Rail installation structure of rail inspection robot

By using a combination of ground piles, guide rails and pull ropes in the installation structure of the track patrol robot, the problem of deformation and instability of the track patrol robot after long-distance installation in outdoors is solved, and the flatness of the track and reliable walking are achieved adapts to the installation needs of the external environment.

CN221985144UActive Publication Date: 2024-11-12NANJING ANXUN INTELLIGENT TECH CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420262720.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-03
Publication Date
2024-11-12
Estimated Expiration
2034-02-03

AI Technical Summary

Technical Problem

Existing track patrol robots are prone to deformation and instability after installation of long-distance outdoor tracks, resulting in unstable walking.

Method used

Using a structure including a floor pile mounting frame, guide rail, track connection and draw rope, the vertical tension and installation hole of the beam are provided through the floor pile to connect the draw rope, ensuring the flatness and stability of the track, and through the reinforcement plate and The support frame increases the structural strength of the track.

Benefits of technology

Effectively prevent track deformation, improve the walking stability and installation reliability of track patrol robots, adapt to the installation needs of the external environment, and ensure the high reliability of track patrol robots when walking long distances.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221985144U_ABST
    Figure CN221985144U_ABST
Patent Text Reader

Abstract

The utility model discloses a track inspection robot mounting structure which comprises a first ground pile mounting frame, a second ground pile mounting frame, a first guide rail, a second guide rail, a third guide rail, a track connecting piece and a second track connecting piece, the first ground pile mounting frame is fixed on the ground, and the first ground pile mounting frame is fixedly provided with the first guide rail; the second ground pile mounting frame is fixed on the ground, and a second guide rail is fixedly arranged on the second ground pile mounting frame; the rail connecting piece connects the first guide rail and the third guide rail. The second rail connecting piece connects the third guide rail and the second guide rail. The first ground pile mounting frame is connected with the track connecting piece through a pull rope; and the second ground pile mounting frame is connected with the second track connecting piece through a pull rope. The guide rail connecting device is high in guide rail connecting flatness and good in reliability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tracks of a track inspection robot, in particular to a track installation structure of a track inspection robot. Background Art

[0002] Existing rail inspection robots generally work indoors and have a short working distance. In order to inspect outdoor pipelines, the inspection robot needs to work over a longer distance, and there is no suitable road around the pipeline for the inspection robot to walk on, so it is necessary to install a rail inspection robot. However, how to ensure that the rail inspection robot's track does not deform after being installed over a long distance, and the track is stable, so that the rail inspection robot can walk easily is a technical problem. Utility Model Content

[0003] The utility model aims to provide a track installation structure for a track inspection robot with stable track erection and high track flatness.

[0004] The technical solution proposed by the utility model is a track inspection robot installation structure, comprising a first ground pile installation frame, a second ground pile installation frame, a first guide rail, a second guide rail, a third guide rail, a track connecting piece, and a second track connecting piece; the first ground pile installation frame is fixed on the ground, and the first ground pile installation frame is fixedly provided with the first guide rail; the second ground pile installation frame is fixed on the ground, and the second ground pile installation frame is fixedly provided with the second guide rail; the track connecting piece connects the first guide rail and the third guide rail, and the second track connecting piece connects the third guide rail and the second guide rail; the first ground pile installation frame is connected to the track connecting piece by a pull rope, and the pull ropes are provided on both sides of the track connecting piece; the second ground pile installation frame is connected to the second track connecting piece by a pull rope, and the pull ropes are provided on both sides of the second track connecting piece.

[0005] Furthermore, the first ground pile mounting frame and the second ground pile mounting frame have the same structure, and the first ground pile mounting frame includes a spiral ground pile, which is fixed under the ground, a concrete fixing block, which is arranged above the spiral ground pile, and a T-shaped vertical frame, which is arranged above the concrete fixing block, and the T-shaped vertical frame is provided with a first support rod and a second support rod, a cross beam is arranged between the two support rods, and a connecting piece is provided on the cross beam, and the connecting piece is used to connect the first guide rail or the second guide rail.

[0006] Furthermore, the T-shaped vertical frame includes a horizontal frame and a vertical frame, the horizontal frame and the vertical frame are vertically arranged, the vertical frame is arranged above the concrete fixed block, one end of the first support rod is connected to one end of the horizontal frame, one end of the second support rod is connected to the other end of the horizontal frame, and the other end of the first support rod is connected to the other end of the second support rod.

