Tunnel drilling device
By designing multiple drilling units and telescopes in the tunnel drilling device and combining the limiting module, the problem of low drilling efficiency in the prior art is solved, and efficient and stable multi-blast drilling operation is achieved.
Patent Information
- Application Number
- CN202420189397.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2034-01-25
AI Technical Summary
The existing tunnel automatic drilling device is less efficient when drilling holes, and requires multiple movement of the driller to form multiple gun holes, which takes a long time.
A tunnel drilling device is designed, including a mobile module and a drilling module, the drilling module comprises at least two drilling units, each unit is equipped with a drilling device, and the height can be adjusted by a first telescopic device and a second telescopic device The drilling machine is telescopic, and the top and bottom limit modules are used for fixing devices to improve drilling efficiency and stability.
By working at the same time by multiple drillers, the drilling efficiency is significantly improved, multiple gun holes can be drilled at the same time, adapted to different height positions, avoiding the device from tipping, and improving work efficiency and stability.
Smart Images

Figure CN221957512U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of tunnels, and in particular relates to a tunnel drilling device. Background Art
[0002] Tunnels are engineering structures buried in the ground, and are a form of human use of underground space. As the railway lines are extended, the number of railway tunnels is also increasing rapidly. In the process of tunnel construction, the commonly used methods include shield method and drilling and blasting method. The shield method is to use a shield machine to automatically move in the rock formation to eventually form a tunnel. The drilling and blasting method is to drill holes in the rock formation, then fill the blast holes with explosives, and then detonate the explosives to form a tunnel.
[0003] In conventional drilling and blasting methods, blastholes are usually drilled manually by workers. However, when performing a one-time blasting, in order to ensure a wider blasting area, the blastholes need to be as many as possible and cover a wider area. Therefore, in conventional drilling and blasting methods, workers need to drill multiple blastholes before blasting, which is a relatively time-consuming process.
[0004] In order to improve the efficiency of drilling, some devices that can automatically drill holes have begun to appear in the prior art. Conventional drilling devices usually include a mobile chassis and a drilling module, the drilling module is installed on the mobile chassis, and the drilling module includes a drill for drilling holes. When drilling is required, the mobile chassis drives the drilling module to move so that the drilling module reaches different positions, and then the drill automatically drills holes. For example: the tunnel blasting drilling device disclosed in application number: 201510938698.6.
[0005] However, the above-mentioned drilling devices are only equipped with one drill. Therefore, in order to form multiple blast holes required for one blast, the drill needs to be moved to different positions and the drilling operation needs to be repeated multiple times. In this process, it still takes a lot of time and the drilling efficiency is still low.
[0006] In summary, the prior art has the problem of low efficiency when the automatic tunnel drilling device drills multiple holes. Utility Model Content
[0007] The utility model provides a tunnel drilling device, which aims to solve the problem of low efficiency of conventional tunnel automatic drilling devices when drilling multiple holes.
[0008] In order to achieve the above-mentioned object, the utility model provides a tunnel drilling device, comprising a moving module and a drilling module, wherein the drilling module is installed on the moving module, and the moving module is used to drive the drilling module to move;
[0009] The drilling module includes at least two drilling units, and each drilling module includes a drill for drilling.
[0010] At least two drilling units are configured in this solution, and each drilling unit includes a drill. Therefore, the tunnel drilling device in this solution can drill at least two blastholes at the same time, which undoubtedly significantly improves the work efficiency compared with the single blasthole in the prior art.
[0011] Optionally, since the tunnel as a whole has a movable height, in order to enable drilling at all height positions of the tunnel, the present solution preferably arranges the drilling units in an up-and-down arrangement, and different drilling units are located at different height positions. In the present solution, the drilling units are arranged up and down, so different drilling units are located at different height positions. Furthermore, since each drilling unit includes a borer, when different drilling units are located at different height positions, the borers are located at different height positions, and borers of different heights can drill at different height positions.
