Central control system of high-temperature sintering furnace plant
By designing the central control system of the high-temperature sintering furnace factory, centralized monitoring and control of multiple high-temperature sintering furnaces is achieved, and problems of high labor intensity and safety hazards are solved, and safety and troubleshooting efficiency are improved.
Patent Information
- Application Number
- CN202323590679.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2033-12-27
AI Technical Summary
The existing high-temperature sintering furnace equipment requires multiple people to be on duty, which is labor-intensive and has a long inspection time, making it easy to miss or emergency situations not discovered in time, resulting in economic losses and safety accidents.
Design a central control system for high-temperature sintering furnace factory. Through the central central control module and workshop central control module, the monitoring switch, sintering furnace switch, camera, PLC controller, display equipment and acoustic and light alarm unit are used to realize the high temperature of multiple units. Centralized monitoring and control of the sintering furnace and its key support equipment, real-time monitoring and immediately stop heating in abnormal situations.
It has achieved the ability to take care of multiple high-temperature sintering furnaces by a single person, which reduces labor intensity, improves safety, promptly detects and eliminates faults, and reduces potential risks.
Smart Images

Figure CN221960435U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of high-temperature sintering furnaces, and in particular relates to a central control system of a high-temperature sintering furnace plant. Background Art
[0002] At present, the production of silicon carbide, boron carbide and composite new materials requires the use of high-temperature equipment such as high-temperature sintering furnaces. Since the existing high-temperature sintering furnaces come from many manufacturers and each device is independently controlled, there are the following disadvantages:
[0003] 1. The operation of each device requires manual operation and regular inspection of the working status. The high-temperature sintering furnace takes about 2 days to sinter one furnace each time, during which many people need to take shifts, and the labor intensity is very high;
[0004] 2. Equipment operation and inspection must be performed on-site by experienced personnel. However, a factory has multiple workshops, each with dozens of high-temperature sintering furnaces. Inspections one by one take a lot of time and are prone to omissions.
[0005] 3. If an emergency occurs in a single high-temperature sintering furnace, it may cause great economic losses or even safety accidents if it is not discovered immediately.
[0006] 4. The key supporting equipment that provides cooling water, electricity, compressed air, etc. for the high-temperature sintering furnace are all independent equipment and require separate inspections, which is a large workload.
[0007] Based on the above-mentioned problems existing in the prior art, it is now urgently necessary to develop a central control system for a high-temperature sintering furnace plant to realize centralized monitoring of the operating status of multiple high-temperature sintering furnaces and their key supporting equipment, so that one person can take care of multiple equipment and reduce the labor intensity of personnel. Utility Model Content
[0008] The technical problem to be solved by the utility model is to provide a central control system of a high-temperature sintering furnace plant which can monitor all high-temperature sintering furnaces in multiple plants and realize that a single person can watch over multiple high-temperature sintering furnaces.
[0009] The utility model provides a central control system for a high-temperature sintering furnace plant, comprising a central central control module and a plurality of workshop central control modules; the workshop central control module comprises a monitoring switch and a sintering furnace switch; the monitoring switch is electrically connected to the central central control module, the monitoring switch is connected to a plurality of cameras, and the plurality of cameras can shoot all the high-temperature sintering furnaces in a designated workshop; the sintering furnace switch is interactively connected to the central central control module, the sintering furnace switch is connected to the control systems and monitoring systems of all the high-temperature sintering furnaces in the designated workshop, and is used for the central central control module to obtain the status of all the high-temperature sintering furnaces and control the operation of all the high-temperature sintering furnaces.
[0010] Furthermore, the monitoring system includes a furnace temperature monitoring unit, a liquid level monitoring unit, a water temperature monitoring sensor, a furnace pressure monitoring sensor, a current monitoring sensor, a voltage monitoring sensor and an atmosphere monitoring sensor.
