Equipment for cleaning pipeline in upper module of FPSO (floating production storage and offloading)

By introducing pre-cleaning, purging, and circulating cleaning units into the FPSO upper module pipeline, combined with degreasing agents and temperature control, the degreasing problem caused by the complex pipeline structure was solved, achieving efficient and low-cost cleaning results and ensuring the safety and compliance of the FPSO system.

CN221983401UActive Publication Date: 2024-11-12中化蓝星清洗科技(北京)有限公司
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420052215.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-09
Publication Date
2024-11-12
Estimated Expiration
2034-01-09

AI Technical Summary

Technical Problem

Due to the characteristics of the FPSO top module pipeline, such as variable pipe diameter, numerous interfaces, multiple diameter changes, many bends, and complex paths, it is difficult to completely degrease the pipeline, which takes a long time and affects the normal commissioning of the FPSO system.

Method used

A device for cleaning pipelines in the upper module of an FPSO is provided, including a pre-cleaning unit, a purging unit, a circulating cleaning unit, and a detection unit. Through components such as ultrasonic cleaning, a drying filter, a circulation tank, and filter elements, a circulation loop is established to achieve circulating cleaning and bidirectional flushing. Combined with degreasing agents and temperature control, the cleaning effect is ensured.

Benefits of technology

It significantly improved cleaning efficiency, shortened the construction period, reduced costs, ensured the cleanliness and safety of pipelines, and met environmental regulations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221983401U_ABST
    Figure CN221983401U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of FPSO (floating production storage and offloading) cleaning, and discloses a device for cleaning a pipeline in an FPSO upper module, which comprises a pre-cleaning unit for pre-cleaning a temporary pipeline; the purging unit is used for purging the pre-cleaned temporary pipeline; the circulating cleaning unit comprises a circulating tank, the circulating tank is communicated with two end ports of a to-be-cleaned pipeline in the FPSO upper module through the temporary pipeline to form a circulating loop, and the circulating loop is provided with a degreasing agent feeding port and a circulating pump; and the detection unit is used for detecting the pH of the liquid in the circulation loop. The cleaning device can improve the cleaning efficiency and reduce the cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of FPSO cleaning, in particular to a device for cleaning pipelines in an upper module of a FPSO. Background Art

[0002] Floating Production Storage and Offloading (FPSO) is a comprehensive facility in the oil and gas industry used to process, store and unload subsea oil and gas in offshore areas. It integrates oil and gas processing, storage and transmission, power generation, sewage treatment and other functions. It is used to produce, store and transfer oil and gas from subsea oil wells to onshore facilities.

[0003] The pipeline system of the FPSO upper module is a key component in the offshore oil and gas collection and production process. It requires precise and complex design, installation and maintenance to ensure the safe and efficient operation of the entire platform. The pipeline interface between the FPSO upper module and the hull mainly includes: oil and gas transmission, heat medium circulation, sewage, fire protection, public gas, instrument gas, chlorine, inert gas, seawater system, flare system, etc. In order to meet the needs of modular construction, they are arranged in the module as much as possible and hoisted together with the module. Therefore, in addition to the stress, temperature, hull movement and deformation required by the pipeline itself, the module pipeline also has the characteristics of variable pipe diameter, multiple interfaces, multiple diameter changes, multiple elbows, and complex pipeline paths in order to meet the requirements of compact spatial arrangement. Due to its particularity, the FPSO upper module pipeline is difficult to completely degrease before delivery, and it usually takes a long time. The degreasing period and efficiency have a very important direct impact on whether the FPSO system can be put into use normally. In order to make the degreasing effect meet the delivery requirements within the specified time, the cleaning process must be scientifically and globally controlled.