[0012] Optionally, since the heights of the two sides of the tunnel are inconsistent with the middle position, specifically, the middle position is higher than the positions on the two sides of the tunnel. Therefore, in order to enable the borer to adapt to different positions of the tunnel, this solution preferably includes a first telescopic device for each drilling unit, and the first telescopic device is connected to the borer by transmission, and the first telescopic device is used to adjust the drilling height of the borer. In this solution, when it is necessary to drill holes on both sides of the tunnel or in the middle of the tunnel, the first telescopic device can be extended or retracted, so that the height position of the borer changes, and the height of the borer is adapted to the blastholes required at different positions of the tunnel.
[0013] Optionally, in order to adjust the height of the drill, the first telescopic device preferably connects the adjacent drilling units through the first telescopic device, and the first telescopic device can raise or lower the drilling module as a whole. In this solution, the upper and lower adjacent drilling units are connected through the first telescopic device, and when the first telescopic device is extended, the height of the drilling unit changes accordingly. Since the drilling unit includes a drill, the height of the drill changes accordingly.
[0014] In this solution, the first telescopic device is preferably arranged vertically. The vertically arranged first telescopic device can be more suitable for the up and down driving of the drill.
[0015] Optionally, when the drill is drilling, the drill needs to contact the rock formation, and when the drill does not need to drill, the drill needs to retract to avoid exposure and damage. Therefore, in this solution, the drilling unit preferably includes a second telescopic device and a mounting component, the drill is installed on the mounting component, the second telescopic device is transmission-connected to the mounting component, and the second telescopic device drives the mounting component to telescopically move. In this solution, the drill is installed on the mounting component, and the second telescopic device is transmission-connected to the mounting component. When the second telescopic device is extended, the second telescopic device drives the drill to extend, and the drill can contact the rock formation; when the drilling is completed, the second telescopic device retracts, and the second telescopic device drives the drill to retract to avoid the drill being exposed and damaged.
[0016] In order to make the drilling efficiency higher, in this solution, each drilling unit preferably includes at least two drills. In this solution, each drilling unit includes at least two drills, and the drills in each drilling unit can drill independently. Therefore, each drilling unit can drill multiple holes at the same time, further improving the drilling efficiency.
[0017] Optionally, in order to ensure uniform drilling and perform uniform blasting during blasting, the present solution preferably arranges the at least two drills in a straight line.
[0018] Optionally, in order to prevent the drilling device from tipping over during drilling, the present solution preferably further includes a top stop module, the top stop module being located at the top of the tunnel drilling device, and the top stop module being used to abut against the top wall of the tunnel. In the present solution, a top stop module is configured at the top of the tunnel drilling device. During drilling, the top stop module can abut against the top wall of the tunnel to fix the tunnel drilling device, thereby preventing the tunnel drilling device from tipping over due to recoil during drilling.
[0019] In order to prevent the drilling device from tipping over during drilling, the present solution preferably further includes a bottom stop module, which is located at the bottom end of the tunnel drilling device and is used to abut against the ground. In the present solution, a bottom stop module is configured at the bottom end of the tunnel drilling device. When drilling, the bottom stop module can abut against the tunnel ground to fix the tunnel drilling device and prevent the tunnel drilling device from tipping over due to recoil during drilling.
[0020] Optionally, in order to achieve the cooperation and release with the top wall of the tunnel, the top limit module of this solution preferably includes a limit block and a first lifter, wherein the limit block is connected to the first lifter by transmission, and the first lifter drives the limit block to rise and fall, so that the limit block is against the top wall of the tunnel. In this solution, the limit block is used to contact the top of the tunnel, and the limit block is connected to the first lifter by transmission. When the first lifter rises, the limit block is driven to be lifted up by the first lifter, and the limit block contacts and gets stuck with the top wall of the tunnel; when the first lifter descends, the limit block is driven to descend by the first lifter, and the limit block is separated from the top wall of the tunnel, and the limit block will not hinder the movement of the tunnel drilling device.
