjustable excavation module can cover the excavation edge of the excavation piece adjacent to it.

[0014] In a specific embodiment, along the height direction of the tunnel, the excavation height of the adjustable excavation module is greater than or equal to the excavation height of the excavation member.

[0015] In a specific embodiment, the first excavation structure has at least two edge excavation cutterheads located on both sides of the tunnel, and the adjustable excavation module and the at least two edge excavation cutterheads are located in the same excavation plane.

[0016] In a specific embodiment, the second excavation structure has two excavation members and one adjustable excavation module, the two excavation members are Lelo triangle excavation cutter discs, and the excavation module is a circular excavation cutter disc.

[0017] In a specific embodiment, the tunnel jacking device further comprises an additional pipe segment structure, wherein the additional pipe segment structure is connected to the shield shell and the pipe segment mechanism, and a signal cable capable of supplying power to the cutterhead mechanism is arranged in the additional pipe segment structure.

[0018] In a specific embodiment, along the height direction of the tunnel, the additional pipe segment structure is connected to the bottom of the shield shell and the pipe segment mechanism, and a first groove for placing the signal cable is formed between the additional pipe segment structure and the bottom surfaces of the shield shell and the pipe segment mechanism, and the bottom surface of the additional pipe segment structure is higher than or parallel to the bottom surface of the adjustable excavation module.

[0019] In a specific embodiment, at least one scraping tool is provided on the top of the shield shell, and the at least one scraping tool is arranged between two adjacent excavation cutter discs along the width direction of the tunnel.

[0020] In a specific embodiment, at least two of the plurality of driving cutter discs of the first driving structure are Lelo triangle driving cutter discs.

[0021] In a specific embodiment, the plurality of excavation cutter discs of the first excavation structure are arranged front and back along the excavation direction of the tunnel jacking device, and at least one of the plurality of excavation cutter discs is a circular excavation cutter disc.

[0022] In a specific embodiment, the tunnel jacking device further includes a slag discharge mechanism, wherein the slag discharge mechanism is located in the shield shell and connected between the cutter head mechanism and the pipe joint mechanism.

[0023] Compared with the prior art, the technical solution described in the utility model has the following characteristics and advantages:

[0024] The utility model can, when coping with a geological environment that is soft at the top and hard at the bottom, distinguish the excavation capacity of the cutterhead mechanism through the first excavation structure and the second excavation structure of the cutterhead mechanism, and respectively set different adjustable excavation modules and excavation pieces to ensure the overall jacking excavation capacity of the tunnel jacking device; at the same time, the excavation pieces on both sides of the second excavation structure can be Leroy triangular cutterheads to achieve the hard rock cracking capacity while ensuring that the edge angle is rectangular to avoid over-excavation; at the same time, the excavation section of the adjustable excavation module between the two Leroy triangular cutterheads can be limited to the excavation edge of the excavation piece adjacent to it, which can ensure that the excavation module only performs over-excavation operations on the bottom line of the rectangular tunnel, limiting the over-excavation range, and the over-excavated part of the bottom can also be used for laying the pipeline system. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural diagram of the first embodiment of the tunnel pipe jacking device of the utility model;

[0026] Figure 2 It is a structural diagram of a second embodiment of a tunnel pipe jacking device of the utility model;

[0027] Figure 3 It is a front view of a third embodiment of a tunnel pipe jacking device of the utility model;

[0028] Figure 4 It is a front view of a second embodiment of a tunnel pipe jacking device of the utility model;

[0029] Figure 5It is a second structural diagram of the first embodiment of the tunnel pipe jacking device of the utility model;

[0030] Figure 6 It is a third structural diagram of the first embodiment of the tunnel pipe jacking device of the utility model;

[0031] Figure 7 It is a structural diagram of the pipe segment mechanism of the tunnel pipe jacking device of the utility model;

[0032] Figure 8 It is a structural diagram of the first groove of the tunnel jacking device of the utility model;

[0033] Fig. 9 It is a fourth structural diagram of the first embodiment of the tunnel pipe jacking device of the utility model.