[0004] The purpose of degreasing before the upper module is to ensure the safety of the equipment and pipelines, and to prepare for the receipt of the products, paving the way for commissioning. Due to the long cycle, the FPSO upper module pipeline will inevitably produce pollutants such as oil, welding slag, floating dust, silt and floating rust during the manufacturing, transportation, storage and installation process. The presence of these pollutants, especially oil, will cause safety hazards and equipment damage during the use of the device after startup. In severe cases, explosions will occur, causing great losses to personnel and equipment. Through the degreasing operation before the upper module is delivered, oil and impurities can be effectively removed, creating good conditions for the normal operation of equipment and pipelines after delivery.

[0005] The importance of pipeline degreasing before delivery of FPSO topside modules can be summarized as follows:

[0006] 1. Improve FPSO production efficiency. Grease and other impurities deposited inside the pipeline will have an adverse effect on the operation of FPSO production equipment, causing fluid resistance and energy loss, thereby reducing production efficiency. Pipeline degreasing before the delivery of the upper module can remove these impurities, keep the pipeline unobstructed and clean, and help improve the production efficiency of FPSO.

[0007] 2. Extend equipment life: Pipeline degreasing can extend the service life of FPSO upper module equipment.

[0008] Impurities deposited inside the pipeline will have an adverse effect on the life of the FPSO upper module equipment, shorten the service life of the equipment, and increase the cost of equipment maintenance and replacement. Pre-delivery degreasing can remove these impurities, protect the equipment, extend the service life of the equipment, and reduce the operating cost of the FPSO.

[0009] 3. Compliance: FPSO is subject to strict environmental regulations, requiring operators to maintain high standards of cleanliness and safety. Degreasing the topside module before delivery can remove pollutants that may harm the environment and ensure that the new FPSO complies with environmental regulations.

[0010] 4. Enhanced safety: Contaminants and impurities in the pipelines of the upper modules of FPSO may cause blockage and leakage of the pipelines, which may easily lead to safety accidents such as fire and explosion, posing a huge threat to personnel and equipment. Degreasing can remove these impurities and reduce the risk of safety accidents.

[0011] Ensure safety.

[0012] In conclusion, degreasing FPSO pipelines before delivery is an important operation to maintain the efficiency, safety and compliance of FPSOs in the offshore oil and gas industry. Utility Model Content

[0013] The purpose of the utility model is to overcome the problem in the prior art that the pipelines of the upper modules of FPSO have the characteristics of variable pipe diameters, multiple interfaces, multiple diameter changes, multiple elbows, and complex pipeline paths, which makes it difficult to completely degrease the pipelines of the upper modules of FPSO and usually takes a long time. The utility model provides a device for cleaning the pipelines in the upper modules of FPSO, which can improve the cleaning efficiency and reduce the cost.

[0014] In order to achieve the above-mentioned object, the utility model provides a device for cleaning pipelines in an upper module of an FPSO, wherein the device for cleaning pipelines in an upper module of an FPSO comprises:

[0015] Pre-cleaning unit, used for pre-cleaning temporary pipelines;

[0016] A purge unit, used for purging the temporary pipeline after pre-cleaning;

[0017] The circulation cleaning unit comprises a circulation tank, which is connected to the two end ports of the pipeline to be cleaned in the upper module of the FPSO through the temporary pipeline to form a circulation loop, and a degreasing agent feeding port is opened on the circulation loop and a circulation pump is installed;

[0018] The detection unit is used to detect the pH of the liquid in the circulation loop.

[0019] In some embodiments, the pre-cleaning unit includes an ultrasonic cleaning device.

[0020] In some embodiments, the purge unit includes an air compressor and a dry filter that are connected to each other. The dry filter is connected to a purge pipeline, and the purge pipeline is detachably connected to a pipeline in the upper module of the FPSO.

[0021] In some embodiments, the temporary pipeline includes a hose on which a valve, a connector and the circulation pump are installed.

[0022] In some embodiments, the circulation cleaning unit includes a filter element and a heating device installed on the circulation loop.