[0021] Optionally, in order to achieve the coordination and separation of the bottom limit module with the tunnel ground, the present solution preferably comprises a second lifter and a support leg, wherein the second lifter is connected to the support leg in a transmission manner, and the second lifter drives the support leg to descend so that the bracket is against the ground. In the present solution, the support leg is used to contact the tunnel ground, and the support leg is connected to the second lifter in a transmission manner. When the second lifter is extended, the support leg is driven down by the second lifter, and the support leg contacts the tunnel ground and abuts against each other; when the second lifter is retracted, the support leg is driven up by the second lifter, and the support leg is separated from the tunnel ground, and the support leg will not hinder the movement of the tunnel drilling device.
[0022] Optionally, in order to achieve stable driving of the drilling module, the mobile module preferably includes a mover and support wheels in this solution, wherein the mover is used to drive the drilling module to move, and the support wheels are arranged on the side of the mover. In this solution, the mover serves as the moving power of the drilling module, so that the drilling module can be driven to move. At the same time, in order to make the movement of the mobile module more stable, the solution preferably configures auxiliary balancing support wheels on the side of the mover to ensure that it will not tip over during movement.
[0023] The beneficial effect of the utility model is that at least two drilling units are configured in the present solution, and each drilling unit includes a drill. Each drill can work independently. Therefore, when it is necessary to drill multiple blastholes, multiple drills can work simultaneously to drill holes, thereby improving the efficiency of drilling multiple holes. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 The figure is a schematic diagram of the structure of a tunnel boring device.
[0025] Figure 2 A perspective view of a mobile module.
[0026] Figure 3 This is a front view of the mobile module.
[0027] Figure 4 A three-dimensional diagram of the drilling unit.
[0028] Figure 5 This is a schematic diagram when the drill is not extended.
[0029] Figure 6 A schematic diagram of the drill being extended.
[0030] Figure 7 It is a structural diagram of the top limit module.
[0031] Figure 8 This is the front view of the top limit module.
[0032] Fig. 9 This is the front view of the bottom limit module.
[0033] The figure marks include: moving module 1, supporting frame 11, column 111, mounting frame 112, mover 12, supporting wheel 13, drilling module 2, drilling unit 21, first telescope 211, inner tube 211a, outer tube 211b, second telescope 212, mounting frame 213, mounting component 214, drill 215, top limit module 3, first lifter 31, arc-shaped mounting frame 32, limit block 33, bottom limit module 4, second lifter 41, support leg 42, tunnel 6. DETAILED DESCRIPTION
[0034] In order to make the purpose, technical solutions and advantages of the embodiments more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with the present disclosure. Instead, they are only examples of devices and methods consistent with some aspects of the present disclosure as detailed in the attached claims.
[0035] It should be noted that all actions to obtain signals, information or data in this application are carried out in compliance with the relevant data protection laws and policies of the country where they are located, and with the authorization given by the owner of the corresponding device.
[0036] In the present disclosure, unless otherwise stated, the directional words used, such as "inside" and "outside", are defined according to the corresponding parts' own contours. The terms used in the present disclosure, such as "first" and "second", etc., are used to distinguish one element from another element and do not have order and importance.
[0037] Example 1
[0038] Basically as attached Figure 1As shown, a tunnel drilling device includes a mobile module 1 and a drilling module 2. The mobile module 1 is used to drive the drilling module 2 to move on the ground so that the drilling module 2 reaches different positions for drilling. At the same time, when entering and exiting the tunnel 6, the mobile module 1 is also used as a moving power. The drilling module 2 includes at least two drilling units 21, and each drilling unit 21 includes a drill 215. Each drill 215 in the embodiment of the present disclosure can work independently to drill, and finally form a blast hole for blasting.
[0039] In the embodiment of the present disclosure, since each drilling unit 21 is equipped with a drill 215, and there are at least two drilling units 21, when multiple blast holes need to be drilled, each drill 215 can work independently to drill, thereby drilling multiple blast holes in a short time and improving the work efficiency during drilling.
