Hydrolysis ammonia production wastewater treatment system for urea workshop
By designing a hydrolysis ammonia-making wastewater treatment system in the urea workshop and using circulation pumps and dosing systems to treat wastewater in the urea workshop, the problem of wastewater wasted during regular maintenance of traditional hydrolysis machines was solved, and the reuse and economic improvement of wastewater was achieved.
Patent Information
- Application Number
- CN202420162083.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-23
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2034-01-23
AI Technical Summary
Traditional hydrolysis machines need to be regularly inspected and produced more wastewater, and ammonia is wasted after wastewater treatment, reducing economic efficiency.
A urea workshop hydrolysis ammonia wastewater treatment system is designed, including installation base, hydrolysis wastewater puddle, storage tank, urea dissolution tank, hydrolyzer, neutralization tank and conveying components, and the wastewater is treated through the circulation pump and dosing system to ensure that the wastewater is treated. Recycle it after the pH value is qualified to reduce wastewater discharge.
After the system is processed, the wastewater generation during regular maintenance of the hydrolysis device is reduced, the wastewater is reused, the economy is improved, and the pressure on environmental protection facilities is reduced.
Smart Images

Figure CN222007448U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of wastewater treatment for hydrolysis ammonia production, in particular to a system for treating wastewater for hydrolysis ammonia production in a urea workshop. Background Art
[0002] How to deal with the wastewater generated by power plants is a difficult problem that plagues the industry. If effective measures can be taken to solve the wastewater generated by hydrolysis of ammonia and it can be comprehensively utilized, it will reduce the pressure on the company's environmental protection facilities and meet environmental protection requirements.
[0003] The hydrolysis and dissolution of urea in the urea workshop will produce a lot of wastewater. If the wastewater cannot be effectively handled, environmental incidents are likely to occur.
[0004] Traditional hydrolyzers require regular maintenance. If the internal solution is discharged, a large amount of wastewater will be produced. The treatment and discharge of wastewater will cause ammonia waste in the wastewater, reducing economic efficiency.
[0005] Therefore, it is necessary to provide a urea workshop hydrolysis ammonia wastewater treatment system to solve the above technical problems. Utility Model Content
[0006] The utility model provides a urea workshop hydrolysis ammonia wastewater treatment system, which solves the problem that a conventional hydrolyzer needs to be regularly inspected and repaired, such as discharging an internal solution to generate more wastewater, and the wastewater is discharged through treatment, which causes ammonia waste in the wastewater and reduces the economic efficiency.
[0007] In order to solve the above technical problems, the utility model provides a urea workshop hydrolysis ammonia wastewater treatment system comprising: a mounting base;
[0008] A first hydrolysis wastewater pit, wherein the first hydrolysis wastewater pit is installed on the top of a mounting base, a second hydrolysis wastewater pit is installed on the top of the mounting base, a first storage tank is installed on the top of the mounting base, a second storage tank is installed on the top of the mounting base, a urea dissolution tank is installed on the top of the mounting base, a first hydrolyzer is installed on the top of the mounting base, a second hydrolyzer is installed on the top of the mounting base, and a neutralization tank is installed on the top of the mounting base;
[0009] A first conveying assembly is installed on the top of a second hydrolysis wastewater pit, and two fixed pipes are installed at the outlet of the first conveying assembly through a tee joint. A second conveying assembly is installed on the top of the urea dissolution tank, and a connecting pipe is fixedly connected to the outlet of the second conveying assembly. A third conveying assembly is installed on the top of the neutralization tank, and a circulation assembly is installed on one side of the neutralization tank.
