Analog simulation experiment device for rock stratum piling
By using calibration components of flexible ropes and scales on the mine pressure similar simulation experiment bench, the accuracy and convenience problems of manual scribe calibration are solved, and more accurate and flexible rock formation simulation is achieved, and the experimental applicable scenarios are expanded.
Patent Information
- Application Number
- CN202420406144.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-04
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-03-04
AI Technical Summary
The existing mine pressure similarity simulation experiment bench calibrates the height of the rock formation by manually marking the lines, which has differences in clarity and accuracy, especially when simulating inclined rock formations, which limits the accuracy and convenience of the experiment and reduces the applicable scenarios.
A similar simulation experimental device for rock formation building was designed, using calibration components combining flexible ropes and scales to accurately calibrate the height of rock formations through sliding grooves and fixed joints, and ensure flush and tightening of the ropes through the wire-retraction mechanism. , simplifies the marking determination process and is suitable for simulation of parallel and inclined rock formations.
It improves the accuracy and convenience of simulation experiments, reduces experimental errors, expands the applicable scenarios of experimental devices, avoids the problem of calibration lines being erased, and achieves a more flexible and reliable simulation experiment.
Smart Images

Figure CN221993453U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of rock stratum similarity simulation experiments, in particular to a rock stratum stacking similarity simulation experiment device. Background Art
[0002] In order to simulate the problems of instability and deformation of overburden structure and surface collapse caused by mining activities in coal seam mining, similar simulation experimental equipment is usually used to lay similar materials of coal rock layer. The excavation process of similar simulated rock layer and the recording and analysis of experimental data are monitored by monitoring equipment. The obtained rules have important reference value for the site.
[0003] The existing mine pressure similarity simulation test bench basically uses manual marking to calibrate the rock layer height. The clarity and accuracy of the marking calibration are poor, and there is a problem that the calibration line will be erased during the addition of similar materials, which reduces the accuracy and convenience of the simulation experiment; especially when simulating inclined rock layers, the calibration height is prone to errors and confusion, and the experimental purpose cannot be achieved well. There may be certain restrictions on different types of experiments and tests, which narrows the applicable scenarios of mine pressure similarity simulation experiments and reduces their versatility.
[0004] Therefore, how to improve the accuracy and convenience of similar simulation test benches and expand the applicable scenarios of similar simulation test benches is a technical problem that technical personnel in this field currently need to solve. Utility Model Content
[0005] In view of this, the purpose of the utility model is to provide a rock stacking similarity simulation experimental device to improve the accuracy and convenience of the similarity simulation experimental platform, while expanding the applicable scenarios of the similarity simulation experimental platform.
[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0007] A rock stacking similarity simulation experimental device, comprising:
[0008] Base;
[0009] A laboratory table frame is arranged on the base;
[0010] A baffle plate is detachably arranged in the experimental platform frame, and the baffle plate and the experimental platform frame are enclosed to form a rock stratum laying space for laying rock stratum similar materials;
[0011] A calibration component is arranged on two opposite sides of the laboratory bench frame, the calibration component includes a scale, a flexible rope and a fixed clamping piece, the laboratory bench frame includes a first side and a second side arranged opposite to each other, the first side and the second side are both provided with scales, and the scales are provided with a slide groove extending in a vertical direction, the fixed clamping piece is located on the first side, and the first end of the flexible rope passes through the slide groove on the scale on the first side and is connected to the fixed clamping piece;
[0012] The wire-receiving mechanism is located on the second side, and the second end of the flexible rope passes through the slide groove on the scale on the second side and is connected to the wire-receiving mechanism.
[0013] Optionally, in the above-mentioned rock formation stacking similarity simulation experimental device, the calibration component further includes:
[0014] A tension rod vertically passes through the slide slot of the scale, and a first through hole is provided inside the tension rod along its axial direction, and the flexible rope passes through the first through hole;
[0015] A tensioning plate is provided with a conductor groove, the tensioning rod is welded in the conductor groove, and the tensioning plate is located on a side of the scale close to the rock stratum laying space;
[0016] A tension block is detachably connected to one end of the tension rod, and the tension block is located on a side of the scale away from the rock stratum laying space.