[0007] Furthermore, first mounting holes are provided at both ends of the crossbeam, and the first mounting holes are used to install the pull rope, and one end of the first guide rail or the second guide rail is fixed below the crossbeam.

[0008] Furthermore, the track connector and the second track connector have the same structure, and the track connector includes:

[0009] A connecting piece on the track, wherein the connecting piece on the track is a support plate, and a second mounting hole is provided on the support plate;

[0010] The track lower connecting piece includes a left mounting plate and a right mounting plate, wherein the left mounting plate and the right mounting plate are arranged below the support plate, a mounting groove is formed between the left mounting plate and the right mounting plate, and the left mounting plate and the right mounting plate are both provided with through holes;

[0011] The other ends of the first guide rail and the second guide rail are both arranged in the mounting groove, and the upper surfaces of the two guide rails are provided with bolt holes, and the fasteners pass through the second mounting hole, the through hole, and the bolt hole in sequence.

[0012] Furthermore, a vertical mounting plate is provided, the vertical mounting plate is arranged perpendicular to the support plate, and a pull rope hole is provided on the vertical mounting plate. One end of the pull rope is connected to the vertical mounting plate, and the other end of the pull rope is connected to the first ground pile mounting frame. The support plate is a rectangular parallelepiped, and flanges are provided at the four corners of the rectangular parallelepiped, and rope holes are provided in the flanges, and the rope holes are used to connect the pull ropes. In order to ensure the flatness, one end of the pull rope is connected to the flange, and the other end of the pull rope is connected to the crossbeam. There are two pull ropes on the left and right sides of the crossbeam. On the left side, one of the pull ropes is connected to the flange at the left position of the support plate, and on the right side, the other pull rope is connected to the flange at the right position of the support plate.

[0013] Further, the first guide rail and the second guide rail have the same structure, and the first guide rail comprises: an upper crossbeam, which is a rectangular frame, and at least one vertical plate is arranged in the upper crossbeam;

[0014] The vertical beam is a rectangular frame, the vertical beam connects the upper cross beam and the lower cross beam, and a reinforcing plate is arranged inside the vertical beam.

[0015] Furthermore, the reinforcing plate is arranged perpendicular to the cross beam, a mounting block is arranged in the middle of the reinforcing plate, connecting plates are arranged at the four corners of the mounting block, the connecting plates are connected to the inner wall of the vertical beam, the mounting block is a rectangular parallelepiped, the cross-section of the mounting block is square, and a circular through hole is arranged in the middle of the mounting block.

[0016] Furthermore, the lower cross beam includes a base plate and a supporting protrusion, and a plurality of supporting protrusions form a track groove. A supporting frame is arranged in the track groove, and the supporting frame extends along the length direction of the track. One end of the supporting frame is connected to the base plate, and the other end of the supporting frame is connected to the supporting protrusion. The supporting frame is arc-shaped, and the bottom end of the arc-shaped supporting frame is connected to the base plate, and the arc end of the arc-shaped supporting frame is connected to the supporting protrusion. The upper cross beam, the vertical beam, and the lower cross beam are connected to form an I-shape, and the upper surface and the lower surface at the end of the upper cross beam are provided with third mounting holes, and the mounting holes are used for bolts to pass through.

[0017] Compared with the prior art, the beneficial effects of the technical solution of the utility model are:

[0018] By setting a vertical plate on the upper beam, a reinforcing plate in the vertical beam, and a support frame in the lower beam, the stability of the track inspection robot walking on the track can be improved, ensuring that the track inspection robot is installed on the track with balanced force and ensuring that the long-distance track is not deformed.

[0019] 2. The lower part of the ground pile mounting frame is equipped with concrete fixing blocks, spiral ground piles and T-shaped brackets, which improve the reliability of track support and pull the track up through the rope hole.

[0020] 3. Reliably connect the two tracks through the installation groove, and apply tension to the connecting piece through the installation hole on the upper connecting piece to ensure that the two tracks are aligned, thereby improving the flatness of the multi-track docking.

[0021] 4. A track connection structure is proposed, which is suitable for installing a track inspection robot in an external environment without causing deformation, and the track inspection robot has high walking reliability. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a three-dimensional diagram of the installation structure of the track inspection robot in the utility model;

[0023] Figure 2 It is a structural diagram of the first ground pile mounting frame in the utility model;

[0024] Figure 3 This is a cross-sectional view of the track on which the track inspection robot is installed in the utility model;

[0025] Figure 4 It is a structural diagram of the track connector in the utility model.