[0010] The fixed pipe on the first conveying assembly at the top of the second hydrolysis wastewater pit is connected to the first storage tank and the second storage tank respectively, the inlet of the first conveying assembly at the top of the second hydrolysis wastewater pit is connected to the second hydrolysis wastewater pit through a pipeline, the connecting pipe on the first conveying assembly at the top of the urea dissolution tank is connected to the second hydrolysis wastewater pit, the inlet of the first conveying assembly at the top of the urea dissolution tank is connected to the urea dissolution tank through a pipeline, and the outlet of the third conveying assembly is connected to the first hydrolysis wastewater pit and the second hydrolysis wastewater pit respectively through a pipeline. The first conveying assembly and the second conveying assembly are the same, both including a shell and a conveying pump. The positional relationship of the top of the mounting base is referenced to Figure 1 The circulation component 16 includes a shell and a circulation pump. A recirculation pump and a recirculation pipeline are arranged at the outlet of the neutralization tank. The outlet of the recirculation pipeline is arranged at the front end of the neutralization tank. The acid-base neutralization tank of this scheme is provided with an acid-base dosing pipeline and a pH meter measuring instrument. When urea hydrolysis wastewater is discharged into the neutralization tank, the recirculation pump, the acid-base dosing system, etc. are started to fully mix and add the wastewater generated by urea hydrolysis. At the same time, the wastewater tank and the pH meter measuring instrument of the recirculation pipeline perform real-time detection of the pH. After the pH is qualified, the wastewater delivery pump is started to deliver it to the subsequent wastewater treatment system.
[0011] Preferably, the first hydrolysis wastewater pit and the second hydrolysis wastewater pit are connected via a second conveying component, and the first hydrolyzer and the second hydrolyzer are connected via the first conveying component and a pipeline for entering wastewater to be decomposed.
[0012] Preferably, a control box is installed on the top of the mounting base, and a box door is rotatably connected to one side of the control box.
[0013] The control box is equipped with equipment for controlling the conveying components.
[0014] Preferably, two silt discharge pipes are fixedly connected to the front of the first hydrolysis wastewater pit, and a discharge pipe is fixedly connected to one side of the first hydrolysis wastewater pit.
[0015] The two sludge discharge pipes are connected to the first separation chamber and the second separation chamber.
[0016] Preferably, the interior of the first hydrolysis wastewater pit is divided into a first separation chamber, a second separation chamber and a discharge chamber by a separation component and a fixed plate.
[0017] The separation component is composed of a structure on a fixed plate, the discharge bin and the discharge pipe are in corresponding positions, and the bottom, front and back of the fixed plate and the separation component are respectively fixedly connected to the bottom, front and back of the inner wall of the first hydrolysis wastewater pit.
[0018] Preferably, two filter plates are fixedly connected to the top of the fixed plate at two sides, and a plurality of baffles are arranged between the two filter plates.
[0019] The baffle is stuck between the two filter plates and can be removed.
[0020] Preferably, a top cover is provided on the top of the first hydrolysis wastewater pit, and an injection pipe is installed on the top of the top cover.
[0021] The injection pipe is connected to the outlet of the second transport assembly at the top of the first hydrolyzer and the second hydrolyzer.
[0022] Compared with the related art, the urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model has the following beneficial effects:
[0023] The utility model provides a urea workshop hydrolysis ammonia production wastewater treatment system. In order to facilitate the regular sewage discharge of the hydrolyzer and the reuse of ammonia water in the wastewater to reduce the discharge, the first hydrolysis wastewater pit and the second hydrolysis wastewater pit are respectively installed on the installation base, and the two are connected through a second conveying component and a connecting pipe. At the same time, the first storage tank and the second storage tank are installed on the installation base, and the first hydrolysis wastewater pit and the second hydrolysis wastewater pit are connected to the first storage tank and the second storage tank through the first conveying component, a three-way head and a fixed pipe. In addition, the first hydrolyzer and the second hydrolyzer are installed on the installation base and are connected with the first hydrolysis wastewater pit through the second conveying component and the connecting pipe, and the urea dissolving tank is installed on the installation base and is connected with the second hydrolysis wastewater pit through the second conveying component and the connecting pipe. In actual work, the first hydrolyzer and the second The wastewater generated by the hydrolyzer is transported to the interior of the first hydrolysis wastewater pit through the second conveying component, and after treatment, it is transported to the interior of the second hydrolysis wastewater pit through the second conveying component. At the same time, the dissolved urea is transported to the interior of the second hydrolysis wastewater pit through the second conveying component. It is treated frequently. The ammonia water obtained after the treatment is transported to the interior of the first storage tank and the second storage tank respectively through the first conveying component, and the treated wastewater is transported to the interior of the neutralization tank for treatment through the third conveying component. This structure facilitates the regular maintenance of the hydrolyzer. If the internal solution is discharged, more wastewater will be generated. After treatment through this solution, this part of the solution is reused, which reduces the generation of wastewater and improves the economy. The solution generated by the regular maintenance of the hydrolysis ammonia hydrolyzer is transported to the interior of the two storage tanks for recycling. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 A schematic structural diagram of a first embodiment of a urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model;
[0025] Figure 2 A structural schematic diagram of a second hydrolyzer is provided for the utility model;
[0026] Figure 3 A schematic structural diagram of a second embodiment of a urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model;
[0027] Figure 4 An enlarged view of the baffle is provided for the utility model;
[0028] Figure 5 Provided for the utility model Figure 4 An enlarged view of point A is shown.
