Basement skip construction structure

By designing the straight and raised sections of the waterstop steel plate body and utilizing the sealant layer and sealing plate fasteners, the problems of high labor costs and leakage in the welding connection of the waterstop steel plate were solved, achieving an efficient and reliable waterstop connection.

CN222009009UActive Publication Date: 2024-11-15CHINA FIRST HIGHWAY ENGINEERING CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420637836.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-11-15
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

Existing welded connections for waterstop steel plates suffer from high labor costs, difficulty in operation, and easy leakage at the weld seams.

Method used

The design incorporates a water-stop steel plate body, including a straight section and a raised section, and is connected by a weld-free fastener. It is fixed using a sealant layer and a sealing plate, avoiding welding.

Benefits of technology

This technology enables weld-free connection of water-stop steel plates, reducing labor costs, improving construction efficiency, and preventing leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222009009U_ABST
    Figure CN222009009U_ABST
Patent Text Reader

Abstract

The utility model provides a construction structure for a basement by adopting a skip-bay method, and relates to the technical field of construction by adopting the skip-bay method. Comprising water stop steel plate bodies, a straight section is arranged at one end of each water stop steel plate body, a lifting section is arranged at the other end of each water stop steel plate body, a welding-free fixing piece is arranged between every two adjacent water stop steel plate bodies, and each welding-free fixing piece comprises a top sealing plate arranged above the corresponding lifting section and a bottom sealing plate arranged below the corresponding lifting section; the top sealing plate and the bottom sealing plate are attached to the upper side and the lower side of the water stop steel plate body and are fixedly connected through bolts. The utility model solves the problems of high labor cost, difficulty in operation and easiness in leakage at a welding seam due to the welding connection of the existing water stop steel plate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model provides a basement skip-bin construction structure, and relates to the technical field of skip-bin construction. Background Art

[0002] The skipping method makes full use of the "resistance and release" property principle of concrete, which is easy to release internal stress before its performance is stable and completely solidified during 5 to 10 days. It divides the building foundation or large-area concrete plane structure into several areas, and constructs according to the principle of "block planning, block construction, layered pouring, and overall forming". Its pattern is the same as that of checkers, that is, pouring one section at a time.

[0003] When the skip warehouse method is used for basement construction, it will lead to an increase in concrete construction joints, which will lead to a significant increase in the amount of waterproofing construction. At present, steel plate waterstops are mostly used for waterproofing construction. Most of the existing waterstop steel plates are fixed in length of 3m. Therefore, when using them, multiple waterstop steel plates must be welded and connected, and the waterstops must be simply spot welded to the steel bars to fix them. Waterstop steel plates are usually welded by lap welding, which requires professional special operations welders to install and construct. The labor cost is high. When the thickness of the foundation raft is less than 500mm, the double-sided welding of the waterstop steel plate at the post-casting belt is not easy to operate, and the on-site welding time is long, which affects the progress of construction. Since the joints of the two waterstop steel plates are overlapped, the waterstop steel plates on both sides are prone to deformation after welding, and leakage is prone to occur at the welds. For this reason, we propose a basement skip warehouse construction structure. Utility Model Content

[0004] The technical problem to be solved by the utility model is that the existing water-stop steel plates are connected by welding, which has the problems of high labor cost, difficult operation and easy leakage at the weld.

[0005] In order to solve the above-mentioned technical problems, the technical solution provided by the utility model is: a basement skip-bin construction structure, comprising a waterstop steel plate body, wherein a straight section is provided at one end of the waterstop steel plate body and a lifting section is provided at the other end, and a welding-free fixing part is provided between two adjacent waterstop steel plate bodies, and the welding-free fixing part comprises a top sealing plate arranged above the lifting section and a bottom sealing plate arranged below the lifting section, and the top sealing plate and the bottom sealing plate are fitted on the upper and lower sides of the waterstop steel plate body and fixed by bolts.

[0006] Preferably, sealing blocks are provided on both sides of the bottom of the top sealing plate, and the sealing blocks are arranged on both sides of the lifting section.

[0007] Preferably, connecting burrs are provided on both sides of the top sealing plate.

[0008] Preferably, L-shaped burrs are provided on both sides of the bottom sealing plate, and the L-shaped burrs are fitted with the connecting burrs, and the L-shaped burrs and the connecting burrs are fixed with bolts.

[0009] Preferably, a sealing and waterproof adhesive layer is coated between the lifting section and the straight section between two adjacent waterstop steel plate bodies.

[0010] Preferably, the length of the lifting section is greater than 5 cm.

[0011] Preferably, the lifting height of the lifting section is 3 to 6 mm greater than the thickness of the waterstop steel plate body.

[0012] Beneficial effects of the utility model:

[0013] By setting the lifting section, it is convenient to connect the two waterstop steel plate bodies to ensure that the waterstop steel plate bodies are in the same horizontal plane, and then by setting the weld-free fixing parts, the two waterstop steel plate bodies are fixed together to achieve weld-free connection, thereby avoiding the problems of high labor costs, difficult operation, and easy leakage at the welds caused by welding connections. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 The utility model is a schematic diagram of the overall structure of a basement skipping method construction structure.

[0015] Figure 2 This is a disassembled diagram of a basement skipping method construction structure of the utility model.

[0016] Figure 3 It is a schematic diagram of the overlapping state of two adjacent waterstop steel plate bodies after the welding-free fixing parts are removed in a basement skipping method construction structure of the utility model.

[0017] Figure 4 It is a bottom view of the top sealing plate of a basement skipping method construction structure of the utility model.

[0018] Figure 5 The utility model is a schematic diagram of the bottom sealing plate structure of a basement skipping method construction structure.