[0023] In some embodiments, the filtering accuracy of the filter element is 20-30 meshes, and the filter element is installed on a hose of a temporary pipeline and is located between a circulation pump and a circulation tank.

[0024] In some embodiments, the circulation tank is provided with a cleaning liquid inlet and a degreasing agent feeding port; the heating device comprises a heat exchange coil, and the heat exchange coil is installed in the circulation tank to heat the liquid in the circulation tank.

[0025] In some embodiments, the bottom surface of the circulation tank is configured as an inclined surface, a sediment discharge pipeline is provided at the bottom of the circulation tank, and a sediment discharge pump is installed on the sediment discharge pipeline.

[0026] In some embodiments, a return liquid bypass pipeline is short-circuited on each of the temporary pipelines, one end of which is installed on a hose between the circulation pump and the upper module of the FPSO, and the other end is installed on a hose between the filter element and the circulation tank.

[0027] In some embodiments, the detection unit includes a sample placement portion and a detection portion, the sample placement portion includes a test tube and a test tube rack, and the detection portion includes a pH meter.

[0028] In some embodiments, the equipment for cleaning the pipeline in the upper module of the FPSO includes a post-processing unit, the post-processing unit is provided with a neutralization buffer tank, and the neutralization buffer tank is connected to the temporary pipeline through a post-processing pipeline equipped with a delivery pump.

[0029] Through the above technical solution, the utility model has the following advantages:

[0030] 1. Reduce the risk of new impurities being introduced into temporary piping by pre-cleaning units.

[0031] 2. Establishing a circulation loop among the circulation tank, temporary pipeline and pipeline to be cleaned in the upper module of FPSO can realize circulation cleaning and two-way flushing to reduce gas resistance and the effects of incomplete cleaning and low cleaning efficiency caused by many pipeline fluctuations, branches and diameter changes.

[0032] 3. By setting the filter element and the inclined bottom surface of the circulation tank, it is prevented that the cleaned impurities return to the system with the circulation. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a schematic diagram for explaining a device for cleaning pipelines in an upper module of a FPSO according to a specific embodiment of the utility model;

[0034] Figure 2 It is a schematic diagram of sample arrangement for sampling test of the utility model.

[0035] Reference numerals

[0036] 1FPSO upper module; 2temporary pipeline; 4circulation tank; 5neutralization buffer tank; 6heat exchange coil; 21return liquid bypass pipeline; 22first circulation pump; 23filter element; 24second circulation pump; 41cleaning liquid inlet; 42sludge discharge pipeline; 43degreasing agent pipeline; 421slag discharge pump; 431dosing pump; 432degreasing agent storage tank; 51post-processing pipeline; 511transport pump; 512sewage pump. DETAILED DESCRIPTION

[0037] The specific implementation of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the present invention, and is not used to limit the present invention.

[0038] The endpoints and any values ​​of the ranges disclosed in this article are not limited to the precise ranges or values, and these ranges or values ​​should be understood to include values ​​close to these ranges or values. For numerical ranges, the endpoint values ​​of each range, the endpoint values ​​of each range and the individual point values, and the individual point values ​​can be combined with each other to obtain one or more new numerical ranges, which should be regarded as specifically disclosed in this article. In the utility model, the pipeline to be cleaned, the pipeline in the upper module of the FPSO, and the pipeline to be cleaned in the upper module of the FPSO refer to the same pipeline.

[0039] The utility model discloses a device for cleaning pipelines in an upper module of an FPSO. The device for cleaning pipelines in an upper module of an FPSO comprises:

[0040] A pre-cleaning unit, used for pre-cleaning the temporary pipeline 2;

[0041] A purge unit, used for purging the temporary pipeline 2 after pre-cleaning;

[0042] The circulation cleaning unit includes a circulation tank 4, which is connected to the two end ports of the pipeline to be cleaned in the FPSO upper module 1 through a temporary pipeline 2 to form a circulation loop, and a degreasing agent feeding port is opened on the circulation loop and a circulation pump is installed;

[0043] The detection unit is used to detect the pH of the liquid in the circulation loop.