[0029] Numbers in the figure: 1. Installation base, 2. First hydrolysis wastewater pit, 3. Second hydrolysis wastewater pit, 4. First storage tank, 5. First conveying assembly, 6. Connecting pipe, 7. Second conveying assembly, 8. Urea dissolution tank, 9. Fixed pipe, 10. Tee head, 11. Second storage tank, 12. First hydrolyzer, 13. Second hydrolyzer, 14. Third conveying assembly, 15. Neutralization tank, 16. Circulation assembly, 17. Box door, 18. Control box, 19. Discharge pipe, 20. Drain pipe, 21. Top cover, 22. Injection pipe, 23. First separation bin, 24. Second separation bin, 25. Separation assembly, 26. Fixed plate, 27. Discharge bin, 28. Filter plate, 29. Baffle. DETAILED DESCRIPTION
[0030] The utility model is further described below in conjunction with the accompanying drawings and implementation modes.
[0031] Please refer to Figure 1 , Figure 2 ,in, Figure 1 A schematic structural diagram of a first embodiment of a urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model; Figure 2 The utility model provides a structural schematic diagram of the second hydrolyzer. The urea workshop hydrolysis ammonia wastewater treatment system comprises: a mounting base 1;
[0032] A first hydrolysis wastewater pit 2, wherein the first hydrolysis wastewater pit 2 is installed on the top of the mounting base 1, a second hydrolysis wastewater pit 3 is installed on the top of the mounting base 1, a first storage tank 4 is installed on the top of the mounting base 1, a second storage tank 11 is installed on the top of the mounting base 1, a urea dissolution tank 8 is installed on the top of the mounting base 1, a first hydrolyzer 12 is installed on the top of the mounting base 1, a second hydrolyzer 13 is installed on the top of the mounting base 1, and a neutralization tank 15 is installed on the top of the mounting base 1;
[0033] A first conveying component 5 is installed on the top of the second hydrolysis wastewater pit 3, and two fixed pipes 9 are installed at the outlet of the first conveying component 5 through a three-way head 10. A second conveying component 7 is installed on the top of the urea dissolution tank, and a connecting pipe 6 is fixedly connected to the outlet of the second conveying component 7. A third conveying component 14 is installed on the top of the neutralization tank 15, and a circulation component 16 is installed on one side of the neutralization tank 15.