[0034] Description of Figure Numbers:

[0035] 1. Shield;

[0036] 2. Pipe joint mechanism;

[0037] 3. Cutterhead mechanism; 31. First excavation structure; 311. Excavation cutterhead; 312. Edge excavation cutterhead; 32. Second excavation structure; 321. Excavation member; 322. Adjustable excavation module;

[0038] 4. Additional pipe joint structure; 41. Signal cable;

[0039] 5. The first groove;

[0040] 6. Scraping tools;

[0041] 7. Slag discharge mechanism;

[0042] D. The width of the tunnel;

[0043] H, height direction of the tunnel;

[0044] F. The excavation direction of the tunnel jacking device. DETAILED DESCRIPTION

[0045] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0046] It should be noted that when an element is referred to as being "disposed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and are not intended to be the only embodiment.

[0047] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art in the technical field of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0048] like Figures 1 to 4 As shown, the utility model provides a tunnel jacking device, comprising:

[0049] The shield shell 1 has a plurality of pipe joint mechanisms 2 connected to its rear end;

[0050] The cutter head mechanism 3 is connected to the front end of the shield shell 1, and the cutter head mechanism 3 has:

[0051] A first excavation structure 31 having a plurality of excavation cutter discs 311 arranged along a width direction D of the tunnel;

[0052] The second excavation structure 32 is arranged below the first excavation structure 31 along the height direction H of the tunnel. The second excavation structure 32 has at least two excavation pieces 321 arranged on both sides of the tunnel along the width direction D of the tunnel, and an adjustable excavation module 322 located between the at least two excavation pieces 321. The excavation section of the adjustable excavation module 322 can cover the excavation edge of the excavation piece 321 adjacent to it.

[0053] The tunnel jacking device of the utility model can ensure that while reducing the excavation blind area, it can cope with the composite geology of soft upper and hard lower strata, and realize non-stop high-efficiency excavation construction; further, the first excavation structure 31 can cope with the soft soil geology in the composite geology, and the second excavation structure 32 can ensure that there is no excavation blind area at the bottom of the tunnel through the excavation piece 321 and the adjustable excavation module 322, that is, the adjustable excavation module 322 covers the excavation edge of the excavation piece 321 adjacent to it on the excavation section to avoid the formation of blind areas.

[0054] For details, please refer to Figure 1 and Figure 2As shown, the tunnel jacking device includes a cutterhead mechanism 3, a shield shell 1, and a plurality of pipe segment mechanisms 2 connected in sequence. In the height direction H of the tunnel, the first excavation structure 31 of the cutterhead mechanism 3 is arranged above the second excavation structure 32. The plurality of excavation cutterheads 311 of the first excavation structure 31 are arranged at intervals along the width direction D of the tunnel, and the plurality of excavation cutterheads 311 are arranged front and back on different excavation planes, and the excavation sections of two adjacent excavation cutterheads 311 overlap and cover each other. The second excavation structure 32 and the first excavation structure 31 are both connected to the front end of the shield shell 1. The second excavation structure 32 has at least two excavation members 321 arranged on opposite sides of the tunnel. In a specific embodiment, There are two excavation pieces 321, and the adjustable excavation module 322 is arranged between the two excavation pieces 321. The excavation section of the adjustable excavation module 322 can cover the excavation edges of the two adjacent excavation pieces 321 to achieve excavation without blind spots at the bottom of the tunnel. In another other embodiment, four excavation pieces 321 can be arranged on both sides of the tunnel according to the width of the tunnel and the required shape of the tunnel, that is, two excavation pieces 321 are arranged on one side of the tunnel, and two excavation pieces 321 are also arranged on the other side of the tunnel. The adjustable excavation module 322 is arranged between the two excavation pieces 321 close to the center of the tunnel, and there is no specific limitation on the number of excavation pieces 321 arranged.