[0011] Furthermore, the central control module includes a PLC controller, an input device and a display device. The PLC controller, the input device and the display device are electrically connected. The PLC controller is used to receive monitoring data transmitted by the workshop central control module and issue instructions to the workshop central control module. The input device is used to manually input control commands to the PLC controller. The display device is used to display the monitoring data of all workshop central control modules.
[0012] Furthermore, the central control module also includes an audible and visual alarm unit. When an abnormality occurs in the value monitored by any sensor in the monitoring system, the abnormal data is displayed on the display device and the audible and visual alarm unit sounds an alarm.
[0013] Furthermore, the central control module also includes a master voice device, and the workshop control module also includes a slave voice device connected to the master voice device, and the master voice device can have voice calls with the slave voice device.
[0014] Furthermore, the workshop central control module also includes a power central control unit; the power central control unit is used to monitor and control the cooling system, power system and industrial gas supply system of the high-temperature sintering furnace. The cooling system includes a liquid level meter installed in the cooling clear water tank and the circulating water tank of the high-temperature sintering furnace, and a water pressure gauge installed at the tap water pipe and the fire water pipe. The power system includes a temperature sensor installed at the transformer to read the real-time maximum temperature of the aluminum busbar or the copper busbar, an oil temperature gauge installed in the transformer to read the oil temperature parameters, and a temperature detector installed in the low-voltage distribution room. The industrial gas supply system includes flow meters installed at the compressed air main valve, the nitrogen main valve and the argon main valve.
[0015] Furthermore, the temperature sensor, oil temperature gauge, thermometer and flow meter are all equipped with RS485 communication modules.
[0016] Furthermore, the central control module and the workshop control module are connected via optical fiber.
[0017] Furthermore, a camera is installed in each distribution room, and the camera is connected to a display device.
[0018] The central control system of the high-temperature sintering furnace plant provided by the utility model can centrally monitor the status of each high-temperature sintering furnace in each workshop through a central central control module and can independently control a single high-temperature sintering furnace, so that a single person can take care of multiple high-temperature sintering furnaces, thereby reducing labor intensity. At the same time, the configuration of the monitoring switch and the sintering furnace switch can monitor the working status of the high-temperature sintering furnace in real time, and when an abnormality occurs in the high-temperature sintering furnace, the heating of the high-temperature sintering furnace can be stopped immediately to improve the safety factor; the power central control unit can also be used to centrally monitor the layout of the power transformers and water tanks and industrial gas supply equipment dispersed in the plant in real time, accurately understand the real-time operation status of the transformers and industrial gas supply equipment in each workshop, eliminate adverse faults in time, reduce potential risks, and summarize all detection information and display it on the display device in the central control room to achieve efficient and all-round monitoring. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Attached Figure 1 It is a connection diagram of the central control system of the high temperature sintering furnace plant of the utility model;
[0020] Attached Figure 2 It is a connection diagram of the workshop central control module of a single workshop in the utility model;
[0021] Attached Figure 3 It is a schematic diagram of the connection of power central control units of multiple workshops in one embodiment of the utility model.
[0022] In the figure, 1-central control module; 2-workshop control module; 21-monitoring switch; 22-sintering furnace switch; 23-camera; 3-workshop; 4-high temperature sintering furnace; 5-optical fiber; 6-video monitoring line; 7-parameter data line. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0024] In the present invention, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, a physical connection, or a wireless communication connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0025] In addition, the technical solutions between the various embodiments of the present invention can be combined with each other, but it must be based on the fact that ordinary technicians in the field can implement it. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by the present invention.
[0026] As attached Figure 1 -Attached Figure 2 As shown, the utility model provides a central control system of a high-temperature sintering furnace plant, which is used to monitor multiple high-temperature sintering furnaces 4 in multiple workshops 3, so as to manage all the high-temperature sintering furnaces 4 on one terminal, so as to realize single-person supervision of multiple high-temperature sintering furnaces 4, thereby reducing the labor intensity of personnel. The central control system of the high-temperature sintering furnace plant includes a central central control module 1 and several workshop central control modules 2. Each workshop central control module 2 is used to monitor the high-temperature sintering furnaces 4 in a workshop. Specifically, the central central control module 1 can be equipped with a central control room for layout, or it can be directly set in any workshop 3; the workshop central control module 2 includes a monitoring switch 21 and a sintering furnace switch 22; the central central control module 1 and the workshop central control module 2 are connected by an optical fiber 5.