[0034] The fixed pipe 9 on the first conveying assembly 5 at the top of the second hydrolysis wastewater pit 3 is connected to the first storage tank 4 and the second storage tank 11 respectively, the inlet of the first conveying assembly 5 at the top of the second hydrolysis wastewater pit 3 is connected to the second hydrolysis wastewater pit 3 through a pipeline, the connecting pipe 6 on the first conveying assembly 5 at the top of the urea dissolution tank 8 is connected to the second hydrolysis wastewater pit 3, the inlet of the first conveying assembly 5 at the top of the urea dissolution tank 8 is connected to the urea dissolution tank 8 through a pipeline, and the outlet of the third conveying assembly 14 is connected to the first hydrolysis wastewater pit 2 and the second hydrolysis wastewater pit 3 through a pipeline, the first conveying assembly 5 and the second conveying assembly 7 are the same, both include a shell and a conveying pump, and the positional relationship of the top of the mounting base 1 is referenced. Figure 1 The circulation component 16 includes a shell and a circulation pump. A recirculation pump and a recirculation pipeline are arranged at the outlet of the neutralization tank 15. The outlet of the recirculation pipeline is arranged at the front end of the neutralization tank. The acid-base neutralization tank of this scheme is provided with an acid-base dosing pipeline and a pH meter measuring instrument. When the urea hydrolysis wastewater is discharged into the neutralization tank, the recirculation pump, the acid-base dosing system, etc. are started to fully mix and add the wastewater generated by the urea hydrolysis. At the same time, the wastewater tank and the pH meter measuring instrument of the recirculation pipeline detect the pH in real time. After the pH is qualified, the wastewater delivery pump is started to deliver it to the subsequent wastewater treatment system;
[0035] The main function of regular sewage discharge of urea hydrolyzer is to discharge impurities deposited at the bottom of the hydrolyzer. This part of sewage is discharged to the wastewater pit in the hydrolysis area for collection. The wastewater pump in the hydrolysis area is set to start interlocking. When the liquid level is high, the wastewater pump is started. The discharge pipeline is designed and laid to the wastewater pit in the dissolution area for collection;
[0036] A wastewater pit is set up in the urea dissolution area, which mainly collects wastewater generated by the dissolution tank and storage tank, and also collects wastewater discharged to the wastewater pool by the wastewater pump in the hydrolysis area. The hydrolyzer needs to be regularly inspected and maintained, and the internal water storage volume is large. If all the internal ammonia water is discharged to the wastewater pit in the hydrolysis area, it will produce great pressure on the wastewater treatment system, and at the same time cause all the ammonia water to be wasted and the economic efficiency is reduced. A regular inspection discharge pipe is set at the bottom of the hydrolyzer to the inlet of the dissolution water pump. When the hydrolyzer needs regular inspection to discharge the internal solution, open the bottom drain gate, close the dissolution tank outlet gate, and start the dissolution water pump. The dissolution water pump can directly discharge the internal solution of the hydrolyzer into the solution storage tank for storage and recovery.
[0037] The first hydrolysis wastewater pit 2 and the second hydrolysis wastewater pit 3 are connected via a second conveying assembly 7 , and the first hydrolyzer 12 and the second hydrolyzer 13 are connected via a first conveying assembly 5 to a wastewater pipeline entering the wastewater to be decomposed.
[0038] A control box 18 is installed on the top of the installation base 1 , and a box door 17 is rotatably connected to one side of the control box 18 .
[0039] The control box 18 is internally installed with equipment for controlling the conveying assembly, and the box door 17 is provided with a lock.
[0040] The working principle of the urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model is as follows:
[0041] First, the first hydrolysis wastewater pit 2 and the second hydrolysis wastewater pit 3 are respectively installed on the installation base 1, and the two are connected through the second conveying component 7 and the connecting pipe 6. At the same time, the first storage tank 4 and the second storage tank 11 are installed on the installation base 1, and the first hydrolysis wastewater pit 2 and the second hydrolysis wastewater pit 3 are connected to the first storage tank 4 and the second storage tank 11 through the first conveying component 5, the tee head 10 and the fixed pipe 9. In addition, the first hydrolyzer 12 and the second hydrolyzer 13 are installed on the installation base 1 and are connected to the first hydrolysis wastewater pit 2 through the second conveying component 7 and the connecting pipe 6, and the urea dissolution tank 8 is installed on the installation base 1 through the second conveying component 5. The conveying component 7 is connected to the connecting pipe 6 and the second hydrolysis wastewater pit 3. In actual work, the wastewater generated by the first hydrolyzer 12 and the second hydrolyzer 13 is conveyed to the interior of the first hydrolysis wastewater pit 2 through the second conveying component 7, and after treatment, it is conveyed to the interior of the second hydrolysis wastewater pit 3 through the second conveying component 7. At the same time, the dissolved urea is conveyed to the interior of the second hydrolysis wastewater pit 3 through the second conveying component 7. It is often treated. The ammonia water obtained after the treatment is completed will be conveyed to the interior of the first storage tank 4 and the second storage tank 11 respectively through the first conveying component 5, and the treated wastewater is conveyed to the interior of the neutralization tank 15 through the third conveying component 14 for treatment.