[0040] like Figure 2 and Figure 3 As shown, the mobile module 1 in the disclosed embodiment specifically includes a support frame 11, a mover 12 and a support wheel 13. The support frame 11 includes columns 111 symmetrically arranged at the four corners and a horizontally arranged installation frame 112. The column 111 is specifically a cylindrical column, which is preferably made of metal. The installation frame 112 is a rectangular frame, which is also preferably made of metal. The four columns 111 are respectively located at the four corners of the installation frame 112, and the installation frame 112 is fixed to the column 111 by welding or fastener connection. The installation frame 112 is supported by the column 111, and the installation frame 112 is separated from the ground, and the installation frame 112 will not be scratched with the ground. At the same time, in order to further make the connection between the installation frame 112 and the column 111 more stable, reinforcing ribs can also be welded at the connection between the installation frame 112 and the column 111 to strengthen the connection tightness between the installation frame 112 and the column 111.
[0041] The mover 12 of the disclosed embodiment is specifically installed on the mounting frame 112, and can be specifically installed at the bottom of the mounting frame 112. The mover 12 can be a small tracked vehicle or an AGV vehicle, etc. The mover 12 is fixedly installed at the bottom of the mounting frame 112, and the bottom of the mover 12 is in contact with the ground. When the mover 12 is working, it can drive the entire tunnel boring device to move. This movement can be forward or backward movement, or it can be left and right lateral movement.
[0042] The mover 12 can be fixed to the bottom column of the mounting frame 112 by welding or by configuring fasteners. At the same time, in order to make the mobile module 1 more stable when moving, the embodiment of the present disclosure also configures support wheels 13 at the lower end of each column 111. The support wheels 13 can jointly support the entire mobile module 1 on both sides in front and both sides in the rear of the mover 12 to prevent the mobile module 1 from tipping over due to uneven ground when moving. During implementation, in order to install the support wheel 13, a mounting protrusion for installing the support wheel 13 can be configured on the outer surface of the column 111, and the support wheel 13 can be installed at the bottom of the mounting protrusion by welding or configuring fasteners. In the embodiment of the present disclosure, the support wheel 13 is preferably a universal wheel, which can be rotated at multiple angles to adapt to the movement of the mover 12 in different directions.
[0043] In one application scenario, when the mover 12 moves forward, the entire device moves forward accordingly. During the forward movement of the entire device, the support wheel 13 rotates to the same direction as the moving direction of the mover 12, and the support wheel 13 moves in the same direction as the mover 12. When the mover 12 turns, the support wheel 13 can also rotate to the same direction as the moving direction of the mover 12. The support wheel 13 can ensure that it moves in the same direction as the mover 12, and the support wheel 13 will not hinder the movement of the mover 12. At the same time, the support wheel 13 can also maintain support for the mobile module 1 when the mover 12 moves to different directions to prevent the mobile module 1 from tilting.
[0044] like Figure 1 As shown, in the embodiment of the present disclosure, the drilling module 2 is installed on the top of the mobile module 1, and the drilling module 2 specifically includes four drilling units 21 (in some other embodiments, the number of drilling units 21 can be changed, for example, 2, 3 or 5, etc.). The four drilling units 21 are arranged in an up-and-down manner and are connected in sequence. The four drilling units 21 are located at different heights, and the drill 215 in each drilling unit 21 can drill rock formations at different heights to form blastholes at different heights, thereby achieving a better blasting effect.
[0045] like Figure 4 and Figure 5 As shown, the drilling unit 21 in the embodiment of the present disclosure includes a first retractor 211 , a second retractor 212 , a mounting frame 213 , a mounting component 214 and a drill 215 .
[0046] like Figure 4As shown, in the embodiment of the present disclosure, four first telescoping devices 211 are provided, which are symmetrically arranged at the four corners. In the drilling unit 21 located at the bottom layer, the bottom of the first telescoping device 211 is fixedly welded to the column 111 in the mobile module 1, so that the drilling unit 21 is fixedly connected to the mobile module 1, and the mobile module 1 can drive the drilling unit 21 to move. The other drilling units 21 located on the bottom layer of the drilling unit 21 are also welded and connected through the first telescoping device 211. In other words, the drilling units 21 adjacent to each other are connected through the first telescoping device 211.