[0026] Description of reference numerals:

[0027] 10. First pile mounting frame; 11. Screw pile; 12. Concrete fixing block; 13. T-shaped vertical frame; 14. Horizontal frame; 15. Vertical frame; 16. First support rod; 17. Second support rod; 18. Horizontal beam; 19. Connector; 191. First mounting hole; 20. Second pile mounting frame;

[0028] 30. First guide rail; 31. Upper crossbeam; 32. Vertical plate; 33. Vertical beam; 34. Mounting block; 35. Reinforcement plate; 36. Mounting block; 37. Circular through hole; 38. Connecting plate; 39. Lower crossbeam; 391. Support protrusion; 392. Arc end; 393. Bottom end; 394. Third mounting hole; 295. Bottom plate; 296. Support protrusion; 40. Second guide rail; 41. Bolt hole; 42. Third guide rail; 50. Track connector; 51. Vertical mounting plate; 52. Rope hole; 501. Upper track connector; 53. Flange; 54. Rope threading hole; 55. Second mounting hole; 56. Lower track connector; 57. Left mounting plate; 58. Right mounting plate; 59. Through hole; 591. Mounting groove; 60. Second track connector. DETAILED DESCRIPTION

[0029] The drawings are only used for illustrative purposes and should not be construed as limitations on this patent. In order to better illustrate this embodiment, some parts of the drawings may be omitted, enlarged, or reduced, and do not represent the size of the actual product. For those skilled in the art, it is understandable that some well-known structures and their descriptions in the drawings may be omitted.

[0030] like Figure 1 As shown, a track inspection robot installation structure includes a first ground pile mounting frame 10, a second ground pile mounting frame 20, a first guide rail 30, a second guide rail 40, a third guide rail 42, a track connector 50, and a second track connector 50. The first guide rail 30, the second guide rail 40 or the third guide rail 42 is connected to the track inspection robot, the first ground pile mounting frame 10 is fixed on the ground, and the first ground pile mounting frame 10 is fixedly provided with the first guide rail 30; the second ground pile mounting frame 20 is fixed on the ground, and the second ground pile mounting frame 20 is fixedly provided with the second guide rail 40; the track connector 50 connects the first guide rail 30 and the third guide rail 42, and the second track connector 50 connects the third guide rail 42 and the second guide rail 40.

[0031] In order to prevent the deformation of the multi-track due to gravity, the ground pile mounting frame is used to provide vertical tension for the guide rail, and the first ground pile mounting frame 10 is connected to the track connector 50 through a pull rope; the second ground pile mounting frame 20 is connected to the second track connector 50 through a pull rope. Pull ropes are provided on both sides of the track connector 50, and pull ropes are provided on both sides of the second track connector 50.

[0032] like Figure 2 As shown, the first ground pile mounting frame 10 and the second ground pile mounting frame 20 have the same structure. The first ground pile mounting frame 10 includes a spiral ground pile 11, which is fixed under the ground, a concrete fixing block 12, which is arranged above the spiral ground pile 11, and a T-shaped vertical frame 13, which is arranged above the concrete fixing block 12.

[0033] The T-shaped vertical frame 13 is provided with a first support rod 16 and a second support rod 17 . A cross beam 18 is provided between the two support rods. A connecting member 19 is provided on the cross beam 18 . The connecting member 19 is used to connect the first guide rail 30 or the second guide rail 40 .

[0034] Furthermore, the T-shaped vertical frame 13 includes a horizontal frame 14 and a vertical frame 15, the horizontal frame 14 and the vertical frame 15 are vertically arranged, the vertical frame 15 is arranged above the concrete fixed block 12, one end of the first support rod 16 is connected to one end of the horizontal frame 14, one end of the second support rod 17 is connected to the other end of the horizontal frame 14, and the other end of the first support rod 16 is connected to the other end of the second support rod. The two support rods are connected to each other, which, on the one hand, ensures the structural stability of the T-shaped vertical frame 13, and on the other hand, provides a force application point for the guide rail when providing pulling force in the vertical direction.

[0035] In order to prevent the multiple guide rails from deviating in the horizontal direction and ensure the verticality of the guide rails, first mounting holes 191 are provided at both ends of the beam 18. The first mounting holes 191 are used to connect the pull rope. The two ends of the beam 18 are used to pull the two sides of the first guide rail 30 respectively to ensure the verticality of the guide rails. One end of the first guide rail 30 or the second guide rail 40 is fixed at the bottom of the beam 18.