[0042] Compared with the related art, the urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model has the following beneficial effects:
[0043] In order to facilitate the regular discharge of sewage from the hydrolyzer and the reuse of ammonia in the wastewater to reduce emissions, the first hydrolysis wastewater pit 2 and the second hydrolysis wastewater pit 3 are respectively installed on the mounting base 1, and the two are connected through the second conveying component 7 and the connecting pipe 6. At the same time, the first storage tank 4 and the second storage tank 11 are installed on the mounting base 1, and the first hydrolysis wastewater pit 2 and the second hydrolysis wastewater pit 3 are connected to the first storage tank 4 and the second storage tank 11 through the first conveying component 5, the tee head 10 and the fixed pipe 9. In addition, the first hydrolyzer 12 and the second hydrolyzer 13 are installed on the mounting base 1 and are connected to the first hydrolysis wastewater pit 2 through the second conveying component 7 and the connecting pipe 6. In addition, the urea dissolution tank 8 is installed on the mounting base 1 and is connected to the second hydrolysis wastewater pit 3 through the second conveying component 7 and the connecting pipe 6. In actual work, the first hydrolyzer 12 and the second hydrolyzer 13 are connected. The wastewater generated by 13 is transported to the interior of the first hydrolysis wastewater pit 2 through the second conveying component 7, and after treatment, it is transported to the interior of the second hydrolysis wastewater pit 3 through the second conveying component 7. At the same time, the dissolved urea is transported to the interior of the second hydrolysis wastewater pit 3 through the second conveying component 7. It is often treated. The ammonia water obtained after the treatment is transported to the interior of the first storage tank 4 and the second storage tank 11 through the first conveying component 5 respectively, and the treated wastewater is transported to the interior of the neutralization tank 15 through the third conveying component 14 for treatment. This structure facilitates the regular maintenance of the hydrolyzer. If the internal solution is discharged, more wastewater will be generated. After treatment by this solution, this part of the solution is reused, which reduces the generation of wastewater and improves the economy. The solution generated by the regular maintenance of the hydrolysis ammonia hydrolyzer is transported to the interior of the two storage tanks for recycling.
[0044] Second embodiment
[0045] Please refer to Figure 3-Figure 4 - Figure 5 , Figure 3 A schematic structural diagram of a second embodiment of a urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model; Figure 4 An enlarged view of the baffle is provided for the utility model;
[0046] Figure 5 Provided for the utility model Figure 4 The enlarged view of A shown in the figure is based on the urea workshop hydrolysis ammonia production wastewater treatment system provided by the first embodiment of the present application. The second embodiment of the present application proposes another urea workshop hydrolysis ammonia production wastewater treatment system. The second embodiment is only a preferred mode of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.
[0047] Specifically, the difference of the urea workshop hydrolysis ammonia production wastewater treatment system provided in the second embodiment of the present application is that two silt discharge pipes 20 are fixedly connected to the front of the first hydrolysis wastewater pit 2, and a discharge pipe 19 is fixedly connected to one side of the first hydrolysis wastewater pit 2.
[0048] The two silt discharge pipes 20 are connected to the first separation chamber 23 and the second separation chamber 24 , and the discharge pipe 19 is connected to the inlet of the first conveying assembly 5 .
[0049] The interior of the first hydrolysis wastewater pit 2 is divided into a first separation chamber 23 , a second separation chamber 24 and a discharge chamber 27 by a separation assembly 25 and a fixing plate 26 .
[0050] The separation assembly 25 is composed of a structure on a fixed plate 26, and the discharge chamber 27 corresponds to the discharge pipe 19. The bottom, front and back of the fixed plate 26 and the separation assembly 25 are respectively fixedly connected to the bottom, front and back of the inner wall of the first hydrolysis wastewater pit 2. For details, please refer to Figure 4 .
[0051] Two filter plates 28 are fixedly connected to the top of the fixing plate 26 at two sides, and a plurality of baffles 29 are arranged between the two filter plates 28 .