[0017] Optionally, in the above-mentioned rock stacking similar simulation experimental device, the tension rod is a threaded rod with external threads, and the tension block is a nut that can be connected to the threaded rod through threads.
[0018] Optionally, in the above-mentioned rock formation stacking similarity simulation experimental device, the wire-receiving mechanism comprises:
[0019] The wire collection box body is provided with a wire collection space;
[0020] A winding drum, rotatably disposed in the wire-collecting space, and the second end of the flexible rope is wound around the winding drum;
[0021] The winding handle is connected to the winding drum and is used to drive the winding drum to rotate.
[0022] Optionally, in the above-mentioned rock stacking similar simulation experimental device, the first leg and the second leg are fixedly arranged in the wire taking-up box body, the winding drum is rotatably arranged between the first leg and the second leg, and a clamping piece is arranged between at least one of the first leg and the second leg and the winding drum.
[0023] Optionally, in the above-mentioned rock stacking similarity simulation experimental device, it also includes:
[0024] A first group of loading mechanisms is arranged at the upper end of the experimental platform frame;
[0025] A second group of loading mechanisms is arranged in the rock stratum laying space, and a loading direction of the second group of loading mechanisms is perpendicular to a loading direction of the first group of loading mechanisms;
[0026] The third group of loading mechanisms is arranged in the rock stratum laying space opposite to the second group of loading mechanisms.
[0027] Optionally, in the above-mentioned rock stacking similar simulation experimental device, each group of loading mechanisms includes a hydraulic loader, a pressurizing plate connected to the telescopic end of the hydraulic loader, and a pressure display for monitoring the pressurizing pressure.
[0028] Optionally, in the above-mentioned rock stacking similarity simulation experimental device, a support beam is also provided above the experimental platform frame, and a lifting drive assembly is provided on the support beam for lifting similar materials to be laid to a preset height.
[0029] Optionally, in the above-mentioned rock stacking similar simulation experimental device, the lifting drive assembly includes a lifting motor, a steel wire rope connected to the output shaft of the lifting motor, and a hook hinged to the steel wire rope.
[0030] When using the rock stacking simulation experiment device provided by the utility model, the baffles are gradually and detachably arranged on the experimental platform frame according to the stacking height, and the baffles and the experimental platform frame are enclosed to form a rock layer laying space; the calibration components on both sides are slid along the corresponding slide grooves of the scale to the zero scale of the scale, and the first end of the flexible rope is passed through the slide groove of the scale on the first side from the inside of the rock layer laying space toward the outside of the rock layer laying space, and then connected to the fixed clamping part on the first side; according to the height designed on the drawing, the two ends of the flexible rope are slid along the slide groove on the scale to the height of the first layer of the stacked rock layer, driving the flexible rope to be flush with the height of the first layer of the stacked rock layer, and through the wire-winding mechanism Tighten the flexible rope; then, pour the proportioned rock-similar material into the rock-laying space, gently grab the flexible rope and then release it, ensure that the flexible rope is flush with the height of the first layer of rock and is in a straight state, compact and flatten the rock-similar material, and after the first layer of rock is piled to the same horizontal position as the flexible rope, sprinkle a layer of mica, and then slide the two ends of the flexible rope along the slide groove of the scale to the height of the second layer of rock, continue to lay similar materials in the rock-laying space, and lay them layer by layer according to the above method until the designed rock height is reached, then untie one end of the flexible rope connected to the fixed clamp, and retract the other end through the take-up mechanism and then remove the take-up mechanism.