[0044] In the utility model, the temporary pipeline 2 comprises a hose, on which a valve, a joint and a circulation pump are installed.

[0045] It should be noted that the temporary pipeline includes a hose and a valve and a joint (such as a joint for connecting to a purge gas pipeline, etc.) arranged on the hose. In order to remove dust particles attached to the temporary pipeline during production and transportation and prevent the temporary connection from affecting the cleaning effect, the temporary pipeline is pre-cleaned before being connected to the pipeline to be cleaned. In the present utility model, the pre-cleaning unit includes an ultrasonic cleaning device. The present utility model has no special requirements for the ultrasonic cleaning device. Conventional ultrasonic cleaning machines with a power of more than 30KHz in the prior art can be used for the present utility model.

[0046] In order to obtain dry and dust-free compressed gas, in the utility model, the purge unit includes an air compressor and a dry filter connected to each other, the dry filter is connected to a purge pipeline, and the purge pipeline is detachably connected to the pipeline in the FPSO upper module 1 to purge the pipeline in the FPSO upper module 1 as needed.

[0047] In the utility model, the circulation cleaning unit comprises a filter element 23 and a heating device installed on the circulation loop.

[0048] In the present invention, the filtering accuracy of the filter element 23 is 20-30 meshes. The filter element 23 is installed on the hose of the temporary pipeline 2 and is located between the circulation pump and the circulation tank 4. The present invention has no special requirements for the filter element, as long as the filtering accuracy can be met. For example, a 20-30 mesh filter can be used in the present invention.

[0049] In the utility model, the circulation tank 4 is provided with a cleaning liquid inlet 41 and a degreasing agent feeding port; the heating device includes a heat exchange coil 6 connected to the heat exchanger, and the heat exchange coil 6 is installed in the circulation tank 4 to control the liquid temperature in the circulation tank 4, thereby improving the grease removal effect in the pipeline to be cleaned.

[0050] like Figure 1As shown, the cleaning circulation tank 4 is connected to the pipeline to be cleaned in the upper module 1 of the FPSO through two temporary pipelines. A circulation pump is installed on each temporary pipeline 2. For the convenience of description, the circulation pumps on the two temporary pipelines are named the first circulation pump 22 and the second circulation pump 24 respectively. To prevent the backflow of solid impurities, in the utility model, the bottom surface of the circulation tank 4 is set as an inclined surface, and a sediment discharge pipeline 42 is provided at the bottom of the circulation tank 4. A sediment discharge pump 421 is installed on the sediment discharge pipeline 42. In this way, the residue flushed down from the pipeline is separated and simply collected. If the amount of sediment generated during the cleaning process is not large, there is no need to discharge the sediment. If the amount of sediment is large, the sediment discharge pump 421 can be turned on to discharge the sediment. Figure 1 As shown, the degreasing agent inlet on the circulation tank 4 is connected to the degreasing agent storage tank 432 through a degreasing agent pipeline 43 installed with a dosing pump 431, so as to control the feeding of the degreasing agent.

[0051] In the utility model, a return liquid bypass pipeline 21 is short-circuited on each temporary pipeline 2, one end of the return liquid bypass pipeline 21 is installed on a hose between the circulation pump and the FPSO upper module 1, and the other end is installed on a hose between the filter element 23 and the circulation tank 4. It can be understood that a control valve and a 20-30 mesh filter element are respectively installed on each temporary pipeline 2 and the return liquid bypass pipeline 21.

[0052] In the utility model, the detection unit comprises a sample placement part and a detection part, the sampling placement part comprises a test tube and a test tube rack, and the detection part comprises a pH meter or a titration tool in the prior art.