[0055] In a specific embodiment of the present invention, both the tunneling member 321 and the adjustable tunneling module 322 use a circular tunneling cutterhead. In a feasible embodiment, the tunneling center position of the adjustable tunneling module 322 is lower than the tunneling center position of the tunneling member 321 to cover the tunneling edge of the circular tunneling cutterhead of the adjacent tunneling member 321. Alternatively, in another feasible embodiment, the outer diameter of the adjustable tunneling module 322 is larger than the outer diameter of the tunneling member 321 to cover the tunneling edge of the adjacent tunneling member 321. In the above two embodiments, the tunneling section of the adjustable tunneling module 322 can achieve downward over-excavation on the bottom line of the tunnel.

[0056] In another specific embodiment, the excavation member 321 and the adjustable excavation module 322 may also adopt a Lelo triangle excavation cutter disc according to actual needs, and the utility model does not specifically limit the type of cutter disc adopted; in yet another specific embodiment, the adjustable excavation module 322 may be a plurality of excavation cutter discs 311, and the excavation section of the adjustable excavation module 322 composed of a plurality of excavation cutter discs 311 can cover the excavation edge of the excavation cutter disc 311 adjacent to it.

[0057] According to one embodiment of the present utility model, Figure 2 and Figure 4 As shown, along the height direction H of the tunnel, the excavation height of the adjustable excavation module 322 is greater than or equal to the excavation height of the excavation member 321 .

[0058] The excavation height of the adjustable excavation module 322 is higher than the excavation height of the excavation member 321 , and the excavation section of the adjustable excavation module 322 can cover the excavation blind area between the second excavation structure 32 and the first excavation structure 31 .

[0059] Specifically, the excavation height of the adjustable excavation module 322 is greater than the excavation height of the excavation member 321, that is, on the second excavation structure 32, the setting position of the central axis of the adjustable excavation module 322 is higher than the setting position of the central axis of the excavation member 321. In this embodiment, the excavation member 321 and the adjustable excavation module 322 both adopt circular excavation cutter discs, and the setting position of the central axis of the adjustable excavation module 322 is higher than the setting position of the central axis of the circular excavation cutter disc of the excavation member 321. The excavation section of the adjustable excavation module 322 needs to cover the excavation edge of the excavation member 321 adjacent to it, that is, the outer diameter of the adjustable excavation module 322 is greater than the outer diameter of the excavation member 321, that is, the excavation section of the adjustable excavation module 322 exceeds the bottom line of the tunnel. In other embodiments, the adjustable tunneling module 322 and the tunneling member 321 may also adopt a Leroy triangle tunneling cutterhead, and there is no specific restriction on the cutterhead model of the adjustable tunneling module 322 and the tunneling member 321.

[0060] In one embodiment of the present invention, Figure 1 and Figure 2 As shown, the first excavation structure 31 has at least two edge excavation cutter discs 312 located on both sides of the tunnel, and the adjustable excavation module 322 and at least two edge excavation cutter discs 312 are located in the same excavation plane.

[0061] By setting the excavation plane in layers, spatial interference between adjacent cutter heads can be avoided. At the same time, the layered setting method can make the excavation sections of adjacent cutter heads overlap with each other, solving the problem of excavation blind spots.

[0062] Specifically, the two edge excavation cutter discs 312 and the adjustable excavation module 322 are located in the same excavation plane, and the excavation plane where the two edge excavation cutter discs 312 and the adjustable excavation module 322 are located is located at the front end along the excavation direction F of the tunnel jacking device; in other embodiments, the excavation plane where the two edge excavation cutter discs 312 and the adjustable excavation module 322 are located can also be located behind the excavation plane where other excavation cutter discs are located along the excavation direction F of the tunnel jacking device, and there is no specific restriction on the stratification of the excavation planes of other excavation cutter discs.