[0031] It can be seen that the rock stacking similarity simulation experiment device provided by the utility model calibrates the rock layer height by using a flexible rope, which has the following advantages over the prior art which uses manual marking to calibrate:
[0032] (1) The steps of determining the thickness of the simulated rock formation by marking the line are simplified;
[0033] (2) When used to simulate parallel rock formations, the experimental device can be adjusted in height, precision, and flexibility as needed, thereby achieving a more flexible, accurate, and reliable simulation experiment;
[0034] (3) When used to simulate inclined rock formations, the height of the flexible ropes at both ends can be adjusted to build a complete and flat rock formation with an angle, which improves the applicable scenarios and has good versatility;
[0035] (4) When used for rock formation simulation with more rock layers, the calibration is more accurate, which greatly reduces the experimental error;
[0036] (5) The clarity and accuracy of line marking are improved, the phenomenon of calibration line being erased is avoided, and the accuracy and convenience of simulation are improved;
[0037] (6) Easy to adjust, saving time and labor. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0039] Figure 1 A schematic diagram of the axonometric structure of a rock stacking similarity simulation experimental device provided by an embodiment of the utility model;
[0040] Figure 2 A schematic diagram of the structure of a rock stacking similarity simulation experimental device provided by an embodiment of the utility model when used for horizontal model stacking;
[0041] Figure 3 A schematic diagram of the structure of a rock stacking similarity simulation experimental device provided by an embodiment of the utility model when used for tilted model stacking;
[0042] Figure 4 A schematic diagram of a partial structure of a tensioning assembly provided in an embodiment of the utility model;
[0043] Figure 5A schematic diagram of the structure of a wire-taking mechanism provided by an embodiment of the utility model;
[0044] Figure 6 A schematic diagram of the structure of a tensioning sheet provided by an embodiment of the utility model;
[0045] Figure 7 A schematic diagram of the structure of a tension block provided by an embodiment of the utility model;
[0046] Figure 8 A side structural schematic diagram of a rock stacking similarity simulation experimental device provided in an embodiment of the utility model.
[0047] Among them, 100 is the experimental bench frame, 101 is the base, 102 is the rivet, 200 is the baffle, 300 is the calibration component, 301 is the scale, 3011 is the slide groove, 302 is the flexible rope, 303 is the fixed clamping part, 304 is the tensioning rod, 305 is the tensioning plate, 3051 is the wire groove, 306 is the tensioning block, 400 is the wire taking-up mechanism, 401 is the wire taking-up box body, 402 is the winding drum, 403 is the wire shaking handle, 404 is the clamping part, 500 is the first group of loading mechanisms, 600 is the second group of loading mechanisms, 601 is the hydraulic loading part, 602 is the pressure plate, 603 is the pressure display, 700 is the third group of loading mechanisms, 800 is the support beam, 900 is the lifting drive assembly, 901 is the lifting motor, 902 is the wire rope, and 903 is the hook. DETAILED DESCRIPTION
[0048] In view of this, the core of the utility model is to provide a rock stacking similarity simulation experimental device to improve the accuracy and convenience of the similarity simulation experimental platform, while expanding the applicable scenarios of the similarity simulation experimental platform.
[0049] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0050] like Figures 1 to 8 As shown, an embodiment of the utility model discloses a rock stacking similarity simulation experimental device, including an experimental platform frame 100, a baffle 200, a calibration component 300 and a wire-reeling mechanism 400.
[0051] The baffle 200 is detachably arranged in the experimental platform frame 100, the experimental platform frame 100 is arranged on the base 101, and the baffle 200 and the experimental platform frame 100 are enclosed to form a rock paving space for laying rock-like materials; the calibration component 300 is arranged on two opposite sides of the experimental platform frame 100, and the calibration component 300 includes a scale 301, a flexible rope 302 and a fixed clamp 303. The experimental platform frame 100 includes two oppositely arranged first sides and second sides. On both sides, a scale 301 is set on the first side and the second side, and a slide groove 3011 extending in the vertical direction is provided on the scale 301, and the fixed clamping part 303 is located on the first side, and the first end of the flexible rope 302 passes through the slide groove 3011 on the scale 301 on the first side and is connected to the fixed clamping part 303; the take-up mechanism 400 is located on the second side, and the second end of the flexible rope 302 passes through the slide groove 3011 on the scale 301 on the second side and is connected to the take-up mechanism 400.