[0027] Among them, the monitoring switch 21 is connected to the central control module 1, that is, the monitoring switch 21 and the central control module 1 are connected for one-way signal transmission, that is, the monitoring switch 21 transmits video signals to the central control module 1, and the monitoring switch 21 is connected to a number of cameras 23, and the cameras 23 are connected to the monitoring switch 21 through the video monitoring line 6. The cameras 23 can shoot all the high-temperature sintering furnaces 4 in the workshop 3, thereby realizing the real-time transmission of the external status of all high-temperature sintering furnaces 4 to the central control module 1, so that the central control module 1 and its monitors can understand the external status of the high-temperature sintering furnace 4 in real time, which is convenient for timely discovery of safety hazards and safety accidents. In addition, the camera 23 can also be used to monitor the operation process of the high-temperature sintering furnace 4 by the employees in the monitoring workshop 3, confirm whether the operation time and operation process meet the requirements, and facilitate the management of on-site employees. A number of cameras 23 are connected to the central control module 1 through the monitoring switch 21, which is convenient for data aggregation and collection, and can simplify the line or network layout;
[0028] The sintering furnace switch 22 is interactively connected with the central control module 1, that is, the sintering furnace switch 22 is connected with the central control module 1 for two-way signal transmission, that is, the sintering furnace switch 22 transmits the status information of the high-temperature sintering furnace 4 to the central control module 1, and the central control module 1 transmits the control information to the sintering furnace switch 22, and the control information is controlled to one or more of the high-temperature sintering furnaces 4 through the sintering furnace switch 22, and the sintering furnace switch 22 is connected to the high-temperature sintering furnace 4 through the parameter data line 7. Specifically, the sintering furnace switch 22 is connected to the control system and monitoring system of all high-temperature sintering furnaces 4 in the workshop 3, wherein the control system is to control the operation start and stop, parameter adjustment and other operation controls of the high-temperature sintering furnace 4, and the monitoring system is to detect the working state of the high-temperature sintering furnace 4, and then used for the central control module 1 to obtain the state of all high-temperature sintering furnaces 4 and control the operation of all high-temperature sintering furnaces 4. In a preferred embodiment, controlling the operation of all high-temperature sintering furnaces 4 at least includes controlling the emergency stop of the high-temperature sintering furnace 4, thereby avoiding safety hazards. As for other control functions, they can be configured as needed.
[0029] The central control system of the high-temperature sintering furnace plant provided by the utility model can centrally monitor the status of each high-temperature sintering furnace 4 in each workshop 3 through a central control module 1 and can independently control a single high-temperature sintering furnace 4, so that a single person can take care of multiple high-temperature sintering furnaces 4, thereby reducing labor intensity. At the same time, the configuration of the monitoring switch 21 and the sintering furnace switch 22 can monitor the working status of the high-temperature sintering furnace 4 in real time, and when an abnormality occurs in the high-temperature sintering furnace 4, the heating of the high-temperature sintering furnace 4 can be stopped immediately, thereby improving the safety factor.
[0030] In one embodiment, the monitoring system includes a furnace temperature monitoring unit, a liquid level monitoring unit, a water temperature monitoring sensor, a furnace pressure monitoring sensor, a current monitoring sensor, a voltage monitoring sensor and an atmosphere monitoring sensor, so as to perform multi-faceted monitoring of the high-temperature sintering furnace 4. It should be particularly noted that the atmosphere monitoring sensor includes a flow meter configured in each of the compressed air, nitrogen main valve and argon main valve. The high-temperature sintering furnace 4 needs to be filled with a specific process gas, and the high-temperature sintering furnace 4 is ensured to work safely by real-time flow monitoring of the gas.