[0063] In one embodiment of the present invention, Figures 1 to 4 As shown, the second excavation structure 32 has two excavation members 321 and an adjustable excavation module 322. The two excavation members 321 are Lelo triangle excavation cutter heads, and the adjustable excavation module 322 is a circular excavation cutter head.

[0064] The second excavation structure 32 provided in this embodiment can realize right-angle and flat surface excavation of the tunnel by setting the excavation member 321 as a Lelo triangle excavation cutterhead, and the excavation section of the adjustable excavation module 322 can exceed the bottom line of the tunnel by setting the adjustable excavation module 322 as a circular excavation cutterhead, thereby achieving a certain degree of over-excavation, and the over-excavation area can realize the installation of the pipeline system.

[0065] Specifically, two excavation components 321 (i.e., Leleau triangular excavation cutter discs) are respectively arranged on both sides of the tunnel. The Leleau triangular excavation cutter discs can process a square excavation section to realize excavation in the corner area of ​​the rectangular tunnel. The adjustable excavation module 322 (i.e., a circular excavation cutter disc) between the two Leleau triangular excavation cutter discs is arranged in the middle of the rectangular tunnel. The excavation section of the circular excavation cutter disc can cover the excavation edges of the two Leleau triangular excavation cutter discs.

[0066] According to one embodiment of the present utility model, Figure 2 , Figure 5 and Figure 6 As shown, the tunnel jacking device also includes an additional pipe segment structure 4, which is connected to the shield shell 1 and the pipe segment mechanism 2, and a signal cable 41 capable of supplying power to the cutterhead mechanism 3 is arranged inside the additional pipe segment structure 4.

[0067] The signal cable 41 of the additional pipe joint structure 4 can provide corresponding power for the rotational drive of multiple cutter discs of the cutter disc mechanism 3. Specifically, the signal cable 41 of the additional pipe joint structure 4 is passed through the inside of the shield shell 1 and multiple pipe joint mechanisms 2, and the signal cable 41 is fixed on the inner wall of the shield shell 1 and multiple pipe joint mechanisms 2.

[0068] In a specific embodiment, refer to Figure 2 , Figures 5 to 9 As shown, along the height direction H of the tunnel, the additional pipe segment structure 4 is connected to the bottom of the shield shell 1 and the pipe segment mechanism 2, and a first groove 5 for placing the signal cable 41 is formed between the additional pipe segment structure 4 and the bottom surfaces of the shield shell 1 and the pipe segment mechanism 2, and the bottom surface of the additional pipe segment structure 4 is higher than or parallel to the bottom surface of the adjustable excavation module 322.

[0069] Specifically, the first groove 5 formed between the additional pipe segment structure 4 and the bottom surface of the shield shell 1 and the bottom surface of the pipe segment mechanism 2 is located at the bottom of the shield shell 1 and the bottom of the pipe segment mechanism 2. In the present embodiment, the first groove 5 is detachably connected to the pipe segment mechanism 2, and the signal cable 41 of the additional pipe segment structure 4 is placed in the first groove 5. When the tunnel boring machine is advancing, the signal cable 41 can be placed in the first groove 5 all the time, and the newly added pipe segment mechanism 2 can be directly connected to the upper part of the first groove 5 from the rear end of the tunnel jacking device, thereby avoiding the situation in which the signal cable 41 of the traditional shield machine needs to be installed after the jacking device is shut down, that is, avoiding the situation in which the traditional pipe segment mechanism 2 passes the signal cable 41 through the new pipe segment mechanism 2 after lowering the new pipe segment for installation, and then connects to the cutter head mechanism 3 to restart the shield machine. The tunnel jacking device of the present embodiment can quickly install a new pipe segment device without stopping.

[0070] Furthermore, the bottom surface of the additional pipe segment structure 4 is higher than or parallel to the bottom surface of the adjustable excavation module 322 to match the tunnel space that has been excavated and avoid secondary excavation construction; when the excavation section of the adjustable excavation module 322 exceeds the bottom line of the tunnel, the first groove 5 can also be set in the excavation space of the adjustable excavation module 322 that exceeds the bottom line of the tunnel.