[0052] When using the rock stacking simulation experiment device provided by the utility model, the baffle 200 is gradually detachably arranged on the experimental platform frame 100 according to the stacking height, and the baffle 200 and the experimental platform frame 100 are enclosed to form a rock layer laying space; the calibration components 300 on both sides are slid along the corresponding slide groove 3011 of the scale 301 to the zero scale of the scale 301, and the first end of the flexible rope 302 is passed through the slide groove 3011 of the scale 301 on the first side from the inside of the rock layer laying space toward the outside of the rock layer laying space, and then connected with the fixed clamping part 303 on the first side; according to the height designed in the drawing, the two ends of the flexible rope 302 are slid along the slide groove 3011 on the scale 301 to the height of the first layer of the stacked rock layer, driving the flexible rope 302 to be flush with the height of the first layer of the stacked rock layer, And tighten the flexible rope 302 through the take-up mechanism 400; then, pour the proportioned rock-similar material into the rock-laying space, gently grab the flexible rope 302 and then release it, ensure that the flexible rope 302 is flush with the height of the first layer of rock and is in a straight state, compact and flatten the rock-similar material, and after the first layer of rock is piled to the same horizontal position as the flexible rope 302, sprinkle a layer of mica, and then slide the two ends of the flexible rope 302 along the slide groove 3011 of the scale 301 to the height of the second layer of rock, continue to lay similar materials in the rock-laying space, and lay them layer by layer according to the above method until the designed rock height is reached, then untie one end of the flexible rope 302 connected to the fixed clamp 303, and retract the other end through the take-up mechanism 400 and then remove the take-up mechanism 400.
[0053] It can be seen that the rock stacking similarity simulation experiment device provided by the utility model calibrates the rock layer height by using the flexible rope 302, which has the following advantages over the prior art which uses the manual marking method for calibration:
[0054] (1) The steps of determining the thickness of the simulated rock formation by marking the line are simplified;
[0055] (2) When used to simulate parallel rock formations, the experimental device can be adjusted in height, precision, and flexibility as needed, thereby achieving a more flexible, accurate, and reliable simulation experiment;
[0056] (3) When used to simulate inclined rock formations, the height of the flexible ropes 302 at both ends can be adjusted to build a complete and flat rock formation with an angle, which improves the applicable scenarios and has good versatility;
[0057] (4) When used for rock formation simulation with more rock layers, the calibration is more accurate, which greatly reduces the experimental error;
[0058] (5) The clarity and accuracy of line marking are improved, the phenomenon of calibration line being erased is avoided, and the accuracy and convenience of simulation are improved;
[0059] (6) Easy to adjust, saving time and labor.
[0060] It should be noted that the above-mentioned baffle 200 can be detachably arranged in the experimental bench frame 100 by means of bolt connection or clamping, and any setting method that can meet the use requirements belongs to the protection scope of the present utility model; optionally, in a specific embodiment of the present utility model, multiple fixed installation holes are provided at both ends of the experimental bench frame 100 from bottom to top, and the baffle 200 is installed in the corresponding fixed installation holes by bolt connection; and, the side of the baffle 200 close to the rock paving space is brushed with lubricating oil to reduce the friction between the baffle 200 and similar materials.
[0061] In addition, the above-mentioned flexible rope 302 can be a cotton rope, a cotton wax rope or a braided rope, etc., as long as the type can meet the use requirements, it belongs to the protection scope of the present utility model; similarly, the above-mentioned fixed clamp 303 can be a clamping ring, a clamping plate or a clamping clip, etc., as long as the type of part can meet the use requirements, it belongs to the protection scope of the present utility model; optionally, the fixed clamp 303 provided in the embodiment of the present utility model is a clamping ring, which is convenient for connecting with the flexible rope 302.
[0062] The above-mentioned scale 301 can be set on two opposite sides of the laboratory bench frame 100 by welding, bonding or screw connection. As long as the connection requirements are met, it falls within the protection scope of the present utility model; optionally, the scale 301 provided in the embodiment of the present utility model is anchored on both sides of the laboratory bench frame 100 by rivets 102.