[0036] Furthermore, the track connector 50 and the second track connector 50 have the same structure, and the track connector 50 includes:

[0037] The track connecting member 501 is a support plate, and a second mounting hole 55 is provided on the support plate;

[0038] The track lower connecting member 56 includes a left mounting plate 57 and a right mounting plate 58, wherein the left mounting plate 57 and the right mounting plate 58 are arranged below the support plate, a mounting groove 591 is formed between the left mounting plate 57 and the right mounting plate 58, and a through hole 59 is opened in the left mounting plate 57 and the right mounting plate 58;

[0039] The other ends of the first guide rail 30 and the second guide rail 40 are both arranged in the mounting groove 591. The upper surfaces of the two guide rails have bolt holes 41. The fasteners pass through the second mounting hole 55, the through hole 59, and the bolt hole 41 in sequence, thereby fixing the first guide rail 30 or the second guide rail 40 on the lower rail connecting member 56.

[0040] like Figure 4As shown, a vertical mounting plate 51 is provided, the vertical mounting plate 51 is arranged perpendicular to the supporting plate, and a pull rope hole 52 is provided on the vertical mounting plate 51. One end of the pull rope is connected to the vertical mounting plate 51, and the other end of the pull rope is connected to the first pile mounting frame 10. The supporting plate is a rectangular parallelepiped, and flanges 53 are provided at the four corners of the rectangular parallelepiped. A rope threading hole 54 is provided in the flange 53, and the rope threading hole 54 is used to connect the pull rope. In order to ensure the flatness, one end of the pull rope is connected to the flange 53, and the other end of the pull rope is connected to the cross beam 18. There are two pull ropes on the left and right sides of the cross beam 18. On the left side, one of the pull ropes is connected to the flange 53 at the left side of the supporting plate, and on the right side, the other pull rope is connected to the flange 53 at the right side of the supporting plate.

[0041] like Figure 3 As shown, the first guide rail 30 and the second guide rail 40 have the same structure. In order to ensure the structural strength of the first guide rail 30 and the second guide rail 40 and facilitate the installation of the track inspection robot, different strength reinforcement structures are used for the upper crossbeam 31, the vertical beam 33, and the lower crossbeam 39. Specifically, the first guide rail 30 includes: an upper crossbeam 31, which is a rectangular frame, and at least one vertical plate 32 is arranged in the upper crossbeam 31;

[0042] The vertical beam 33 is a rectangular frame, and the vertical beam 33 connects the upper cross beam 31 and the lower cross beam 39 . A reinforcing plate 35 is disposed inside the vertical beam 33 .

[0043] Furthermore, the reinforcing plate 35 is arranged perpendicular to the cross beam 18, and a mounting block 36 is arranged in the middle of the reinforcing plate 35. Connecting plates 38 are respectively arranged at the four corners of the mounting block 36. The connecting plates 38 are connected to the inner wall of the vertical beam 33. The mounting block 36 is a rectangular parallelepiped, and the cross-section of the mounting block 36 is square. A circular through hole 5937 is arranged in the middle of the mounting block 36.

[0044] Furthermore, the lower cross beam 39 includes a base plate 295 and support protrusions 296, and a plurality of support protrusions 296 form a track groove. A support frame is arranged in the track groove, and the support frame extends along the length direction of the track. One end of the support frame is connected to the base plate 295, and the other end of the support frame is connected to the support protrusions 296. The support frame is arc-shaped, and the bottom end 393 of the arc-shaped support frame is connected to the base plate 295, and the arc end 392 of the arc-shaped support frame is connected to the support protrusions 296. The upper cross beam 31, the vertical beam 33, and the lower cross beam 39 are connected to form an I-shape, and the upper surface and the lower surface at the end of the upper cross beam 31 are provided with third mounting holes 394, and the mounting holes are used for bolts to pass through.

[0045] The beneficial effect of the utility model is that by arranging the vertical plate 32 on the upper cross beam 31 and arranging the reinforcing plate 35 in the vertical beam 33, it is ensured that the track inspection robot is installed on the track and the force is balanced, and the long-distance track is ensured not to be deformed.

[0046] Obviously, the above embodiments of the utility model are only examples for clearly explaining the utility model, and are not intended to limit the implementation methods of the utility model. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made on the basis of the above description. It is not necessary and impossible to list all the implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the utility model should be included in the protection scope of the claims of the utility model.