[0031] In one embodiment, the central control module 1 includes a PLC controller, an input device and a display device, wherein the PLC controller is used to receive data information from the monitoring switch 21 and the sintering furnace switch 22, and display it on the display device; it is also used to receive operation instructions from the input device, and transmit the operation instructions to the sintering furnace switch 22 for corresponding control operations; wherein the data information received from the sintering furnace switch 22 includes detection elements such as water temperature, water pressure, furnace temperature, furnace pressure, current, voltage, and gas flow meters of nitrogen and argon of the high-temperature sintering furnace 4.
[0032] In one of the embodiments, the central control module 1 also includes a sound and light alarm unit. When an abnormality occurs in the value monitored by any sensor in the monitoring system, the abnormal data is displayed on the display device, and the sound and light alarm unit sounds an alarm, so that workers can promptly discover the fault and eliminate it to reduce safety hazards. In this embodiment, the sound and light alarm unit is connected to the PLC controller, and the PLC controller starts the sound and light alarm lights to give an alarm prompt according to the actual settings.
[0033] In one of the embodiments, the central control module 1 also includes a main voice device, and the workshop control module 2 also includes a slave voice device connected to the main voice device. The main voice device can communicate with the slave voice device, thereby realizing one-to-one communication between each workshop 3, making it convenient to quickly issue instructions to on-site workers to improve work efficiency and troubleshooting efficiency.
[0034] In one embodiment, the workshop central control module 2 also includes a power central control unit; the power central control unit is used to monitor and control the cooling system, power system and industrial gas supply system of the high-temperature sintering furnace, thereby realizing the monitoring and control of the peripheral auxiliary equipment of the high-temperature sintering furnace 4, and improving the comprehensiveness of the monitoring. The cooling system includes a liquid level meter arranged in the cooling clear water tank and the circulating water tank of the high-temperature sintering furnace, and a water pressure meter arranged at the tap water pipe and the fire water pipe. The power system includes a temperature sensor arranged at the transformer to read the real-time maximum temperature of the aluminum bar or copper bar, an oil temperature meter arranged in the transformer to read the oil temperature parameter, and a temperature detector arranged in the low-voltage distribution room. The industrial gas supply system includes a flow meter arranged at the compressed air main valve, the nitrogen main valve and the argon main valve. The temperature sensor, the oil temperature meter, the temperature detector and the flow meter are all equipped with an RS485 communication module to send the real-time detection data to the PLC controller and display it on the display device.
[0035] See attached Figure 3 In one embodiment shown, a schematic diagram of the connection of the power central control units of multiple workshops 3 is shown. There are 3 workshops 3 and 8 distribution rooms in total. A transformer is provided in each distribution room. An oil temperature gauge is provided in each transformer. A temperature sensor for detecting the real-time maximum temperature is provided at the aluminum or copper bar of each transformer. Each oil temperature gauge and temperature sensor are connected by a data line. An argon pressure gauge flow meter is provided in the high-pressure room for real-time monitoring of the pressure value of argon gas, and a flow meter is provided at the gas storage tank; a liquid level meter is provided at the circulation pool and sewage pool, and a water pressure meter is provided at the air compressor room. A camera is provided in each distribution room, and the camera is connected to the display device in the central control room through a video monitoring line.
[0036] In this embodiment, a single power transformer is used as a unit, and the main operating parameters of multiple power transformers are monitored and managed together through the modbus communication protocol. A capacitive pressure measuring instrument with RS485 communication function is configured for tap water and fire water to monitor the tap water and fire water, so as to avoid sudden water outages in municipal pipelines, which may cause the interruption of cooling water supply of high-temperature sintering furnace, but the situation that manual monitoring is not possible. In this embodiment, a flow meter is configured for each of the compressed air, nitrogen main valve, and argon main valve to realize real-time flow monitoring of specific process gas filled into the high-temperature sintering furnace, so as to ensure the safe operation of the high-temperature sintering furnace. The power central control unit of this embodiment has an alarm function, which can monitor the operation of the distribution room and transformer through a camera. The display device in the central control room can display the oil temperature status, real-time current, voltage, power and other information of all power transformers. In addition to displaying the emergency alarm on the screen, the system itself will sound a reminder; it can realize real-time centralized monitoring of the layout of power transformers and water tanks and industrial gas supply equipment dispersed in the plant, accurately understand the real-time operation of the transformers and industrial gas supply equipment in each workshop 3, timely eliminate adverse faults, and reduce potential risks.