[0063] Furthermore, the calibration assembly 300 further includes a tensioning rod 304, a tensioning sheet 305 and a tensioning block 306; wherein the tensioning rod 304 vertically penetrates the slide groove 3011 of the scale 301, and the interior of the tensioning rod 304 is provided with a first through hole along its axial direction, and the flexible rope 302 penetrates the first through hole, so that the flexible rope 302 passes through the first through hole, and the flexible rope 302 is tensioned by the tensioning rod 304, and the fixed clamping piece 303 is located on the side of the tensioning rod 304 close to the rock stratum laying space, so as to facilitate the connection of the first end of the flexible rope 302 through the fixed clamping piece 303; the tensioning sheet 305 is provided with a wire groove 3051, and the tensioning rod 304 is welded in the wire groove 3051, and the tensioning sheet 305 is located on the side of the scale 301 close to the rock laying space, so as to keep the position of the flexible rope 302 in the middle of the two opposite sides of the experimental table frame 100 during the laying of similar materials, and prevent the position of the flexible rope 302 from moving or deflecting; the tensioning block 306 is detachably connected to one end of the tensioning rod 304, and the tensioning block 306 is located on the side of the scale 301 away from the rock laying space. On the one hand, the flexible rope 302 can be driven to move along the slide groove 3011 by the tensioning block 306, and on the other hand, the anti-falling function of the flexible rope 302 can be realized by the tensioning block 306.
[0064] It should be understood that after the above-mentioned flexible rope 302 is tensioned, the tensioning block 306 fits against the scale 301 and the tensioning block 306 presses the scale 301, and the static friction between the tensioning block 306 and the scale 301 prevents the tensioning block 306 from sliding along the scale 301, thereby achieving the fixation of the end of the flexible rope 302; of course, a stopper can be further provided after the flexible rope 302 is tensioned to prevent the tensioning block 306 from sliding off. As long as the implementation method can meet the use requirements, it belongs to the protection scope of the present utility model.
[0065] In addition, the tensioning block 306 and the tensioning rod 304 can be detachably connected by means of bolt connection or clamp connection. As long as the detachable connection method can meet the use requirements, it belongs to the protection scope of the present utility model; optionally, the tensioning block 306 and the tensioning rod 304 provided in the embodiment of the present utility model are connected by threads.
[0066] Specifically, in some specific embodiments of the present invention, the above-mentioned tensioning rod 304 is a hollow threaded round rod with an external thread, and the tensioning block 306 is a nut that cooperates with the hollow threaded round rod through threads, so as to facilitate the connection between the hollow threaded round rod and the nut by rotation. When the relative position between the nut and the hollow threaded round rod needs to be adjusted, it is only necessary to rotate the nut, which improves convenience.
[0067] The above-mentioned take-up mechanism 400 can recycle the flexible rope 302 by rotation or reciprocating movement. As long as the take-up method can meet the use requirements, it belongs to the protection scope of the present utility model; optionally, the take-up mechanism 400 provided in the embodiment of the present utility model realizes the recovery of the flexible rope 302 by rotation.
[0068] like Figure 5 As shown, the wire taking-up mechanism 400 includes a wire taking-up box body 401, a winding drum 402 and a wire shaking handle 403; wherein the wire taking-up box body 401 is provided with a wire taking-up space; the winding drum 402 is rotatably arranged in the wire taking-up space, and the second end of the flexible rope 302 is wound around the winding drum 402; the wire shaking handle 403 is embedded in the winding drum, and is used to drive the winding drum 402 to rotate; when it is necessary to take up the wire, the wire shaking handle 403 is rotated so that the wire shaking handle 403 drives the winding drum 402 to rotate, and based on the winding relationship between the flexible rope 302 and the winding drum 402, the flexible rope is wound and stored in the winding drum 402.
[0069] The first leg and the second leg are fixedly arranged in the above-mentioned wire collection box body 401, and the winding drum 402 is rotatably arranged between the first leg and the second leg, and a clamping piece 404 is arranged between at least one of the first leg and the second leg and the winding drum 402, so that after the flexible rope 302 is adjusted, the winding drum 402 can be clamped by the clamping piece 404 to prevent the winding drum 402 from continuing to rotate and causing the flexible rope 302 to loosen, affecting the calibration.
[0070] The clamping member 404 provided by the present invention may be a clamping sheet or a V-shaped clamping spring or other types of clamping member 404. As long as the clamping member 404 can meet the clamping requirements, it belongs to the protection scope of the present invention. Optionally, the clamping member 404 provided in the embodiment of the present invention is a clamping sheet.