[0071] According to one embodiment of the present utility model, Figure 3 and Figure 4 As shown, at least one scraping tool 6 is provided on the top of the shield shell 1, and at least one scraping tool 6 is arranged between two adjacent excavation cutter discs 311 along the width direction D of the tunnel. The scraping tool 6 can be used to remove the soil layer in the excavation blind area generated by the multiple excavation cutter discs 311 of the first excavation structure 31 in the soil stratum.

[0072] Specifically, the scraping tool 6 is connected to the top of the shield shell 1, that is, the top inner side of the shield shell 1, and the scraping tool 6 is set obliquely upward toward the shield shell 1 to scrape out the rectangular straight edge required at the top of the tunnel. In other embodiments of the scraping tool 6, the setting method of the scraping tool 6 can be set according to the required tunnel shape; in this embodiment, the first excavation structure 31 is connected to the front end of the shield shell 1, and a scraping tool 6 is arranged between two adjacent excavation cutter discs 311 of the first excavation structure 31 along the width direction D of the tunnel, that is, along the width direction D of the tunnel, the scraping section of the scraping tool 6 is located between the excavation sections of two adjacent excavation cutter discs 311 of the first excavation structure 31, so as to scrape out the rectangular straight edge required at the top of the tunnel and remove the excavation blind area of ​​the excavation sections of the two adjacent excavation cutter discs 311. In other embodiments, two scraping tools 6 may be arranged between two adjacent excavation cutter discs 311 of the first excavation structure 31 in the width direction D of the tunnel, and there is no specific limitation on the number of scraping tools 6.

[0073] In a feasible embodiment, at least two of the plurality of driving cutter discs 311 of the first driving structure 31 are Reuleaux triangle driving cutter discs.

[0074] The straight edges required by each side of the tunnel or the corners required by the rectangular tunnel can be excavated by the Reuleaux triangle excavation cutter disc. In this embodiment, two Reuleaux triangle excavation cutter discs are arranged on both sides of the tunnel to process the right angle corners of the rectangular tunnel. In other embodiments, two Reuleaux triangle excavation cutter discs can also be arranged in the middle of the tunnel to process the straight area on the top of the tunnel.

[0075] Furthermore, all of the multiple boring cutter discs 311 of the first boring structure 31 can be Leroy triangular boring cutter discs to process the square tunnel top required for the tunnel. There is no specific restriction on the number of Leroy triangular boring cutter discs in the first boring structure 31.

[0076] According to one embodiment of the present utility model, Figure 1 and Figure 2 As shown, the multiple excavation cutter discs 311 of the first excavation structure 31 are arranged front and back along the excavation direction F of the tunnel jacking device, and at least one of the multiple excavation cutter discs 311 is a circular excavation cutter disc.

[0077] By dividing the front and back layers into multiple excavation plane layers, the overlap rate of the excavation sections of multiple excavation cutter discs 311 can be improved, further eliminating the generation of excavation blind spots. The use of at least one circular excavation cutter disc can achieve a larger excavation range under the condition of a fixed cutter disc diameter, reducing the number of excavation cutter discs 311 arranged.

[0078] Specifically, the first excavation structure 31 has three circular excavation cutter discs arranged at intervals along the width direction D of the tunnel, and the two circular excavation cutter discs located on both sides of the tunnel are located in the same excavation plane, and the excavation sections of the three circular excavation cutter discs partially overlap. Along the excavation direction F of the tunnel jacking device, the two circular excavation cutter discs located on both sides of the tunnel are in front of a circular excavation cutter disc located in the middle of the tunnel. In other embodiments, along the excavation direction F of the tunnel jacking device, a circular excavation cutter disc located in the middle of the tunnel can also be in front of the two circular excavation cutter discs located on both sides of the tunnel, and there is no specific limitation on this.