[0053] In the utility model, the equipment for cleaning the pipeline in the upper module 1 of the FPSO includes a post-processing unit, which is provided with a neutralization buffer tank 5, which is connected to the temporary pipeline 2 through a post-processing pipeline 51 equipped with a delivery pump 511, and the neutralization buffer tank 5 is connected to a sewage pipeline equipped with a sewage pump 512. For example, when the degreasing is qualified, the heating of the degreasing liquid is stopped, and when the temperature drops to 50°C, the circulation is stopped, the shower is opened, and the degreasing liquid in the circulation loop is discharged. In order to achieve environmental protection, the degreasing liquid is collected in the neutralization buffer tank 5 during discharge, and is discharged through the sewage pipeline after environmental protection treatment.

[0054] In the utility model, a drain valve and an exhaust port are provided on the circulation loop to discharge the air stored inside the cleaning pipeline before water delivery or the air that enters with the water due to improper water inlet operation. To facilitate the discharge of water and air, the drain valve is located at the lowest point of the pipeline to be cleaned in the upper module 1 of the FPSO, and the exhaust port is usually located at the highest point of the liquid inlet end.

[0055] The utility model discloses a method for cleaning pipelines in an upper module of an FPSO, the method comprising the following steps:

[0056] 1) After pre-cleaning the temporary pipeline, connect the temporary pipeline and the pipeline to be cleaned;

[0057] 2) Introduce purge gas to purge the pipeline to be cleaned;

[0058] 3) During cleaning, the cleaning liquid is introduced into the pipeline to be cleaned, and a circulation loop is formed by connecting the temporary pipeline, the pipeline to be cleaned and the circulation tank, so that the cleaning liquid can circulate and flush the pipeline to be cleaned;

[0059] 4) Add degreasing agent into the circulation loop, circulate with the cleaning liquid, mix the degreasing agent with the cleaning liquid to form a degreasing liquid, and make the degreasing liquid form turbulence in the pipeline to be cleaned;

[0060] 5) Switch the flow direction of the degreasing liquid in the circulation loop;

[0061] 6) After degreasing is qualified, the degreasing liquid in the circulation loop is discharged;

[0062] 7) Feed cleaning liquid into the circulation loop. When pH <8 and total suspended solids <100ppm, end the flushing.

[0063] In the present invention, in step 1), pre-cleaning includes: using ultrasonic cleaning of temporary pipelines, and then drying. For example, immerse the hose, valves and joints in the cleaning chamber of an ultrasonic cleaning machine, use a power of more than 30KHz to clean for 5-20 minutes, remove small particles attached to the pipelines and valves, and then use dried and filtered compressed air to blow dry. The method provided by the present invention can control the degreasing process as a whole, effectively shorten the construction period required for acceptance, improve efficiency and reduce costs.

[0064] The qualified standard for pre-cleaning is: the inner surface of the temporary pipeline has no grease fluorescence under the black light. This indicates that there is no grease inside the pipeline before the piping connection is made.

[0065] In the present invention, in step 2), the purge gas is selected from air and / or an inert gas (such as nitrogen).

[0066] In the present invention, the purge gas in step 2) is compressed gas, and preferably the purge gas is dry and dust-free compressed gas.

[0067] In the utility model, a white cloth inspection is performed at the purge end of the pipeline to be cleaned, and the purge is considered to be completed when no rust stains or impurities are observed on the white cloth.

[0068] In the utility model, in step 2), the flushing circuit is flushed several times with dry and dust-free compressed air to blow the dust and debris remaining in the pipeline system out of the system.

[0069] In order to prevent impurities outside the system from flowing back into the pipeline, in the utility model, in step 3), the cleaning liquid is filtered through a 20-30 mesh filter element and then passed into the pipeline to be cleaned.

[0070] In the present invention, in order to improve the grease removal effect, in step 3), during cleaning, the temperature of the cleaning liquid is controlled to be 70° C.-90° C.