[0071] Furthermore, the above-mentioned rock stacking similarity simulation experimental device also includes a first group of loading mechanisms 500, a second group of loading mechanisms 600 and a third group of loading mechanisms 700; wherein, the first group of loading mechanisms 500 is arranged at the upper end of the experimental platform frame 100; the second group of loading mechanisms 600 is arranged in the rock stratum laying space, and the loading direction of the second group of loading mechanisms 600 is perpendicular to the loading direction of the first group of loading mechanisms 500; the third group of loading mechanisms 700 is arranged in the rock stratum laying space opposite to the second group of loading mechanisms 600, so as to pressurize similar materials in the vertical direction through the first group of loading mechanisms 500, and pressurize similar materials in the horizontal direction through the second group of loading mechanisms 600 and the third group of loading mechanisms 700.
[0072] The above-mentioned first group of loading mechanisms 500, second group of loading mechanisms 600 and third group of loading mechanisms 700 can all be loaded by hydraulic means, electric telescopic means or pneumatic means, and any loading mechanism that can meet the loading requirements belongs to the protection scope of the present utility model; optionally, in the embodiment of the present utility model, each group of loading mechanisms includes a hydraulic loader 601, a pressure plate 602 and a pressure display 603, the pressure plate 602 is connected to the telescopic end of the hydraulic loader 601, and the pressure display 603 is used to monitor the pressurization pressure, so that the hydraulic loader 601 pressurizes similar materials through the pressure plate 602, and the operator reads the pressurization pressure through the pressure display 603.
[0073] like Figures 1 to 3 As shown, a support beam 800 is also provided above the experimental platform frame 100, and a lifting drive assembly 900 is provided on the support beam 800, so that when the rock layer is laid to a higher height, the lifting drive assembly 900 can be used to lift similar materials to be laid to a preset height, thereby improving convenience.
[0074] Specifically, the lifting drive assembly 900 includes a lifting motor 901, a steel wire rope 902 connected to the output shaft of the lifting motor 901, and a hook 903 hinged to the steel wire rope 902, so as to lift the similar materials to be laid through the hook 903, and the lifting motor 901 lifts the similar materials to be laid to a preset height.
[0075] The method for using the rock stacking similarity simulation experiment device provided by the utility model to conduct a parallel rock formation similarity simulation experiment is as follows:
[0076] The first step is to design the distance between rock layers in proportion to the height of a similar simulation experimental device and the height of a comprehensive columnar diagram of the mine rock mass, and draw a design drawing according to the scale.
[0077] The second step is to adjust each pressure plate 602 in the first group of loading mechanisms 500 to the same height, each pressure plate 602 in the second group of loading mechanisms 600 to the same position in the horizontal direction, and each pressure plate 602 in the third group of loading mechanisms 700 to the same position in the horizontal direction, clean up the residue on similar simulation experimental devices, and gradually fix the baffles 200 brushed with lubricating oil in the fixed installation holes of the experimental table frame 100 according to the stacking height.
[0078] The third step is to slide the calibration component 300 through the slide groove 3011 to the zero scale of the scale 301, pass the flexible rope 302 through the first through hole of the tensioning rod 304 and connect it to the tensioning rod 304 at the other end and then clamp it with the fixed clamp 303; according to the height designed in the drawing, slide the tensioning blocks 306 at both ends to the height of the first layer of rock formation, drive the flexible rope 302 to be flush with the height of the first layer of rock formation; tighten the flexible rope 302 through the wire shaking handle 403 of the take-up mechanism 400 until the winding reel can no longer rotate, so that the flexible rope 302 is in a taut state through the tensioning plate 305 and the tensioning rod 304; clamp the clamping piece 404 at the end of the winding reel 402 to clamp the winding reel 402.
[0079] The fourth step is to pour the proportioned rock-similar materials into the rock laying space formed by the experimental platform frame 100 and the baffle 200, gently grab the flexible rope 302 and then release it, ensure that the flexible rope 302 is in a straight state, compact and flatten it until the rock layer is piled to the same level as the flexible rope 302.
[0080] The fifth step is to pave the first layer of rock and sprinkle a layer of mica, move the flexible ropes 302 at both ends to the designed height of the second layer, pave similar materials into the rock laying space, and continue to pave the rock layer upward layer by layer according to the steps of the fourth step until it reaches the designed rock height.
[0081] Step 6: Untie the end of the flexible rope 302 connected to the fixed clamping piece 303 from the tensioning rod 304, and retract the other end through the wire-retracting mechanism 400, and then remove the wire-retracting mechanism 400.