[0047] In the embodiment of the present disclosure, the first telescopic device 211 is a telescopic sleeve. The telescopic sleeve in the embodiment of the present disclosure includes an inner tube 211a and an outer tube 211b. The inner tube 211a is accommodated inside the outer tube 211b, and the inner tube 211a can be telescoped inside the outer tube 211b. At the same time, a power device is fixedly welded and installed on the surface of the outer tube 211b. The power device can be a telescopic cylinder or a telescopic oil cylinder. The telescopic end of the power device is fixedly connected to the surface of the inner tube 211a, and the fixed end of the power device is fixed to the surface of the outer tube 211b. When the power device is extended, the inner tube 211a can extend from the outer tube 211b, so that the distance between adjacent drilling units 21 is expanded; when the power device is retracted, the inner tube 211a can be retracted into the outer tube 211b, so that the distance between adjacent drilling units 21 is reduced.
[0048] The mounting frame 213 of the disclosed embodiment is specifically a rectangular frame, and its four corners are respectively connected to the inner tube 211a of the first telescoping device 211. During implementation, the connection can be fixed by welding or fastener connection. The mounting frame 213 is preferably arranged horizontally. In an application scenario, when the first telescoping device 211 is extended, the mounting frame 213 is also raised; when the first telescoping device 211 is retracted, the mounting frame 213 is also retracted.
[0049] like Figure 5 As shown, in the embodiment of the present disclosure, the mounting component 214 is specifically frame-shaped, and is located on the upper surface of the mounting frame 213. A drill 215 is fixedly welded or connected with fasteners on the surface of the mounting component 214. The drill 215 can be a rock drill. The drills 215 are preferably arranged in a plurality and arranged in a straight line. The drills 215 arranged in a straight line can drill a row of blast holes at the same time, thereby achieving uniform blasting. The second telescopic device 212 is fixedly mounted on the upper surface of the mounting frame 213, and the tail end of the second telescopic device 212 is fixedly mounted on the surface of the mounting frame 213, and the front end of the second telescopic device 212 is fixedly connected to the mounting component 214. The second telescopic device 212 can be a horizontally arranged telescopic cylinder or a telescopic oil cylinder.
[0050] like Figure 5 and Figure 6As shown, in one application scenario, before drilling begins, the second telescopic device 212 is in a retracted state, and the drill 215 does not extend out of the mounting frame 213, so as to prevent the drill 215 from being exposed and damaged. When the drilling position is reached, the second telescopic device 212 extends out, pushing the mounting component 214 to move, and the drill 215 located on the mounting component 214 extends out of the mounting frame 213 as the mounting component 214 moves, and contacts the rock formation for drilling. During the drilling process, the second telescopic device 212 will continue to push the mounting component 214 to move, so as to ensure that the drilling depth meets the needs of blasting. When the blast hole reaches the predetermined depth, the second telescopic device 212 drives the mounting component 214 to retreat, and the drill 215 retracts into the mounting frame 213.
[0051] In order to avoid friction damage between the mounting component 214 and the mounting frame 213 in the disclosed embodiment, a sliding rod can be configured at the top of the mounting frame 213, and a circular arc sliding groove can be configured at the bottom of the mounting component 214. The sliding rod is accommodated in the sliding groove. When the mounting component 214 moves, the sliding groove moves along the setting direction of the sliding rod to avoid friction damage between the mounting component 214 and the mounting frame 213. At the same time, in the disclosed embodiment, it is preferred that sliding rods are configured on both sides of the mounting frame 213, and sliding grooves are also configured on both sides of the bottom of the mounting component 214. The sliding rods on both sides are configured correspondingly to the sliding grooves on both sides.
[0052] In the embodiment of the present disclosure, the upper and lower adjacent drilling units 21 are connected by a first expansion joint 211, and the first expansion joint 211 can support the overlapping drilling units 21 to ensure that different drilling units 21 are located at different heights. During implementation, the bottom of the outer tube 211b of the upper drilling unit 21 is welded to the top of the inner tube 211a of the lower drilling unit 21.
[0053] In one application scenario, when the first telescoping device 211 of any drilling unit 21 in the disclosed embodiment is raised, it can drive the drilling unit 21 above it to rise, and finally increase the height of the entire tunnel drilling device to adapt to different areas of the tunnel 6.