Claims

1. A track installation structure for a track inspection robot, characterized in that: It includes a first ground pile mounting frame, a second ground pile mounting frame, a first guide rail, a second guide rail, a third guide rail, a track connecting piece, and a second track connecting piece. The first ground pile mounting frame is fixed on the ground, and the first ground pile mounting frame is fixedly provided with the first guide rail; The second ground pile mounting frame is fixed on the ground, and the second ground pile mounting frame is fixedly provided with a second guide rail; The track connector connects the first guide rail and the third guide rail, and the second track connector connects the third guide rail and the second guide rail; The first ground pile mounting frame is connected to the track connecting member through a pull rope, and pull ropes are provided on both sides of the track connecting member; The second ground pile mounting frame is connected to the second track connecting member via a pull rope, and pull ropes are provided on both sides of the second track connecting member.

2. The rail installation structure according to claim 1, characterized in that: The first ground pile mounting frame and the second ground pile mounting frame have the same structure. The first ground pile mounting frame includes a spiral ground pile, which is fixed under the ground, a concrete fixing block, which is arranged above the spiral ground pile, and a T-shaped vertical frame, which is arranged above the concrete fixing block. The T-shaped vertical frame is provided with a first support rod and a second support rod, a cross beam is arranged between the two support rods, and a connecting piece is provided on the cross beam, which is used to connect the first guide rail or the second guide rail.

3. The rail installation structure according to claim 2, characterized in that: The T-shaped vertical frame includes a horizontal frame and a vertical frame. The horizontal frame and the vertical frame are vertically arranged. The vertical frame is arranged above the concrete fixed block. One end of the first support rod is connected to one end of the horizontal frame, one end of the second support rod is connected to the other end of the horizontal frame, and the other end of the first support rod is connected to the other end of the second support rod.

4. The rail installation structure according to claim 3, characterized in that: Both ends of the crossbeam are provided with first mounting holes, and one end of the first guide rail or the second guide rail is fixed below the crossbeam.

5. The track installation structure according to claim 4, characterized in that: The track connector and the second track connector have the same structure, and the track connector includes: A connecting piece on the track, wherein the connecting piece on the track is a support plate, and a second mounting hole is provided on the support plate; The track lower connecting piece includes a left mounting plate and a right mounting plate, wherein the left mounting plate and the right mounting plate are arranged below the support plate, a mounting groove is formed between the left mounting plate and the right mounting plate, and the left mounting plate and the right mounting plate are both provided with through holes; The other ends of the first guide rail and the second guide rail are both arranged in the mounting groove, and the upper surfaces of the two guide rails are provided with bolt holes, and the fasteners pass through the second mounting hole, the through hole, and the bolt hole in sequence.

6. The rail installation structure according to claim 5, characterized in that: A vertical mounting plate is arranged perpendicular to the supporting plate, a rope hole is arranged on the vertical mounting plate, the supporting plate is a rectangular parallelepiped, flanges are arranged at the four corners of the rectangular parallelepiped, and rope holes are arranged in the flanges.

7. The rail installation structure according to claim 6, characterized in that: The first guide rail and the second guide rail have the same structure, and the first guide rail comprises: an upper crossbeam, which is a rectangular frame, and at least one vertical plate is arranged in the upper crossbeam; The vertical beam is a rectangular frame, the vertical beam connects the upper cross beam and the lower cross beam, and a reinforcing plate is arranged inside the vertical beam.

8. The rail installation structure according to claim 7, characterized in that: The reinforcing plate is arranged perpendicular to the cross beam, a mounting block is arranged in the middle of the reinforcing plate, connecting plates are arranged at the four corners of the mounting block, the connecting plates are connected to the inner wall of the vertical beam, the mounting block is a rectangular parallelepiped, the cross section of the mounting block is square, and a circular through hole is arranged in the middle of the mounting block.

9. The rail installation structure according to claim 8, characterized in that: The lower cross beam includes a base plate and support protrusions, and a plurality of support protrusions form a track groove. A support frame is arranged in the track groove, and the support frame extends along the length direction of the track. One end of the support frame is connected to the base plate, and the other end of the support frame is connected to the support protrusion. The support frame is arc-shaped, and the bottom end of the arc-shaped support frame is connected to the base plate, and the arc end of the arc-shaped support frame is connected to the support protrusion. The upper cross beam, the vertical beam, and the lower cross beam are connected to form an I-shape, and the upper surface and the lower surface at the end of the upper cross beam are provided with a third mounting hole, and the third mounting hole is used for bolts to pass through.

Citation Information

Cited By

  • Rail installation structure of rail inspection robot

    CN117961969A