[0071] In the utility model, in step 3), the turbidity of the cleaning liquid is detected, and when the turbidity is stable, the circulation loop is connected, otherwise, the flushing water is discharged to the post-processing unit; specifically, for example, a cleaning liquid at 70°C-90°C is passed into the pipeline to be cleaned, and when flushing just starts, the flushing water obtained after flushing is discharged to the post-processing unit, and the turbidity of the flushing water quality is detected by sampling detection or online detection. When the turbidity of the clear flushing water quality is stable, the outlet water is connected to the circulation tank 4, and a circulation loop of the temporary pipeline 2, the pipeline to be cleaned and the circulation tank 4 is established. Steam can be passed into the heat exchange coil 6 to keep the flushing liquid at a constant temperature of 70°C-90°C. The cleaning liquid can be desalted water.

[0072] In the present invention, there is no special requirement for the source and composition of the degreasing agent, as long as the mass concentration of the degreasing agent in the degreasing liquid is controlled at 3-3.5%. The following is an exemplary description, but it does not limit the scope of the present invention. In the present invention, in step 4), the degreasing agent is selected from at least one of sodium carbonate, sodium phosphate, sodium metasilicate, nonionic surfactant, anionic surfactant, sodium gluconate, sodium dihydrogen phosphate or tetrasodium EDTA.

[0073] In the utility model, a degreasing agent is added to the circulation loop to control the turbulence with a Reynolds number Re of ≥4000 in the pipeline to be cleaned. Preferably, the cleaning flow rate V is adjusted by the first circulation pump 22 and the second circulation pump 24 to control the Reynolds number of the turbulence, wherein V=Re·μ / ρd, wherein μ is the dynamic viscosity of the cleaning liquid, ρ is the density of the cleaning liquid, and d is the minimum nominal diameter of the pipeline to be cleaned. The Reynolds number Re in the cleaning branch can be adjusted to be greater than 4000 by selecting the circulation pump and adjusting the speed, so that the cleaning liquid can flush each pipeline in a turbulent state to ensure the cleaning effect.

[0074] In order to improve the problem of air blocking caused by multiple internal pipeline interfaces, multiple diameter changes, and multiple elbows affecting the cleaning effect, in the utility model, in step 5), when the alkalinity and turbidity of the degreasing liquid in the circulation loop are basically balanced, the flow direction of the degreasing liquid is switched. Specifically, for example, the first circulation pump 22 is originally used to drive the degreasing liquid in the circulation loop. When the alkalinity and turbidity of the degreasing liquid in the circulation loop are basically balanced, the flow direction of the degreasing liquid is switched by switching to the second circulation pump 24.

[0075] It should be noted that in the present utility model, Figure 2As shown, at the beginning of the cycle, a sample is taken at the return liquid end every half an hour, the sample is placed in a test tube and arranged in a row on the test tube rack in chronological order, and the turbidity change is observed by the light scattering method or colorimetry method in the prior art. When the turbidity change of three consecutive samples cannot be detected, the sample alkalinity is tested with a pH meter or titration method. Within 1 hour, when the values ​​of two consecutive sampling tests are basically unchanged (the absolute difference is less than 0.2%), it is considered that the alkalinity and turbidity of the degreasing liquid in the circulation loop are basically balanced.

[0076] Since the pipelines in the upper module 1 of the FPSO have the characteristics of variable diameters, multiple interfaces, multiple diameter changes, multiple elbows, and complex pipeline paths, in order to improve the cleaning effect, after each cycle starts, the shower valve and exhaust port on the circulation loop are opened every 5 minutes.

[0077] In the present invention, in step 6), the qualified standard for degreasing is: 4-8 hours after the two-way circulation cleaning, the absolute difference of the alkalinity detected by two consecutive samplings within 1 hour is less than 0.2%.

[0078] In the utility model, in step 7), the cleaning liquid is fed into the circulation loop through the circulation tank 4, the cleaning liquid is controlled to be 55-60°C, and discharged after circulating for 1 hour. The pH value is sampled and tested. When the pH>8, the above cycle is repeated; when the pH<8 and the total suspended solids<100ppm, the flushing is ended.