[0054] It is understandable that the top of the tunnel 6 is usually curved, that is, the heights of the two sides of the top of the tunnel 6 are lower than those of the middle area of the top of the tunnel 6. Therefore, in one application scenario. When it is necessary to drill holes on both sides of the tunnel 6, the controller can be used to control the partial elevation of each drilling unit 21 (for example, each first telescoping device 211 is raised by half), so that the drilling device is highly adapted to the two sides of the tunnel 6. When it is necessary to drill holes in the middle of the tunnel 6, the controller can be used to control the full elevation of each drilling unit 21 (for example, each first telescoping device 211 is fully elevated), so that the drilling device is highly adapted to the middle of the tunnel 6.
[0055] In addition to the above working modes, in one application scenario, the first retractor 211 in the drilling unit 21 at the upper end (e.g., the uppermost layer or the uppermost two layers of the drilling unit 21) can be controlled by the controller to not work, and only the first retractor 211 in the drilling unit 21 at the lower end works, so as to ensure that the drilling device is highly adapted to both sides of the tunnel 6. The controller can be a PLC control module, a single chip microcomputer or an industrial computer module, etc.
[0056] Since the drill 215 needs to enter the rock formation during drilling, in order to prevent the drilling device from tipping over due to the recoil during drilling, in the disclosed embodiment, a top stop module 3 is preferably configured at the top of the drilling device, and a bottom stop module 4 is also configured at the bottom of the drilling device. The top stop module 3 and the bottom stop module 4 can respectively and simultaneously abut against the top of the tunnel 6 and the ground, so that the entire drilling device is fixed to prevent tipping over due to the recoil of drilling.
[0057] Of course, in some other embodiments, only one of the top stop module 3 or the bottom stop module 4 may be provided, and the entire drilling device may be fixed by the top stop module 3 or the bottom stop module 4. Of course, the fixing effect of this fixing method is slightly worse than that of configuring both the top stop module 3 and the bottom stop module 4.
[0058] like Figure 7As shown, the top limit module 3 in the embodiment of the present disclosure specifically includes a first lifter 31, an arc-shaped mounting frame 32 and a limit block 33. The first lifter 31 can be a lifting cylinder, and the lifting cylinders are preferably configured as four, and are respectively fixedly welded and installed on the top of the first telescopic device 211 of the uppermost drilling unit 21. The top of the arc-shaped mounting frame 32 is arc-shaped, and the whole is plate-shaped. The four bottom corners of the arc-shaped mounting frame 32 are respectively welded and installed on the top of the first lifter 31. When the four first lifters 31 are raised, the arc-shaped mounting frame 32 is raised as a whole, and when the first lifter 31 is lowered, the arc-shaped mounting frame 32 is lowered as a whole. The limit blocks 33 in the embodiment of the present disclosure are evenly arranged on the top of the arc-shaped mounting frame 32, and can be installed by bonding or the like. The limit blocks 33 can be made of rubber or silicone.
[0059] like Figure 7 and Figure 8 As shown, in one application scenario, when the tunnel boring device is drilling, the four first lifters 31 are all raised, so that the arc-shaped mounting frame 32 is raised as a whole, and the limit block 33 contacts the top wall of the tunnel 6. The limit block 33 and the top wall of the tunnel 6 are against each other to prevent the tunnel boring device from tipping over. When the drilling is completed, the four first lifters 31 are all lowered, so that the arc-shaped mounting frame 32 is lowered, and the limit block 33 is separated from the top wall of the tunnel 6.
[0060] like Fig. 9 As shown, the bottom limit module 4 in the embodiment of the present disclosure includes a second lifter 41 and a support leg 42. The second lifter 41 is preferably set to four, and is respectively installed at the bottom of the four columns 111 of the mobile module 1. The second lifter 41 can be a lifting cylinder. The upper end of the second lifter 41 is fixedly welded and installed at the bottom of the column 111, and the lower end of the second lifter 41 is fixedly welded and connected to the support leg 42. The right angle is disc-shaped as a whole, and the bottom of the support leg 42 is also provided with a plurality of raised cones.