[0052] The baffle plate 29 is stuck between the two filter plates 28 and can be taken out, so as to facilitate the adjustment of the blocking height.
[0053] A top cover 21 is provided on the top of the first hydrolysis wastewater pit 2 , and an injection pipe 22 is installed on the top of the top cover 21 .
[0054] The injection pipe 22 is connected to the outlet of the second conveying assembly 7 at the top of the first hydrolyzer 12 and the second hydrolyzer 13 , and the injection pipe 22 is located above the second separation chamber 24 .
[0055] Compared with the related art, the urea workshop hydrolysis ammonia wastewater treatment system provided by the utility model has the following beneficial effects:
[0056] In order to achieve rapid separation of sludge and wastewater in wastewater, the first hydrolysis wastewater pit 2 is divided into a first separation chamber 23, a second separation chamber 24 and a discharge chamber 27 by a fixed plate 26 and a separation assembly, and two layers of filter plates 28 are fixedly connected to the top of the fixed plate 26, and a baffle 29 can be used to block the two layers of filter plates 28, which can increase the height of the blockage. After the adjustment is completed, the wastewater containing dirt is injected into the second separation chamber 24 through the injection pipe 22, and the larger particles of dirt are retained in the second separation chamber 24 through the separation assembly 25, while the smaller particles of dirt are filtered through the separation assembly 25 and flow into the first separation chamber 23, and then the dirt is filtered out by the two filter plates 28 and remains in the first separation chamber 23, and then the filtered water flows into the discharge chamber 27 and is transported to the second hydrolysis wastewater pit 3 through the discharge pipe 19. The dirt and particles in the sewage can be removed through this structure, which is convenient for cleaning.
[0057] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A urea workshop hydrolysis ammonia wastewater treatment system, characterized in that: include: Install the base; A first hydrolysis wastewater pit, wherein the first hydrolysis wastewater pit is installed on the top of a mounting base, a second hydrolysis wastewater pit is installed on the top of the mounting base, a first storage tank is installed on the top of the mounting base, a second storage tank is installed on the top of the mounting base, a urea dissolution tank is installed on the top of the mounting base, a first hydrolyzer is installed on the top of the mounting base, a second hydrolyzer is installed on the top of the mounting base, and a neutralization tank is installed on the top of the mounting base; A first conveying assembly is installed on the top of a second hydrolysis wastewater pit, and two fixed pipes are installed at the outlet of the first conveying assembly through a tee joint. A second conveying assembly is installed on the top of the urea dissolution tank, and a connecting pipe is fixedly connected to the outlet of the second conveying assembly. A third conveying assembly is installed on the top of the neutralization tank, and a circulation assembly is installed on one side of the neutralization tank.
2. The urea workshop hydrolysis ammonia production wastewater treatment system according to claim 1, characterized in that: The first hydrolysis wastewater pit and the second hydrolysis wastewater pit are connected via a second conveying component, and the first hydrolyzer and the second hydrolyzer are connected via the first conveying component and a wastewater pipeline entering the wastewater to be decomposed.
3. The urea workshop hydrolysis ammonia production wastewater treatment system according to claim 1, characterized in that: A control box is installed on the top of the installation base, and a box door is rotatably connected to one side of the control box.
4. The urea workshop hydrolysis ammonia production wastewater treatment system according to claim 1, characterized in that: Two silt discharge pipes are fixedly connected to the front of the first hydrolysis wastewater pit, and a discharge pipe is fixedly connected to one side of the first hydrolysis wastewater pit.
5. The urea workshop hydrolysis ammonia production wastewater treatment system according to claim 1, characterized in that: The interior of the first hydrolysis wastewater pit is divided into a first separation chamber, a second separation chamber and a discharge chamber by a separation component and a fixed plate.
6. The urea workshop hydrolysis ammonia production wastewater treatment system according to claim 5, characterized in that: Two filter plates are fixedly connected to the top of the fixed plate at two sides, and a plurality of baffles are arranged between the two filter plates.
7. The urea workshop hydrolysis ammonia production wastewater treatment system according to claim 1, characterized in that: A top cover is provided on the top of the first hydrolysis wastewater pit, and an injection pipe is installed on the top of the top cover.