[0079] In the utility model, the method also includes: 8) drying the pipeline in the upper module of the FPSO, preferably blowing and drying with oil-free compressed air with a dew point below -30°C, using the detection method disclosed in the ISO8573 standard to detect the dew point below -30 degrees Celsius, the oil content below 0.5ppm, and the cleanliness ISO Class 5 or above standard for dry oil-free and dust-free compressed air.

[0080] The advantages of the present invention are described below by way of embodiments, but the present invention is not limited thereto.

[0081] Example

[0082] Pipeline degreasing and cleaning of the acid gas removal (AGRU) system of a FPSO topside module, including:

[0083] Immerse the hoses, joints and valves of the temporary pipeline into the cleaning chamber of the ultrasonic cleaning machine and clean them at 50KHz for 15 minutes. After the cleanliness reaches the standard, press Figure 1 As shown, the FPSO upper module acid gas removal (AGRU) system pipeline, the temporary pipeline 2 and the circulation tank 4 are connected, and a 20-mesh filter is installed on the temporary pipeline 2.

[0084] After the purge unit is turned on and the accumulated water in the system is drained by using dry air, desalted water is introduced into the system. When flushing begins, the delivery pump 511 is started to discharge the flushing water into the neutralization buffer tank 5. When the turbidity of the flushing water does not change, the delivery pump 511 is turned off and started, and the temporary pipeline 2, the pipeline to be cleaned and the circulation tank 4 are connected to form a circulation loop. The circulation pump is started as a drive, and the circulation is circulated and maintained at a constant temperature of 80°C through the heating device.

[0085] The degreasing agent is gradually added to the circulation loop by the dosing pump 431, so that the degreasing agent and the cleaning liquid are mixed to form a degreasing liquid, and a turbulent flow of ≥4000 is controlled to be formed in the pipeline to be cleaned; the flow direction of the degreasing liquid in the circulation loop is switched every one hour of flushing;

[0086] During the flushing cycle, open the shower valve and exhaust port on the flushing circuit every 5 minutes.

[0087] After the degreasing is qualified, stop heating the degreasing liquid. When the temperature drops to 50°C, stop the circulation, open the drain, and discharge the degreasing liquid in the circulation loop to the neutralization buffer tank 5.

[0088] After the degreasing liquid is drained, the cleaning liquid (desalted water) is fed into the circulation loop. The cleaning liquid is controlled at 60°C. After circulating for 1 hour, the desalted water in the system is drained, replaced with fresh desalted water and the direction is changed for flushing. When the pH value of the inlet and outlet water is less than 8, the suspended solids are <100ppm, and the turbidity (visual colorimetry) difference is small, the water flushing is terminated.

[0089] During the cleaning process, the sedimentation at the bottom of the circulation tank 4 is checked. When a large amount of sediment is found, the slag discharge pump 421 is turned on to discharge the slag.

[0090] After cleaning is complete, perform a detailed inspection of the cleaned system.

[0091] After acceptance, the FPSO upper module acid gas removal (AGRU) system pipelines are blown dry.

[0092] Results: The construction period required for acceptance is 30% shorter than the cleaning construction period of the comparative example not using the equipment of the utility model. The construction period required for acceptance refers to the period from the arrival of the equipment at the project site to the passing of the pipeline cleaning acceptance.

[0093] Degreasing quality requirements

[0094] 1. The cleaned inner surface has no grease fluorescence under the irradiation of black light (ultraviolet light with a wavelength of 320-380nm).

[0095] 2. The oil content of the cleaning fluid sampled for testing shall not exceed 350 mg / L.