[0037] The above is only an embodiment and does not limit the present invention in any way. Any person skilled in the art can make many possible changes, modifications or modifications to the present invention without departing from the scope of the present invention by using the above disclosed technical contents. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the present invention should fall within the scope of protection of the present invention.
Claims
1. A central control system for a high-temperature sintering furnace plant, characterized in that: It comprises a central control module (1) and a plurality of workshop control modules (2); the workshop control module (2) comprises a monitoring switch (21) and a sintering furnace switch (22); The monitoring switch (21) is electrically connected to the central control module (1), and the monitoring switch (21) is connected to a plurality of cameras (23), and the plurality of cameras (23) can photograph all high-temperature sintering furnaces (4) in a designated workshop (3); The sintering furnace switch (22) is interactively connected to the central control module (1), and the sintering furnace switch (22) is connected to the control system and monitoring system of all high-temperature sintering furnaces (4) in the designated workshop (3), so as to enable the central control module (1) to obtain and control the working status of all the high-temperature sintering furnaces (4).
2. The central control system of the high temperature sintering furnace plant as claimed in claim 1, characterized in that: The monitoring system includes a furnace temperature monitoring unit, a liquid level monitoring unit, a water temperature monitoring sensor, a furnace pressure monitoring sensor, a current monitoring sensor, a voltage monitoring sensor and an atmosphere monitoring sensor.
3. The central control system of the high temperature sintering furnace plant as claimed in claim 2, characterized in that: The central control module (1) comprises a PLC controller, an input device and a display device, and the PLC controller, the input device and the display device are electrically connected.
4. The central control system of the high temperature sintering furnace plant as claimed in claim 3, characterized in that: The central control module (1) also includes an audible and visual alarm unit. When an abnormality occurs in a value monitored by any sensor in the monitoring system, the abnormal data is displayed in the display device and the audible and visual alarm unit sounds an alarm.
5. The central control system of the high temperature sintering furnace plant as claimed in claim 4, characterized in that: The central control module (1) further comprises a master voice device, and the workshop central control module (2) further comprises a slave voice device connected to the master voice device, wherein the master voice device can have a voice conversation with the slave voice device.
6. The central control system of the high temperature sintering furnace plant as claimed in claim 1, characterized in that: The workshop central control module (2) also includes a power central control unit; The power central control unit is used to monitor and control the cooling system, power system and industrial gas supply system of the high-temperature sintering furnace. The cooling system includes a liquid level meter arranged in the cooling clear water tank and the circulating water tank of the high-temperature sintering furnace, and a water pressure meter arranged at the tap water pipe and the fire water pipe. The power system includes a temperature sensor arranged at the transformer to read the real-time maximum temperature of the aluminum busbar or the copper busbar, an oil temperature gauge arranged in the transformer to read the oil temperature parameters, and a temperature detector arranged in the low-voltage distribution room. The industrial gas supply system includes flow meters arranged at the compressed air main valve, the nitrogen main valve and the argon main valve.
7. The central control system of the high temperature sintering furnace plant as claimed in claim 6, characterized in that: The temperature sensor, the oil temperature gauge, the temperature detector and the flow meter are all provided with RS485 communication modules.
8. The central control system of a high temperature sintering furnace plant according to any one of claims 1 to 7, characterized in that: The central control module (1) and the workshop control module (2) are connected via an optical fiber (5).