[0061] In one application scenario, when the mobile module 1 is in the process of moving, the second lifter 41 is in the raised state, the support leg 42 is separated from the ground, and the support leg 42 does not hinder the mobile module 1; when the mobile module 1 moves to the predetermined position, the second lifter 41 descends, driving the support leg 42 to descend as well. The bottom of the support leg 42 contacts the ground and presses against the ground, ensuring that the mobile module 1 is more stable.
[0062] The following is a further detailed description through a specific implementation method: When drilling is required, the mobile module 1 drives the drilling module 2 to enter the tunnel 6 until it moves to the front end of the tunnel 6. When the mobile module 1 reaches the predetermined position, the first telescoping device 211 in each drilling unit 21 works so that the height of the entire drilling unit 21 is adapted to the height of the tunnel 6. Then the top limit module 3 and the bottom limit module 4 work to ensure that the entire drilling module 2 remains stable. The drill 215 in each drilling unit 21 completes the drilling in the tunnel 6, and finally completes multiple blast holes.
[0063] When the drilling is completed, the first telescoping device 211 in each drilling unit 21 retracts, the top limiting module 3 and the bottom limiting module 4 are separated from the top wall and the ground of the tunnel 6 respectively, and finally the moving module 1 drives the drilling module 2 to exit the tunnel 6.
[0064] The above is only an embodiment of the utility model, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the utility model, which should also be regarded as the protection scope of the utility model, and these will not affect the effect of the implementation of the utility model and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. A tunnel boring device, characterized in that: It comprises a moving module (1) and a drilling module (2), wherein the drilling module (2) is installed on the moving module (1), and the moving module (1) is used to drive the drilling module (2) to move; The drilling module (2) comprises at least two drilling units (21), and each drilling module (2) comprises a drill (215) for drilling.
2. The tunnel boring device according to claim 1, characterized in that: The drilling units (21) are arranged in an up-and-down arrangement, and different drilling units (21) are located at different height positions.
3. The tunnel boring device according to claim 1 or 2, characterized in that: Each drilling unit (21) comprises a first telescopic device (211), wherein the first telescopic device (211) is transmission-connected to a drill (215), and the first telescopic device (211) is used to adjust the drilling height of the drill (215).
4. The tunnel boring device according to claim 3, characterized in that: Adjacent drilling units (21) are connected via the first telescopic device (211), and the first telescopic device (211) can raise or lower the drilling module (2) as a whole; and / or; The first retractor (211) is arranged vertically.
5. The tunnel boring device according to claim 1, characterized in that: The drilling unit (21) comprises a second telescopic device (212) and a mounting component (214); the drilling device (215) is mounted on the mounting component (214); the second telescopic device (212) is transmission-connected to the mounting component (214); the second telescopic device (212) drives the mounting component (214) to perform telescopic movement; and / or; Each of the drilling units (21) includes at least two drills (215).
6. The tunnel boring device according to claim 5, characterized in that: The at least two drills (215) are arranged in a straight line.
7. The tunnel boring device according to claim 1, characterized in that: It also comprises a top stop module (3), the top stop module (3) being located at the top of the tunnel boring device, and the top stop module (3) being used to abut against the top wall of the tunnel (6); and / or; It also comprises a bottom limit module (4), which is located at the bottom end of the tunnel boring device and is used to abut against the ground.
8. The tunnel boring device according to claim 7, characterized in that: The top limit module (3) comprises a limit block (33) and a first lifter (31); the limit block (33) is transmission-connected to the first lifter (31); the first lifter (31) drives the limit block (33) to rise and fall, so that the limit block (33) abuts against the top wall of the tunnel (6).
9. The tunnel boring device according to claim 7, characterized in that: The bottom limiting module (4) comprises a second lifter (41) and a support leg (42); the second lifter (41) and the support leg (42) are connected in a transmission manner; the second lifter (41) drives the support leg (42) to descend, so that the support is against the ground.
10. The tunnel boring device according to claim 1, characterized in that: The moving module (1) comprises a mover (12) and a support wheel (13); the mover (12) is used to drive the drilling module (2) to move; and the support wheel (13) is arranged on the side of the mover (12).