[0079] According to one embodiment of the present utility model, Figure 5 and Figure 6 As shown, the tunnel jacking device also includes a slag discharge mechanism 7, which is located in the shield shell 1 and connected between the cutterhead mechanism 3 and the pipe segment mechanism 2. The slag discharge mechanism 7 can be used to transport the slag produced by the cutterhead mechanism 3 out of the shield machine.

[0080] Specifically, the slag discharge mechanism 7 is disposed in the shield shell 1 , one end of the slag discharge mechanism 7 is connected to the cutter disc mechanism 3 , and the other end of the slag discharge mechanism 7 is connected to the pipe joint mechanism 2 and passes through the rear end of the pipe joint mechanism 2 .

[0081] The specific embodiments described above further illustrate the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only a specific embodiment of the utility model and is not intended to limit the scope of protection of the utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the scope of protection of the utility model.

Claims

1. A tunnel pipe jacking device, It is characterized in that include: A shield shell, a rear end of which is connected to a plurality of pipe joint mechanisms; A cutter disc mechanism is connected to the front end of the shield shell, and the cutter disc mechanism has: A first excavation structure having a plurality of excavation cutterheads arranged along the width direction of the tunnel; A second excavation structure is arranged below the first excavation structure along the height direction of the tunnel. The second excavation structure has at least two excavation pieces arranged on both sides of the tunnel along the width direction of the tunnel, and an adjustable excavation module located between the at least two excavation pieces. The excavation section of the adjustable excavation module can cover the excavation edge of the excavation piece adjacent to it.

2. The tunnel pipe jacking device according to claim 1, It is characterized in that Along the height direction of the tunnel, the excavation height of the adjustable excavation module is greater than or equal to the excavation height of the excavation member.

3. The tunnel pipe jacking device according to claim 1 or 2, It is characterized in that The first excavation structure has at least two edge excavation cutter discs located on both sides of the tunnel, and the adjustable excavation module and at least two edge excavation cutter discs are located in the same excavation plane.

4. The tunnel pipe jacking device according to claim 3, It is characterized in that The second excavation structure comprises two excavation members and one adjustable excavation module, the two excavation members are Lelo triangle excavation cutter discs, and the excavation module is a circular excavation cutter disc.

5. The tunnel pipe jacking device according to claim 1, It is characterized in that The tunnel jacking device also includes an additional pipe segment structure, which is connected to the shield shell and the pipe segment mechanism. A signal cable that can supply power to the cutter head mechanism is arranged in the additional pipe segment structure.

6. The tunnel pipe jacking device according to claim 5, It is characterized in that Along the height direction of the tunnel, the additional pipe segment structure is connected to the bottom of the shield shell and the pipe segment mechanism, and a first groove for placing the signal cable is formed between the additional pipe segment structure and the bottom surfaces of the shield shell and the pipe segment mechanism, and the bottom surface of the additional pipe segment structure is higher than or parallel to the bottom surface of the adjustable excavation module.

7. The tunnel pipe jacking device according to claim 1, It is characterized in that At least one scraping tool is disposed on the top of the shield shell, and the at least one scraping tool is arranged between two adjacent excavation cutter discs along the width direction of the tunnel.

8. The tunnel pipe jacking device according to claim 7, It is characterized in that At least two of the plurality of excavation cutter discs of the first excavation structure are Lelo triangle excavation cutter discs.

9. The tunnel pipe jacking device according to claim 8, It is characterized in that The plurality of excavation cutter discs of the first excavation structure are arranged front and back along the excavation direction of the tunnel jacking device, and at least one of the plurality of excavation cutter discs is a circular excavation cutter disc.

10. The tunnel pipe jacking device according to claim 1, It is characterized in that The tunnel jacking device also includes a slag discharge mechanism, which is located in the shield shell and connected between the cutter head mechanism and the pipe joint mechanism.