[0019] Figure 6 This is a cross-sectional view of the connection between two adjacent water-stop steel plate bodies of a basement skipping construction structure of the utility model. (1, water-stop steel plate body; 11, lifting section; 12, straight section; 2, welding-free fixings; 21, top sealing plate; 211, sealing block; 212, connecting burrs; 22, sealing waterproof adhesive layer; 23, bottom sealing plate; 231, L-shaped burrs) DETAILED DESCRIPTION

[0020] The preferred embodiments of the present utility model will be described in detail below in conjunction with the accompanying drawings.

[0021] Reference Figures 1 to 6The utility model provides a basement skipping construction structure, comprising a water-stop steel plate body 1, wherein one end of the water-stop steel plate body 1 is provided with a straight section 12 and the other end is provided with a lifting section 11, and the length of the lifting section 11 is greater than 5 cm. Figure 3 As shown, the lifting section 11 is higher than the straight section 12 on one side. When two waterstop steel plate bodies 1 are connected, one end of the straight section 12 can be placed below the lifting section 11 to ensure that multiple waterstop steel plate bodies 1 are on the same horizontal plane after being connected.

[0022] Furthermore, the lifting height of the lifting section 11 described in the utility model is greater than the thickness of the water-stop steel plate body 1 by 3 to 6 mm, and a sealing waterproof adhesive layer 22 is coated between the lifting section 11 and the straight section 12 between two adjacent water-stop steel plate bodies 1. Specifically, after the straight section 12 is placed under the lifting section 11, a gap of 3 to 6 mm is left between the straight section 12 and the lifting section 11 for coating the sealing waterproof adhesive layer 22, so as to bond the two water-stop steel plate bodies 1 together, and at the same time have the effect of sealing and waterproofing.

[0023] Furthermore, in the utility model, a weld-free fixing part 2 is arranged between two adjacent waterstop steel plate bodies 1, and the weld-free fixing part 2 includes a top sealing plate 21 arranged above the lifting section 11 and a bottom sealing plate 23 arranged below the lifting section 11, and sealing blocks 211 are arranged on both sides of the bottom of the top sealing plate 21, and the sealing blocks 211 are arranged on both sides of the lifting section 11, and connecting burrs 212 are arranged on both sides of the top sealing plate 21, and L-shaped burrs 231 are arranged on both sides of the bottom sealing plate 23, and the L-shaped burrs 231 are fitted with the connecting burrs 212, and the L-shaped burrs 231 and the connecting burrs 212 are fixed by bolts. Specifically, as Figure 2 , Figure 4 , Figure 5 , Figure 6 As shown, after two adjacent waterstop steel plate bodies 1 are bonded and fixed by a sealing waterproof adhesive layer 22, a top sealing plate 21 is placed above the lifting section 11, and the sealing block 211 is placed on both sides of the lifting section 11, and then a bottom sealing plate 23 is placed at the bottom of the waterstop steel plate body 1, so that the top sealing plate 21 and the bottom sealing plate 23 are butt-jointed together to wrap the connected parts of the two waterstop steel plate bodies 1, and then the L-shaped burrs 231 and the connecting burrs 212 are fixed together by bolts, so that the top sealing plates 21 and the bottom sealing plates 23 are pressed against both sides of the waterstop steel plate body 1, thereby fixing the two waterstop steel plate bodies 1 together to achieve a welding-free connection.

[0024] Working principle: First, connect two adjacent waterstop steel plate bodies 1, place the straight section 12 under the lifting section 11, and apply a sealing and waterproof adhesive layer 22 between the two, and glue the two waterstop steel plate bodies 1 together end to end. Then, place the top sealing plate 21 and the bottom sealing plate 23 on the upper and lower sides of the lifting section 11 respectively, and fix the L-shaped burrs 231 and the connecting burrs 212 together with bolts, so that the top sealing plate 21 and the bottom sealing plate 23 are pressed against the two sides of the waterstop steel plate body 1, thereby fixing the two waterstop steel plate bodies 1 together to achieve a welding-free connection.

[0025] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.

Claims

1. A basement skipping construction structure, comprising a water-stop steel plate body, characterized in that: The waterstop steel plate body is provided with a straight section at one end and a lifting section at the other end, and a weld-free fixing part is provided between two adjacent waterstop steel plate bodies. The weld-free fixing part includes a top sealing plate arranged above the lifting section and a bottom sealing plate arranged below the lifting section. The top sealing plate and the bottom sealing plate are fitted on the upper and lower sides of the waterstop steel plate body and fixed by bolts.

2. A basement skipping construction structure according to claim 1, characterized in that: Sealing blocks are provided on both sides of the bottom of the top sealing plate, and the sealing blocks are arranged on both sides of the lifting section.

3. A basement skipping construction structure according to claim 1, characterized in that: Connecting burrs are arranged on both sides of the top sealing plate.

4. A basement skipping construction structure according to claim 3, characterized in that: L-shaped burrs are arranged on both sides of the bottom sealing plate, and the L-shaped burrs are fitted with the connecting burrs, and the L-shaped burrs and the connecting burrs are fixed by bolts.

5. The basement skipping construction structure according to claim 1 is characterized by: A sealing waterproof adhesive layer is coated between the lifting section and the straight section between two adjacent water-stop steel plate bodies.

6. A basement skipping construction structure according to claim 1, characterized in that: The length of the lifting section is greater than 5 cm.

7. The basement skipping construction structure according to claim 1 is characterized by: The lifting height of the lifting section is 3 to 6 mm greater than the thickness of the water-stop steel plate body.