[0082] The above steps are the technical methods for designing parallel rock formations. The experimental device can also be used to design similar simulation experiments for inclined rock formations. The method is to design the height of the inclined rock formation according to the required rock formation scale, fix the position of the flexible rope 302 at one end of the experimental platform frame 100, and then fix the height of the tension block 306 and the flexible rope 302 at the other end, and then operate according to the laying method of parallel rock formations in sequence to obtain a similar simulation experiment of the designed inclined rock mass.
[0083] The terms "first" and "second" in the specification and claims of the utility model and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may include steps or units that are not listed.
[0084] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A rock stacking similarity simulation experimental device, characterized in that: include: Base; A laboratory table frame is arranged on the base; A baffle plate is detachably arranged in the experimental platform frame, and the baffle plate and the experimental platform frame are enclosed to form a rock stratum laying space for laying rock stratum similar materials; A calibration component is arranged on two opposite sides of the laboratory bench frame, the calibration component includes a scale, a flexible rope and a fixed clamping piece, the laboratory bench frame includes a first side and a second side arranged opposite to each other, the first side and the second side are both provided with scales, and the scales are provided with a slide groove extending in a vertical direction, the fixed clamping piece is located on the first side, and the first end of the flexible rope passes through the slide groove on the scale on the first side and is connected to the fixed clamping piece; The wire-receiving mechanism is located on the second side, and the second end of the flexible rope passes through the slide groove on the scale on the second side and is connected to the wire-receiving mechanism.
2. The rock stacking similarity simulation experimental device according to claim 1 is characterized in that: The calibration component also includes: A tension rod vertically passes through the slide slot of the scale, and a first through hole is provided inside the tension rod along its axial direction, and the flexible rope passes through the first through hole; A tensioning plate is provided with a conductor groove, the tensioning rod is welded in the conductor groove, and the tensioning plate is located on a side of the scale close to the rock stratum laying space; A tension block is detachably connected to one end of the tension rod, and the tension block is located on a side of the scale away from the rock stratum laying space.
3. The rock stacking similarity simulation experimental device according to claim 2 is characterized in that: The tension rod is a threaded rod with external threads, and the tension block is a nut that can be connected to the threaded rod through threads.
4. The rock stacking similarity simulation experimental device according to claim 1 is characterized in that: The wire taking-up mechanism comprises: The wire collection box body is provided with a wire collection space; A winding drum, rotatably disposed in the wire-collecting space, and the second end of the flexible rope is wound around the winding drum; The winding handle is connected to the winding drum and is used to drive the winding drum to rotate.
5. The rock stacking similarity simulation experimental device according to claim 4 is characterized in that: A first leg and a second leg are fixedly arranged in the wire take-up box body, the wire reel is rotatably arranged between the first leg and the second leg, and a clamping piece is arranged between at least one of the first leg and the second leg and the wire reel.
6. The rock stacking similarity simulation experimental device according to claim 1 is characterized in that: Also includes: A first group of loading mechanisms is arranged at the upper end of the experimental platform frame; A second group of loading mechanisms is arranged in the rock stratum laying space, and a loading direction of the second group of loading mechanisms is perpendicular to a loading direction of the first group of loading mechanisms; The third group of loading mechanisms is arranged in the rock stratum laying space opposite to the second group of loading mechanisms.
7. The rock stacking similarity simulation experimental device according to claim 6 is characterized in that: Each group of loading mechanisms includes a hydraulic loading component, a pressurizing plate connected to the telescopic end of the hydraulic loading component, and a pressure display for monitoring the pressurizing pressure.
8. The rock stacking similarity simulation experimental device according to claim 1 is characterized in that: A support beam is also provided above the experimental table frame, and a lifting drive component is provided on the support beam for lifting similar materials to be laid to a preset height.
9. The rock stacking similarity simulation experimental device according to claim 8, characterized in that: The lifting drive assembly comprises a lifting motor, a steel wire rope connected to the output shaft of the lifting motor, and a hook hinged to the steel wire rope.
Citation Information
Cited By
Analog simulation experiment device for rock stratum piling
CN118091085A
A rock stratum stacking similar simulation experiment device
CN118091085B