[0096] Quality control and sampling are carried out according to the following table:

[0097]

[0098]

[0099] Degreasing process:

[0100] Test items Sampling frequency Alkalinity 1 time / 30 minutes Turbidity 1 time / 30 minutes temperature 1 time / 30 minutes

[0101] Water flushing process:

[0102] Test items Sampling frequency Turbidity 1 time / 30 minutes pH 1 time / 30 minutes Suspended solids 1 time / 30 minutes temperature 1 time / 30 minutes

[0103] Comparative Example

[0104] The traditional cleaning method cleans the same AGRU system, using a single pump plus a cleaning tank connection system without switching the direction of the cleaning liquid for circulation cleaning, and the pipeline is not pre-cleaned, the cleaning tank does not discharge sediment, and does not pay attention to process control and turbidity alkalinity status. It usually takes two months from the arrival of the equipment at the cleaning site to the completion of the cleaning work acceptance (acceptance requirements are the same as in Example 1). Using the method described in the utility model can save up to 30% of the cleaning time.

[0105] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited thereto. Within the technical concept of the present invention, the technical solution of the present invention can be subjected to a variety of simple modifications, including the combination of various specific technical features in any appropriate manner. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations. However, these simple modifications and combinations should also be regarded as the contents disclosed by the present invention and belong to the protection scope of the present invention.

Claims

1. A device for cleaning pipelines in an upper module of an FPSO, characterized in that: The equipment for cleaning pipelines in the upper module of FPSO comprises: A pre-cleaning unit, used for pre-cleaning a temporary pipeline (2); A purge unit, used for purging the temporary pipeline (2) after pre-cleaning; The circulation cleaning unit comprises a circulation tank (4), wherein the circulation tank (4) is connected to two end ports of the pipeline to be cleaned in the upper module (1) of the FPSO through the temporary pipeline (2) to form a circulation loop, and a degreasing agent feeding port is provided on the circulation loop and a circulation pump is installed; The detection unit is used to detect the pH of the liquid in the circulation loop.

2. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The purge unit comprises an air compressor and a dry filter which are connected to each other. The dry filter is connected to a purge pipeline, and the purge pipeline is detachably connected to a pipeline in the FPSO upper module (1).

3. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The temporary pipeline (2) comprises a hose, on which a valve, a joint and the circulation pump are installed.

4. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The circulation cleaning unit comprises a filter element (23) and a heating device installed on the circulation loop.

5. The equipment for cleaning pipelines in the upper module of FPSO according to claim 4, characterized in that: The filtering accuracy of the filter element (23) is 20-30 meshes. The filter element (23) is installed on the hose of the temporary pipeline (2) and is located between the circulation pump and the circulation tank (4).

6. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The circulation tank (4) is provided with a cleaning liquid inlet (41) and a degreasing agent feeding port; the heating device comprises a heat exchange coil (6), and the heat exchange coil (6) is installed in the circulation tank (4) to heat the liquid in the circulation tank (4).

7. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The bottom surface of the circulation tank (4) is arranged as an inclined surface. A sludge discharge pipeline (42) is arranged at the bottom of the circulation tank (4). A sludge discharge pump (421) is installed on the sludge discharge pipeline (42).

8. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: A liquid return bypass pipeline (21) is short-circuited on each of the temporary pipelines (2), one end of the liquid return bypass pipeline (21) is installed on a hose between the circulation pump and the FPSO upper module (1), and the other end is installed on a hose between the filter element (23) and the circulation tank (4).

9. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The detection unit comprises a sample placement portion and a detection portion, wherein the sample placement portion comprises a test tube and a test tube rack, and the detection portion comprises a pH meter.

10. The equipment for cleaning pipelines in the upper module of FPSO according to claim 1, characterized in that: The equipment for cleaning the pipeline in the upper module (1) of the FPSO comprises a post-processing unit, wherein the post-processing unit is provided with a neutralization buffer tank (5), and the neutralization buffer tank (5) is connected to the temporary pipeline (2) via a post-processing pipeline (51) equipped with a delivery pump (511).